ANNUAL INFORMATION FORM

ALEXCO RESOURCE CORP.
Suite 1150, 200 Granville Street
Vancouver, British Columbia, V6C 1S4
Telephone: (604) 633-4888
Facsimile: (604) 633-4887
E-Mail: info@alexcoresource.com
Website: www.alexcoresource.com

For the year ended June 30, 2010

Dated September 17, 2010


TABLE OF CONTENTS

      Page
PRELIMINARY NOTES 3
GLOSSARY OF TECHNICAL TERMS 5
CORPORATE STRUCTURE 9
GENERAL DEVELOPMENT OF THE BUSINESS 9
  Formation of the Corporation 9
  Three Year History and Significant Acquisitions 9
DESCRIPTION OF THE BUSINESS 11
  Mineral Exploration and Development 11
    Bellekeno Property 11
    Elsa Tailings Property 20
  Environmental Consulting Services 27
    General 27
    Keno Hill Project 27
  Risk Factors 28
    Exploration and Development 28
    Figures for the Corporation's Resources are Estimates Based on Interpretation and Assumptions and May Yield Less Mineral Production Under Actual Conditions than is Currently Estimated 28
    Keno Hill District 29
    Construction and Operation of the Bellekeno Mine 29
    Permitting and Environmental Risks and Other Regulatory Requirements 30
    Environmental Consulting Services 30
Potential Profitability Of Mineral Properties Depends Upon Metal Prices and Other Factors Beyond the Control of Alexco 31
    First Nation Rights and Title 31
    Title to Mineral Properties 31
    Capitalization and Commercial Viability 31
General Economic Conditions May Adversely Affect Alexco’s Growth and Profitability 31
    Operating Hazards and Risks 32
    Competition 32
Certain of the Corporation’s Directors and Officers are Involved with Other Natural Resource Companies, Which May Create Conflicts of Interest from Time to Time 32
The Corporation May Fail to Maintain Adequate Internal Control Over Financial Reporting Pursuant to the Requirements of the Sarbanes-Oxley Act. 32
DIVIDENDS 33
DESCRIPTION OF CAPITAL STRUCTURE 33
MARKET FOR SECURITIES 33
  Trading Price and Volume 33
  Securities Not Listed or Quoted 35
DIRECTORS AND OFFICERS 35
  Name, Occupation and Security Holding 35
  Cease Trade Orders, Bankruptcies, Penalties or Sanctions 37
  Conflicts of Interest 38
AUDIT COMMITTEE INFORMATION 38
  Audit Committee Charter 38
  Composition of the Audit Committee 44



  Reliance on Certain Exemptions 45
  Audit Committee Oversight 45
  Pre-Approval Policies and Procedures 45
  External Auditor Service Fees (By Category) 45
LEGAL PROCEEDINGS AND REGULATORY ACTIONS 46
INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS 46
TRANSFER AGENTS AND REGISTRARS 46
MATERIAL CONTRACTS 47
INTERESTS OF EXPERTS 47
  Names of Experts 47
  Interests of Experts 48
ADDITIONAL INFORMATION 48


- 3 -

PRELIMINARY NOTES

In this Annual Information Form (“AIF”), Alexco Resource Corp. is referred to as the “Corporation” or “Alexco”. All information contained herein is as at and for the year ended June 30, 2010, unless otherwise specified. All dollar amounts in this AIF are expressed in Canadian dollars unless otherwise indicated.

Cautionary Statement Regarding Forward-Looking Statements

This AIF contains “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of applicable Canadian securities laws concerning the Corporation's business plans, including but not limited to anticipated results and developments in the Corporation’s operations in future periods, planned exploration and development of its properties, plans related to its business and other matters that may occur in the future, made as of the date of this AIF. Forward-looking statements may include, but are not limited to, statements with respect to future remediation and reclamation activities, future mineral exploration, the estimation of mineral reserves and mineral resources, the realization of mineral reserve and mineral resource estimates, the timing of activities and the amount of estimated revenues and expenses, the success of exploration activities, permitting time lines, the success of mine development and construction activities, the success of future mine operations, the success of other future business operations, requirements for additional capital and sources and uses of funds. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as “expects”, “anticipates”, “plans”, “estimates”, “intends”, “strategy”, “goals”, “objectives” or stating that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be “forward-looking statements”.

Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors which could cause actual events or results to differ from those expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results of exploration activities; actual results of remediation and reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of gold, silver and other commodities; possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; and delays in obtaining governmental approvals or financing or in the completion of development activities. Furthermore, forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Corporation or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including but not limited to those referred to in this AIF under the heading “Description of the Business – Risk Factors” and elsewhere. Forward-looking statements are based on certain assumptions that management believes are reasonable at the time they are made. In making the forward-looking statements included in this AIF, the Corporation has applied several material assumptions, including, but not limited to, the assumption that: (1) the proposed development of its mineral projects will be viable operationally and economically and proceed as planned; (2) market fundamentals will result in sustained silver, lead and zinc demand and prices, and such prices will be materially consistent with those anticipated in the Development Plan (as hereinafter defined), (3) the actual nature, size and grade of its mineral resources are materially consistent with the resource estimates reported in the most recent applicable technical report; and (4) any additional financing needed will be available on reasonable terms.

The Corporation's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made, and the Corporation does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change, except as required by applicable law. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.


- 4 -

Cautionary Note to U.S. Investors – Information Concerning Preparation of Resource Estimates

This AIF has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of United States securities laws. Unless otherwise indicated, all resource and reserve estimates included in this AIF have been prepared in accordance with Canadian National Instrument 43-101 (“NI 43-101”) and the Canadian Institute of Mining and Metallurgy Classification System. NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. NI 43-101 permits the disclosure of an historical estimate made prior to the adoption of NI 43-101 that does not otherwise comply with NI 43-101, using the historical terminology, if the disclosure: (a) identifies the source and date of the historical estimate; (b) comments on the relevance and reliability of the historical estimate; (c) states whether the historical estimate uses categories other than those prescribed by NI 43-101 and if so includes an explanation of the differences, and (d) includes any more recent estimates or data available. Such historical estimates are presented concerning certain of the Corporation’s properties described herein.

Canadian standards, including NI 43-101, differ significantly from the requirements of Industry Guide 7 promulgated by the United States Securities and Exchange Commission (“SEC”) under the United States Securities Act of 1933, as amended, and resource and reserve information contained herein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term "resource" does not equate to the term "reserves". Under U.S. standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. The SEC's disclosure standards under Industry Guide 7 do not define the terms and normally do not permit the inclusion of information concerning "measured mineral resources", "indicated mineral resources" or "inferred mineral resources" or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the SEC. U.S. Investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is economically or legally mineable.

Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute “reserves” by SEC standards as in place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of “reserves” are also not the same as those of the SEC’s Industry Guide 7, and reserves reported by the Corporation in compliance with NI 43-101 may not qualify as “reserves” under Industry Guide 7 standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.

Qualified Person Under NI 43-101

Except where specifically indicated otherwise, technical information included in this AIF regarding Alexco’s mineral properties has been prepared by or under the supervision of Stanton Dodd, L.Geo., Vice President, Exploration for Alexco and a Qualified Person as defined by NI 43-101.


- 5 -

GLOSSARY OF TECHNICAL TERMS

The following is a glossary of certain mining terms used in this AIF:

Acre

An area of 4,840 square yards or 43,560 square feet.

 

Ag

Silver.

 

Assay

In economic geology, to analyze the proportions of metal in a rock or overburden sample; to test an ore or mineral for composition, purity, weight or other properties of commercial interest.

 

Au

Gold.

 

CIM

Canadian Institute of Mining and Metallurgy.

 

Deposit

A mineralized body which has been physically delineated by sufficient drilling, trenching, and/or underground work, and found to contain a sufficient average grade of metal or metals to warrant further exploration and/or development expenditures; such a deposit does not qualify as a commercially mineable ore body or as containing ore reserves, until final legal, technical, and economic factors have been resolved.

 

Dip

The angle at which a stratum is inclined from the horizontal.

 

Fold

A bend in strata or any planar structure.

 

g/t Au

Grams per tonne gold.

 

Grade

The amount of valuable metal in each tonne of ore, expressed as grams per tonne (g/t) for precious metals, as percent (%) for copper, lead, zinc and nickel.

 

Hectare

An area equal to 100 meters by 100 meters.

 

km

Kilometers.

 

m

Meters.

 

Mineral Reserve, Proven Mineral Reserve, Probable Mineral Reserve

Under CIM standards, a Mineral Reserve is the economically mineable part of a Measured or Indicated Mineral Resource demonstrated by a preliminary feasibility study or feasibility study. This study must include adequate information on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified. A Mineral Reserve includes diluting materials and allowances for losses that may occur when the material is mined.

 

The terms “Mineral Reserve”, “Proven Mineral Reserve” and “Probable Mineral Reserve” used in this AIF are mining terms defined under CIM standards and used in accordance with NI 43-101. Mineral Reserves, Proven Mineral Reserves and Probable Mineral Reserves presented under CIM standards may not conform with the definitions of “reserves” or “proven reserves” or “probable reserves” under United States standards. See "Preliminary Notes – Cautionary Note to U.S. Investors – Information Concerning Preparation of Resource Estimates".



- 6 -

Mineral Reserves under CIM standards are those parts of Mineral Resources which, after the application of all mining factors, result in an estimated tonnage and grade which, in the opinion of the qualified person(s) making the estimates, is the basis of an economically viable project after taking account of all relevant processing, metallurgical, economic, marketing, legal, environment, socio-economic and government factors. Mineral Reserves are inclusive of diluting material that will be mined in conjunction with the Mineral Reserves and delivered to the treatment plant or equivalent facility. The term ‘Mineral Reserve’ need not necessarily signify that extraction facilities are in place or operative or that all governmental approvals have been received. It does signify that there are reasonable expectations of such approvals.

 

Under CIM standards, Mineral Reserves are sub-divided in order of increasing confidence into Probable Mineral Reserves and Proven Mineral Reserves. A Probable Mineral Reserve has a lower level of confidence than a Proven Mineral Reserve.

 

Proven Mineral Reserve: A Proven Mineral Reserve is the economically mineable part of a Measured Mineral Resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the time of reporting, that the economic extraction can be justified.

 

Probable Mineral Reserve: A Probable Mineral Reserve is the economically mineable part of an Indicated and, in some circumstances, a Measured Mineral Resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic, and other relevant factors that demonstrate, at the time of reporting, that the economic extraction can be justified.

 

Mineral Resource, Measured Mineral Resource, Indicated Mineral Resource, Inferred Mineral Resource

Under CIM standards, Mineral Resource is a concentration or occurrence of natural, solid, inorganic or fossilized organic material in or on the earth's crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge.

 

The terms "mineral resource", "measured mineral resource", "indicated mineral resource", and "inferred mineral resource" used in this Prospectus are mining terms defined under CIM standards and used in accordance with NI 43-101. They are not defined terms under United States standards and generally may not be used in documents filed with the SEC by U.S. companies. See “Preliminary Notes – Cautionary Note to U.S. Investors Information Concerning Preparation of Resource Estimates”.

 

A mineral resource estimate is based on information on the geology of the deposit and the continuity of mineralization. Assumptions concerning economic and operating parameters, including cut-off grades and economic mining widths, based on factors typical for the type of deposit, may be used if these factors have not been specifically established for the deposit at the time of the mineral resource estimate. A mineral resource is categorized on the basis of the degree of confidence in the estimate of quantity and grade or quality of the deposit, as follows:



- 7 -

Inferred Mineral Resource: Under CIM standards, an Inferred Mineral Resource is that part of a Mineral Resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.
   
Indicated Mineral Resource: Under CIM standards, an Indicated Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.
   
Measured Mineral Resource: Under CIM standards, a Measured Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape, physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.
   
Mineralization The concentration of metals and their chemical compounds within a body of rock.
   
Ore A metal or mineral or a combination of these of sufficient value as to quality and
  quantity to enable it to be mined at a profit.
   
Ounce or oz A troy ounce or twenty penny weights or 480 grains or 31.103 grams.
   
Outcrop An exposure of bedrock at the surface.
   
Pb Lead.
   
Quartz A mineral composed of silicon dioxide.
   
Strike Direction or trend of a geologic structure.
   
Tonne Metric unit of weight equivalent to volume multiplied by specific gravity; equivalent
  to 1.102 tons or 1,000 kilograms (2,204.6 pounds).
   
Vein Thin sheet-like intrusion into a fissure or crack, commonly bearing quartz.
   
Zn Zinc.


- 8 -

Metric Equivalents

The following table sets forth the factors for converting between Imperial measurements and metric equivalents:

To Convert From To Multiply By
Feet Meters 0.305
Meters Feet 3.281
Miles Kilometers (“km”) 1.609
Kilometers Miles 0.6214
Acres Hectares (“ha”) 0.405
Hectares Acres 2.471
Grams Ounces (Troy) 0.03215
Grams/Tonnes Ounces (Troy)/Short Ton 0.02917
Tonnes (metric) Pounds 2,205
Tonnes (metric) Short Tons 1.1023


- 9 -

CORPORATE STRUCTURE

The Corporation was incorporated under the Business Corporations Act (Yukon) on December 3, 2004 under the name “Alexco Resource Corp.” Effective December 28, 2007, it was continued under the Business Corporations Act (British Columbia).

The Corporation's head office is located at Suite 1150, 200 Granville Street, Vancouver, British Columbia, V6C 1S4, Canada, and its registered and records office is located at 10th Floor, 595 Howe Street, Vancouver, British Columbia, V6C 2T5, Canada.

