EX-99.7 8 exhibit99-7.htm EXHIBIT 99.7 Quaterra Resources Inc.: Exhibit 99.7 - Filed by newsfilecorp.com

 



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

DATE AND SIGNATURES PAGE


 

The effective date of this report is 31 October 2012 and the amended date of this report is 7 January 2014. The Certificates of Qualified Persons are included in Appendix A.

“Signed” Joshua Snider, P.E.   7 January 2014
Signature   Date

Note: Revision 1 was issued on 20 December 2012 with the following edits:

  1.

A sentence was added to the end of Section 13.4 describing recovery improvement through reagent and flotation optimization.

     
  2.

The lead and zinc grades were adjusted in Table 22- 4 due to a decimal place error.

Revision 2 was issued on 7 January 2014 with the following edits:

  1.

The report’s title was changed to “Amended Preliminary Economic Assessment.”

     
  2.

Cautionary language was added to Section 22 indicating that mineral resources that are not mineral reserves do not have demonstrated economic viability.

     
  3.

The use of the term “ore” with regards to the mine plan and financial model was modified to indicate “mineralized material,” to clarify that the project does not currently have mineral reserves.

     
  4.

Qualified Person assignments for sections 17, 20, and 27 were clarified.

These modifications did not change project economics.


     
M3-PN120008
7 January 2014
Revision 2
i



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

NIEVES PROJECT
FORM 43-101F1 TECHNICAL REPORT
AMENDED PRELIMINARY ECONOMIC ASSESSMENT

TABLE OF CONTENTS

SECTION   PAGE
     
DATE AND SIGNATURES PAGE I
   
TABLE OF CONTENTS II
 
LIST OF FIGURES AND ILLUSTRATIONS VIII
   
LIST OF TABLES XI
   
1 SUMMARY 1
     
  1.1 KEY DATA 1
       
  1.2 PROPERTY DESCRIPTION AND OWNERSHIP 2
       
  1.3 GEOLOGY AND MINERALIZATION 4
       
  1.4 EXPLORATION STATUS 5
       
  1.5 OVERALL PROJECT 6
       
  1.6 MINERAL RESOURCE ESTIMATE 8
       
  1.7 MINING 8
       
  1.8 METALLURGY 9
       
  1.9 PROCESS FACILITIES 10
       
  1.10 INFRASTRUCTURE 12
       
  1.11 CAPITAL COSTS 13
       
  1.12 OPERATING COSTS 13
       
  1.13 FINANCIAL MODEL 13
       
  1.14 RESULTS, CONCLUSIONS AND RECOMMENDATIONS 14
       
2 INTRODUCTION 15
     
  2.1 PURPOSE 15
       
  2.2 AUTHORS 15
       
  2.3 SOURCES OF INFORMATION 16
       
  2.4 UNITS AND TERMS OF REFERENCE 16
       
3 RELIANCE ON OTHER EXPERTS 18
     
4 PROPERTY DESCRIPTION AND LOCATION 19
     
  4.1 LOCATION 19

     
M3-PN120008
7 January 2014
Revision 2
ii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  4.2 DESCRIPTION AND OWNERSHIP 22
       
5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 27
     
  5.1 ACCESS   27
         
  5.2 PHYSIOGRAPHY, CLIMATE AND VEGETATION 28
       
6 HISTORY   31
       
  6.1 EXPLORATION ACTIVITIES BETWEEN 1560 AND 1994 31
       
  6.2 EXPLORATION ACTIVITIES BETWEEN 1994 AND 2010 33
       
    6.2.1 Kennecott exploration between 1994 and 1996 34
    6.2.2 Western Copper exploration in 1997 and 1998 34
    6.2.3 Quaterra exploration in 1999 and 2000 34
    6.2.4 Quaterra and Blackberry 2003-2010 37
    6.2.5 Geophysical Surveys 47
         
  6.3 HISTORICAL MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES 48
       
    6.3.1 CRM 1992 48
    6.3.2 Quaterra/Blackberry 2009 and 2010 resource estimates 48
         
7 GEOLOGICAL SETTING AND MINERALIZATION 49
     
  7.1 REGIONAL GEOLOGY 49
       
  7.2 PROPERTY GEOLOGY 49
       
    7.2.1 Mesozoic Rocks 49
    7.2.2 Tertiary Clastic Rocks 50
    7.2.3 Tertiary Volcanic Rocks 51
    7.2.4 Structural Geology 51
         
  7.3 MINERALIZATION 54
       
    7.3.1 Alteration and Styles of Mineralization 54
    7.3.2 Jasperoid Structures 54
    7.3.3 Iron Carbonate Veins 54
    7.3.4 Carbonate-Quartz-Sulphide Veins 54
    7.3.5 Calcite-Manganese-Oxide Breccias and Veins 55
    7.3.6 Mineralized Zones 56
    7.3.7 California Vein System 56
    7.3.8 Concordia- San Gregorio-Dolores Vein System 57
    7.3.9 Santa Rita Vein System 57
    7.3.10 Manganese Mineralization 58
         
8 DEPOSIT  TYPES 59
       
  8.1 EPITHERMAL HIGH-GRADE SILVER VEINS 59
       
  8.2 OTHER DEPOSIT TYPES IN THE DISTRICT 60

     
M3-PN120008
7 January 2014
Revision 2
iii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

9 EXPLORATION   63
       
  9.1 GEOPHYSICAL WORK 63
       
    9.1.1 2011 63
    9.1.2 2012 63
         
  9.2 MAPPING AND SAMPLING 68
       
10 DRILLING   70
       
  10.1 DRILLING PROGRESS 70
       
    10.1.1 Phase VII 71
    10.1.2 Phase VIII 74
         
  10.2 SAMPLING PROCEDURES 77
       
  10.3 DRILL DATA AND DRILLING RESULTS 81
       
    10.3.1 Concordia 81
    10.3.2 California 82
    10.3.3 Gregorio North 82
    10.3.4 Santa Rita 82
    10.3.5 Other areas 83
         
11 SAMPLE PREPARATION, ANALYSES AND SECURITY 90
     
  11.1 SAMPLE SECURITY 90
       
  11.2 QA/QC PROCEDURES 91
       
    11.2.1 Frequency of QC samples 91
    11.2.2 Blanks and standards 95
    11.2.3 Duplicates 96
         
  11.3 SAMPLE PREPARATION 96
       
  11.4 ANALYTICAL METHODS 97
       
  11.5 QA/QC PROCEDURES IN ALS MINERALS LABS 97
       
  11.6 CHECK ASSAYS 99
       
    11.6.1 Phase VII 99
    11.6.2 Phase VIII 100
         
12 DATA VERIFICATION 102
     
  12.1 CARACLE CREEK SITE VISIT 102
       
  12.2 QUALITY CONTROL 110
       
    12.2.1 External blank and standard 110
    12.2.2 Laboratory standards 116
    12.2.3 Duplicates 117
    12.2.4 Phase VII check assays (Skyline) 121
    12.2.5 Phase VIII check assays (AGAT) 123

     
M3-PN120008
7 January 2014
Revision 2
iv



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

    12.2.6 QA/QC of phases IV, V, and VI and gold reassay results 125
    12.2.7 Conclusions and Recommendations 126
         
13 MINERAL PROCESSING AND METALLURGICAL TESTING 128
     
  13.1 MINERALOGY 128
       
  13.2 METALLURGICAL SAMPLES 129
       
  13.3 COMMINUTION TESTING 130
       
  13.4 FLOTATION   130
         
  13.5 QUALITY OF CONCENTRATE 133
       
  13.6 GRAVITY CONCENTRATION 133
       
  13.7 CYANIDATION 133
       
14 MINERAL RESOURCE ESTIMATES 134
     
  14.1 INTRODUCTION 134
       
  14.2 RESOURCE ESTIMATION METHODOLOGY 135
       
    14.2.1 Resource Database, Preparation & Compositing 135
    14.2.2 Variography 141
    14.2.3 Block Model 141
    14.2.4 Resource Model Validation 143
    14.2.5 Mineral Resource Classification 144
         
  14.3 MINERAL RESOURCE STATEMENT 145
       
  14.4 ISSUES THAT COULD AFFECT THE MINERAL RESOURCE 146
       
15 MINERAL RESERVE ESTIMATES 147
     
16 MINING METHODS 148
     
  16.1 OPEN PIT MINE PLAN 148
       
    16.1.1 Pit Optimization 149
    16.1.2 Pit Design 150
    16.1.3 Waste Dump Design 155
         
  16.2 PRODUCTION SCHEDULE 155
       
    16.2.1 Production Schedule Parameters 157
    16.2.2 Drill and Blast Parameters 157
    16.2.3 Load and Haul Parameters 158
         
