We have commitments in the form of unconditional purchase obligations as of December 31, 2017. These include commitments for the purchase of property, plant & equipment of $134,458,000 and commitments for noncapital purchases of $32,145,000. These commitments are due as follows:





 

 



 

 



Unconditional

 



Purchase

 

in thousands

Obligations

 

Property, Plant & Equipment

 

 

2018

$      134,458 

 

Thereafter

 

Total

$      134,458 

 

Noncapital (primarily transportation and electricity contracts)

 

 

2018

$        10,449 

 

2019–2020

15,109 

 

2021–2022

3,587 

 

Thereafter

3,000 

 

Total

$        32,145 

 



Commitments for the purchase of property, plant & equipment for 2018 include $68,951,000 for the remaining construction of two new Panamax-class, self-unloading ships. Expenditures under noncapital purchase commitments totaled $40,526,000 in 2017, $60,591,000 in 2016 and $76,178,000 in 2015.

We have commitments in the form of minimum royalties under mineral leases as of December 31, 2017 in the amount of $211,432,000, due as follows:





 

 



 

 



Mineral

 

in thousands

Leases

 

Minimum Royalties

 

 

2018

$        22,531 

 

2019–2020

34,022 

 

2021–2022

22,703 

 

Thereafter

132,176 

 

Total

$      211,432 

 



Expenditures for royalties under mineral leases totaled $67,933,000 in 2017, $62,978,000 in 2016 and $58,048,000 in 2015. Refer to Note 7 for future minimum nonmineral operating lease payments.

Certain of our aggregates reserves are burdened by volumetric production payments (nonoperating interest) as described in Note 1 under the caption Deferred Revenue. As the holder of the working interest, we have responsibility to bear the cost of mining and producing the reserves attributable to this nonoperating interest.

As summarized by purpose in Note 6, our standby letters of credit totaled $43,239,000 as of December 31, 2017.

As described in Note 9, our liability for unrecognized tax benefits is $11,643,000 as of December 31, 2017.

As described in Note 17, our asset retirement obligations totaled $218,117,000 as of December 31, 2017.

LITIGATION AND ENVIRONMENTAL MATTERS

We are subject to occasional governmental proceedings and orders pertaining to occupational safety and health or to protection of the environment, such as proceedings or orders relating to noise abatement, air emissions or water discharges. As part of our continuing program of stewardship in safety, health and environmental matters, we have been able to resolve such proceedings and to comply with such orders without any material adverse effects on our business.

We have received notices from the United States Environmental Protection Agency (EPA) or similar state or local agencies that we are considered a potentially responsible party (PRP) at a limited number of sites under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA or Superfund) or similar state and local environmental laws. Generally we share the cost of remediation at these sites with other PRPs or alleged PRPs in accordance with negotiated or prescribed allocations. There is inherent uncertainty in determining the potential cost of remediating a given site and in determining any individual party's share in that cost. As a result, estimates can change substantially as additional information becomes available regarding the nature or extent of site contamination, remediation methods, other PRPs and their probable level of involvement, and actions by or against governmental agencies or private parties.

We have reviewed the nature and extent of our involvement at each Superfund site, as well as potential obligations arising under other federal, state and local environmental laws. While ultimate resolution and financial liability is uncertain at a number of the sites, in our opinion based on information currently available, the ultimate resolution of claims and assessments related to these sites will not have a material effect on our consolidated results of operations, financial position or cash flows, although amounts recorded in a given period could be material to our results of operations or cash flows for that period. Amounts accrued for environmental matters are presented in Note 8.

We are a defendant in various lawsuits in the ordinary course of business. It is not possible to determine with precision the outcome, or the amount of liability, if any, under these lawsuits, especially where the cases involve possible jury trials with as yet undetermined jury panels.

In addition to these lawsuits in which we are involved in the ordinary course of business, certain other material legal proceedings are specifically described below.