At the end of its most recently completed financial year, the Corporation had the following wholly-owned subsidiaries:

  • Alexco Keno Hill Mining Corp. (formerly Alexco Resource Canada Corp.), organized under the laws of British Columbia;

  • Alexco Exploration Canada Corp., organized under the laws of British Columbia;

  • Elsa Reclamation & Development Company Ltd., organized under the laws of Yukon (“ERDC”);

  • Access Mining Consultants Ltd., organized under the laws of Yukon (“Access”); and

  • Alexco Resource U.S. Corp., organized under the laws of Colorado (“Alexco US”).

Unless the context otherwise indicates, reference to the term the “Corporation” or “Alexco” in this AIF includes Alexco Resource Corp. and its subsidiaries.

GENERAL DEVELOPMENT OF THE BUSINESS

Formation of the Corporation

In 2005, the Corporation completed a series of transactions pursuant to which it acquired a number of mineral property interests and rights to certain operating contracts in Yukon and British Columbia, the most significant of which properties are located in the Yukon’s Keno Hill silver district.

Three Year History and Significant Acquisitions

In June 2005, the Corporation was selected as the preferred purchaser of the assets of United Keno Hill Mines Limited and UKH Minerals Limited (collectively, “UKHM”) by a court appointed interim receiver and receiver-manager of UKHM. In February 2006, following negotiation of a Subsidiary Agreement between the Government of Canada, the Government of Yukon (collectively, “Government”) and the Corporation, the Supreme Court of Yukon approved the purchase of the assets of UKHM by Alexco through its wholly-owned subsidiary, ERDC. “Final Closing” of this acquisition was conditional upon issuance of a water license to the Corporation by the Yukon Water Board to set the standards for care and maintenance activities to be carried out at Keno Hill. This water license was issued in November 2007 and Final Closing was effected in December 2007, resulting in the transfer to the Corporation of ownership and title to the Keno Hill mining claims and the other UKHM assets. In addition, under the terms of the Subsidiary Agreement the Corporation is indemnified by the Government of Canada for all liabilities, including environmental liabilities, arising directly or indirectly as a result of the pre-existing condition of the Keno Hill mining claims and other assets acquired from UKHM. The Subsidiary Agreement provides that ERDC may bring any mine into production on the UKHM properties by designating a production unit from the mineral property interests relevant to that purpose and then assuming responsibility for all costs of the production unit’s water related care and maintenance and water related components of closure reclamation. The Subsidiary Agreement further requires ERDC to pay into a separate reclamation trust a 1.5% net smelter return royalty, up to an aggregate maximum of $4 million for all production units, from any future production from the UKHM properties, commencing once earnings from mining before interest, taxes and depreciation exceed actual exploration costs, up to a maximum of $6.2 million, plus actual development and construction capital.


- 10 -

Also under the Subsidiary Agreement, ERDC is retained through Government as a paid contractor responsible on a continuing basis for the environmental care and maintenance and ultimate closure reclamation of the former UKHM properties. The Subsidiary Agreement provides that ERDC is responsible for the development of the ultimate closure reclamation plan for fees of 65% of agreed commercial contractor rates, and this plan development is currently ongoing. Upon acceptance and regulatory approval, the closure reclamation plan will be implemented by ERDC at agreed commercial contractor rates. During the period required to develop the plan, ERDC is also responsible for carrying out the environmental care and maintenance of the UKHM properties for a reducing fixed annual fee adjusted each year for certain operating and inflationary factors.

Since 2006, the Corporation has carried out exploration activities on several of its Keno Hill properties, with a significant component of that activity having been focused on the Bellekeno property. A Development Plan in respect of Bellekeno was completed in November 2009 and supported by a NI 43-101 compliant technical report, outlining a project with a pre-tax net present value to Alexco of $31.9 million over an initial mine life of approximately four years (see “Description of Business – Mineral Exploration and Development – Bellekeno Property”). Development and construction of the Bellekeno mine was initiated immediately, and the start of commissioning is anticipated to occur by the end of the third quarter of calendar 2010.

Further particulars relating to the acquired mineral property interests located in the Keno Hill district, including the above-referenced technical reports, are described below under “Description of the Business – Mineral Exploration and Development”. Further particulars relating to the care and maintenance and closure reclamation activities being conducted by the Corporation in the Keno Hill district under the Subsidiary Agreement are described below under “Description of the Business – Environmental Consulting Services – Keno Hill Project”.

On June 30, 2006, the Corporation completed the acquisition of Access, a privately owned mid-tier environmental consulting firm headquartered in Whitehorse, Yukon Territory. Originally formed in March 1995, Access provided locally-experienced professional project management and environmental services for industrial land and resource development projects in northern Canada. On February 16, 2007, the Corporation expanded its services business into the United States through the establishment of Alexco US, combined with the acquisition of certain intellectual property and project rights from Green World Science of Nevada, Inc. (“Green World”) as well as the addition of the principals of Green World to the Alexco US management team.

The assets acquired from Green World included six patents registered in the U.S., some of which are registered or are in the process of being registered in Canada and other countries (the “Patents”). The Patents pertain to the in situ immobilization of metals and are specifically suited to mine closure related remediation, and have terms that expire variously between 2015 and 2020. Two of the Patents, as registered in Canada, were previously under license to the Corporation. The acquisition of the Patents, together with the interests of Green World in certain ongoing projects, provided Alexco US with immediate remediation services revenue and cash flow, and laid the foundation on which it could further develop and establish its U.S. based business over the next several years.

The Corporation completed a listing of its common shares on the Toronto Stock Exchange (the “TSX”) under the trading symbol “AXR” on January 26, 2006. On September 20, 2007, the Corporation began trading its common shares on the NYSE AMEX Equities Exchange (the “AMEX”), formerly the American Stock Exchange, under the symbol “AXU”.

On October 2, 2008, the Corporation entered into a silver purchase agreement with Silver Wheaton Corp. (“Silver Wheaton”) under which Silver Wheaton will purchase 25% of the life of mine silver produced by the Corporation from its Keno Hill silver district properties. The agreement anticipates that the initial silver deliveries will come from the Bellekeno property at Keno Hill. The agreement was subsequently amended on October 20, 2008, December 10, 2008, December 22, 2009 and March 31, 2010.


- 11 -

The Corporation will receive an up-front deposit payment from Silver Wheaton of US$50 million, plus a further payment of the lesser of US $3.90 (increasing by 1% per annum after the third year of full production) and the prevailing market price for each ounce of silver delivered. US$15 million of the up-front payment was advanced to the Corporation on December 23, 2008 as certain conditions were met. The US$15 million funded underground development, definition drilling and continued exploration of the Bellekeno resource as well as other work required to refine and complete engineering studies. The remaining US$35 million is being paid on a monthly draw-down basis to fund the Bellekeno mine development and infrastructure and ore processing mill construction costs, and as of the date of this AIF a total of US$18,308,000 of such remaining funds had been received.

With respect to its consulting services group, the Corporation remains engaged in the on-going environmental care and maintenance program and reclamation and closure projects in the Keno Hill district under its contract through ERDC with Government and in accordance with the Subsidiary Agreement, and continues to service its private sector client base in the Yukon through Access. Similarly, the Corporation intends to continue expanding its environmental services activities, in the North, and also in the United States and elsewhere through the Americas.

DESCRIPTION OF THE BUSINESS

The Corporation operates two principal businesses: mineral exploration and development in Canada, primarily in Yukon Territory; and under its Alexco Environmental Group division (“AEG”), the provision of consulting and project management services in respect of environmental permitting and compliance and site remediation and reclamation, in Canada, the United States and elsewhere in the Americas. At June 30, 2010, the Corporation had 110 permanent and seasonal employees. A total of 64 were employed in the mineral exploration and development business and a total of 33 were employed in the environmental consulting services business, with the remaining 13 employed in respect of executive management and administrative support.

Mineral Exploration and Development

The Corporation's principal mineral exploration and development activities are currently being carried out within the Keno Hill district in the Yukon. The Corporation’s main property within the Keno Hill district is the Bellekeno property, and the Bellekeno mine is currently in development and construction. A resource estimate has also been prepared with respect to the historical Elsa Tailings property within the district. The Corporation holds several other property interests within the district, including but not limited to Onek, Lucky Queen, Silver King and Husky, which may potentially become material properties depending on the results of exploration programs the Corporation may carry out on them in the future. In aggregate, Alexco’s mineral property interests in the Keno Hill district comprise a total of 717 surveyed quartz mining leases, 864 unsurveyed quartz mining claims and two crown grants.

Other non-material property interests of the Corporation include the Brewery Creek, McQuesten, Sprogge, Harlan and Klondike properties in the Yukon, and certain 1% net smelter return royalties in respect of the Telegraph Creek, Iskut River, Kiniskan Lake and Manson Creek properties in British Columbia.

Bellekeno Property

The Corporation’s 100% owned Bellekeno property comprises 70 surveyed quartz mining leases and 14 unsurveyed quartz mining claims, and is subject to the capped 1.5% net smelter return royalty provided for under the Subsidiary Agreement in respect of any future production from the UKHM properties (see “General Development of the Business – Three Year History and Significant Acquisitions”). The Bellekeno property has been the subject of four technical reports, all filed on SEDAR and all NI 43-101 compliant.


- 12 -

The most recent of these technical reports is the updated preliminary economic assessment dated December 9, 2009 and entitled “Bellekeno Project – Updated Preliminary Economic Assessment Technical Report”, prepared by an integrated team of personnel from Alexco, Wardrop Engineering Inc. (“Wardrop”) and SRK Consulting (Canada) Inc. (“SRK”). As disclosed in that technical report, Alexco has so far defined at Bellekeno an indicated resource estimated at a total of 401,000 tonnes grading 921 grams per tonne silver, 9.4% lead and 6.5% zinc, reflecting a total of 11,870,000 contained ounces of silver, plus an inferred resource estimated at 111,100 tonnes grading 320 grams per tonne silver, 3.1% lead and 17.9% zinc, reflecting a total of 1,143,000 contained ounces of silver. The updated economic analysis disclosed in the technical report incorporated the terms of Alexco’s silver purchase agreement with Silver Wheaton and outlined a project with a pre-tax net present value to Alexco of C$31.9 million at 8% over an initial mine life of approximately four years and a pay-back period to Alexco of 0.5 years, net of deposit funds received from Silver Wheaton. This economic analysis was based on metal prices of US$15.16 per ounce for silver, US$996 per ounce for gold, US$0.72 per pound for lead and US$0.85 per pound for zinc and an exchange rate of US$0.92 per Canadian dollar, representing consensus average metal price and currency exchange forecasts as of November 6, 2009 as published publicly by a basket of independent Canadian investment analysts and compiled by Alexco.

The detailed disclosure contained in the technical report is hereby incorporated by reference, and the summary section from that report is reproduced as follows.

Introduction

This Bellekeno Project Updated Preliminary Economic Assessment (PEA) Technical Report was prepared for Alexco Resource Corp. (Alexco) by Wardrop Engineering Inc. (Wardrop), and SRK Consulting (Canada) Inc. (SRK) to provide a more detailed overview of the economic potential of extracting and processing mineralized material from the Bellekeno polymetallic deposits.

Wardrop completed the metallurgical, mineral processing, and economic analysis sections of this report with input contributions from SRK and Alexco. SRK completed the underground mining and geotechnical sections of this report. Numerous Alexco personnel, particularly Tim Hall (Operations Manager) and Tom Fudge, P.Eng., (Alexco Independent Consultant), provided significant information and technical input into the report.

Location and Land Holdings

The Bellekeno deposit is located in the historic Keno Hill Mining District that envelopes the villages of Elsa and Keno City (63°55'N, 135°29'W) in central Yukon. The region has been mined intermittently for over 90 years. The closest town is Mayo, approximately 55 km to the south of the project via an all-weather road. Whitehorse is approximately 460 km south of Mayo.

The land controlled by Alexco, following the issuance of a Care and Maintenance Water License in late November 2007, comprises 713 surveyed quartz mining leases, 794 unsurveyed quartz mining claims, and two crown grants. The total area is approximately 23,350 ha. Mineral exploration at Keno Hill is permitted under the terms and conditions set out by the Yukon Government in a Class IV Quartz Mining Land Use Permit – LQ-00240, issued in June 2008, which governs all exploration activities on the property including advanced underground exploration, for the Bellekeno deposit. The permit supersedes the earlier mining land use permits for the property. The mineral resources and the underground infrastructure of the Bellekeno Project reported herein are all located within six contiguous Quartz claims inside the large Keno Hill property.

The climate of the Bellekeno area is characterized by a sub-arctic continental climate with cold winters and warm summers. Average temperatures in the winter are between -15°C and -20°C while summer temperatures average around 15°C. Exploration and mining can be conducted year-round. The landscape around the Bellekeno project is characterized by rolling hills and mountains up to 1200 m in elevation. Vegetation is abundant.


- 13 -

Exploration

On June 19, 2008, Alexco announced it was granted a Class IV Quartz Mining Land Use Permit – LQ0024, allowing the development of an exploration decline in the central portion of the Bellekeno deposit. Procon Mining and Tunnelling Ltd. (Procon) was awarded a contract to drive approximately 650 m of decline and ancillary development that accessed old workings and established diamond drilling locations for a 9,300 m exploration and definition diamond drilling program. The underground exploration program comprised 140 holes drilled between February and August 2009. Prior to rehabilitating the historic working a Type B water license was secured by Alexco to allow for the dewatering of the Bellekeno Mine.