  16.3 PREPRODUCTION DEVELOPMENT 159
       
  16.4 MINING EQUIPMENT 159
       
    16.4.1 Staffing 160
         
17 RECOVERY METHODS 162

     
M3-PN120008
7 January 2014
Revision 2
v



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  17.1 CRUSHING AND COARSE MINERALIZED MATERIAL STORAGE 162
       
  17.2 PRIMARY CRUSHED MINERALIZED MATERIAL RECLAIM 163
       
  17.3 GRINDING 163
       
  17.4 FLOTATION AND REGRIND 164
       
  17.5 DEWATERING AND FILTRATION 165
       
  17.6 FLOTATION TAILING TREATMENT 165
       
  17.7 REAGENT STORAGE AND MIXING 166
       
  17.8 WATER SYSTEM 166
       
  17.9 COMPRESSED AIR 167
       
18 PROJECT INFRASTRUCTURE 168
     
  18.1 TRANSPORTATION 168
       
  18.2 POWER 168
       
  18.3 WATER 168
       
  18.4 TAILING STORAGE FACILITY 168
       
19 MARKET STUDIES AND CONTRACTS 169
     
20 ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT 170
     
  20.1 ENVIRONMENTAL STUDY RESULTS AND KNOWN ENVIRONMENTAL ISSUES 170
       
    20.1.1 Environmental Characterization 170
    20.1.2 Seismic Activity 170
    20.1.3 Hydrologic and Underground Surface Information 171
    20.1.4 Land Use and Vegetation 171
20.1.5 Regiones Terrestres Prioritarias (RTP) or Priority/Protected Land Areas 171
    20.1.6 Important Areas for the Conservation of Birds 171
20.1.7 Regiones Hidrologicos Prioritarias (RHP) or Priority/Protected Hydrological Areas 172
    20.1.8 Natural Protected Areas 172
         
20.2 REGULATIONS AND MANAGEMENT REQUIREMENTS (PERMITS/AUTHORIZATIONS) 172
       
20.2.1 Project Compatibility with Participatory Planning Instruments 172
    20.2.2 Viability Criteria 173
         
  20.3 POTENTIAL SOCIAL & COMMUNITY REQUIREMENTS AND PLANS 173
       
    20.3.1 Background 174
    20.3.2 Economy and Employment 174

     
M3-PN120008
7 January 2014
Revision 2
vi



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  20.4 SOCIAL AND COMMUNITY NEEDS 175
       
    20.4.1 Status of Agreements with the Community 176
         
  20.5 MINE CLOSURE 177
       
21 CAPITAL AND OPERATING COSTS 179
     
  21.1 CAPITAL COSTS 179
       
    21.1.1 Process Plant & Infrastructure 179
    21.1.2 Mine Capital Costs 181
         
  21.2 SUSTAINING CAPITAL COST ESTIMATE 182
       
  21.3 OPERATING COST 182
       
    21.3.1 Mine Operating Costs 183
         
22 ECONOMIC ANALYSIS 184
     
  22.1 ASSUMPTIONS 184
       
  22.2 PRODUCTION STATISTICS 184
       
  22.3 REVENUES 185
         
    22.3.1 Other 186
         
  22.4 FINANCIAL MODEL 186
       
23 ADJACENT PROPERTIES 191
     
24 OTHER RELEVANT DATA AND INFORMATION 192
     
25 INTERPRETATION AND CONCLUSIONS 193
     
26 RECOMMENDATIONS 194
     
  26.1 CARACLE CREEK RECOMMENDATIONS 194
       
  26.2 HARD ROCK CONSULTING RECOMMENDATIONS 194
       
  26.3 M3 RECOMMENDATIONS 195
       
    26.3.1 Metallurgy 195
         
27 REFERENCES   196
       
APPENDIX A: PEA CONTRIBUTORS AND PROFESSIONAL QUALIFICATIONS 198
     
M3-PN120008
7 January 2014
Revision 2
vii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

LIST OF FIGURES AND ILLUSTRATIONS

FIGURE DESCRIPTION PAGE
   
Figure 1-1: Nieves Property Location 3
   
Figure 1-2: Overall Project Site Plan 7
   
Figure 1-3: Overall Process Flow Sheet 11
   
Figure 1-4: NPV 8% After Tax Sensitivity Table 14
   
Figure 4-1: Location of the Nieves Property 20
   
Figure 4-2: Location of the Nieves Property Showing Major Roads and Waterways 21
   
Figure 4-3: Concessions on the Nieves Property 24
   
Figure 5-1: Dirt Road Accessing Nieves Property (Photo from Doris Fox) 28
   
Figure 5-2: Major geological and physiographical regions and mining districts in Mexico (after Stone 2010) 29
   
Figure 5-3: Typical Landscape on the Nieves Property Looking North 30
   
Figure 6-1: Location of Old Mines on the Nieves Property 32
   
Figure 6-2: Location of holes drilled by Kennecott, Western and Quaterra between 1994 and 2000 36
   
Figure 6-3: Location of drill holes in Phase I, II and III drill programs 44
   
Figure 6-4: Location of drill holes in Phase IV drill program 45
   
Figure 6-5: Location of drill holes in Phase V and VI drill programs 46
   
Figure 7-1: Sedimentary layers in argillite 50
   
Figure 7-2: Surface Expression of Clastic Sediments on the Property 51
   
Figure 7-3: Geology map of the Nieves Property 53
   
Figure 7-4: Carbonate- Quartz-Sulphide Mineralized Veins 55
   
Figure 7-5: Mineralized Oxide-Breccia in Core 56
   
Figure 8-1: Schematic cross section of a typical rift related epithermal low-sulphidation system (after Corbett 2004) 60
   
Figure 9-1: Geology and location of drill holes and geophysical survey lines (red lines) in the Santa Rita area 65
   
Figure 9-2: Geology and location of channels, samples and geophysical survey lines in the West Santa Rita area 66
   
Figure 9-3: Pole-Dipole Resistivity/IP data along Line 6800 in the West Santa Rita Area 67
   
Figure 9-4: Pole-Dipole Resistivity/IP data along Line 7200 in the West Santa Rita Area 68
   
Figure 10-1: Typical Drill Hole Cap and Marker 70

     
M3-PN120008
7 January 2014
Revision 2
viii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 10-2: Areas of mineralization on the Nieves Property 73
   
Figure 10-3: Location of drill holes in Phase VII and VIII drill programs 76
   
Figure 10-4: A) Core tray marked with hole ID, depth to-from of core and box number; B) typical sample ID marking in core box; C) Locked core storage 1 of 5; D) Core storage. 78
   
Figure 11-1: Core Cutting and sample prep area at core logging / core storage facility 91
   
Figure 12-1: Core storage and logging compound 102
   
Figure 12-2: Core storage by hole and depth 103
   
Figure 12-3: Water well at logging compound 104
   
Figure 12-4: Federal survey claim marker monument 105
   
Figure 12-5: Federal survey claim marker with datum peg showing date, datum and federal identification number 105
   
Figure 12-6: Dolores vein looking down the shaft 106
   
Figure 12-7: Concordia Shaft 107
   
Figure 12-8: Control chart of standard KM2653 for Ag analyzed with ME-ICP41 method in Phase VII 111
   
Figure 12-9: Control chart of standard KM2653 for Ag analyzed with ME-GRA21 method in Phase VII 112
   
Figure 12-10: Analytical results of blank samples for Ag with ME-ICP41 method in Phase VII 113
   
Figure 12-11: Analytical results of blank samples for Ag with ME-GRA21 method in Phase VII 113
   
Figure 12-12: Control chart of standard KM2653 for Ag analyzed with ME-ICP41 method in Phase VIII 114
   
Figure 12-13: Control chart of standard KM2653 for Ag analyzed with ME-GRA21 method in Phase VIII 114
   
Figure 12-14: Analytical results of blank samples for Ag with ME-ICP41 method in Phase VIII 115
   
Figure 12-15: Analytical results of blank samples for Ag with ME-GRA21 method in Phase VIII 115
   
Figure 12-16: Pulp duplicate versus original plot for Ag analyzed with ME -ICP41 method 118
   
Figure 12-17: Pulp duplicate versus original plot for Ag analyzed with ME -GRA21 method 118
   
Figure 12-18: Pulp duplicate versus original plot for Ag analyzed with ME-ICP41 method 119
   
Figure 12-19: Pulp duplicate versus original plot for Ag analyzed with ME -GRA21 method 119
   
Figure 12-20: Core duplicate versus original plot for Ag analyzed with ME-ICP41 method 120
   
Figure 12-21: Core duplicate versus original plot for Ag analyzed with ME -GRA21 method 120
   
Figure 12-22: Plot of check assays versus original assays for Ag analyzed with ICP 122
   
Figure 12-23: Plot of check assays versus original assays for Ag analyzed with gravimetric method 123
   
Figure 12-24: Plot of check assays versus original assays for Ag analyzed with ICP 124

     
M3-PN120008
7 January 2014
Revision 2
ix



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-25: Plot of check assays versus original assays for Ag analyzed with gravimetric method 125
   
Figure 13-1: Rougher Flotation Silver Performance 131
   
Figure 13-2: Cleaner Flotation Silver Performance 132
   
Figure 14-1: Drill Hole Distribution of all holes at Nieves 136
   
Figure 14-2: View of Topo & Mineralized Domain Looking NW 137
   
Figure 14-3: Sectional view of mineralized domain showing Ag assays (looking NE) 138
   
Figure 14-4: Histogram plot showing the distribution of assay lengths 139
   
Figure 14-5: Probability plot showing the distribution of assay lengths 139
   
Figure 14-6: Histogram showing Ag composite grade distribution for the La Quinta area 141
   
