XML 136 R19.htm IDEA: XBRL DOCUMENT v2.4.1.9
COMMITMENTS AND CONTINGENCIES
12 Months Ended
Dec. 31, 2014
COMMITMENTS AND CONTINGENCIES [Abstract]  
COMMITMENTS AND CONTINGENCIES

NOTE 12: COMMITMENTS AND CONTINGENCIES

We have commitments in the form of unconditional purchase obligations as of December 31, 2014. These include commitments for the purchase of property, plant & equipment of $34,401,000 and commitments for noncapital purchases of $38,119,000. These commitments are due as follows:

 

 

 

 

 

 

 

 

Unconditional

 

 

Purchase

 

in thousands

Obligations

 

Property, Plant & Equipment

 

 

2015

$        34,401 

 

Thereafter

 

Total

$        34,401 

 

Noncapital (primarily transportation and electricity contracts)

 

 

2015

$        23,348 

 

2016–2017

4,891 

 

2018–2019

3,880 

 

Thereafter

6,000 

 

Total

$        38,119 

 

 

Expenditures under noncapital purchase commitments totaled $65,582,000 in 2014, $83,699,000 in 2013 and $83,599,000 in 2012.

We have commitments in the form of minimum royalties under mineral leases as of December 31, 2014 in the amount of $190,124,000, due as follows:

 

 

 

 

 

 

 

 

Mineral

 

in thousands

Leases

 

Minimum Royalties

 

 

2015

$        19,274 

 

2016–2017

26,954 

 

2018–2019

19,050 

 

Thereafter

124,846 

 

Total

$      190,124 

 

 

Expenditures for royalties under mineral leases totaled $49,685,000 in 2014, $53,768,000 in 2013 and $46,007,000 in 2012. Refer to Note 7 for future minimum nonmineral operating lease payments.

Certain of our aggregates reserves are burdened by volumetric production payments (nonoperating interest) as described in Note 1 under the caption Deferred Revenue. As the holder of the working interest, we have responsibility to bear the cost of mining and producing the reserves attributable to this nonoperating interest.

We provide, in the normal course of business, certain third party beneficiaries standby letters of credit to support our obligations to pay or perform according to the requirements of an underlying agreement. Such letters of credit typically have an initial term of one year, typically renew automatically, and can only be modified or cancelled with the approval of the beneficiary. All of our standby letters of credit are issued by banks that participate in our $500,000,000 line of credit, and reduce the borrowing capacity thereunder. We pay a fee for all standby letters of credit equal to the margin (ranges from 1.50% to 2.25%) applicable to LIBOR based borrowings under the line of credit, plus 0.175%.  Our standby letters of credit as of December 31, 2014 are summarized by purpose in the table below:

 

 

 

 

 

 

 

 

 

 

 

 

 

in thousands

 

 

Standby Letters of Credit

 

 

Risk management insurance

$       33,199 

 

Industrial revenue bond

14,230 

 

Reclamation/restoration requirements

6,121 

 

Total

$       53,550 

 

 

As described in Note 9, our liability for unrecognized tax benefits is $7,057,000 as of December 31, 2014.

We are subject to occasional governmental proceedings and orders pertaining to occupational safety and health or to protection of the environment, such as proceedings or orders relating to noise abatement, air emissions or water discharges. As part of our continuing program of stewardship in safety, health and environmental matters, we have been able to resolve such proceedings and to comply with such orders without any material adverse effects on our business.

We have received notices from the United States Environmental Protection Agency (EPA) or similar state or local agencies that we are considered a potentially responsible party (PRP) at a limited number of sites under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA or Superfund) or similar state and local environmental laws. Generally we share the cost of remediation at these sites with other PRPs or alleged PRPs in accordance with negotiated or prescribed allocations. There is inherent uncertainty in determining the potential cost of remediating a given site and in determining any individual party's share in that cost. As a result, estimates can change substantially as additional information becomes available regarding the nature or extent of site contamination, remediation methods, other PRPs and their probable level of involvement, and actions by or against governmental agencies or private parties.

We have reviewed the nature and extent of our involvement at each Superfund site, as well as potential obligations arising under other federal, state and local environmental laws. While ultimate resolution and financial liability is uncertain at a number of the sites, in our opinion based on information currently available, the ultimate resolution of claims and assessments related to these sites will not have a material effect on our consolidated results of operations, financial position or cash flows, although amounts recorded in a given period could be material to our results of operations or cash flows for that period. Amounts accrued for environmental matters are presented in Note 8.