Metallurgy and Mineral Processing

Test results from three testing programs indicate that the mineralization of the Bellekeno deposit responds well to a lead and zinc differential flotation process using a cyanide-free zinc mineral suppression regime. Silver minerals are intimately associated with lead minerals and will be recovered as a silver-lead concentrate. A separate zinc concentrate will also be produced from the Bellekeno operation.

The design capacity of the process plant will be 408 t/d. Overall plant availability is estimated to be 92%. Run-of-mine (ROM) material from different mineralized zones is planned to be processed by conventional crushing, grinding, and flotation followed by concentrate and tailings dewatering. The tailings will be filtered and stored in a Dry Stack Tailings Facility (DSTF) located adjacent to the mill building. Two separate tailings products will be produced; a low pyrite and high pyrite tailings. 100% of the high pyrite will be transported to the underground mine for storage and 30 to 50% of the low pyrite tailings will also be transported underground for use as backfill material with the balance being stored on surface in the DSTF. Mill makeup water will be sourced from the Galkeno 900 treatment system. The estimated installed power requirement for the mill building and infrastructure is approximately 1.8 MW (at 408 t/d design). Electrical power for the mill will be provided by extending the main 69 kV electrical power line located approximately 1.6 km from the mill location.

Metallurgical performance estimated from test work and assumed for this report is based on test work completed by SGS Lakefield Research Ltd. in 2007 and by Process Research Associates Ltd. in 1996 and 2008/2009. Table 1.1 shows the projected metallurgical performance according to the updated mining plan, dated October 2009 used in this study.


- 14 -

Table 1.1 Summary of Projected Metallurgical Recoveries



Year


Product

Mass
(%)
Grade Recovery
Au
(g/t)
Ag
(g/t)
Pb
(%)
Zn
(%)
Au
(%)
Ag
(%)
Pb
(%)
Zn
(%)
2010

Head 100.0 0.44 1,010 11.73 5.26 100.0 100.0 100.0 100.0
Pb-Ag Conc 16.1 1.3 5,924 71.0 2.2 47.8 94.6 97.6 6.7
Zn Conc 8.5 1.1 305 0.64 54.3 21.2 2.6 0.5 87.4
2011

Head 100.0 0.45 994 11.54 5.43 100.0 100.0 100.0 100.0
Pb-Ag Conc 15.9 1.3 5,921 71.0 2.2 47.8 94.5 97.5 6.4
Zn Conc 8.8 1.1 302 0.63 54.4 21.6 2.7 0.5 87.7
2012

Head 100.0 0.43 820 8.50 5.49 100.0 100.0 100.0 100.0
Pb-Ag Conc 11.8 1.72 6,392 70.1 2.3 47.7 91.7 97.1 4.9
Zn Conc 8.9 1.10 298 0.47 54.4 23.1 3.2 0.5 88.5
2013

Head 100.0 0.37 717 7.04 6.09 100.0 100.0 100.0 100.0
Pb-Ag Conc 9.7 1.8 6,616 68.6 2.8 47.4 90.0 95.0 4.5
Zn Conc 10.0 1.1 297 0.40 54.6 29.5 4.1 0.6 89.4
Average

Head 100.0 0.42 871 9.47 5.6 100.0 100.0 100.0 100.0
Pb-Ag Conc 13.1 1.5 6,185 70.3 2.3 47.7 92.7 96.9 5.4
Zn Conc 9.1 1.1 300 0.52 54.4 23.9 3.1 0.5 88.4

A separate lead and zinc concentrate will be produced. The concentrates will be transported from site to either the port of Skagway or Stewart, BC for transportation overseas or trucked directly to Trail, BC.

Resources

Table 1.2 provides a summary by zone of the Classified Mineral Resources for the Bellekeno project (October 2009).

The resource estimate was prepared under the supervision of Mr. Stanton Dodd (L.Geo.), Vice President of Exploration for Alexco. Mr. Dodd is a qualified person (QP) as defined in National Instrument 43-101 (NI 43-101). The mineral resources for the Bellekeno Project were estimated in conformity with generally accepted Canadian Institute of Mining, Metallurgy, and Petroleum (CIM) “Estimation of Mineral Resource and Mineral Reserves Best Practices” guidelines and are reported in accordance with Canadian Securities Administrators’ NI 43-101.

Table 1.2 Mineral Resource Statement, Bellekeno Project, Yukon – November 2009

  Tonnes Ag (g/t) Pb (%) Zn (%)
Indicated
SW All 215,800 997 12.6 7.2
East 48 Upper 16,900 1,001 3.7 10.0
East 48 Mid 59,600 571 3.9 7.4
East 49 All 17,000 699 4.2 2.4
99 All 91,700 995 7.5 4.2
Total Indicated 401,000 921 9.4 6.5
Inferred
Total (East) 111,100 320 3.1 17.9

Notes:
Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures have been rounded to reflect the relative accuracy of the estimates. Reported at a net smelter return cut-off of $185/t.


- 15 -

Resources are reported based on a net smelter return (NSR) cut-off value of $185/t. NSR values were calculated on an in-situ (undiluted) basis using the price and exchange rate inputs shown in Table 1.3.

Table 1.3 Metal Prices and Exchange Rate, Resource Statement


Zone
US$:Cdn$
Exchange
Ag
US$/oz
Pb
US$/lb
Zn
US$/lb
SW 0.90 15.25 0.675 0.80
99 0.90 15.25 0.675 0.80
East 0.90 14.50 0.600 0.90

Mining

The Bellekeno Project is comprised of one primary vein, the 48 vein, a subsidiary structure, the 49 vein and at least 9 other ancillary structures present in the Southwest, 99, and East zones. Most of the historical mining (totalling approximately 40,000 t) at Bellekeno occurred on the 48 vein in the 99 zone, intermittently between the 1950s and mid 1980s. The veins have variable dip, strike, and thickness. Dips range from 60° to 80° to the east or west. The average strike direction is approximately 030 azimuth. Vein thickness varies from a few centimetres to several metres in an apparent “shoot-like” configuration.

Based on the geotechnical and physical characteristics of the veins, a mining method review was conducted and cut-and-fill mining methods have been selected as the most appropriate for Bellekeno. Cut-and-fill and shrinkage stoping methods typically offer a high degree of selectivity that generally translates into high mineralization extraction and low waste dilution. Significant geotechnical study and design has been completed by SRK and a ground control management plan has been developed to address potential unstable ground conditions encountered in the vein material. Backfill of mined out stopes will be accomplished through cemented rock and tailings fill. Filtered tailings from the mill process will be backhauled underground and used as backfill.

Based on the current updated mineral resource estimate (Alexco, October 2009) the life-of-mine (LOM) production schedule is shown in Table 1.4. Mine production is planned to be 250 t/d using a mining contractor.


- 16 -

Table 1.4 Bellekeno Production Schedule


- 17 -

Financial Analysis

Mill, G&A, and mine operating costs are presented in Table 1.5, Table 1.6, and Table 1.7. The project operating costs were estimated from a number of sources including cost estimating guides, contractor and vendor quotes, previous studies, and experience.

Table 1.5 Process Operating Cost Summary

          Annual Cost     Unit Cost  
Description   Labour     (Cdn$/a)     (Cdn$/t ore)  
Process Personnel                  
Supervision   4     528,247     5.87  
Operation   16     1,177,045     13.08  
Maintenance   6     516,458     5.74  
Sub-total   26     2,221,750     24.69  
Supplies                  
Operating Supplies         631,171     7.01  
Maintenance Supplies         29,063     0.32  
Power Supply         540,143     6.00  
Mobile Equipment         204,451     2.27  
Sub-total         1,404,827     15.61  
Total   28   $ 3,626,577   $ 40.30  

Table 1.6 G&A Operating Cost Summary

                   
          Annual Cost     Unit Cost  
Description   Labour     (Cdn$/a)     (Cdn$/t ore)  
Labour   19     1,820,542     20.23  
Head Office         100,000     1.11  
Insurance         100,000     1.11  
Operating Supplies         742,000     8.24  
Contracts         1,531,363     17.02  
Total   19   $ 4,293,905   $ 47.71  


- 18 -

Table 1.7 Mine Operating Cost Estimate by Function



Mine Function
LOM
Cost
(Cdn$000)
Average
Unit Cost
(Cdn$/t)
Alexco Mine Supervision 1,192 3.79
Contractor Overhead – Monthly 18,425 58.60
Contractor Lateral Development 8,138 25.88
Contractor Raising 856 2.72
Contractor Cut & Fill Stoping 13,395 42.60
Contractor Load Underground Trucks 0 0.00
Alexco Surface Truck Haulage 1,562 4.97
Contractor Backfilling 5,880 18.70
Contractor Mine Services 5,035 16.01
Alexco Surface Waste Pile Maintenance 163 0.52
Alexco Technical Services 3,548 11.28
Alexco Energy 4,917 15.64
Mine Operating Cost 63,110 200.70

Capital cost estimates for the project are shown in Table 1.8.

Table 1.8 Capital Cost Summary


Area Description
Total Cost
(Cdn$000)
Direct Costs
Site Development 3,282
Underground Mining 6,310
Crushing 901
Fine Ore Storage 1,267
Mill Building 7,128
Tailings 1,681
Site Services 1,489
Ancillary Facilities 1,754
Plant Mobile Fleet 797
Temporary Services 754
Indirect Costs
Project Indirects 4,574
Owner Costs 5,928
Contingency* 5,779
Total Project Costs 41,644

* refer to Table 19.36 for contingency allowances.

The pre-tax base case financial model was calculated using the following parameters:

  • assumed current net smelter terms

  • 3.8-year mine life

  • royalties are 1.5% NSR after all initial capital plus $6.2 M in exploration costs paid back through earnings before income taxes, depreciation, and amortization (EBITDA) and accumulated cash flow turns positive and capped at Cdn$4 M, as per Alexco


- 19 -

  • production schedule as outlined in this study

  • operating costs as outlined in this study

  • capital costs as outlined in this study

  • the model was prepared on a pre-tax basis

  • working capital distribution as per Alexco and is credit back end of mine life

  • depreciation costs not calculated

  • Silver Wheaton Corp. (Silver Wheaton) capital contribution and capital distribution as per Alexco.

The economic evaluation indicates a base case pre-tax net present value (NPV) of US$29.4 M at a discount rate of 8.0% for the Bellekeno deposit. The summary of pricing scenarios and project economics is presented in Table 1.9 and Table 1.10.

Table 1.9 Economic Evaluation at Various Cases of Metal Prices

  NPV at 8%
  Discount Rate
Scenario (US$ M)
3-year Average 38.8
Alexco Base Case 29.4
Wardrop 28.7
Current 53.8

Table 1.10 Metal Prices used for LOM Base Case

                         
    2010     2011     2012     2013  
Silver (US$/oz)   16.42     16.38     14.38     13.46  
Lead (US$/lb)   0.80     0.78     0.69     0.61  
Zinc (US$/lb)   0.82     0.91     0.86     0.82  
Gold (US$/oz)   1,067.00     1,092.00     942.00     883.00  
Cdn$/US$   0.92     0.92     0.92     0.92  

The payback period is defined as the time required after revenue is first received in Year 1 to achieve break-even cumulative cash flow. For this project, the payback period for the base case is approximately 0.5 years. The payback period is based on the annual un-discounted cash flows. There is no consideration for inflation, interest, or depreciation in this calculation.

Conclusions

The following conclusions have been made regarding the Bellekeno Project:

  • The testwork results indicate that the tested mineralization responds well to conventional lead/zinc differential flotation process with a cyanide-free zinc mineral suppression regime.


- 20 -

  • Silver and lead minerals associate intimately and will be recovered together to produce a silver-lead bulk concentrate, and zinc minerals will be concentrated into a separate zinc concentrate.

  • The historic underground workings at the Bellekeno mine have been extensively examined and in general remain in very good condition.

  • Based on the mining context of the deposit, a suitable mining method is mechanized overhand cut-and-fill in 3.5 m lifts.

  • An efficient means of backfilling will be the use of a cemented blend of development waste rock and dry (filtered) tailings back hauled from the process plant. Both materials are available in abundant quantities to meet the mine backfill requirements.

  • The deposit contains multi-metals and two metal concentrates will be produced on site. For this reason mine planning must be based on NSR values.

  • Alexco will operate the mine on the basis of contractor mining. The planned mine operating schedule is two 11-h shifts per day, 7 d/wk.

  • SRK concludes that the planned mine will achieve a production rate of 250 t/d over a 3.6-year mine life.

  • Scheduling indicates the mine will be ready to start production at 250 t/d by late June 2010.

  • The most significant mine related risks are geotechnical, related to weak and challenging conditions that may be locally encountered in stoping.

  • The most significant mine opportunity is the potential to increase the mine life as a result of exploration and/or higher metal prices.

  • Providing that the set out design criteria and assumptions are satisfied, there is a strong indication that the project is commercially viable.

  • Structural and stratigraphic studies, as well as extensive drilling of the Bellekeno deposit has resulted in a number of resource expansion and exploration targets in areas within and immediately adjacent to the existing minable resource. It is recommended that these targets be ranked in order of priority and drilling of initial targets adjacent to existing or planned underground infrastructure in the SW, 99, and Upper East be coordinated with pre-production mine development work.