Figure 14-7: Plan View Showing Block Model 143
   
Figure 16-1: Phase 1 Pit Design 152
   
Figure 16-2: Phase 2 Pit Design 153
   
Figure 16-3: Phase 3 Pit Design 154
   
Figure 17-1: Process Area Site Plan 162
     
M3-PN120008
7 January 2014
Revision 2
x



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

LIST OF TABLES

TABLE DESCRIPTION PAGE
   
Table 1-1: Key Project Data 2
   
Table 1-2: Mineral Resource Estimate on the Nieves Property 8
   
Table 1-3: Resources Inside Pit Design 9
   
Table 1-4: Initial Capital Costs 13
   
Table 1-5: Operating Cost Summary 13
   
Table 1-6: Financial Model Indicators 14
   
Table 2-1: Qualified Persons for this Report 16
   
Table 2-2: Terms and Abbreviations 16
   
Table 4-1: List of Concessions on the Nieves Property 25
   
Table 4-2: Details of Tax Payments to the Mexican Government on the Nieves Property 25
   
Table 4-3: Details of NSR on the Nieves Property 26
   
Table 6-1: Summary of Exploration Activities Between 1994 and 2010 33
   
Table 6-2: Drill Programs Completed by Kennecott, Western and Quaterra 35
   
Table 6-3: Significant Drilling Results Completed by Quaterra in 1999 and 2000 35
   
Table 6-4: Drilling Summary on the Nieves Property between 2004 and 2010 38
   
Table 6-5: Drill Highlights on the Nieves Property between 2004 and 2010 39
   
Table 6-6: Historic Santa Rita Resources Calculated by CRM (Cavey, 1999) 48
   
Table 6-7: 2009 Resource Estimate for the Concordia vein system at a 60 g/t cutoff grade 48
   
Table 6-8: 2010 resource estimate for the Concordia and Gregorio North areas at a 45 g/t cutoff grade 48
   
Table 8-1: Stratigraphy and associated mineralization in the Fresnillo District (modified from Ruvalcaba- Ruiz and Ruiz, 1988, Wendt 2002) 61
   
Table 8-2: Major Altiplano Mineralized Material Deposits (after Wendt 2002) 62
   
Table 10-1: Summary of drill holes in Phase VII drill program 72
   
Table 10-2: Summary of Drill Holes in Phase VIII Drill Program 74
   
Table 10-3: Phase VII Sampling Details 79
   
Table 10-4: Phase VIII Sampling Details 80
   
Table 10-5: Drill Highlights of Phase VII Exploration Program 83
   
Table 10-6: Drill Highlights of Phase VIII Exploration Program from Hole QTA140 to QTA 169  85

     
M3-PN120008
7 January 2014
Revision 2
xi



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-7: Ag and Au Drill Highlights in Phase VIII Drill Program from Hole QTA170 to QTA184 88
   
Table 11-1: Frequency of QC Samples in Phase VII Drill Program 92
   
Table 11-2: Frequency of QC Samples in Phase VIII Drilling Program 94
   
Table 11-3: Characteristics of Customized Standards Inserted in Phase VII and VIII Drill Programs 96
   
Table 11-4: Description of Analytical Methods for Ag and Au 97
   
Table 11-5: List of Internal Lab Standards Inserted by ALS Minerals 98
   
Table 11-6: Analytical Methods of Check Assays at Skyline 100
   
Table 11-7: Summary of Lab Standards Used by Skyline for Phase VII Check Assays 100
   
Table 11-8: Summary of external standards inserted in the check assay samples for Phase VIII drill program 101
   
Table 11-9: Analytical Methods of Check Assays for Ag and Au at AGAT Laboratories 101
   
Table 12-1: Verification of Drill Hole Locations 103
   
Table 12-2: Surface Samples Collected on the Site Visit 108
   
Table 12-3: Quarter Core Samples Selected on the Site Visit 108
   
Table 12-4: Assay Results of the Site Visit Samples Compared to the Original Samples 109
   
Table 12-5: Failure Rates of External Blank and Standard Analysis in Phase VII and VIII 110
   
Table 12-6: Failure Rates of Laboratory Standards for Phase VII and VIII 116
   
Table 12-7: Failure Rates of Duplicates in Phase VII 117
   
Table 12-8: Failure Rates of Duplicates in Phase VIII 117
   
Table 12-9: Check Assay Failure Rates of External Blanks and Standards in Phase VII Drill Program 121
   
Table 12-10: Check Assay Failure Rates of Laboratory Standards in Phase VII 121
   
Table 12-11: Failure Rates of Check Assays Versus Original Assays in Phase VII 122
   
Table 12-12: Check Assay Failure Rates of External Standards in Phase VIII 123
   
Table 12-13: Failure Rates of Check Assays Versus Original Assays in Phase VIII 124
   
Table 12-14: Characteristics of Standard CDN-SE-1 125
   
Table 12-15: QC Results for Au and Ag in Phases IV, V and VI 126
   
Table 13-1: Chemical and Mineral Composition – Master Composite 1 128
   
Table 13-2: Composite Sample Details 129
   
Table 14-1: Mineral Resource Statement1 (Caracle Creek, June 22nd, 2012) 134
   
Table 14-2: Data used in estimating the mineral resources at Nieves 135
   
Table 14-3: Summary of raw assay data statistics for all samples within the mineralized domain 140

     
M3-PN120008
7 January 2014
Revision 2
xii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 14-4: Summary of 2m composite data statistics for all samples within the mineralized domain 140
   
Table 14-5: Block model definitions for Nieves 142
   
Table 14-6: Nieves Block Model Parameters 142
   
Table 14-7: Ag Block Model vs. 2m Composite Statistical Analysis 144
   
Table 14-8: Mineral Resource Statement1 (Caracle Creek, June 22nd 2012) 145
   
Table 14-9: Block Model Quantities and Grades Reported at Various Cut-off Grades 146
   
Table 16-1: Resources Inside Pit Design 148
   
Table 16-2: AgEq Calculation Parameters 149
   
Table 16-3: Pit Optimization Parameters 149
   
Table 16-4: Optimization Capital and Operating Costs 150
   
Table 16-5: Pit Design Criteria 150
   
Table 16-6: Yearly Production Schedule 156
   
Table 16-7: Production Schedule by Pit Phase 156
   
Table 16-8: Mine Schedule Parameters 157
   
Table 16-9: Equipment Availabilities 157
   
Table 16-10: Drill and Blast Parameters 158
   
Table 16-11: Load and Haul Parameters 159
   
Table 16-12: Mine Production Equipment 160
   
Table 16-13: Mine Support Equipment 160
   
Table 16-14: Mine Department Manpower 161
   
Table 21-1: Process & Infrastructure Capital Cost Estimate Summary 180
   
Table 21-2: Mine Capital Cost Estimate 182
   
Table 21-3: Summary of Sustaining Costs (in Millions of $) 182
   
Table 21-4: Average Operating Cost Summary 183
   
Table 22-1: Mine Production 184
   
Table 22-2: Commodity Production 185
   
Table 22-3: Smelter Return Factors 185
   
Table 22-4: Financial Model 187
   
Table 26-1: Recommended Exploration Budget on the Nieves Property 194

     
M3-PN120008
7 January 2014
Revision 2
xiii



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

LIST OF APPENDICES

APPENDIX DESCRIPTION
   
     A PEA Contributors and Professional Qualifications
   
  •            Certificate of Qualified Person (“QP”) and Consent of Author

     
M3-PN120008
7 January 2014
Revision 2
xiv



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

1          SUMMARY

M3 Engineering and Technology of Tucson, AZ was contracted by Quaterra Resources Inc. ("Quaterra") of Vancouver, British Columbia, Canada, to prepare a Preliminary Economic Assessment (the “PEA) and Independent Technical Report (the "Report"), compliant with National Instrument 43-101 ("NI 43-101”) on the Nieves Property (the "Property").

This section briefly summarizes the findings of the PEA. The proposed project is an open pit silver mine that delivers feed to a 10,000 tpd (metric tons per day) grinding and flotation facility. The project is located near Rio Grande, Zacatecas Mexico which has a balance of remoteness and proximity to infrastructure. Over the life of the project, 52,365,000 ounces (troy ounces) of silver and 25,000 ounces of gold are projected to be produced.

This PEA is preliminary in nature and includes discussion of mineral resources including inferred mineral resources that are too speculative geologically to have economic considerations applied to them. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.

M3 Engineering & Technology Corporation (M3), and other Quaterra consultants, developed mine plans, process flow sheets and estimates for the project.

1.1        KEY DATA

Key project data are presented in Table 1-1 including a summary of the project size, production, operating costs, metal prices, and financial indicators.