We are a defendant in various lawsuits in the ordinary course of business. It is not possible to determine with precision the outcome, or the amount of liability, if any, under these lawsuits, especially where the cases involve possible jury trials with as yet undetermined jury panels.

In addition to these lawsuits in which we are involved in the ordinary course of business, certain other material legal proceedings are specifically described below.

LOWER PASSAIC RIVER MATTER

§

Lower Passaic River Study Area (Superfund Site) — The Lower Passaic River Study Area is part of the Diamond Shamrock Superfund Site in New Jersey. Vulcan and approximately 70 other companies are parties to a May 2007 Administrative Order on Consent (AOC) with the U.S. Environmental Protection Agency (EPA) to perform a Remedial Investigation/Feasibility Study (RI/FS) of the lower 17 miles of the Passaic River (River). On April 11, 2014, the EPA issued a proposed Focused Feasibility Study (FFS) that calls for a bank-to-bank dredging remedy for the lower 8 miles of the River. The EPA estimates that the cost of implementing this proposal is approximately $950 million to $1.73 billion. The period for public comment on the proposed FFS is closed.  The RI/FS should be completed in 2015, and it is anticipated that the EPA will issue its final record of decision sometime in 2015.

At this time, we cannot reasonably estimate our ultimate liability related to this matter. Furthermore, the AOC does not obligate us to fund or perform the remedial action contemplated by either the RI/FS or the FFS. Vulcan formerly owned a chemicals operation near River Mile 0.1, which was sold in 1974. The Company has found no evidence that its former chemicals operation contributed any of the primary contaminants of concern to the River. Neither the ultimate remedial approach and associated costs (or range of costs), nor the parties who will participate in funding the remediation and their respective allocations, have been determined.

Based on the facts available at this time, we believe our liability related to any remedial actions will be immaterial.

OTHER LITIGATION

§

TEXAS BRINE MATTER  During the operation of its former Chemicals Division, Vulcan was the lessee to a salt lease from 1976 – 2005 in an underground salt dome formation in Assumption Parish, Louisiana. The Texas Brine Company operated this salt mine for the account of Vulcan. Vulcan sold its Chemicals Division in 2005 and assigned the lease to the purchaser, and Vulcan has had no association with the leased premises or Texas Brine Company since that time. In August 2012, a sinkhole developed near the salt dome and numerous lawsuits were filed in state court in Assumption Parish, Louisiana. Other lawsuits, including class action litigation, were also filed in August 2012 in federal court in the Eastern District of Louisiana in New Orleans. Certain of the plaintiffs and Texas Brine settled the Federal Court class action for approximately $48.1 million. This settlement has been approved by the court, and the settlement process is now subject to the terms of the court’s order and settlement agreement. Vulcan is named as a released party in the settlement agreement along with the other released parties, including Texas Brine, and its insurers. Texas Brine and its insurers did not, however, release Vulcan from any alleged claims, including claims for contribution and indemnity.

There are numerous defendants to the litigation in state and federal court. Vulcan was first brought into the litigation as a third-party defendant in August 2013 by the Texas Brine Company. Vulcan has since been added as a direct and third-party defendant by other parties, including a direct claim by the State of Louisiana. The damages alleged in the litigation range from individual plaintiffs’ claims for property damage, to the State of Louisiana’s claim for response costs, to claims for alleged physical damages to oil pipelines, to various alleged business interruption claims, and to claims for indemnity and contribution from Texas Brine. It is alleged that the sinkhole was caused, in whole or in part, by Vulcan’s negligent actions or failure to act. It is also alleged that Vulcan breached the salt lease, as well as an operating agreement with Texas Brine. Vulcan denies any liability in this matter and will vigorously defend the litigation. We cannot reasonably estimate any liability related to this matter.

It is not possible to predict with certainty the ultimate outcome of these and other legal proceedings in which we are involved and a number of factors, including developments in ongoing discovery or adverse rulings, or the verdict of a particular jury, could cause actual losses to differ materially from accrued costs. No liability was recorded for claims and litigation for which a loss was determined to be only reasonably possible or for which a loss could not be reasonably estimated. Legal costs incurred in defense of lawsuits are expensed as incurred. In addition, losses on certain claims and litigation described above may be subject to limitations on a per occurrence basis by excess insurance, as described in Note 1 under the caption Claims and Litigation Including Self-insurance.