XML 30 R16.htm IDEA: XBRL DOCUMENT v3.23.1
RELATED PARTY (Tables)
3 Months Ended
Mar. 31, 2023
RELATED PARTY  
Schedule of related party transactions

Balance of funds paid under the Cost Share Agreement at December 31, 2022

$

6,700

Funds transferred to General Atomics during the quarter ended March 31, 2023

1,000

Company's share of Demonstration Plant project costs incurred through March 31, 2023

(5,834)

Balance of funds remaining on deposit as a prepaid expense with General Atomics at March 31, 2023

$

1,866

Schedule of related party receivables

Balance of receivables due from General Atomics at December 31, 2022

$

174

Reimbursable costs incurred by the Company during the quarter ended March 31, 2023

125

Reimbursements received from General Atomics during the quarter ended March 31, 2023

(213)

Balance of receivables due from General Atomics at March 31, 2023

$

86