     
M3-PN120008
7 January 2014
Revision 2
1



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 1-1: Key Project Data

Open Pit Mine Life (years) 10
Mine Type: Open Pit
Process Description: Crushing, Grinding, Flotation
Mill Throughput (Metric Tonnes Per day) 10,000
Initial Capital Costs ($US Millions) $231.6
Sustaining Capital Costs ($US Millions) $64.1
Reclamation Remediation Costs ($US Millions) $10.0
   
Payable Metals  
Average Feed Grade, Ag (grams/tonne) 56.822
Average Feed Grade, Au (grams/tonne) 0.042
Average Mill Recovery % (silver and gold) 86
Average Annual Silver (ounces) 5,236,500
Average Annual Gold (ounces) 2,530
   
Unit Operating Cost:  
Mining Cost per total tonne material $1.10
Mining Cost per processed feed tonne $6.75
Milling Cost per processed feed tonne $9.43
G&A per processed tonne of mill feed $1.41
Refining Cost per processed tonne of mill feed $4.59
Total cost per processed tonne of mill feed $22.18
   
Silver Price (price per troy ounce) $27.0
Gold Price (price per troy ounce) $1,300
Pre-Tax Project Internal Rate of Return (IRR) 21.9%
Pre-Tax NPV at 5% Discount Rate ($ Millions) 199.2
Pre-Tax Payback (years) 3.4
After Tax Project Internal Rate of Return (IRR) 15.7%
After Tax NPV at 5% Discount Rate ($ Millions) 123.0
After Tax Payback (years) 4.4

1.2        PROPERTY DESCRIPTION AND OWNERSHIP

The Property is located in the Francisco R. Murguía Municipality of the Zacatecas Mining District near the southeastern boundary of the Sierra Madre Occidental Physiographic Province in central Mexico (see Figure 1-1). The Property is centered approximately at 694856E, 2651009N (NAD27 Mexico, Zone13N), approximately 150 km northwest of the state capital of Zacatecas and 90 km north of the mining community of Fresnillo.

     
M3-PN120008
7 January 2014
Revision 2
2



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 1-1: Nieves Property Location

     
M3-PN120008
7 January 2014
Revision 2
3



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The Property consists of 18 concessions covering approximately 12,064.0725 ha. The concessions are registered in the name Minera Cerro Gregorio, as of August 5, 2011, a Mexican company wholly owned by Quaterra. The Nieves Property is jointly owned by Quaterra and Blackberry Ventures 1, LLC. (“Blackberry”). In 2011, Quaterra and Blackberry (through Minera Cerro Gregorio) paid US $44,538 in taxes to maintain the concessions. In 2012, Quaterra and Blackberry paid US $33,854 and are required to pay an additional US $36,519 to maintain the Nieves Property. Taxes are payable every six months to the Mexican government. Net smelter return royalties remain outstanding on each of the concessions acquired from Kennecott (recently purchased by Royal Gold Inc.) and the Mexican concessionaires (Abelardo Garza Hernandez, Noel McAnulty and Bill Shafer) (Table 4-3).

1.3        GEOLOGY AND MINERALIZATION

The Nieves project is a low sulfidation epithermal silver deposit hosted in three east-northeast trending, steeply south dipping vein systems with alteration and mineralization bearing strong similarities to the Fresnillo silver deposit.

The most economically significant mineralization occurs in anastomosing carbonate-quartz-sulphide veins that have been defined over a total strike length of 3.8 kilometers by 54,814 meters of drilling in 187 holes. The system develops to a maximum true width of in excess of 200 meters and has a proven down dip extent of approximately 525 meters.

The carbonate-quartz-sulphide veins contain the best grades of silver, gold, lead and zinc. This vein type consists of calcite that is partially to totally replaced by grey to white, chalcedonic, fine-grained quartz veins and veinlets. Individual veins vary in size from a few centimetres in width with a few up to 1.5 m wide with up to 50% sulphide minerals. Sulphides include pyrite, stibnite, sphalerite, galena, chalcopyrite and the silver sulphosalts: proustite, pyrargyrite, jamesonite and scarce tetrahedrite.

The central and most important of the three vein systems is the Concordia-San Gregorio-Dolores system which includes both the La Quinta and Gregorio North zones. Mineralization along the Concordia-San Gregorio-Dolores vein has a known total strike length of 1,300 meters and a true width up to 100 meters. The mineralized zone in the Gregorio North area is approximately 1,200 meters long and up to 200 meters wide. The La Quinta and Gregorio North zones are the subject of the resource estimate in this report. Only the La Quinta zone has a designed open pit for the economic assessment.

The attitude and size of the mineralized zones along the Santa Rita zone to the south and California vein system to the north are not well understood at this stage of exploration. Drilling along the Santa Rita system suggests that the mineralized zone is at least 750 meters long and may be up to 340 meters wide. The mineralized zone along the California vein system is at least 550 meters long and may be up to 130 meters wide.

Recent drilling has expanded the size of mineralized zones along all vein systems and additional drilling may significantly enhance the resources and economics of the project. Many of the vein systems are open along strike and all remain open to depth. Because some zones may be terminated along strike by late vertical fault structures such as the one that offsets the Concordia from the San Gregorio vein systems, the discovery of strike extensions to the Nieves vein systems will only require continued drilling guided the promising results of surface geophysical surveys.

     
M3-PN120008
7 January 2014
Revision 2
4



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

1.4        EXPLORATION STATUS

Between March 2010 and June 2012, Quaterra and Blackberry completed an exploration program on the Nieves Property consisting of a geophysical survey, mapping and sampling and drilling.

The geophysical survey consists of six lines, a total of 28.4 line-kilometers, of vector controlled source audio-magnetotellurics and induced polarization (CSAMT/CSIP) and nine follow-up lines of pole/dipole induced polarization (IP) totaling 16.5 line-kilometers. Nine anomalous zones were detected and validated with IP lines using 50 meter dipole spacings. Most of the anomalies appear to be westward extensions of mineralized veins previously drilled, including the Dolores, Santa Rita, Niño and Orion veins. The most interesting area identified to date is West Santa Rita, located 1,000 to 1,200 meters west of the main Santa Rita mine and over 500 meters from Quaterra’s nearest drill hole.

Mapping and sampling was completed to follow up the geophysical anomalies. The most interesting area was identified in the West Santa Rita, where mapping identified two groups of narrow, sub-parallel 2 to 30 centimeter wide calcite-quartz veinlets, some of which contain strong gold and silver mineralization. Gold values are up to 8.11 g/t over 0.2 m and silver values are up to 253 g/t over 0.4 m.

Quaterra and Blackberry completed two phases of drill programs (VII and VIII) between March 2010 and October 2011, consisting of 73 drill holes and totaling 18,547.25 m. Most of the drilling concentrated on the Concordia-Dolores-San Gregorio vein system, but a significant amount of drilling is located in the California and Santa Rita vein systems as well.

The drill program was very successful at increasing the size of known mineralized zones along all the major vein systems. Mineralization along the Concordia vein system was extended an additional 400 m, to a total of approximately 1,300 m. The length of known mineralization along the California vein system was increased to a total of approximately 550 m and it remains open to the east. Phase VII and VIII drill programs were successful in doubling the strike length of the Gregorio North mineralized zone located north of the San Gregorio vein, extending the strike length of the mineralized zone to approximately 1200 m. A total of 15 drill holes systematically tested the Santa Rita vein system over 500 m along strike, and the total length of mineralization was extended to approximately 750 m and remains open to the west.

The best intersections include 149 g/t Ag and 0.11 g/t Au over 31.25 m, which includes 6320 g/t Ag and 1.82 g/t Au over 0.25 m in drill hole QTA123 along the Concordia West vein, 104 g/t Ag over 19 m, including 6410 g/t Ag over 0.1 m and 5960 g/t over 0.1 m in drill hole QTA137 along the California vein, and 152.2 g/t Ag and 0.12 g/t Au over 57 m in drill hole QTA144 in the Concordia West area.

     
M3-PN120008
7 January 2014
Revision 2
5



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

1.5        OVERALL PROJECT

The Nieves project as evaluated in this PEA consists of a single open pit mine, mine mobile equipment, mineral processing facilities, a tailing storage facility, waste storage and infrastructure. A general arrangement of these facilities is shown in Figure 1-2.

     
M3-PN120008
7 January 2014
Revision 2
6



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 1-2: Overall Project Site Plan

     
M3-PN120008
7 January 2014
Revision 2
7



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

1.6        MINERAL RESOURCE ESTIMATE

Independent, NI 43-101 compliant resources at the Quaterra Resources Nieves property were estimated by Jason Baker P.Eng. (APENS#9627), a Geological Engineer with Caracle Creek and an independent qualified person as defined by NI 43-101. The mineral resources are reported in accordance with National Instrument 43-101 and have been estimated in compliance with generally accepted CIM "Estimation of Mineral Resource and Mineral Reserves Best Practices" guidelines. Block model quantities and grade estimates for the Nieves property were classified according to the latest CIM Definition Standards for Mineral Resources and Mineral Reserves. The results of the updated mineral resource estimate are summarized in Table 1-2.