Elsa Tailings Property

The Corporation’s 100% owned Elsa Tailings property comprises 8 surveyed quartz mining leases in the Keno Hills district and is located approximately 400 meters northwest of the Elsa town site and the former UKHM mill. The historical impounded tailings extend over an area of approximately 100 hectares and are contained behind a series of low level dam structures. Historical milling operations at Elsa, which started in the 1930’s and operated almost continuously until 1988, produced a lead concentrate, and periodically a zinc concentrate. The tailings consist of unconsolidated fine sand to silty grained material, with sieve analyses indicating that the material is all finer than 250 microns with as much as 40 percent being less than 74 microns (200 mesh).


- 21 -

The dominant minerals making up the tailings fragments are quartz and siderite (80 percent), with the balance composed of muscovite, other silicate minerals and pyrite. As reported in the news release dated May 6, 2010 entitled “Alexco Announces Initial Elsa Tailings Resource Estimate, Keno Hill”, an indicated resource for the Elsa Tailings has so far been defined estimated at 2,490,000 tonnes grading 119 grams per tonne silver, 0.12 grams per tonne gold, 0.99% lead and 0.70% zinc. This resource estimate is supported by a technical report filed on SEDAR dated June 16, 2010 and entitled “Mineral Resource Estimation, Elsa Tailings Project, Yukon, Canada”. The estimate has been prepared by SRK under the responsibility of G. David Keller, P.Geo., an Independent Qualified Person as defined by NI 43-101, in conformity with generally accepted CIM Estimation of Mineral Resource and Mineral Reserve Best Practices Guidelines. The resource estimate may be affected by further infill and exploration drilling that may result in increases or decreases in subsequent resource estimates. The resource estimate may also be affected by subsequent assessments of mining, environmental, processing, permitting, taxation, socio-economic and other factors.

The detailed disclosure contained in the technical report is hereby incorporated by reference, and the summary section from that report is reproduced as follows.

Executive Summary

Introduction

The Elsa Tailings Project is an advanced project exploring the mineral potential of historical tailings from the former United Keno Hill Mines (“UKHM”) mill located in the town of Elsa, Yukon. The Elsa tailings are impounded on the south-eastern slopes of the McQuesten River valley approximately 400 metres from the UKHM mill

Milling operations at Elsa started in the 1930s and continued almost without interruption until 1988. Historical production records indicate that approximately 4,050,000 tons of tailings were deposited at the Elsa site. Historical resource estimates on the Elsa Tailings Project were made by UKHM in 1970 and 1988.

On June 29, 2009 SRK Consulting (Canada) Inc. (“SRK”) was commissioned by Alexco Resource Corporation (“Alexco”) to prepare a mineral resource estimate for the Elsa Tailings Project. The resource herein represents a first resource estimate for the deposit prepared for Alexco.

This technical report documents the resource model constructed by SRK. It was prepared following the guidelines of the Canadian Securities Administrators’ National Instrument 43-101 and Form 43-101F1, and in conformity with generally accepted CIM “Estimation of Mineral Resources and Mineral Reserves Best Practice Guidelines.”

Property Description and Agreements

The land under the control of Alexco comprises 717 surveyed quartz mining leases, 864 unsurveyed quartz mining claims, and two crown grants. The total area approximates 24,300 hectares. Certain UKHM claims may be subject to unknown or unregistered royalties and/or agreements.

Quartz mining leases provide mineral title to the area occupied by the tailings and are part of a large land package controlled by Alexco through its subsidiaries, Elsa Reclamation and Development Co. (“ERDC”) and Alexco Keno Hill Mining Corp. The tailings are located on Quartz Leases: Orchid 1, 3, 15, 26, 31 & 37; Betty and Mud.


- 22 -

Alexco’s rights to much of the Keno Hill property are held through the ERDC, a wholly owned subsidiary. In June 2005, PriceWaterhouseCoopers LLP (“PWC”), a court appointed interim receiver and receiver-manager of United Keno Hill Mines Limited and UKH Minerals Limited (collectively “UKHM”), selected Alexco as the preferred purchaser of the assets of UKHM. In February 2006, following negotiation of a Subsidiary Agreement between the Government of Canada, the Government of Yukon, and Alexco, the Supreme Court of Yukon approved the purchase of the assets of UKHM by Alexco through its wholly owned subsidiary, ERDC. The UKHM assets comprised two Crown Grants, 674 mining leases, 289 mineral claims, an ore concentration plant, various buildings and equipment, as well as partial ownership interest in three mining leases, 36 mineral claims, in addition to a leasehold interest in one mineral claim. PWC and Alexco entered into an agreement (the “Purchase Agreement”) dated August 4, 2005, as amended on November 2, 2005 and January 31, 2006. Alexco assigned the Purchase Agreement to its wholly owned subsidiary ERDC on February 6, 2006. “Interim Closing” of the UKHM transaction was completed on April 18, 2006. Alexco assumed responsibility for care and maintenance operations at the UKHM property. On November 30, 2006, Alexco terminated a contract with a local contractor and started conducting operations utilizing its own employees and equipment. Title to all UKHM assets was transferred to Alexco (“Final Closing”) in November 2007, following the approval of a “Type B” Water License by the Yukon Water Board.

All quartz mining leases have been legally surveyed whereas the quartz mining claims have not. In addition, in 2006 and 2007, 650399 BC Ltd., a wholly owned Alexco subsidiary, staked 673 mineral claims (full size and fractional) adjacent to and contiguous with the UKHM property and purchased 36 quartz claims and 37 quartz mining leases from a third party. In 2008 and 2009, Alexco took four existing claims to lease, acquired an additional 18 claims from a third party, and amalgamated 55 additional existing bordering claims into the holdings. Mineral exploration at Keno Hill was initially permitted under the terms and conditions set out by the Yukon Government in the Class III Quartz Mining Land Use Permit – LQ00186, issued on July 5, 2006 and valid until July 4, 2011. Alexco subsequently obtained a Class IV Quartz Mining Land Use Permit – LQ00240 on June 17, 2008. The two permits were amalgamated on December 8, 2008 under #LQ00240 which is valid until December 16, 2018.

Under the terms of a legal agreement with the Government of Canada and the Government of Yukon, Alexco is indemnified from any and all environmental liability that may be presented by the historic tailings. However, if Alexco were to nominate any part of the tailings as a production unit under the above agreement, responsibility for addressing water- related environmental liabilities would fall to Alexco.

Location Access and Physiography

The Elsa Tailings Project is included within the historic Keno Hill mining camp, located in central Yukon. The closest town is Mayo, located on the Stewart River, about 45 kilometres to the south. Mayo is accessible from Whitehorse via a 407 kilometre all weather road; the town is also serviced by Mayo airport, which is located just to the north. A gravel all-weather road leads from Mayo to the project areas. Historically, the mining camp was linked by river route to the outside world; since 1950, the all-weather highway, which was also used for transporting the ore, has been the main link.


- 23 -

The Keno Hill area is characterized by rolling hills and mountains with relief up to 1200 metres. Slopes are generally gentle with steeper slopes on the north sides of Keno Hill and Sourdough Hill. The Elsa Tailings are located on the south slope of the McQuesten valley centred along the Flat and Porcupine Creek drainages.

History

Milling operations at Elsa started in the 1930s, operating almost continuously until 1988. A lead concentrate with a periodic zinc concentrate was produced from milling operations. A cyanide leach circuit was added in 1958 and operated periodically to 1981 depending on prevailing economics.

It is estimated that in total approximately 4,050,000 tons of tailings were deposited at the Elsa site. Most of this material was allowed to run out onto the flank of the adjacent valley without engineered impoundment. The original ground surface was covered with small trees, brush and a vegetative mat of moss, all of which was eventually covered by the tailings.

The northern portion of the tailings was drilled by UKHM in 1970 and in a second drilling campaign from 1987 to 1988 covering the rest of the tailings area at that time. Metallurgical testing of the tailings was undertaken in 1988 and 1995 by UKHM and a joint venture between UKHM and government agencies.

Regional and Local Geology

The tailings lie on the south slope of the McQuesten valley. The rounded out shape of the valley can be attributed to at least one episode of glaciation followed by the deposition of glaciofluvial sands and gravels related to kame terraces. The glaciofluvial sands and gravels were deposited at higher valley elevations with till deposited at lower valley sides and valley bottoms. During the retreat of glacial ice the McQuesten valley bottom was covered by a shallow lake resulting in the deposition of lacustrine silt. The lacustrine silt became increasingly organic and transitioned to peat as the glacial lake became in filled with sediments.

The Elsa Tailings cover an irregular area of approximately 130 hectares and range from 0.1 to over 4 metres in thickness. While the valley flank on which the tailings have been deposited is relatively smooth topographically, points of higher elevation occur as uncovered “islands” within the body of the tailings. The earliest site of tailings deposition appears to have been directly into Porcupine Creek with the material being mostly flushed downstream into Flat Creek. Beginning in 1946, tailings were directed away from the creeks producing small terraced accumulations immediately below the mill. Somewhat later a pipeline was constructed that discharged tailings further into the valley in the area between Porcupine and Flat Creek. Ten major mines supplied feed to the Elsa Mill during its operation in the 1930s through 1950s.From the 1960s to 1980s ore was processed by the mill underwent a transition from high grade mineralization to lower grade mineralization from small open pits and underground operations.

Deposit Type and Mineralization

The tailings consist of generally unconsolidated silty fine grained sand with minor medium sand grained material, of a variable grey to light brown colour characterized by thin beds to laminae. Detailed mineralogical examination shows that the sand grains are angular and locally aggregated and cemented by limonite. The dominant minerals are quartz and siderite (80 percent) with the balance composed of muscovite and other silicate minerals along with pyrite. Occasional grains contain lead and zinc sulphides and trace amounts of lead and zinc oxide minerals have been identified.


- 24 -

Drilling

UKHM initially carried out a percussion drilling program targeting the thicker northern portion of the tailings in 1970. A total of 114 vertical drill holes were drilled to an average depth of three metres. Drill hole spacing was reported at approximately 60 metres. From 1987 to 1988 a second drilling program was completed by UKHM using a rotary drill for a total of 379 vertical holes (1,770 metres). Alexco and SRK examined historical data and methodologies associated with these programs and conclude that UKHM drilling data were too unreliable to be used for resource evaluation and classification according to CIM best practice guidelines.

Alexco drilled 283 vertical sonic drill holes over the deposit in 2009 for a total of 910 drilled metres. The Alexco drilling campaign consisted of drill holes spaced at 50 metres with lines orientated at an azimuth of 45 degrees. Average thickness of the tailings is 2.3 metres ranging from a maximum thickness of 7.5 metres to a minimum of 0.2 metres.

Tailings core material is inherently difficult to handle as it is unconsolidated and, in some cases, is saturated with water. Because of the nature of the core material some challenges in core recovery, logging and sample collection exist. SRK is of the opinion that the drilling and sampling performed by Alexco was conducted with care and that the location and handling of the core yielded reasonable samples.

Sampling Method, Approach and Analyses

Drill core was sampled generally at each run length of 1.5 metres or to the lower tailings contact. The entire core was sampled to provide a known volume for density measurements. Sampled core intervals were placed in polyethylene bags secured with “zip ties.”

All samples were analyzed by the ISO 9001 accredited ALS Chemex laboratory in North Vancouver, British Columbia. Upon receipt, samples were placed under ovens for high temperature drying and weighed when dry. Following splitting and pulverization samples were analyzed using inductively coupled plasma-atomic emission spectrometry using a four acid digestion. Thirty three elements including silver, lead and zinc were analyzed using this method. Gold assays were analyzed using fire assay with atomic absorption spectrometry.

Quality control samples were placed systematically into the sample stream. Every 20 samples contained at least one blank sample, one standard of known value, and one request for a duplicate assay of the previous sample.

The dry density for each of the 2009 sonic drill samples was determined for each of the assayed cores. Dry density was calculated using the dry weight of the sample from the assay laboratory divided by the drilled interval volume which was based on sampled interval length and the inside diameter of the core tube.

Data Verification

SRK compared 10 percent of the drill hole data assays to original assay certificates. No errors were found in the drill hole assay data base. During the site visit, SRK examined three pits and briefly logged the pit walls of three trenches. SRK also reviewed drill core photos for the sampling program.


- 25 -

Mineral Resource Estimation

Resources were estimated based on 283 drill holes from the 2009 Alexco sonic drilling program. The data set comprises 546 sampled intervals with silver, lead, zinc and gold assays.

A wireframe model of the tailings body was generated by Alexco using high resolution topographic surveys and tailings/sub-surface contacts from the drilling program.

Based on tailings assays the tailings area was subdivided into five domains: A low grade silver-lead, low grade gold, high grade silver-lead, high grade gold, and a zinc-specific gravity domain. A sixth separate domain was created for an isolated area away from the main tailings impoundment.

All tailings drill holes were composited to 1.5 metre intervals from top to bottom with a minimum composite length of 0.20 metres to allow for thin portions of the tailings impoundment. A review of composite statistics and cumulative frequency plots for the metal assays domains indicates that it is not necessary to cap high grade values within the drill hole composites.

Specific gravity composites average 1.7 with a significant dispersion of values ranging from 0.4 to 4.6. Specific gravity composites were capped at a high value of 4.0 and low value of 0.75 for resource estimation.

Variography was undertaken to characterize the spatial continuity of the metal grade data within each resource domain and to determine appropriate grade interpolation ranges. Variograms were developed for four domains including gold, silver, lead, zinc and specific gravity composites. Two structure variograms were developed for each variable in the X and Y directions only. The relatively narrow depth of the tailings precluded development of variograms in the Z direction. Variograms for the high domains with insufficient composites to determine variogram models were assumed to be the same as for low grade domains. Datamine Studio 3 was used to develop a sub-blocked model for the deposit.

