Note 12 — Contingencies

 

This note should be read in conjunction with the complete description under Note 16   Commitments and Contingencies, to the Company's 2018 Form 10-K.

 

Contingencies

 

The Company's material legal proceedings are described below. The Company believes that it has valid defenses to these legal proceedings and intends to defend them vigorously. The Company records reserves for estimated losses from contingencies when information available indicates that a loss is probable and the amount of the loss, or range of loss, can be reasonably estimated. As applicable, the Company has established an adequate reserve for the matters discussed below. In addition, legal costs are expensed as incurred. Management assesses such matters based on current information and makes a judgment concerning its potential outcome, considering the nature of the claim, the amount and nature of damages sought, and the probability of success. The Company is unable to predict the outcome of the legal proceedings below or reasonably estimate the scope or amount of any associated costs and potential liabilities. As additional information becomes available, management adjusts its assessment and estimates of such contingencies accordingly. Because litigation is subject to inherent uncertainties and unfavorable rulings or developments, it is possible that the ultimate resolution of the Company's liabilities and contingencies could be at amounts that are different from its currently recorded reserves and that such difference could be material.

 

In addition to the legal proceedings noted below, the Company and its subsidiaries are party to other litigation or legal proceedings arising in the ordinary course of business. In management's opinion, the disposition of these ordinary course matters will not materially adversely affect the Company's consolidated financial position, results of operations, or cash flows.

 

Nebraska Public Power District Litigation

 

On January 11, 2019, Nebraska Public Power District, or NPPD, sent written notice to certain of the Company’s subsidiaries which own the Laredo Ridge and Elkhorn Ridge wind projects alleging an event of default under each of the PPAs between NPPD and the projects. NPPD alleges that the Company moved forward with certain transactions without obtaining the consent of NPPD. NPPD threatened to terminate the applicable PPAs by February 11, 2019 if the alleged default was not cured. The Company filed a motion for a temporary restraining order and preliminary injunction in the U.S. District Court for the District of Nebraska relating to the Laredo Ridge project, and a similar motion in the District Court of Knox County, Nebraska for the Elkhorn Ridge project, to enjoin NPPD from taking any actions related to the PPAs. On February 19, 2019, the U.S. District Court in the Laredo Ridge matter approved a stipulation between the parties to provide for an injunction preventing NPPD from terminating the PPA pending disposition of the litigation. On February 26, 2019, the Knox County District Court approved a similar stipulation relating to the Elkhorn Ridge project. Additionally, Elkhorn Ridge was added as a third-party defendant to the litigation in the U.S. District Court. On September 23, 2019, NPPD filed amended complaints in the U.S. District Court, to which Laredo Ridge and Elkhorn Ridge responded on October 7, 2019. The Company believes the allegations of NPPD are meritless and the Company is vigorously defending its rights under the PPAs.

 

Buckthorn Solar Litigation

 

On October 8, 2019, the City of Georgetown, Texas, or Georgetown, filed a petition in the District Court of Williamson County, Texas naming Buckthorn Westex, LLC, the Company’s subsidiary that owns the Buckthorn Westex solar project, as the defendant, alleging fraud by nondisclosure and breach of contract in connection with the project and the PPA, and seeking (i) rescission and/or cancellation of the PPA, (ii) declaratory judgment that the alleged breaches constitute an event of default under the PPA entitling Georgetown to terminate, and (iii) recovery of all damages, costs of court, and attorneys’ fees. Buckthorn Westex believes the allegations of Georgetown are meritless, and Buckthorn Westex is vigorously defending its rights under the PPA.