Table 1-2: Mineral Resource Estimate on the Nieves Property

1.7        MINING

The Nieves silver deposit contains mineralization at or near the surface and is distributed in continuous veins that is ideal for open pit mining methods. The open pit is mined in three pit phases designed on the Concordia zone. The San Gregorio zone resulted in minimal mining in the pit optimization studies so this zone was not included in the mine plan but may become viable with additional drilling. The open pit operation was designed for a 10,000 tpd throughput resulting in a ten year mine life with 35.4 Mt of mineralized material grading 56.82 gpt silver and 0.04 gpt gold resulting in a 5.4:1 (waste to mineralized material) strip ratio. The pit will be mined primarily using two 16.5 m3 hydraulic shovels loading 90 t haul trucks. A 12 m3 front end loader will be used as backup to the shovels and two diesel powered rotary drills will be used for production. The major support equipment will include three dozers, a grader, a pre-shear drill and a water truck. The mineralized material will be loaded into 90-tonne haul trucks and transported to the primary jaw crusher, which will be set up at the toe of the waste dump. The plan assumes that the project operator owns, operates, and maintains all equipment. Table 1-3 below lists the resources used in the mine production plan.

     
M3-PN120008
7 January 2014
Revision 2
8



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 1-3: Resources Inside Pit Design

1.8        METALLURGY

In May, 2010, G&T Metallurgical Services Ltd. completed a metallurgical assessment on behalf of Quaterra and Blackberry. The tests were performed on a composite sample consisting of approximately 100 kg of crushed material. The main objectives of the tests were to determine the chemical and mineral content of the composite, assess the mineralized material hardness and develop an outline of a treatment process to recover silver using conventional mineral processing techniques.

The sample contained 79 g/t silver with minor amounts of copper (0.08%), lead (0.14%) and zinc (0.1%). The minerals included quartz, micas, feldspar, pyrite, goethite, sphalerite, galena, silver sulphides (0.07%) and chalcopyrite, in decreasing order of abundance. The silver minerals were polybasite, freibergite and stromeyerite. The material hardness was determined to be 10.8 kWh/tonne (moderately soft) using a Bond ball mill work index test procedure.

Open circuit flotation testing indicated that about 86% of the silver can be recovered into a final concentrate containing 2.3 kg/tonne silver. It was recommended that future test work should investigate coarser primary grind sizes.

The test also suggested that regrinding the rougher concentrate to a nominal 20 µm K80 had no significant benefit on concentrate grade or silver recovery. Increasing the pH level of the cleaner circuit to 10 significantly improved the grade of silver in the final concentrate.

Gravity concentration and cyanidation were ruled out as potential processing methods for the PEA due to the low silver recovery. The results of the open circuit kinetic rougher and batch cleaner tests were performed on mineralized material with a silver grade of 79 grams per tonne and indicated that a silver recovery of 86% was achievable.

     
M3-PN120008
7 January 2014
Revision 2
9



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

1.9        PROCESS FACILITIES

The proposed treatment method and preliminary processing parameters are based on preliminary testwork completed to date and industry standards. M3 developed an overall process flowsheet as shown in Figure 1-3.

     
M3-PN120008
7 January 2014
Revision 2
10



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 1-3: Overall Process Flow Sheet

     
M3-PN120008
7 January 2014
Revision 2
11



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The plant utilizes conventional process and unit operations. Run-of-mine (ROM) mineralized material will be crushed in a jaw crusher, and conveyed to a stockpile. The crushed mineralized material will be reclaimed and conveyed to a grinding circuit. The grinding circuit consists of one SAG mill and one ball mill. The SAG mill will operate in closed circuit with a vibrating screen. The ball mill will operate in closed circuit with hydrocyclones. Hardness of the mineralized rock has not been precisely tested at this time. The mill sizes are therefore estimated based on preliminary tests. Cyclone overflow is feed to the flotation plant.

The flotation plant will consist of rougher flotation and three stages of cleaner flotation with concentrate regrinding between the rougher and cleaner stages. Final concentrate will be thickened, filtered, bagged, and loaded in trucks for shipment.

The auxiliary systems such as the reagent mixing and storage, air and water systems, maintenance and office requirements are listed but not necessarily detailed for this study. Estimates for such items are based on other similar projects. The reagent consumption is estimated from the laboratory flotation tests and data from other properties. The grinding media consumption is estimated from other similar operations.

1.10        INFRASTRUCTURE

The property is within close proximity to highway 49 that runs north-south between Rio Grande and Juan Armada Municipality. From highway 49, a two-lane paved road that goes to the town of Nieves passes within 3 km of the property.

A new unpaved road will be constructed to access the main processing and tailing facility. The mine will construct haul roads with mining equipment to transport mineralized material and waste.

Comisión Federal de Electricidad (CFE) is the regional supplier of power in Mexico. This power is carried largely on Mexico’s high voltage transmission systems. The project is located near a high voltage transmission line that run runs parallel to Highway 45. A new substation will be constructed and a new 115 kV power line will be run a short distance from highway 45 to the site.

Water exploration was not performed as part of the PEA. Deep regional groundwater aquifers can typically be found in this area. It was assumed that a well field could be located within 5 km of the processing facility.

A new tailing storage facility (TSF) utilizing downstream dam construction will be placed south of the processing facility. Topography dictated the location of the dam, which is approximately 2.5 km from the processing facility. Tailing material will be pumped from the process area tailing thickener and spigotted into the facility. The facility will be constructed in phases. The initial phase will hold approximately 3 years of mill production; the dam will then be raised incrementally until the end of the mine life.

     
M3-PN120008
7 January 2014
Revision 2
12



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Ancillary facilities will be constructed to support the mine and processing operations. These facilities include an administration building, mine equipment maintenance shops, mine equipment wash, laboratory, explosives storage, warehouse and gatehouse.

1.11        CAPITAL COSTS

The project costs were estimated using a combination of project specific data and historical and in house data on similar projects. The accuracy of the estimate is PEA or scoping level, which is +/- 30%. Contingency was included at 20% of Process and Infrastructure contracted costs. All costs are in Q3, 2012 US Dollars.

Table 1-4: Initial Capital Costs

Item Estimated Cost
(USD, Millions)
Description
Infrastructure $56.00 General Site, Tailing Dam, Tailing Handling, Power, Electrical, Water Systems, Ancillary Buildings
Processing Facilities $59.50 Primary Crushing, Stockpile, Grinding/Classification, Flotation/regrind, Concentrate Thickening/Filtration, Reagents
Mining Costs $44.40 Mine Equipment and Pre production Operating Costs
Indirect Level Costs $71.70 Contractor Camp Costs, Mobilization, EPCM, First Fills, Owner's Costs, Commissioning, Contingency
Total Cost $231.60  

1.12        OPERATING COSTS

Operating costs were built up based on anticipated labor and estimated consumption rates and presented below.

Table 1-5: Operating Cost Summary

Mining Cost ($/tonne milled) $6.75
Concentrator Operating Cost ($/tonne milled) $9.43
General Administration Cost ($/tonne milled) $1.41
Total Operating Costs / tonne milled $17.59

1.13        FINANCIAL MODEL

The Nieves Project economics were done using a discounted cash flow model. The financial indicators examined for the project included the Net Present Value (NPV), Internal Rate of Return (IRR) and payback period (time in years to recapture the initial capital investment). Annual cash flow projections were estimated over the life of the mine based on capital expenditures, production costs, transportation and treatment charges and sales revenue. The life of the mine is 10 years. Metal price assumptions are $27/ounce silver and $1,300/ounce gold. The after tax financial indicators based on a 100% equity case are summarized as follows:

     
M3-PN120008
7 January 2014
Revision 2
13



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 1-6: Financial Model Indicators

  Before Taxes After Taxes
NPV @ 0% ($000) $333,968 $232,372
NPV @ 5% ($000) $199,224 $122,989
NPV @ 8% ($000) $142,319 $77,116
IRR % 21.9% 15.7%
Payback – years 3.4 4.4

The project is most sensitive to metal prices, capital costs and operating costs as shown below.

Figure 1-4: NPV 8% After Tax Sensitivity Table

1.14        RESULTS, CONCLUSIONS AND RECOMMENDATIONS

The Nieves project is located in a region of Mexico familiar with mining. A workforce exists in the area that is capable of operating the property. The processing facilities described in this report can be considered conventional in nature and do not require specialized, high risk processes. M3 recommends further metallurgical testing. The project should be further evaluated as a pre-feasibility study.

     
M3-PN120008
7 January 2014
Revision 2
14



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

2

INTRODUCTION

   
2.1

PURPOSE

This document was prepared in order to provide a technical evaluation consistent in format with the NI 43-101 standard and to present data and information developed to substantiate technical and economic viability of the Nieves Project in Zacatecas, Mexico.

This report provides an independent Technical Report, compliant with the Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects (NI 43-101).

This report was prepared by M3 Engineering & Technology Corporation (M3) at the request of Quaterra Resources, Inc.

Quaterra Resources Inc.
Head Office
Suite 1100 - 1199 West Hastings Street
Vancouver, B.C.
V6E 3T5
Canada

Toll Free: 1 (855) 681-9059
Tel: 1 (604) 681-9059
Fax: 1 (604) 641-2740

This report is current as of 31 October 2012.

2.2        AUTHORS

Quaterra contracted a team of qualified consultants to assemble the PEA.