Metal grades and specific gravity were estimated in the block model using ordinary kriging for each of the separate domains and estimate variables. Only one estimation pass was made.

Estimation was verified by visual comparison of composited drill holes, cross-validation and estimation of resources using inverse distance squared and nearest neighbour routines at no cut-off.

While drilling and sampling procedures, tightly spaced drilling, and assay results provide a high level of confidence, the inherent challenges related to drilling and sampling unconsolidated material are reflected in significant outliers in specific gravity determinations. These outliers could not be fully explained by expected specific gravity ranges or measurable sampling errors. For this reason SRK is of the opinion that it is appropriate to classify the Elsa Tailings resource blocks as Indicated. This is because the estimates are based on detailed and reliable exploration and testing information gathered through appropriate techniques that are spaced closely enough for geological and grade continuity to be reasonably assumed.


- 26 -

Mineral Resources Statement

Mineral Resources for the Elsa Tailings Project have been estimated at 2.49 million tonnes at 119 grams of silver per tonne (“gpt silver”) , 0.12 gpt gold, 0.99 percent lead, and 0.70 percent zinc at a 50 gpt silver cut-off grade. The Mineral Resource Statement for the Elsa Tailings deposit is tabulated in Table i.

Table i. Mineral Resource Statement* for the Elsa Tailings Project, SRK Consulting, May 6, 2010.

  Category   Quantity     Grade     Contained Metal  
            Ag     Au     Pb     Zn     Ag     Au  
      [Tonnes]     [gpt]     [gpt]     [%]     [%]     [oz]     [oz]  
  Indicated   2,490,000     119.0     0.12     0.99     0.70     9,526,000     9,600  

  *

Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures have been rounded to reflect the relative accuracy of the estimates. Includes all blocks in the block model and effectively reported at a 50 gpt silver cut-off grade assuming metal prices of US$17 per troy ounce silver and US$1,000 per troy ounce gold, silver recovery of 85% and gold recovery of 35%. Lead and zinc values are not considered.

Mineral Resources for the Elsa Tailings Project have been classified according to the “CIM Standards on Mineral Resources and Reserves: Definition and Guidelines” (December, 2005) by Mr. G. David Keller, P. Geo (#1235) an “Independent Qualified Person” as defined by National Instrument 43-101.

Interpretation and Conclusions

Six domains were generated by SRK to separate high grade zones for silver, lead and gold. An additional domain was generated for a geographically distinct tailings area that is physically separate from the main tailings. Metal grades were estimated separately for each domain using ordinary kriging. Capping was not applied to metal assays or composites. Dry specific gravity composites were capped using a lowest and highest capping value.

After validation and classification, SRK used silver and gold grades to determine “reasonable prospects for economic extraction.” The basis of this determination was metal grades, heap leach recoveries and estimated mining and processing costs from comparable projects.

The mineral resource statement prepared by SRK is reported at silver cut-off grades of 50 gpt, which are based on the likely extraction scenario. All material in the resource estimate is above this grade.

Recommendations

It is SRK’s opinion that resources for the Elsa Tailings Project have been defined to sufficient accuracy to support the preparation of a Preliminary Economic Assessment (“PEA”). Alexco has embarked on extensive metallurgical test work to document the metallurgical properties of the tailings material and evaluate appropriate processing options. This aspect is critical for the PEA study. Untested areas containing additional tailings are known to occur peripherally to the current resource area. These zones offer potential to increase the current resource and are recommended for exploration sampling. Estimated costs for the recommended programs are summarized in Table ii.


- 27 -

Table ii. Estimated Costs of Recommended Programs.

Program   Cost [CD$]  
Preliminary Economic Assessment $ 200,000  
Drilling Program $ 50,000  
Total $ 250,000  

Environmental Consulting Services

General

The Corporation’s environmental consulting services division, AEG, is in the business of managing risk and unlocking value at mature, closed or abandoned sites through integration and implementation of the Corporation's core competencies, which include management of environmental services, implementation of innovative treatment technologies, execution of site reclamation and closure operations, and, if appropriate, rejuvenation of exploration and development activity. The Corporation’s principal markets for these services are in Canada, the United States and the Americas, with the Canadian market serviced primarily through Access and ERDC, the U.S. market through Alexco US, and the balance of the Americas through either Access or Alexco US. The Corporation provides its services to a range of industrial sectors, but with a particular focus on current and former mine sites.

The Corporation offers its clients a unique combination of environmental remediation expertise in the area of site reclamation and closure, an ability to manage complex permitting and regulatory programs on a turnkey basis, and strong operations management. In addition, the Corporation seeks to strategically leverage off its environmental consulting services group, accessing opportunities to enhance asset value through effective liability risk management and efficient site operations. This is accomplished through unlocking potential exploration and development opportunities at contaminated or abandoned sites through cost effective and responsible environmental remediation and liability transfer.

The Corporation executes its environmental consulting services business plan by using and applying the intellectual property assets, including the Patents, and the specialized skill sets and knowledge it maintains in-house. While there are a significant number of firms providing environmental consulting services in North America, these assets, skill sets and knowledge provide Alexco with a strong competitive advantage. Consolidated revenues from environmental consulting services in the year ended June 30, 2010 totaled $4,641,000, compared to $5,818,000 in the year preceding. During the 2010 fiscal year, the Corporation recorded revenues from one customer representing 10% or more of total revenue, in the amount of $1,971,000. In 2009, the Corporation had two customers representing 10% or more of total revenue, in the amounts of $3,181,000 and $926,000 respectively. The Corporation’s largest single customer is Government, with a substantial component of Government revenues earned from the Federal Government’s Indian and Northern Affairs Canada.

Keno Hill Project

As described above (see “General Development of the Business – Three Year History and Significant Acquisitions”), under the Subsidiary Agreement, Alexco’s subsidiary ERDC is retained through Government as a paid contractor responsible on a continuing basis for the environmental care and maintenance and ultimate closure reclamation of the former UKHM properties.

The Subsidiary Agreement provides that ERDC is responsible for the development of the ultimate closure reclamation plan for fees of 65% of agreed scheduled rates, and this plan development is currently ongoing. Upon acceptance and regulatory approval, the closure reclamation plan will be implemented by ERDC at agreed commercial contractor rates.


- 28 -

During the period required to develop the plan, ERDC is responsible for carrying out the environmental care and maintenance at various sites within the UKHM properties, for a fixed annual fee adjusted each year for certain operating and inflationary factors and determined on a site-by-site basis. The portion of the annual fee amount so determined which is billable by ERDC in respect of each site will reduce by 15% each year until all site-specific care and maintenance activities have been replaced by closure reclamation activities; provided however that should a closure reclamation plan be prepared but not accepted and approved, the portion of annual fees billable by ERDC will revert to 85% until the Subsidiary Agreement is either amended or terminated. ERDC receives agreed commercial contractor rates when retained by government to provide consulting services in the Keno Hill district outside the scope of the Subsidiary Agreement.

Risk Factors

The Corporation faces a number of significant risk factors related to its business activities, which are discussed in greater detail below. Such risk factors could materially affect the Corporation's future financial results, and could cause events to differ materially from those described in forward-looking statements relating to the Corporation. While the significant risk factors which the Corporation believes it faces are discussed below, they do not comprise a definitive list of all risk factors related to the Corporation's operations.

Exploration and Development

Mineral exploration and development involves a high degree of risk and few properties which are explored are ultimately developed into producing mines. With respect to Alexco's properties, should any ore reserves exist, substantial expenditures will be required to confirm ore reserves which are sufficient to commercially mine, and to obtain the required environmental approvals and permitting required to commence commercial operations. Should any mineral resource be defined on such properties there can be no assurance that the mineral resource on such properties can be commercially mined or that the metallurgical processing will produce economically viable and saleable products. The decision as to whether a property contains a commercial mineral deposit and should be brought into production will depend upon the results of exploration programs and/or technical studies, and the recommendations of duly qualified engineers and/or geologists, all of which involves significant expense. This decision will involve consideration and evaluation of several significant factors including, but not limited to: (1) costs of bringing a property into production, including exploration and development work, preparation of appropriate technical studies and construction of production facilities; (2) availability and costs of financing; (3) ongoing costs of production; (4) market prices for the minerals to be produced; (5) environmental compliance regulations and restraints (including potential environmental liabilities associated with historical exploration activities); and (6) political climate and/or governmental regulation and control.

The ability of Alexco to sell, and profit from the sale of any eventual production from any of Alexco's properties will be subject to the prevailing conditions in the marketplace at the time of sale. Many of these factors are beyond the control of Alexco and therefore represent a market risk which could impact the long term viability of Alexco and its operations.

Figures for the Corporation's Resources are Estimates Based on Interpretation and Assumptions and May Yield Less Mineral Production Under Actual Conditions than is Currently Estimated

In making determinations about whether to advance any of its projects to development, the Corporation must rely upon estimated calculations as to the mineral resources and grades of mineralization on its properties. Until ore is actually mined and processed, mineral resources and grades of mineralization must be considered as estimates only.


- 29 -

Mineral resource estimates are imprecise and depend upon geological interpretation and statistical inferences drawn from drilling and sampling which may prove to be unreliable. Alexco cannot be certain that:

  • reserve, resource or other mineralization estimates will be accurate; or
  • mineralization can be mined or processed profitably.

Any material changes in mineral resource estimates and grades of mineralization will affect the economic viability of placing a property into production and a property’s return on capital. The Corporation's resource estimates have been determined and valued based on assumed future prices, cut-off grades and operating costs that may prove to be inaccurate. Extended declines in market prices for silver and other metals may render portions of the Corporation’s mineralization uneconomic and result in reduced reported mineral resources.

Keno Hill District

While Alexco has conducted exploration activities in the Keno Hill district, other than with respect to the Bellekeno property, further review of historical records and additional exploration and geological testing will be required to determine whether any of the mineral deposits it contains are economically recoverable. There is no assurance that such exploration and testing will result in favourable results. The history of the Keno Hill district has been one of fluctuating fortunes, with new technologies and concepts reviving the district numerous times from probable closure until 1989, when it did ultimately close down for a variety of economic and technical reasons. Many or all of these economic and technical issues will need to be addressed prior to the commencement of any future production on the Keno Hill properties.

Under the terms of the Subsidiary Agreement, ERDC is responsible for carrying out the environmental care and maintenance activities at various sites in the Keno Hill district during the period required to develop and obtain acceptance and regulatory approval for the Keno Hill district closure reclamation plan, for annual fees based on an annually-determined fixed fee benchmark adjusted each year for certain operating and inflationary factors and determined on a site-by-site basis. The portion of the annually-determined fee benchmark which is billable each year by ERDC in respect of each site will reduce by 15% each year until all site-specific care and maintenance activities have been replaced by closure reclamation activities. Alexco could incur significant costs over the period it undertakes such care and maintenance activities, particularly if acceptance and approval of the closure reclamation plan and commencement of reclamation activities should be significantly delayed.

Construction and Operation of the Bellekeno Mine

The decision by the Corporation to proceed with the construction and development of the Bellekeno mine was based on the Development Plan, which included estimates for metal production and capital and operating costs. Until mined and processed, no assurance can be given that such estimates will be achieved. Failure to achieve these production and capital and operating cost estimates or material increases in costs could have an adverse impact on the Corporation’s future cash flows, profitability, results of operations and financial condition. The Corporation’s actual production and capital and operating costs may vary from estimates for a variety of reasons, including: actual resources mined varying from estimates of grade, tonnage, dilution and metallurgical and other characteristics; short-term operating factors relating to the mineable resources, such as the need for sequential development of resource bodies and the processing of new or different resource grades; revisions to mine plans; risks and hazards associated with mining; natural phenomena, such as inclement weather conditions, water availability, floods and earthquakes; and unexpected labour shortages or strikes. Costs of production may also be affected by a variety of factors, including changing waste ratios, metallurgical grades, labour costs, commodity costs, general inflationary pressures and currency rates.


- 30 -

Permitting and Environmental Risks and Other Regulatory Requirements

The current or future operations of Alexco, including development activities, commencement of production on its properties and activities associated with Alexco's mine reclamation and remediation business, require permits or licenses from various federal, territorial and other governmental authorities, and such operations are and will be governed by laws, regulations and agreements governing prospecting, development, mining, production, taxes, labour standards, occupational health, waste disposal, toxic substances, land use, environmental protection, mine safety and other matters. Companies engaged in the development and operation of mines and related facilities and in mine reclamation and remediation activities generally experience increased costs and delays as a result of the need to comply with the applicable laws, regulations and permits. There can be no assurance that all permits which Alexco may require for the conduct of its operations will be obtainable on reasonable terms or that such laws and regulations would not have an adverse effect on any project which Alexco might undertake, including but not limited to the Bellekeno mine project.

Failure to comply with applicable laws, regulations and permitting requirements may result in enforcement actions including orders issued by regulatory or judicial authorities causing operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment or remedial actions. Parties engaged in mining operations or in mine reclamation and remediation activities may be required to compensate those suffering loss or damage by reason of such activities and may have civil or criminal fines or penalties imposed upon them for violation of applicable laws or regulations.