§

Lower Passaic River Study Area (Superfund Site) — The Lower Passaic River Study Area is part of the Diamond Shamrock Superfund Site in New Jersey. Vulcan and approximately 70 other companies are parties (collectively the Cooperating Parties Group) to a May 2007 Administrative Order on Consent (AOC) with the EPA to perform a Remedial Investigation/Feasibility Study (draft RI/FS) of the lower 17 miles of the Passaic River (River). However, before the draft RI/FS was issued in final form, the EPA issued a record of decision (ROD) in March 2016 that calls for a bank-to-bank dredging remedy for the lower 8 miles of the River. The EPA estimates that the cost of implementing this proposal is $1.38 billion. In September 2016, the EPA entered into an Administrative Settlement Agreement and Order on Consent with Occidental Chemical Corporation (Occidental) in which Occidental agreed to undertake the remedial design for this bank-to-bank dredging remedy, and to reimburse the United States for certain response costs.

In August 2017, the EPA informed certain members of the Cooperating Parties Group, including Vulcan, that it planned to use the services of a third-party allocator with the expectation of offering cash-out settlements to some parties in connection with the bank-to-bank remedy. This voluntary allocation process is intended to establish an impartial third-party expert recommendation that may be considered by the government and the participants as the basis of possible settlements. We have begun participating in this voluntary allocation process, which is likely to take several years.

Efforts to remediate the River have been underway for many years and have involved hundreds of entities that have had operations on or near the River at some point during the past several decades. We formerly owned a chemicals operation near the mouth of the River, which was sold in 1974. The major risk drivers in the River have been identified as dioxins, PCBs, DDx and mercury. We did not manufacture any of these risk drivers and have no evidence that any of these were discharged into the River by Vulcan.

The AOC does not obligate us to fund or perform the remedial action contemplated by either the draft RI/FS or the ROD. Furthermore, the parties who will participate in funding the remediation and their respective allocations have not been determined. We do not agree that a bank-to-bank remedy is warranted, and we are not obligated to fund any of the remedial action at this time; nevertheless, we previously estimated the cost to be incurred by us as a potential participant in a bank-to-bank dredging remedy and recorded an immaterial loss for this matter in 2015.



§

TEXAS BRINE MATTER — During the operation of its former Chemicals Division, Vulcan leased the right to mine salt out of an underground salt dome formation in Assumption Parish, Louisiana from 1976 - 2005. Throughout that period and for all times thereafter, the Texas Brine Company (Texas Brine) was the operator contracted by Vulcan (and later Occidental) to mine and deliver the salt. We sold our Chemicals Division in 2005 and transferred our rights and interest related to the salt and mining operations to the purchaser, a subsidiary of Occidental, and we have had no association with the leased premises or Texas Brine since that time. In August 2012, a sinkhole developed in the vicinity of the Texas Brine mining operations, and numerous lawsuits were filed in state court in Assumption Parish, Louisiana. Other lawsuits, including class action litigation, were also filed in federal court before the Eastern District of Louisiana in New Orleans.

There are numerous defendants, including Texas Brine and Occidental, to the litigation in state and federal court. Vulcan was first brought into the litigation as a third-party defendant in August 2013 by Texas Brine. We have since been added as a direct and third-party defendant by other parties, including a direct claim by the state of Louisiana. Damage categories encompassed within the litigation include individual plaintiffs’ claims for property damage, a claim by the state of Louisiana for response costs and civil penalties, claims by Texas Brine for response costs and lost profits, claims for physical damages to nearby oil and gas pipelines and storage facilities (pipelines), and business interruption claims.

In addition to the plaintiffs’ claims, we were also sued for contractual indemnity and comparative fault by both Texas Brine and Occidental. It is alleged that the sinkhole was caused, in whole or in part, by our negligent actions or failure to act. It is also alleged that we breached the salt lease with Occidental, as well as an operating agreement and related contracts with Texas Brine; that we are strictly liable for certain property damages in our capacity as a former lessee of the salt lease; and that we violated certain covenants and conditions in the agreement under which we sold our Chemicals Division to Occidental. We have likewise made claims for contractual indemnity and on a basis of comparative fault against Texas Brine and Occidental.

Vulcan and Occidental have since dismissed all of their claims against one another. Texas Brine has claims that remain pending against Vulcan and against Occidental. Discovery remains ongoing in various cases.

In December 2016, we settled with plaintiffs in one of the cases involving individual property damages. During the first nine months of 2017, we settled with the plaintiffs in the cases involving physical damages to pipelines. Our insurers have funded the settlements in excess of our self-insured retention amount. Each of the pipeline plaintiffs signed a release in favor of Vulcan and agreed that we would not be responsible to the pipelines for any amount beyond the settlement amount.