     
M3-PN120008
7 January 2014
Revision 2
15



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 2-1: Qualified Persons for this Report

Responsibility Qualified Person Registration Company Sections of
Responsibility
Site Visit
Process Plant Cost & Principal Author Joshua Snider PE M3 Section 1, 2, 3, 4, 18, 19, 20, 21, 22, 23, 24, 25, 26, and 27 October 2012
Mine Design and Planning Jeff Choquette PE HRC Sections 16, 25, 26 and portions of Section 1, 25 and 26 None
Process & Metallurgy Thomas L. Drielick PE M3 Section 13, 17 and portions of Section 1, 25 and 26 None
Geology Zsuzsanna Magyarosi P.Geo CC Sections 5, 6, 7, 8, 9, 10, 11, 12, 15, jointly responsible for sections 25 and 26 (for geology) None
Resource Jason Baker P.Eng. CC Section 14 and portions of Section 1, 25 and 26 None
Geology Doris Fox P.Geo CC Section 12.1 (Site Visit) and jointly responsible for sections 5, 7, 8, 10.2 (Sampling procedures), 11.1 (Sample security) and portions of Section 1, 25 and 26 March 2012

The companies listed above included the following:

  • M3 Engineering & Technology Corporation, Tucson AZ (M3)
  • Caracle Creek International Consulting, Sudbury, Ontario Canada (CC)
  • Hard Rock Consulting, Golden CO (HRC)

2.3        SOURCES OF INFORMATION

This report is based in part on internal company technical reports, previous feasibility studies, maps, published government reports, company letters and memoranda, and public information as listed in the references section in the conclusion of this report.

2.4        UNITS AND TERMS OF REFERENCE

This report uses metric units expressed in metric tonnes, meters, and liters consistent with metric standards. The monetary units are expressed in US Dollars. The important terms used in this report are presented in Table 2-2.

Table 2-2: Terms and Abbreviations

Full Name Abbreviation
AMEC Environment & Infrastructure (a division of AMEC Americas Ltd. ) AMEC E&I
AMEC E&C Services Inc. AMEC E&C
Canadian Institute of Mining, Metallurgy and Petroleum CIM
Catch per Unit Effort CPUE
centimeter cm

     
M3-PN120008
7 January 2014
Revision 2
16



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Full Name Abbreviation
Copper Cu
cubic meter m3
degrees °
degrees Celsius °C
Feasibility Study FS
Global Discovery Laboratory GDL
Global Positioning System GPS
Gold Au
grams per tonne g/t
hectare ha
Inductively Coupled Plasma ICP
International Finance Corporation IFC
Iron Fe
kilogram kg
kilometer km
kilotonnes kt
Labor Secretariat STPS
Labour Party PT
Licencia Ambiental Unica LAU
Local Study Area LSA
M3 Engineering and Technology Corp. M3
Manifestación De Impacto Ambiental (or Environmetnal Impact Statement) MIA
Mean Sea Level MSL
Metal Leaching ML
Meter m
metric tonnes per day MTPD or t/d
metric tonnes per year (or per annum) MTPY or t/a
Mexican National Water Commission (Comisión Nacional de Agua) CONAGUA
Minera Media Luna S.A. de C.V. MML
Minera Nukay Nukay
Miranda Mining Development Corporation MMC
National Action Party PAN
National Council for Evaluation of Social Development Policy CONEVAL
National Population Council CONAPO
National Water Commission CNA
Neutralization Potential Ratios NPRs
Normas Oficiales Mexicanas NOMS
North American Free Trade NAFTA
ordinary kriging OK
Particulate Matter PM
parts per billion ppb
parts per million ppm
Pre-Feasibility study PFS
Qualified Person QP
Quality Assurance and Quality Control QA/QC
Reverse Circulation RC
Silver Ag
Square meter m2
Universal Transverse Mercator UTM
Zinc Zn

     
M3-PN120008
7 January 2014
Revision 2
17



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

3          RELIANCE ON OTHER EXPERTS

M3 Engineering and Technology Corporation has completed this Report in accordance with the methodology and format outlined in National Instrument 43-101. This Report was prepared by competent and professional individuals from M3 and other consulting companies on behalf of the Company and is directed solely for the development and presentation of data with recommendations to allow the Company and current or potential partners to reach informed decisions.

M3 relied upon contributions from a range of technical and engineering consultants as well as Quaterra. M3 has reviewed the work of the other contributors and finds this work has been performed to normal and acceptable industry and professional standards. In conclusion, M3 is not aware of any reason why the information provided by these contributors cannot be relied upon.

An independent verification of land title and tenure was not performed. M3 has not verified the legality of any underlying agreement(s) that may exist concerning the licenses or other agreement(s) between third parties. Likewise, Quaterra has provided data for and verified water rights, land ownership, and claim ownership.

A draft copy of the report has been reviewed for factual errors by Quaterra. Any changes made as a result of these reviews did not involve any alteration to the conclusions.

M3 relied upon José Nieto Caraveo for input on Section 20, Environmental Studies, Permitting and Social or Community Impact.

     
M3-PN120008
7 January 2014
Revision 2
18



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

4

PROPERTY DESCRIPTION AND LOCATION

   
4.1

LOCATION

The Nieves Property is located in the Francisco R. Murguia Municipality of the Zacatecas Mining District near the southeastern boundary of the Sierra Madre Occidental Physiographic Province in central Mexico (Figure 4-1 and Figure 4-2). The Property is centered approximately at 694856E, 2651009N (NAD27 Mexico, Zone13), approximately 150 km northwest of the state capital of Zacatecas and 90 km north of the mining community of Fresnillo.

     
M3-PN120008
7 January 2014
Revision 2
19



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 4-1: Location of the Nieves Property

     
M3-PN120008
7 January 2014
Revision 2
20



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 4-2: Location of the Nieves Property Showing Major Roads and Waterways

     
M3-PN120008
7 January 2014
Revision 2
21



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

4.2        DESCRIPTION AND OWNERSHIP

The Nieves Property consists of 18 concessions, issued for 50 years, covering approximately 12,064 ha (Table 4-1 and Figure 4-3). These concessions are registered in the name Minera Cerro Gregorio, as of August 5, 2011, a Mexican company wholly owned by Quaterra. Minera Cerro Gregorio does not own the surface rights on the concessions. The location of a concession is determined from the position of a single claim monument (“mojonera”). The corners are all located based on surveyed distances and bearings from that monument by a registered Mexican Mineral Concession Surveyor.

The Nieves Property is jointly owned by Quaterra and Blackberry. In 2011, Quaterra and Blackberry (through Minera Cerro Gregorio) paid US $44,538 to the Mexican government in taxes to maintain the concessions (Table 4-2). In 2012, Quaterra and Blackberry paid US $33,854 and are required to pay an additional US $36,519 to maintain the Nieves Property. The taxes are payable every six months. Net smelter return royalties remain outstanding on each of the concessions acquired from Kennecott (recently purchased by Royal Gold Inc.) and the Mexican concessionaires (Abelardo Garza Hernandez, Noel McAnulty and Bill Shafer) (Table 4-3).

On January 16th, 1995, Kennecott entered into an option agreement with Mexican concessionaires that allowed Kennecott to explore and acquire the Nieves Property by making specified option payments over five years, and advance minimum royalty payments.

On March 13th, 1998, Kennecott transferred its rights under the Nieves option to Western in consideration for an uncapped 2% NSR on certain core concessions and a 1% NSR on others. Western subsequently assigned its rights to the Nieves Project as specified in the “Underlying Agreement” to Quaterra on March 26th, 1999, in consideration for 1,444,460 common shares of the Company at a deemed price of CDN$0.20 per share (CDN$288,892). In addition, the Company issued 360,000 common shares at a deemed price of CDN$0.20 per share (CDN$72,000) to the concessionaires in lieu of the US$50,000 option payment otherwise due under the terms of the Underlying Agreement.

The payment schedule in the Underlying Agreement was amended on November 22nd, 1999, February 11th, 2000 and May 2002, such that US$30,000 was paid in January 2000, US$15,000 in May 2002 and US$25,000 in January 2003, for a total of US$70,000. In addition, to acquire the interest in the claim fractions the Company paid US$40,000 to the concessionaires. Advanced minimum royalty (AMR) payments of US$75,000 are due on or before the 26th of January each year from 2004 until the commencement of commercial production. The Nieves concessions are subject to a maximum 3% NSR to the original concession holders, which the Company may purchase at any time for US$2 million (Table 4-3).

On April 10th, 2003, Quaterra completed a US$1.5 million limited partnership financing with Blackberry, whereby Blackberry could earn a 50% interest in the Property by funding two exploration programs of US$750,000 each. The initial payment of US$750,000 received in the 2003 Fiscal Year was expended on a 5,300-metre drill program on the Nieves Property. During the 2004 Fiscal Year, Blackberry elected to continue by advancing a further US$750,000 towards a follow-up drill program completed in May 2005, thereby earning a 50% interest in the Property. The partners signed a joint venture agreement in 2006 and have jointly contributed to all exploration costs subsequently incurred.

     
M3-PN120008
7 January 2014
Revision 2
22



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

On January 24th, 2007, Kennecott’s royalty was purchased by Royal Gold Inc.

On August 5, 2011, the Nieves asset was transferred into a single purpose company, Minera Cerro Gregorio.