Amendments to current laws, regulations and permits governing operations and activities of mining companies and mine reclamation and remediation activities could have a material adverse impact on Alexco. As well, policy changes and political pressures within and on federal, territorial and First Nation governments having jurisdiction over or dealings with Alexco could change the implementation and interpretation of such laws, regulations and permits, also having a material adverse impact on Alexco. Such impacts could result in one or more of increases in capital expenditures or production costs, reductions in levels of production at producing properties or abandonment or delays in the development of new mining properties.

Environmental Consulting Services

A material decline in the level of activity or reduction in industry willingness to spend capital on mine reclamation, remediation or environmental services could adversely affect demand for Alexco's consulting services. Likewise, a material change in mining product commodity prices, the ability of mining companies to raise capital or changes in domestic or international political, regulatory and economic conditions could adversely affect demand for Alexco's services

Two of Alexco's customers accounted for a combined 53% of revenues in the 2010 fiscal year. The loss of, or a significant reduction in the volume of business conducted with, this customer could have a significant detrimental effect on Alexco's environmental consulting services business.

The patents which Alexco owns or has access to or other proprietary technology may not prevent Alexco's competitors from developing substantially similar technology, which may reduce Alexco's competitive advantage. Similarly, the loss of access to any of such patents or other proprietary technology or claims from third parties that such patents or other proprietary technology infringe upon proprietary rights which they may claim or hold would be detrimental to Alexco's reclamation and remediation business.

Alexco may not be able to keep pace with continual and rapid technological developments that characterize the market for Alexco's mine reclamation and remediation services and Alexco's failure to do so may result in a loss of its market share. Similarly, changes in existing regulations relating to mine reclamation and remediation activities could require Alexco to change the way it conducts its business.


- 31 -

Potential Profitability Of Mineral Properties Depends Upon Metal Prices and Other Factors Beyond the Control of Alexco

The potential profitability of mineral properties is dependent upon many factors beyond Alexco's control. For instance, world prices of and markets for gold, silver, lead and zinc are unpredictable, highly volatile, potentially subject to governmental fixing, pegging and/or controls and respond to changes in domestic, international, political, social and economic environments. Another factor is that rates of recovery of mined ore may vary from the rate experienced in tests and a reduction in the recovery rate will adversely affect profitability and, possibly, the economic viability of a property. Profitability also depends on the costs of operations, including costs of labour, equipment, electricity, environmental compliance or other production inputs. Such costs will fluctuate in ways Alexco cannot predict and are beyond Alexco's control, and such fluctuations will impact on profitability and may eliminate profitability altogether. Additionally, due to worldwide economic uncertainty, the availability and cost of funds for development and other costs have become increasingly difficult, if not impossible, to project. These changes and events may materially affect the financial performance of Alexco.

First Nation Rights and Title

The nature and extent of First Nation rights and title remains the subject of active debate, claims and litigation in Canada, including in the Yukon and including with respect to intergovernmental relations between First Nation authorities and federal, provincial and territorial authorities. There can be no guarantee that such claims will not cause permitting delays, unexpected interruptions or additional costs for Alexco's projects.

Title to Mineral Properties

The acquisition of title to mineral properties is a complicated and uncertain process. The properties may be subject to prior unregistered agreements of transfer or land claims, and title may be affected by undetected defects. Alexco has taken steps, in accordance with industry standards, to verify mineral properties in which it has an interest. Although Alexco has made efforts to ensure that legal title to its properties is properly recorded in the name of Alexco, there can be no assurance that such title will ultimately be secured.

Capitalization and Commercial Viability

Alexco will require additional funds to further explore, develop and mine its properties. Alexco has limited financial resources, and there is no assurance that additional funding will be available to Alexco to carry out the completion of all proposed activities, for additional exploration or for the substantial capital that is typically required in order to place a property into commercial production. In addition, while Alexco intends to draw upon the remaining US$35 million Silver Wheaton deposit amount to fund the construction and development of the Bellekeno mine, there remains a risk that Silver Wheaton will be unable or unwilling to pay such funds. Although Alexco has been successful in the past in obtaining financing through the sale of equity securities, there can be no assurance that Alexco will be able to obtain adequate financing in the future or that the terms of such financing will be favourable. Failure to obtain such additional financing could result in the delay or indefinite postponement of further exploration and development of its properties.

General Economic Conditions May Adversely Affect Alexco’s Growth and Profitability

The unprecedented events in global financial markets since 2008 have had a profound impact on the global economy and led to increased levels of volatility. Many industries, including the mining industry, are impacted by these market conditions.


- 32 -

Some of the impacts of the current financial market turmoil include contraction in credit markets resulting in a widening of credit risk, devaluations and high volatility in global equity, commodity, foreign exchange and precious metal markets, and a lack of market liquidity. If the current turmoil and volatility levels continue they may adversely affect Alexco's growth and profitability. Specifically:

  • a global credit/liquidity crisis could impact the cost and availability of financing and Alexco's overall liquidity;

  • the volatility of silver prices would impact Alexco's revenues, profits, losses and cash flow;

  • volatile energy prices, commodity and consumables prices and currency exchange rates would impact Alexco's operating costs; and

  • the devaluation and volatility of global stock markets could impact the valuation of Alexco's equity and other securities.

These factors could have a material adverse effect on Alexco's financial condition and results of operations.

Operating Hazards and Risks

In the course of exploration, development and production of mineral properties, certain risks, particularly including but not limited to unexpected or unusual geological operating conditions including rock bursts, cave-ins, fires, flooding and earthquakes, may occur. It is not always possible to fully insure against such risks and Alexco may decide not to insure against such risks as a result of high premiums or other reasons. Should such liabilities arise, they could reduce or eliminate any future profitability and result in increasing costs and a decline in the value of the securities of Alexco.

Adverse weather conditions could also disrupt Alexco's mine reclamation and remediation business and/or reduce demand for Alexco's services.

Competition

Significant and increasing competition exists for mining opportunities internationally. There are a number of large established mining companies with substantial capabilities and far greater financial and technical resources than Alexco. Alexco may be unable to acquire additional attractive mining properties on terms it considers acceptable and there can be no assurance that Alexco's exploration and acquisition programs will yield any new reserves or result in any commercial mining operation.

Certain of the Corporation’s Directors and Officers are Involved with Other Natural Resource Companies, Which May Create Conflicts of Interest from Time to Time

Some of Alexco's directors and officers are directors or officers of other natural resource or mining-related companies. These associations may give rise to conflicts of interest from time to time. As a result of these conflicts of interest, Alexco may miss the opportunity to participate in certain transactions.

The Corporation May Fail to Maintain Adequate Internal Control Over Financial Reporting Pursuant to the Requirements of the Sarbanes-Oxley Act.

Section 404 of the Sarbanes-Oxley Act (“SOX”) requires an annual assessment by management of the effectiveness of the Corporation's internal control over financial reporting. The Corporation may fail to maintain the adequacy of its internal control over financial reporting as such standards are modified, supplemented or amended from time to time, and the Corporation may not be able to ensure that it can conclude, on an ongoing basis, that it has effective internal control over financial reporting in accordance with Section 404 of SOX. The Corporation's failure to satisfy the requirements of Section 404 of SOX on an ongoing, timely basis could result in the loss of investor confidence in the reliability of its financial statements, which in turn could harm the Corporation's business and negatively impact the trading price or the market value of its securities.


- 33 -

In addition, any failure to implement required new or improved controls, or difficulties encountered in their implementation, could harm the Corporation's operating results or cause it to fail to meet its reporting obligations. Future acquisitions of companies, if any, may provide the Corporation with challenges in implementing the required processes, procedures and controls in its acquired operations. No evaluation can provide complete assurance that the Corporation's internal control over financial reporting will detect or uncover all failures of persons within the Corporation to disclose material information otherwise required to be reported. The effectiveness of the Corporation's processes, procedures and controls could also be limited by simple errors or faulty judgments. Although the Corporation intends to expend substantial time and incur substantial costs, as necessary, to ensure ongoing compliance, there is no certainty that it will be successful in complying with Section 404 of SOX.

DIVIDENDS

The Corporation has not paid any dividends on its common shares since its incorporation. Any decision to pay dividends on common shares in the future will be made by the board of directors on the basis of the earnings, financial requirements and other conditions existing at such time.

DESCRIPTION OF CAPITAL STRUCTURE

The authorized capital of the Corporation consists of an unlimited number of common shares, without par value.

There are no special rights or restrictions of any nature attached to any of the common shares, which all rank equally as to all benefits which might accrue to the holders of the common shares.

MARKET FOR SECURITIES

Trading Price and Volume

The common shares of the Corporation are listed and posted for trading on the TSX under the symbol “AXR”, and on the AMEX under the symbol “AXU”. The following tables set forth the market price range and trading volumes of the Corporation’s common shares on each of the TSX and AMEX for the periods indicated.


- 34 -

TSX

Period   Volume     High (C$)     Low (C$)  
June 2010   1,940,300     $3.58     $3.12  
May 2010   2,992,800     $4.00     $2.93  
April 2010   4,378,700     $4.10     $3.47  
March 2010   2,874,100     $3.55     $3.36  
February 2010   2,443,100     $3.49     $3.10  
January 2010   4,380,500     $4.00     $3.14  
December 2009   2,324,300     $4.45     $2.87  
November 2009   2,046,900     $3.07     $2.66  
October 2009   1,747,100     $3.15     $2.53  
September 2009   1,037,200     $2.91     $2.25  
August 2009   471,300     $2.39     $2.05  
July 2009   761,800     $2.34     $1.98  

AMEX

Period   Volume     High (US$)     Low (US$)  
June 2010   3,091,300     $3.49     $2.97  
May 2010   6,134,700     $3.94     $2.79  
April 2010   4,660,100     $4.09     $3.44  
March 2010   3,832,300     $3.55     $3.21  
February 2010   2,711,700     $3.35     $2.88  
January 2010   4,359,100     $3.99     $2.95  
December 2009   6,689,982     $3.98     $2.75  
November 2009   3,302,066     $2.95     $2.28  
October 2009   4,055,297     $3.50     $2.35  
September 2009   3,719,785     $2.79     $2.05  
August 2009   1,537,713     $2.40     $1.85  
July 2009   2,015,638     $2.1599     $1.72  


- 35 -

Securities Not Listed or Quoted

The only classes of securities of the Corporation that are not listed or quoted on a marketplace are its stock options. During the fiscal year ended June 30, 2010, stock options and warrants were issued as follows:

Date of Issuance Class of Security Number Issued Issuing Price per Security
July 22, 2009 Stock Options 50,000 $1.34
November 16, 2009 Stock Options 20,000 $1.69
March 22, 2010 Stock Options 1,182,000 $1.97

The issuing price per security is the fair value of that security as estimated by the Corporation based on the Black-Scholes option pricing model.

DIRECTORS AND OFFICERS

Name, Occupation and Security Holding

The name, province or state, country of residence, position or office held with the Corporation and principal occupation during the past five years of each director and executive officer of the Corporation as at June 30, 2010 and as at the date hereof are described as follows:


- 36 -

Name and Address(1)
Office or Position
Held
Principal Occupation During the Past Five
Years
Previous Service as a
Director
Clynton R. Nauman Washington, USA President, Chief Executive Officer and Director(4) President and Chief Executive Officer of the Corporation, since December 2004; Chief Executive Officer of Asset Liability Management Group ULC, since February 2003. Since December 3, 2004
Michael Winn California, USA Chairman and Director(3)(4)(5)(6) President of Terrasearch Inc., a consulting company that provides analysis on mining and energy companies, since 1997. Since January 11, 2005
Rick Van Nieuwenhuyse British Columbia, Canada Director(4) President and Chief Executive Officer of NovaGold Resources Inc., a company engaged in the business of mining and mineral exploration and development, since May 1999. Since January 11, 2005
David Searle British Columbia, Canada Director(2)(3)(4)(5) Lawyer with Fasken Martineau DuMoulin LLP, October 2001 to August 2006. Since May 12, 2006
George Brack British Columbia, Canada Chairman and Director(2)(3)(5)(6) Managing Director and Industry Head – Mining with Scotia Capital Inc., from December 2006 to January 2009; President of Macquarie North America Ltd. from January 1999 to November 2006. Since December 11, 2007
Terry Krepiakevich British Columbia, Canada Director(2) Chief Financial Officer of SouthGobi Resources Ltd., a mining company, since June 2006; Chief Financial Officer of Extreme CCTV Inc., an imaging technology company, from November 2000 to June 2006. Since July 22, 2009
Bradley Thrall Washington, USA Chief Operating Officer Chief Operating Officer of the Corporation, since December 2004; President of Asset Liability Management Group ULC, since September 2002. N/A
David Whittle British Columbia, Canada Chief Financial Officer and Corporate Secretary Chief Financial Officer and Corporate Secretary of the Corporation, since October 2007; Chief Financial Officer of Hillsborough Resources Limited, a mining company, from August 2004 to August 2007; Chartered Accountant in public practice prior to August 2004. N/A
Stanton Dodd Washington, USA Vice President, Exploration Vice President, Exploration of the Corporation, since March 2008; Senior Project Geologist for NovaGold from January 2002 to March 2008. N/A
Jim Harrington Idaho, USA President, Alexco Environmental Group President of the Corporation’s AEG division since January 2010 and Vice President of Alexco US since February 2007; a Vice President of ARCADIS U.S., Inc. from 2002 to 2007. N/A
Robert McIntyre Yukon, Canada Vice President, Corporate Affairs and Communications Vice President, Business Development of the Corporation since June 2006; Vice President of Access Mining Consultants Ltd since February 2008. President of Access Mining Consultants Ltd., from March 1999 to February 2008. N/A

(1)

The information as to the jurisdiction of residence and principal occupation, not being within the knowledge of the Corporation, has been furnished by the respective individuals individually.

