XML 151 R112.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Leases - Operating Leases - Data center colocation lease (Details) - USD ($)
$ in Thousands
12 Months Ended
Dec. 31, 2019
Dec. 31, 2018
Jan. 01, 2019
Operating leases      
Operating lease right-of-use assets $ 17,743   $ 88,300
Lease liability $ 23,228   94,900
Asset impairment charge      
Weighted-average discount rate of operating leases (as a percent) 5.80%    
Lease cost $ 19,490    
Data Center Lease, Boston, Massachusetts      
Operating leases      
Annual rent escalation (as a percent) 4.00%    
Operating lease right-of-use assets     600
Lease liability $ 400   $ 600
Asset impairment charge      
Weighted-average discount rate of operating leases (as a percent) 6.00%    
Lease cost $ 200    
Rent expense   $ 200  
Data Center Lease, Boston, Massachusetts | Selling, general and administrative      
Asset impairment charge      
Asset impairment charge $ 500