The author is not aware of any significant environmental liabilities related to the current exploration of the Nieves Property. The areas of primary mineral exploration are generally flat-lying, sparsely populated with a few cultivated areas and the remaining land area used for the periodic grazing of livestock. Minimal rehabilitation measures such as stabilizing slopes and planting local flora (Buffell grass) in areas of disturbance is usually sufficient to satisfy the ecological authorities, the Instituto de Investigaciones Forestales, Agricolas y Pecuarias (“INIFAP”), a government office based in Calera, Zacatecas. There is little to no surface water for exploration or mining activities but an abundance of ground water exists and the ownership of mineral rights generally allows access to ground water as needed.

Dispersed tailings from historic operations are present and a number of the historic workings have old waste dumps associated with them. It is recommended that Quaterra locate and document all of the historic dumps (mineralized material and tailings), mark and fence off or otherwise make secure all open holes and workings, and initiate baseline environmental studies. To the extent known to the author, there are no significant factors or risks that may affect access, title, or the right or ability to perform work on the property. Exploration drilling has been conducted under a permit issued by the Secretaria de Medio Ambiente y Recursos Naturales (SEMARNAT). The permit expired on October 15, 2012, but may be extended by request received prior to September 14, 2013.

     
M3-PN120008
7 January 2014
Revision 2
23



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 4-3: Concessions on the Nieves Property

     
M3-PN120008
7 January 2014
Revision 2
24



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 4-1: List of Concessions on the Nieves Property

Table 4-2: Details of Tax Payments to the Mexican Government on the Nieves Property

 
     
M3-PN120008
7 January 2014
Revision 2
25



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 4-3: Details of NSR on the Nieves Property

 
     
M3-PN120008
7 January 2014
Revision 2
26



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

5

ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

   
5.1

ACCESS

Quaterra/Blackberry exploration activities are co-ordinated from the small town of Nieves (now re-named Francisco R. Murguia) where they maintain an office and a house. The town of Nieves is accessed via Highway 49, a paved, two-lane toll highway approximately 200km north of the city of Zacatecas. The town of Nieves is accessed via a 17 km paved road from Highway 49. The nearest major population and service centre to Nieves is the mining town of Fresnillo located ~90 km to the south. Fresnillo has a population of approximately 75,000 and services the Fresnillo Mine run by Peñoles. Fresnillo offers a substantial professional work force experienced in mining and related activities in addition to most other supplies and services. International airports are located within approximately a three hour drive of the Property in the city of Zacatecas to the south, and in Torreõn (Coahuila state) to the north. Road access to the Property is excellent with the main paved highway to Nieves running along the northern portion of the Property (Figure 4-1 and Figure 4-2). A network of dirt roads and trails provide access to the historical mining operations and extend southward to all areas of the Property. Drill and access roads can be easily built as most of the Nieves Property is flat-lying with only a few dry creek beds (Figure 5-3).

     
M3-PN120008
7 January 2014
Revision 2
27



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 5-1: Dirt Road Accessing Nieves Property (Photo from Doris Fox)

5.2        PHYSIOGRAPHY, CLIMATE AND VEGETATION

The Nieves Property lies within the Mexican Altiplano or Mesa Central region. This region is flanked to the west by the Sierra Madre Occidental and to the east by the Sierra Madre Oriental mountain ranges (Figure 5-2). The Altiplano in this region is dominated by broad alluvium filled plains between rolling to rugged mountain ranges and hills reaching up to 3,000m above mean sea level (“AMSL”) and average elevations in valleys of approximately 1,700m. Elevations on the Nieves Property range from 1,900 m to 2,000 m AMSL. The terrain is generally flat-lying with a prominent north-south trending ridge along the eastern portion of the Property with moderate to vertical slopes (Figure 5-3). There is very little human habitation on the Property, with only a few widely scattered farm houses, although the town of Nieves directly borders the Property to the northeast.

The climate in the region is continental, warm and arid with temperatures ranging from 0oC to 41oC, averaging ~21oC and less than 1,000 mm of annual precipitation. Due to the limited precipitation, vegetation is sparse and hardy consisting mainly of grasses, low thorny shrubs (including mesquite) and various cacti, with scattered oak forests at higher elevations. Surface water is rare but ground water is readily available. Drilling is feasible year round. Rain in the wet season, May to October, can make drilling conditions difficult due to muddy ground conditions, but not impossible.

     
M3-PN120008
7 January 2014
Revision 2
28



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 5-2: Major geological and physiographical regions and mining districts in Mexico (after Stone 2010)

     
M3-PN120008
7 January 2014
Revision 2
29



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 5-3: Typical Landscape on the Nieves Property Looking North

(photo from Doris Fox)

     
M3-PN120008
7 January 2014
Revision 2
30



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

6

HISTORY

   
6.1

EXPLORATION ACTIVITIES BETWEEN 1560 AND 1994

The first discovery on the area covered by the Nieves Property was the Santa Rita Vein in 1560 by Spanish explorers (Turner, 1999; Cavey, 1999). Soon after in 1574 the Concordia vein was discovered. The Santa Rita and Concordia- San Gregorio-Dolores veins were the focus of mining by the Spanish and Mexican miners until 1880.

Most of the activity in the Nieves District occurred between 1880 and 1910, when an English company, the Mexican Rosario Mining Company, and two Californian companies, the Almaden Mining Company and the Concordia M. and M. Company, worked in the area. These companies worked on the Concordia vein primarily while a small independent miner Gonzáles Piñera worked concurrently on the San Gregorio vein (Turner, 1999; Cavey, 1999). The locations of the old mines are shown in Figure 6-1.

Prior to the 1910 revolution, which halted all production in the Nieves District, total ore production in the District was estimated at 50,000 tonnes (Turner, 1999). The only production reported is from the Concordia Mine where 5,414 tonnes at a grade of 4,065 g/t silver were produced (Figure 6-1). This production data cannot be relied upon and has not been verified by the qualified person. The qualified person has not done sufficient work to classify the historical production as current mineral resource and is not treating the historical estimate as current mineral resource.

Between 1910 and 1978 several companies (including Fresnillo Mining: 1936; Scurry-Rainbow: mid-1960’s to 1978) attempted to de-water, sample, and re-open the historical workings in the Concordia and Santa Rita mines, and were largely unsuccessful (Figure 6-1). However, underground drilling from this period intersected and confirmed the presence of the Santa Rita Vein 100 m below the 8th level. Included in this time period, is a site visit by D.B. Dill for Peñoles Mining, in 1954, who compiled and preserved much of the historical data for the Nieves District. Dill (1954) reported 21,500 tonnes of probable mineralized material at a width of 0.92 m and a grade of 0.92 g/t Au, 1131 g/t Ag, and 2-4% Sb, still remained in the Concordia Vein and a prospective 120,000 additional tonnes. This resource estimate cannot be relied upon, has not been verified by the qualified person, nor is it NI43-101 compliant resource estimate. The qualified person has not done sufficient work to classify the historical estimate as current mineral resource and is not treating the historical estimate as current mineral resource.

The Santa Rita vein and refurbished mill and flotation plant were purchased by Fomento Minero in 1978, who operated the mine until 1987. Fomento Minero also sank three shafts and deepened a historic shaft along the Concordia- San Gregorio vein system during the 1970’s (Figure 6-1). The flotation mill was capable of running 100 tonnes/day during this time and was fed 50% tailings and 50% ore with an average head grade of 130 g/t silver, 2% lead, 2.4% zinc and 2.5% antimony, according to Consejo Recursos Minerales (CRM) (Cavey, 1999). Today, all that remains are the building foundations, abandoned shafts and power lines.

     
M3-PN120008
7 January 2014
Revision 2
31



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 6-1: Location of Old Mines on the Nieves Property

     
M3-PN120008
7 January 2014
Revision 2
32



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

6.2        EXPLORATION ACTIVITIES BETWEEN 1994 AND 2010

Exploration activities between 1994 and 2010 included mapping, rock and soil sampling, several geophysical surveys and a total of 9 drill programs (Table 6-1). The companies performing the work included Kennecott, Western Copper, Quaterra and the joint venture of Quaterra and Blackberry.