(2)

Member of the Audit Committee.

(3)

Member of the Corporate Governance Committee.

(4)

Member of the Environmental, Health and Safety Committee.

(5)

Member of the Compensation Committee.

(6)

Mr. Winn ceased to be Chairman of the Corporation’s Board of Directors, and Mr. Brack succeeded Mr. Winn as Chairman, on May 12, 2010.



- 37 -

Each of the Corporation’s directors is elected by the Corporation’s shareholders at an annual meeting to serve until the next annual meeting of shareholders or until a successor is elected or appointed. The board of directors appoints the Corporation’s executive officers annually after each annual meeting, to serve at the discretion of the board of directors.

Based on information provided by such persons, as at the date hereof the directors and executive officers of the Corporation as a group beneficially owned, directly or indirectly, or exercised control or direction over, an aggregate of 4,620,089 common shares of the Corporation (including 1,940,299 shares owned by ALM Investments ULC (formerly Asset Liability Management Group ULC) (“ALM”)), representing approximately 9% of the issued and outstanding common shares of the Corporation. In addition, the directors and executive officers of the Corporation as a group held stock options for the purchase of an aggregate of 2,892,500 common shares in the capital of the Corporation, representing approximately 63% of all outstanding options.

Cease Trade Orders, Bankruptcies, Penalties or Sanctions

Other than as disclosed below, to the knowledge of the Corporation, none of the Corporation's directors or executive officers is, as at the date of this AIF, or has been, within ten years before the date of this AIF, a director, chief executive officer or chief financial officer of any Corporation (including the Corporation) that:

  (a)

was subject to an Order (as defined below) that was issued while the director or executive officer was acting in the capacity as director, chief executive officer or chief financial officer; or

     
  (b)

was subject to an Order that was issued after the director or executive officer ceased to be a director, chief executive officer or chief financial officer and which resulted from an event that occurred while that person was acting in the capacity as director, chief executive officer or chief financial officer;

Order” means a cease trade order, an order similar to a cease trade order, or an order that denied the relevant Corporation access to any exemption under securities legislation and, in each case, that was in effect for a period of more than 30 consecutive days.

Other than as disclosed above, none of the Corporation's directors or executive officers or, to the Corporation's knowledge, any shareholder holding a sufficient number of securities of the Corporation to affect materially the control of the Corporation:

(a)

is, as at the date of this AIF, or has been within the 10 years before the date of this AIF, a director or executive officer of any Corporation (including the Corporation) that, while that person was acting in that capacity, or within a year of that person ceasing to act in that capacity, became bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency or was subject to or instituted any proceedings, arrangement or compromise with creditors or had a receiver, receiver manager or trustee appointed to hold its assets; or

   
(b)

has, within the 10 years before the date of this AIF, become bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency, or become subject to or instituted any proceedings, arrangement or compromise with creditors, or had a receiver, receiver manager or trustee appointed to hold the assets of the proposed director; or

   
(c)

has been subject to:



- 38 -

  (i)

any penalties or sanctions imposed by a court relating to securities legislation or by a securities regulatory authority or has entered into a settlement agreement with a securities regulatory authority; or

     
  (ii)

any other penalties or sanctions imposed by a court or regulatory body that would likely be considered important to a reasonable investor in making an investment decision.

From 1998 through 2001, Clynton Nauman was CEO and a director of Viceroy Resource Corp. (“Viceroy”). Viceroy Australia Pty Ltd. and Bounty (Victoria) Pty Ltd., Australian subsidiaries of Viceroy, were placed under voluntary administration in 2001. Final creditor settlement agreements were reached by approximately 2003, and the two companies were ultimately dissolved in 2006.

From 2004 to 2007, David Whittle was a director of Image Innovations Holdings, Inc. (“Image”), a company incorporated in the United States. Image and its subsidiaries filed voluntary petitions for relief under Chapter 11, Title 11 of the United States Code on July 6, 2006. Image’s Joint Chapter 11 Liquidating Plan was confirmed by the Bankruptcy Court on August 21, 2007, and the Final Decree closing the Chapter 11 cases was entered August 28, 2008.

Conflicts of Interest

The directors of the Corporation are required by law to act honestly and in good faith with a view to the best interest of the Corporation and to disclose any interests which they may have in any project or opportunity of the Corporation. If a conflict of interest arises at a meeting of the board of directors, any director in a conflict will disclose his interest and abstain from voting on such matter. In determining whether or not the Corporation will participate in any project or opportunity, that director will primarily consider the degree of risk to which the Corporation may be exposed and its financial position at that time.

To the best of the Corporation's knowledge, there are no known existing or potential conflicts of interest among the Corporation, its promoters, directors, officers or other members of management of the Corporation as a result of their outside business interests except that certain of the directors, officers, promoters and other members of management serve as directors, officers, promoters and members of management of other public companies, and therefore it is possible that a conflict may arise between their duties as a director, officer, promoter or member of management of such other companies.

The directors and officers of the Corporation are aware of the existence of laws governing accountability of directors and officers for corporate opportunity and requiring disclosures by directors of conflicts of interest and the Corporation relies upon such laws in respect of any directors’ and officers’ conflicts of interest or in respect of any breaches of duty by any of its directors or officers. Such directors or officers in accordance with the Business Corporations Act (British Columbia) are required to disclose all such conflicts and to govern themselves in respect thereof to the best of their ability in accordance with the obligations imposed upon them by law.

AUDIT COMMITTEE INFORMATION

Audit Committee Charter

The following is the text of the Audit Committee's Charter:


- 39 -

I. MANDATE

The Audit Committee (the “Committee”) of the Board of Directors (the “Board”) of Alexco Resource Corp. (the “Company”) shall assist the Board in fulfilling its financial oversight responsibilities. The Committee’s primary duties and responsibilities under this mandate are to serve as an independent and objective party to monitor:

  1.

The quality and integrity of the Company’s financial statements and other financial information;

     
  2.

The compliance of such statements and information with legal and regulatory requirements;

     
  3.

The qualifications and independence of the Company’s independent external auditor (the “Auditor”); and

     
  4.

The performance of the Company’s internal accounting procedures and Auditor.

II. STRUCTURE AND OPERATIONS

  A. Composition

The Committee shall be comprised of three or more independent members.

  B. Qualifications

Each member of the Committee must be a member of the Board.

A majority of the members of the Committee shall not be officers or employees of the Company or of an affiliate of the Company.

Each member of the Committee must be able to read and understand fundamental financial statements, including the Company’s balance sheet, income statement, and cash flow statement.

  C. Appointment and Removal

In accordance with the By-Laws of the Company, the members of the Committee shall be appointed by the Board and shall serve until such member’s successor is duly elected and qualified or until such member’s earlier resignation or removal. Any member of the Committee may be removed, with or without cause, by a majority vote of the Board.

  D. Chair

Unless the Board shall select a Chair, the members of the Committee shall designate a Chair by the majority vote of all of the members of the Committee. The Chair shall call, set the agendas for and chair all meetings of the Committee.


- 40 -

  E. Sub-Committees

The Committee may form and delegate authority to subcommittees consisting of one or more members when appropriate, including the authority to grant pre-approvals of audit and permitted non-audit services, provided that a decision of such subcommittee to grant a pre-approval shall be presented to the full Committee at its next scheduled meeting.

  F. Meetings

The Committee shall meet at least four times in each fiscal year, or more frequently as circumstances dictate. The Auditor shall be given reasonable notice of, and be entitled to attend and speak at, each meeting of the Committee concerning the Company’s annual financial statements and, if the Committee feels it is necessary or appropriate, at every other meeting. On request by the Auditor, the Chair shall call a meeting of the Committee to consider any matter that the Auditor believes should be brought to the attention of the Committee, the Board or the shareholders of the Company.

At each meeting, a quorum shall consist of a majority of members that are not officers or employees of the Company or of an affiliate of the Company.

As part of its goal to foster open communication, the Committee may periodically meet separately with each of management and the Auditor to discuss any matters that the Committee believes would be appropriate to discuss privately. In addition, the Committee should meet with the Auditor and management annually to review the Company’s financial statements in a manner consistent with Section III of this Charter.

The Committee may invite to its meetings any director, any manager of the Company, and any other person whom it deems appropriate to consult in order to carry out its responsibilities. The Committee may also exclude from its meetings any person it deems appropriate to exclude in order to carry out its responsibilities.

  III.

DUTIES

     
  A.

Introduction

The following functions shall be the common recurring duties of the Committee in carrying out its purposes outlined in Section I of this Charter. These duties should serve as a guide with the understanding that the Committee may fulfill additional duties and adopt additional policies and procedures as may be appropriate in light of changing business, legislative, regulatory or other conditions. The Committee shall also carry out any other responsibilities and duties delegated to it by the Board from time to time related to the purposes of the Committee outlined in Section I of this Charter.

The Committee, in discharging its oversight role, is empowered to study or investigate any matter of interest or concern which the Committee in its sole discretion deems appropriate for study or investigation by the Committee.

The Committee shall be given full access to the Company’s internal accounting staff, managers, other staff and Auditor as necessary to carry out these duties. While acting within the scope of its stated purpose, the Committee shall have all the authority of, but shall remain subject to, the Board.


- 41 -

The Committee shall be given all funding as the Committee determines necessary for the payment of: (i) compensation to any registered public accounting firm engaged for the purpose of preparing or issuing an audit report or performing other audit, review or attest services; (ii) compensation to advisors employed by the Committee; and (iii) ordinary administrative expenses.

  B. Powers and Responsibilities

The Committee will have the following responsibilities and, in order to perform and discharge these responsibilities, will be vested with the powers and authorities set forth below, namely, the Committee shall:

Independence of Auditor

  1)

Review and discuss with the Auditor any disclosed relationships or services that may impact the objectivity and independence of the Auditor and, if necessary, obtain a formal written statement from the Auditor setting forth all relationships between the Auditor and the Company, consistent with Independence Standards Board Standard 1.

     
  2)

Take, or recommend that the Board take, appropriate action to oversee the independence of the Auditor.

     
  3)

Require the Auditor to report directly to the Committee.

     
  4)

Review and approve the Company’s hiring policies regarding partners, employees and former partners and employees of the Auditor and former independent external auditor of the Company.

Performance & Completion by Auditor of its Work

  5)

Be directly responsible for the oversight of the work by the Auditor (including resolution of disagreements between management and the Auditor regarding financial reporting) for the purpose of preparing or issuing an audit report or related work.

       
  6)

Review annually the performance of the Auditor and recommend the appointment by the Board of a new, or re-election by the Company’s shareholders of the existing, Auditor.

       
  7)

Pre-approve all auditing services and permitted non-audit services (including the fees and terms thereof) to be performed for the Company by the Auditor unless such non-audit services:

       
  (a)

which are not pre-approved, are reasonably expected not to constitute, in the aggregate, more than 5% of the total amount of revenues paid by the Company to the Auditor during the fiscal year in which the non-audit services are provided;



- 42 -

  (b)

were not recognized by the Company at the time of the engagement to be non-audit services; and

     
  (c)

are promptly brought to the attention of the Committee by Management and approved prior to the completion of the audit by the Committee or by one or more members of the Committee who are members of the Board to whom authority to grant such approvals has been delegated by the Committee.

Internal Financial Controls & Operations of the Company

  8)

Establish procedures for:

       
  (a)

the receipt, retention and treatment of complaints received by the Company regarding accounting, internal accounting controls, or auditing matters; and

       
  (b)

the confidential, anonymous submission by employees of the Company of concerns regarding questionable accounting or auditing matters.

Preparation of Financial Statements

  9)

Discuss with management and the Auditor significant financial reporting issues and judgments made in connection with the preparation of the Company’s financial statements, including any significant changes in the Company’s selection or application of accounting principles, any major issues as to the adequacy of the Company’s internal controls and any special steps adopted in light of material control deficiencies.

     
  10)

Discuss with management and the Auditor any correspondence with regulators or governmental agencies and any employee complaints or published reports which raise material issues regarding the Company’s financial statements or accounting policies.

     
  11)

Discuss with management and the Auditor the effect of regulatory and accounting initiatives as well as off-balance sheet structures on the Company’s financial statements.

     
  12)

Discuss with management the Company’s major financial risk exposures and the steps management has taken to monitor and control such exposures, including the Company’s risk assessment and risk management policies.

     
  13)

Discuss with the Auditor the matters required to be discussed relating to the conduct of any audit, in particular:

     
  14)

The adoption of, or changes to, the Company’s significant auditing and accounting principles and practices as suggested by the Auditor or management.

     
  15)

Any difficulties encountered in the course of the audit work, including any restrictions on the scope of activities or access to requested information, and any significant disagreements with management.



- 43 -

Public Disclosure by the Company

  16)

Review the Company’s annual and quarterly financial statements, management discussion and analysis (MD&A) before the Board approves and the Company publicly discloses this information.

     
  17)

Review the Company’s financial reporting procedures and internal controls to be satisfied that adequate procedures are in place for the review of the Company’s public disclosure of financial information extracted or derived from its financial statements, other than disclosure described in the previous paragraph, and periodically assessing the adequacy of those procedures.

     
  18)

Review any disclosures made to the Committee by the Company’s Chief Executive Officer and Chief Financial Officer during their certification process of the Company’s financial statements about any significant deficiencies in the design or operation of internal controls or material weaknesses therein and any fraud involving management or other employees who have a significant role in the Company’s internal controls.

