Litigation, Environmental and Other Contingencies Lower Passaic River (Details) - Pending Litigation
$ in Millions
3 Months Ended
Oct. 05, 2016
USD ($)
Mar. 31, 2020
USD ($)
mi
Parties
Defendants
claims
Lower Passaic River Study Area    
Site Contingency [Line Items]    
Miles of river | mi   17
Number of Parties at a Joint Defense Group | Parties   44
Lower Passaic River Study Area | EPA preferred alternative estimate    
Site Contingency [Line Items]    
Environmental Remediation Expense | $   $ 1,700
Lower Passaic River Study Area | AOC required engineering and design work    
Site Contingency [Line Items]    
Environmental Remediation Expense | $ $ 165  
Loss Contingency, Pending Claims, Number | claims   2
Loss Contingency, Number of Defendants | Defendants   120
Lower Passaic River Study Area | Design    
Site Contingency [Line Items]    
Estimated Remedy Implementation Period 4 years  
Lower Passaic River Study Area | Clean Up Implementation    
Site Contingency [Line Items]    
Estimated Remedy Implementation Period 6 years  
Lower Passaic River Study Area, Lower Portion    
Site Contingency [Line Items]    
Miles of river | mi   8