Summary of Cost of Owned and Leased Properties by the Company The following is a summary of our cost of owned or leased properties as of June 30, 2020 and December 31, 2019 (in thousands):

As of June 30, 2020 (unaudited):

    

    

Buildings,

    

    

Improvements

Construction

Property Location

Land

and Equipment

in Progress

Total Cost

Atlanta, Georgia Campus (1)

$

44,588

$

563,509

$

235,947

$

844,044

Irving, Texas

8,606

372,151

110,589

491,346

Ashburn, Virginia

16,476

307,744

114,152

438,372

Richmond, Virginia

2,180

197,334

143,850

343,364

Chicago, Illinois

9,400

235,304

82,570

327,274

Suwanee, Georgia (Atlanta-Suwanee)

3,521

176,161

3,117

182,799

Piscataway, New Jersey

7,466

113,795

33,035

154,296

Santa Clara, California (2)

116,638

447

117,085

Fort Worth, Texas

9,079

100,200

15,370

124,649

Hillsboro, Oregon

18,414

21,088

78,810

118,312

Leased Facilities (4)

84,550

2,110

86,660

Sacramento, California

1,481

65,595

268

67,344

Dulles, Virginia

3,154

51,913

4,852

59,919

Manassas, Virginia (3)

18

58,990

59,008

Princeton, New Jersey

20,701

35,225

76

56,002

Eemshaven, Netherlands

55,084

55,084

Phoenix, Arizona (3)

32,927

32,927

Groningen, Netherlands

1,744

9,858

3,266

14,868

Other (5)

2,213

36,296

797

39,306

$

149,023

$

2,487,379

$

976,257

$

3,612,659

(1)The “Atlanta, Georgia Campus” includes both the existing data center Atlanta (DC-1) as well as new property development associated with construction of a second megascale data center Atlanta (DC-2) on land adjacent to the existing Atlanta DC-1 facility.
(2)Owned facility subject to long-term ground sublease.
(3)Represent land purchases. Land acquisition costs, as well as subsequent development costs, are included within construction in progress until development on the land has ended and the asset is ready for its intended use.
(4)Includes 7 facilities. All facilities are leased, including those subject to finance leases.
(5)Consists of Miami, FL; Lenexa, KS and Overland Park, KS facilities.

As of December 31, 2019:

    

Buildings,

    

Improvements

Construction

Property Location

Land

and Equipment

in Progress

Total Cost

Atlanta, Georgia Campus (1)

$

44,588

$

525,300

$

128,930

$

698,818

Irving, Texas

8,606

369,727

98,170

476,503

Ashburn, Virginia (2)

16,476

156,396

189,375

362,247

Richmond, Virginia

2,180

195,684

139,948

337,812

Chicago, Illinois

9,400

205,026

86,878

301,304

Suwanee, Georgia (Atlanta-Suwanee)

3,521

174,124

5,559

183,204

Piscataway, New Jersey

7,466

103,553

36,056

147,075

Santa Clara, California (3)

114,499

1,238

115,737

Fort Worth, Texas

9,079

55,018

35,722

99,819

Leased Facilities (4)

82,813

666

83,479

Sacramento, California

1,481

65,258

163

66,902

Hillsboro, Oregon (2)

63,573

63,573

Manassas, Virginia (2)

57,662

57,662

Princeton, New Jersey

20,700

35,192

39

55,931

Dulles, Virginia

3,154

48,651

4,688

56,493

Eemshaven, Netherlands

37,267

37,267

Phoenix, Arizona (2)

2,412

31,840

34,252

Groningen, Netherlands

1,741

9,085

3,028

13,854

Other (5)

2,213

36,163

120

38,496

$

130,605

$

2,178,901

$

920,922

$

3,230,428

(1)The “Atlanta, Georgia Campus” includes both the existing data center Atlanta (DC-1) as well as new property development associated with construction of a second megascale data center Atlanta (DC-2) on land adjacent to the existing Atlanta DC-1 facility.
(2)Represent land purchases. Land acquisition costs, as well as subsequent development costs, are included within construction in progress until development on the land has ended and the asset is ready for its intended use.
(3)Owned facility subject to long-term ground sublease.
(4)Includes 7 facilities. All facilities are leased, including those subject to finance leases.
(5)Consists of Miami, FL; Lenexa, KS and Overland Park, KS facilities.