A bench trial (judge only) began in September 2017 and ended in October in the pipeline cases. The trial was limited in scope to the allocation of comparative fault or liability for causing the sinkhole, with a damages phase of the trial to be held at a later date. Vulcan participated in the trial, as the liability finding could impact cross-party and third-party claims against us. In December 2017, the judge issued a ruling on the allocation of fault among the three defendants, as follows: Occidental 50%, Texas Brine 35% and Vulcan 15%. Motions for a new trial have been filed, and it is likely that one or more parties will appeal the judge’s ruling.

Also in December 2017, we agreed to a settlement in a federal putative class action. It will take time to finalize this settlement due to required court proceedings relating to class action notice and approval. Our insurers participated in the settlement discussions and have agreed to fund the settlement.

We cannot reasonably estimate a range of liability pertaining to the open cases at this time.

§

HEWITT LANDFILL MATTER (SUPERFUND SITE) — In September 2015, the Los Angeles Regional Water Quality Control Board (RWQCB) issued a Cleanup and Abatement Order (CAO) directing Vulcan to assess, monitor, cleanup and abate wastes that have been discharged to soil, soil vapor, and/or groundwater at the former Hewitt Landfill in Los Angeles. The CAO follows a 2014 Investigative Order from the RWQCB that sought data and a technical evaluation regarding the Hewitt Landfill, and a subsequent amendment to the Investigative Order requiring us to provide groundwater monitoring results to the RWQCB and to create and implement a work plan for further investigation of the Hewitt Landfill. In April 2016, we submitted an interim remedial action plan (IRAP) to the RWQCB, proposing an on-site pilot test of a pump and treat system; testing and implementation of a leachate recovery system; and storm water capture and conveyance improvements.

Operation of the on-site pilot-scale treatment system began in January 2017, and was completed in April 2017. With completion of the pilot testing and other investigative work to date, we submitted an amendment to the IRAP (AIRAP) to RWQCB in August 2017 proposing the use of a pump, treat and reinjection system. In December 2017, we submitted an addendum to the AIRAP, incorporating new data acquired since the prior submission. In February 2018, the AIRAP was approved by RWQCB. As a result of this approval, we will begin to implement the on-site source control activities described in the AIRAP. Based on the preliminary design of this system, we accrued $15,239,000  in 2017 (reflected in other operating expense).

We are also engaged in an ongoing dialogue with the EPA, the Los Angeles Department of Water and Power, and other stakeholders regarding the potential contribution of the Hewitt Landfill to groundwater contamination in the North Hollywood Operable Unit (NHOU) of the San Fernando Valley Superfund Site. We are gathering and analyzing data and developing technical information to determine the extent of possible contribution by the Hewitt Landfill to the groundwater contamination in the area. This work is also intended to assist in identification of other PRPs that may have contributed to groundwater contamination in the area.

In July 2016, the EPA sent us a letter requesting that we enter into an AOC for remedial design work in the NHOU. We entered into an AOC and Statement of Work effective September 2017, for the design of two extraction wells south of the Hewitt Site to protect the North Hollywood West well field. In November 2017, we submitted a Pre-Design Investigation Work Plan to the EPA, which sets forth the activities and schedule for our evaluation of the need for a two-well remedy. Estimated cost to comply with this AOC are immaterial and have been accrued. Until the remedial design work and evaluation of the two-well remedy is complete, we cannot identify an appropriate remedial action or reasonably estimate a loss pertaining to this matter.

It is not possible to predict with certainty the ultimate outcome of these and other legal proceedings in which we are involved and a number of factors, including developments in ongoing discovery or adverse rulings, or the verdict of a particular jury, could cause actual losses to differ materially from accrued costs. No liability was recorded for claims and litigation for which a loss was determined to be only reasonably possible or for which a loss could not be reasonably estimated. Legal costs incurred in defense of lawsuits are expensed as incurred. In addition, losses on certain claims and litigation described above may be subject to limitations on a per occurrence basis by excess insurance, as described in Note 1 under the caption Claims and Litigation Including Self-insurance.