Related Party Transactions

  19)

Review all related party or conflict of interest transactions of the Company and make appropriate recommendation to the Board of Directors.

Manner of Carrying Out its Mandate

  20)

Consult, to the extent it deems necessary or appropriate, with the Auditor but without the presence of management, about the quality of the Company’s accounting principles, internal controls and the completeness and accuracy of the Company’s financial statements.

     
  21)

Request any officer or employee of the Company or the Company’s outside counsel or Auditor to attend a meeting of the Committee or to meet with any members of, or consultants to, the Committee.

     
  22)

Have the authority, to the extent it deems necessary or appropriate, to retain independent legal, accounting or other consultants to advise the Committee advisors.

     
  23)

Meet, to the extent it deems necessary or appropriate, with management and the Auditor in separate executive sessions at least quarterly.

     
  24)

Have the authority, to the extent it deems necessary or appropriate, to retain independent legal, accounting or other consultants to advise the Committee advisors.

     
  25)

Make regular reports to the Board.

     
  26)

Review and reassess the adequacy of this Charter annually and recommend any proposed changes to the Board for approval.

     
  27)

Annually review the Committee’s own performance.



- 44 -

  28)

Provide an open avenue of communication among the Auditor the Board.

   

29)

Not delegate these responsibilities other than to one or more independent members of the Committee the authority to pre-approve, which the Committee must ratify at its next meeting, non-audit services to be provided by the Auditor.

   

  F.

Limitation of Audit Committee’s Role

While the Committee has the responsibilities and powers set forth in this Charter, it is not the duty of the Committee to plan or conduct audits or to determine that the Company’s financial statements and disclosures are complete and accurate and are in accordance with generally accepted accounting principles and applicable rules and regulations. These are the responsibilities of management and the Auditor.

Composition of the Audit Committee

As at June 30, 2010 and the date of this AIF, , the members of the Audit Committee are Terry Krepiakevich, George Brack and David Searle, with Mr. Krepiakevich serving as the Chair of the Audit Committee. All of these members are financially literate and independent for the purposes of Multilateral Instrument 52-110 (“MI 52-110”).

Mr. Krepiakevich qualifies as a financial expert and is financially sophisticated, in that he has an understanding of generally accepted accounting principles and financial statements; is able to assess the general application of accounting principles in connection with the accounting for estimates, accruals and reserves; has experience analyzing or evaluating financial statements that entail accounting issues of equal complexity to the Corporation's financial statements (or actively supervising another person who did so); and has a general understanding of internal controls and procedures for financial reporting and an understanding of audit committee functions.

Mr. Krepiakevich is the Chief Financial Officer of SouthGobi Resources Ltd., a publicly-listed mining company focused on exploring and developing coal deposits in Mongolia's South Gobi Region. Previously, Mr. Krepiakevich was Chief Financial Officer for Extreme CCTV Inc., a publicly traded company on the TSX involved in manufacturing high tech surveillance equipment, and Vice-President Finance and Chief Financial Officer of Maynards Industries Ltd., a private firm specializing in retailing, auctioneering, liquidating, and mergers and acquisition services. Prior to his position with Maynards, Mr. Krepiakevich was a senior officer in a number of private and public issuers. He is a Canadian qualified Chartered Accountant and was employed with the international accounting firm Peat Marwick Thorne (KPMG), where he worked with a number of companies in mining and related industries.

Mr. Brack was Managing Director and Industry Head – Mining of Scotia Capital Inc. from December 2006 to January 2009. Prior to joining Scotia Capital, he held the position of President of Macquarie North America Ltd., an investment banking firm specializing in mergers and acquisitions as well as other advisory functions for North American resource companies. Mr. Brack has also held positions with Placer Dome as Vice President Corporate Development, and with CIBC Wood Gundy where he was Vice President of the Investment Banking Group. Mr. Brack is financially literate, possessing extensive experience in corporate finance and investment banking, particularly with respect to the mining sector.

Mr. Searle is a lawyer and a retired partner at Fasken Martineau DuMoulin LLP and brings to the Board 44 years of experience practicing law in western and northern Canada. He has extensive experience in environmental assessment, the permitting of major projects and in the area of mine closure and reclamation.


- 45 -

Mr. Searle regularly appeared in all three northern jurisdictions before the Boards that conduct environmental assessments and issue water licenses and land use permits and has extensive experience dealing with contaminated sites in British Columbia. Mr. Searle is financially literate in that he has the ability to read and understand a set of financial statements that present a breadth and level of complexity of accounting issues that are generally comparable to the breadth and complexity of the issues that can reasonably be expected to be raised by the Corporation's financial statements.

Reliance on Certain Exemptions

At no time since the commencement of the Corporation's most recently completed financial year has the Corporation relied on the exemption in Section 2.4 of MI 52-110 (De Minimis Non-audit Services), Section 3.2 of MI 52-110 (Initial Public Offerings), Section 3.3(2) of MI 52-110 (Controlled Companies), Section 3.4 of MI 52-110 (Events Outside Control of Member), Section 3.5 of MI 52-110 (Death, Disability or Resignation of Audit Committee Member), Section 3.6 of MI 52-110 (Temporary Exemption for Limited and Exceptional Circumstances) or Section 3.8 of MI 52-110 (Acquisition of Financial Literacy), or an exemption from MI 52-110, in whole or in part, granted under Part 8 of MI 52-110 (Exemptions).

Audit Committee Oversight

At no time since the commencement of the Corporation's most recently completed financial year was a recommendation of the Committee to nominate or compensate an external auditor not adopted by the board of directors.

Pre-Approval Policies and Procedures

The Audit Committee nominates and engages the independent auditors to audit the financial statements, and approves all audit, audit-related services, tax services and other services provided by the Corporation’s independent auditors, PricewaterhouseCoopers LLP, Chartered Accountants. Any services provided by PricewaterhouseCoopers LLP that are not specifically included within the scope of the audit must be pre-approved by the audit committee prior to any engagement. The audit committee is permitted to approve certain fees for audit-related services, tax services and other services pursuant to a de minimus exception before the completion of the engagement. No fees paid to PricewaterhouseCoopers LLP in either of the fiscal years ended June 30, 2010 or 2009 were approved pursuant to the de minimus exception.

External Auditor Service Fees (By Category)

PricewaterhouseCoopers LLP, Chartered Accountants, serve as the independent auditors for the Corporation and have acted as the Corporation's independent auditor for the fiscal years ended June 30, 2010 and June 30, 2009. The chart below sets forth the total amount billed the Corporation by PricewaterhouseCoopers LLP for services performed in these periods and breaks down these amounts by category of service (for audit fees, audit-related fees, tax fees and all other fees):

External Auditor Service Fees (By Category)

 Financial Year Ended Audit Fees Audit Related Fees Tax Fees All Other Fees
June 30, 2010 $262,000 $144,705 $Nil $65,750
June 30, 2009 $319,000 $ 54,000 $Nil $Nil


- 46 -

“Audit Fees” are the aggregate fees billed by PricewaterhouseCoopers LLP for the audits of the Corporation’s consolidated annual financial statements and internal control over financial reporting that are provided in connection with statutory and regulatory filings or engagements.

“Audit-Related Fees” are fees charged by PricewaterhouseCoopers LLP for assurance and related services that are reasonably related to the performance of the audit or review of the Corporation’s financial statements and are not reported under “Audit Fees”. This category includes but is not limited to fees billed for independent accountant review of the interim financial statements, advisory services associated with the Corporation’s financial reporting and fees charged for services rendered in connection with registration statements and other securities offering documents.

“Tax Fees” are fees for professional services rendered by PricewaterhouseCoopers LLP for tax compliance, tax advice on actual or contemplated transactions.

“All Other Fees” include all fees charged by PricewaterhouseCoopers LLP for products or services other than those charged for “Audit Fees”, “Audit-Related Fees” and “Tax Fees”.

LEGAL PROCEEDINGS AND REGULATORY ACTIONS

The Corporation is not a party to any legal proceedings or regulatory actions and is not aware of any such proceedings or actions known to be contemplated.

INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS

The directors, executive officers and principal shareholders of the Corporation or any associate or affiliate of the foregoing have had no material interest, direct or indirect, in any transactions in which the Corporation has participated within the three most recently completed financial periods prior to the date of this AIF or in the current financial year, and do not have any material interest in any proposed transaction, which has materially affected or is reasonably expected to materially affect the Corporation, except as set out elsewhere in this AIF or as follows:

Certain directors and/or officers of the Corporation have subscribed for common shares of the Corporation pursuant to the public and private placement financings of the Corporation.

The Corporation incurred $97,000 during the year ended June 30, 2010 (2009 – $95,000; 2008 – $97,000) for rent of office space under an agreement with Access Field Services, a Corporation owned by certain individuals who are executive officers of Alexco and its subsidiary Access. At June 30, 2010, accounts payable and accrued liabilities include $5,400 due to Access Field Services (2009 and 2008 – $nil).

In January 2009, NovaGold Resources Inc. (“NovaGold”) reported that it reduced its shareholding in the Corporation to nil, and as a consequence ceased to be a related party of the Corporation. During the year ended June 30, 2009, and while NovaGold was considered to be a related party, the Corporation incurred technical service fees with NovaGold totaling $274,000 (2008 – $696,000;), which have been capitalized to mineral properties and deferred exploration costs. As at June 30, 2009, accounts payable and accrued liabilities include $nil due to NovaGold (2008 – $nil).

TRANSFER AGENTS AND REGISTRARS

The registrar and transfer agent for the common shares of the Corporation in British Columbia and Ontario is Computershare Investor Services Inc., Vancouver, British Columbia.


- 47 -

MATERIAL CONTRACTS

The only material contracts entered into by the Corporation within the year ended June 30, 2010 or before such time that are still in effect, other than in the ordinary course of business, are as follows:

  1.

The Silver Wheaton silver purchase agreement described under “General Development of the Business – Three Year History and Significant Acquisitions” in this AIF.

The agreement and subsequent amendments are available on SEDAR at www.sedar.com under the Corporation’s profile.

INTERESTS OF EXPERTS

Names of Experts

The following persons are “qualified persons”, and where indicated are independent, as defined in NI 43-101, and are the qualified persons responsible for the preparation of the Bellekeno updated preliminary economic assessment technical report (see “Description of Business – Mineral Exploration and Development – Bellekeno Property”):

  Independent
   
  G. David Keller, P.Geo., of SRK Consulting (Canada) Inc.
  Ken Reipas, P.Eng., of SRK Consulting (Canada) Inc.
  Bruce Murphy, FSAIMM, of SRK Consulting (Canada) Inc.
  Hassan Ghaffari, P.Eng., of Wardrop Engineering Inc.
   
  Non-Independent
   
  Stanton Dodd, L.Geo., Vice President, Exploration, Alexco
  Robert Vincent Scartozzi, L.Geo., Chief Mine Geologist, Alexco

The following persons are independent and “qualified persons” as defined in NI 43-101, and are the qualified persons responsible for the preparation of the Elsa Tailings resource estimate technical report (see “Description of Business – Mineral Exploration and Development – Elsa Tailings Property”):

  Independent
   
  G. David Keller, P.Geo., of SRK Consulting (Canada) Inc.
  Lars Weiershäuser, Ph.D, P.Geo., of SRK Consulting (Canada) Inc.

Stanton Dodd, L.Geo., a “qualified person” as defined in NI 43-101, is the Corporation’s Vice President, Exploration, and except where specifically indicated otherwise is the person responsible for the technical information included in this AIF regarding Alexco’s mineral properties.

The audited financial statements of the Corporation have been subject to audit by PricewaterhouseCoopers LLP, Chartered Accountants.


- 48 -

Interests of Experts

Based on information provided by the experts, other than with respect to Stanton Dodd and Robert Vincent Scartozzi as described below and PricewaterhouseCoopers LLP, Chartered Accountants as auditors, none of the experts named under "Names of Experts", when or after they prepared the statement, report or valuation, has received any registered or beneficial interests, direct or indirect, in any securities or other property of the Corporation or of one of the Corporation's associates or affiliates (based on information provided to the Corporation by the experts) or is or is expected to be elected, appointed or employed as a director, officer or employee of the Corporation or of any associate or affiliate of the Corporation.

Stanton Dodd is the Corporation’s Vice President, Exploration, and Robert Vincent Scartozzi is the Corporation’s Chief Mine Geologist, and accordingly neither is considered independent as defined in NI 43-101. Both Mr. Dodd and Mr. Scartozzi have been granted stock options of the Corporation, with respect to each of them representing less than one percent of the issued and outstanding common shares of the Corporation.

The auditors of the Corporation are PricewaterhouseCoopers LLP, Chartered Accountants, of Vancouver, British Columbia. PricewaterhouseCoopers LLP, Chartered Accountants, report that they are independent of the Corporation in accordance with the Rules of Professional Conduct of the Institute of Chartered Accountants of British Columbia, Canada. PricewaterhouseCoopers LLP is registered with the Public Company Accounting Oversight Board.

ADDITIONAL INFORMATION

Additional information relating to the Corporation may be found on SEDAR at www.sedar.com.

Additional information, including directors' and officers' remuneration and indebtedness, principal holders of the Corporation's securities, and securities authorized for issuance under equity compensation plans, where applicable, is contained in the Corporation's information circular for its most recent annual general meeting of securityholders that involved the election of directors.

Additional financial information is provided in the Corporation's consolidated financial statements and management's discussion and analysis for its most recently completed financial year, being the year ended June 30, 2010.