Table 6-1: Summary of Exploration Activities Between 1994 and 2010

Company Year

Exploration Activities

Kennecott 1994-1996

Reconnaissance geologic mapping at 1:25,000 scale

  

535 rock samples assayed for gold, silver, arsenic, antimony, mercury, copper, lead, zinc and molybdenum

  

131 rock chip samples analyzed for gold, silver, arsenic, antimony, mercury, copper, lead, zinc, molybdenum, tin and tungsten

    

completed three (3) soil sampling surveys  

  

geophysical surveys including airborne and ground magnetics, a single dipole-dipole induced polarization-resistivity (IPR) line, and seven controlled source audio- frequency magneto-telluric (CSAMT) lines

   

drilled 8 RC holes

Western Copper 1997-1998

drilled 5 RC holes

Quaterra 1999-2000

geological mapping at 1:10,000 scale over an area of 6 x 8 km

    

detailed mapping at 1:20,000 scale over the Concordia vein system (approximately 2 km x 800m area)

  

205 rock chip samples were analyzed for gold, silver, arsenic, antimony, copper, lead and zinc

    

drilled 10 RC holes and deepened 4 holes by diamond drilling (QTA03, QTA07, QTA08, NV05)

Quaterra-Blackberry 2003 to 2006

air photograph interpretation

   

established a property wide grid

   

CSAMT and IP geophysical surveying

   

surveying of historic drill collars

   

surface sampling and assaying

   

drilled 32 diamond drill holes (total = 16,369.94m; Phases I-III)

   

Independent Technical Report (Wetherup, 2006)

  2007 and 2008

air photograph interpretation

   

field checking possible geochemical/geophysical/geological anomalies

   

drilled 40 diamond drill holes (total = 11,562.80m; Phases IV and V)

  2009

Initial Mineral Resource Estimate and Independent Technical Report (Stone, 2009)

  2009 and 2010

Drilled 29 holes (6,118.70m; Phase VI)

   

Geophysical surveying

     

Updated Mineral Resource Estimate and Independent Technical Report (Stone, 2010)


     
M3-PN120008
7 January 2014
Revision 2
33



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

6.2.1      Kennecott exploration between 1994 and 1996

In the early 1990’s, a group of Mexican concessionaires (Abelardo Garza Hernandez, Noel McAnulty and Bill Shafer) assembled a land position in the area and presented it to Kennecott who signed the option agreement on January 16th, 1995. Exploration work completed by Kennecott included geologic mapping, surface sampling (535 rock samples and 131 rock chip samples), three soil surveys, geophysical surveying (airborne and ground magnetic surveys, IPR survey, controlled source audio-frequency magneto-telluric survey) and reverse circulation (RC) drilling of the San Gregorio, California and Orion West veins (Figure 6-2 and Table 6-2).

In 1995 and 1996, 8 drill holes (NV01 to NV08) were drilled totaling 1532.5 m. The drilling intersected several zones of significant silver mineralization hosted by two distinct styles of mineralization. Drill hole NV08 in the California area intercepted two separate 2m intervals of high grade silver vein mineralization that returned assay values of 367 g/t and 795 g/t of silver at depths of 108m and 116m, respectively. In contrast, drill hole NV03 intersected a large low grade zone of silver mineralization at a depth of 180 m depth that averaged 82 g/t silver over 28 m. Drill hole NV03 also encountered a high grade silver vein at 148 m depth that returned 254 g/t silver over 2 m. Drill hole NV06 also encountered a large zone of low-grade silver mineralization that returned 67 g/t silver over 68 m.

Kennecott conducted several geophysical surveys including airborne and ground magnetic surveys, a single dipole-dipole induced polarization and resistivity (IPR) line and seven controlled source audio- frequency magneto-telluric (CSAMT) lines. No results were available to the author.

6.2.2      Western Copper exploration in 1997 and 1998

On March 13th, 1998, Kennecott transferred its rights under the Nieves option to Western Copper in consideration for an uncapped 2% NSR on certain core concessions and a 1% NSR royalty on others. Before assigning its rights to the Nieves Project to Quaterra on March 26th, 1999, Western Copper drilled 5 RC holes testing the California vein system (Figure 6-2 and Table 6-2). The holes were drilled in the area around hole NV08. Western Copper also twinned hole NV08 and reproduced similar assay values for the intercepts reported by Kennecott including 890 g/t Silver over 1.0 m in drill hole WCNV01. Holes drilled to intercept mineralization below drill hole NV08 returned assay values of 841 g/t silver over 0.45 m, 109 g/t silver over 0.8 m, and 1,081 g/t silver over 0.35 m in drill hole WCNV04.

6.2.3      Quaterra exploration in 1999 and 2000

Western Copper transferred its rights to the Nieves Property to Quaterra on March 26, 1999. In 1999 and 2000 Quaterra completed an exploration program consisting of geological mapping, sampling and drilling (Figure 6-2 and Table 6-1). Quaterra completed 10 drill holes on the Concordia and Gregorio North veins in conjunction with surface mapping and sampling programs during 1999 and 2000 and deepened four holes (Table 6-1 and Table 6-2). Table 6-3 shows significant drill results.

     
M3-PN120008
7 January 2014
Revision 2
34



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 6-2: Drill Programs Completed by Kennecott, Western and Quaterra

Table 6-3: Significant Drilling Results Completed by Quaterra in 1999 and 2000

 
     
M3-PN120008
7 January 2014
Revision 2
35



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 6-2: Location of holes drilled by Kennecott, Western and Quaterra between 1994 and 2000

     
M3-PN120008
7 January 2014
Revision 2
36



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

6.2.4      Quaterra and Blackberry 2003-2010

On April 10th, 2003, Quaterra completed a US$1.5 million limited partnership financing with Blackberry, whereby Blackberry could earn a 50% interest in the Property by funding two exploration programs of US$750,000 each, which was fulfilled. In 2006 Quaterra and Blackberry signed a joint venture agreement and have jointly contributed to all exploration costs subsequently incurred.

Exploration between 2003 and 2010 by Quaterra and Blackberry included air photograph interpretation, surface sampling, field work, two geophysical surveys, six drill programs and three 43-101 independent technical reports, two of which include 43-101 compliant resource estimations.

6.2.4.1    Drilling

Drilling by Quaterra and Blackberry started in 2004 and included six drill programs consisting of 72 drill holes, totaling 34,048.43 m (Figure 6-3 to Figure 6-5 and Table 6-4). Holes were drilled on every vein system on the property, but most of the veins concentrated on the Concordia vein system, where the resource was estimated.

Most of the drill holes were planned to target geophysical anomalies, to extend the known mineralized zones in length and depth and for in-fill drilling to increase the confidence in the resource estimation.

The drill programs were very successful and extended the known mineralized zones in several areas. The Concordia vein system was extended to at least 1,100 m along strike and 400 m down dip. Drill highlights are summarized in Table 6-5.

     
M3-PN120008
7 January 2014
Revision 2
37



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 6-4: Drilling Summary on the Nieves Property between 2004 and 2010

 
     
M3-PN120008
7 January 2014
Revision 2
38



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 6-5: Drill Highlights on the Nieves Property between 2004 and 2010

(Continued on next page.)

     
M3-PN120008
7 January 2014
Revision 2
39



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
40



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
41



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
42



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
43



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 6-3: Location of drill holes in Phase I, II and III drill programs

     
M3-PN120008
7 January 2014
Revision 2
44



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 6-4: Location of drill holes in Phase IV drill program

     
M3-PN120008
7 January 2014
Revision 2
45



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 6-5: Location of drill holes in Phase V and VI drill programs

     
M3-PN120008
7 January 2014
Revision 2
46



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

6.2.5

Geophysical Surveys

   
6.2.5.1

Geophysical survey 2003

In November and December 2003, Quaterra and Blackberry completed a geophysical survey consisting of 10 lines (6.6 km in length) of CSAMT and Controlled Source Induced Polarization (CSIP) for a total of 66 line-km. In addition, a Ground Magnetometer survey was completed consisting of 12 lines including the 10 lines surveyed with CSAMT for total of 76 line-km of magnetic surveying. The work was performed by Zonge Engineering and Research Organization of Tucson, Arizona (Job No. 0319). The CSAMT survey greatly extended coverage of the survey completed in 1995 and 1996 by Zonge Engineering on behalf of Kennecott. The survey identified several prospective anomalies, a number of which correspond to areas of known mineralization, but extend far beyond the limits of previous drilling (Quaterra News Release February 3, 2004).

The CSAMT survey identified six conductive features, three of which correspond to the areas of known mineralization along the Santa Rita, San Gregorio and Majada veins, the rest were previously unknown. These conductive zones coincide with some of the IP anomalies. The anomalies are interpreted to represent mineralization, have a southwest-northeast trend extending for distances up to 3.5 km and spaced at intervals of approximately 1000 m from north to south across the Nieves property.

The survey also identified a large undrilled IP anomaly west of San Gregorio and several smaller untested anomalies in the adjacent areas.

6.2.5.2    Geophysical survey 2010

Between May and August 2010, Quaterra and Blackberry conducted a geophysical survey performed by Zonge Engineering (Job No. 10094). The survey consists of 25 lines utilizing dipole-dipole or pole-dipole IPR (Induced Polarization and Resistivity) arrays, covering the Concordia-San Gregorio-Dolores vein system (14 lines); east extension of Santa Rita vein system (4 lines); the California vein system (4 lines); Manto-1 CSAMT target (1 line); and the El Rosario mercury occurrence (2 lines).

The results of the survey indicate the Concordia and San Gregorio are two separate veins and not fault offsets of the same vein, and identified strong anomalies along strike to the east and west of both veins that have not been drilled. The San Gregorio vein appears to be the eastern extension of the Orion vein, which is generally unexplored and under-explored for a distance of over 2500 meters.

The results of the survey east of the historic mine at Santa Rita vein indicate a zone of anomalies extending eastward a distance of 1000 m. The results from the two lines surveyed at the El Rosario mercury occurrence identified narrow zones of weak IP anomalies.

     
M3-PN120008
7 January 2014
Revision 2
47



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT
3

6.3

HISTORICAL MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES

   
6.3.1

CRM 1992

In 1992, CRM estimated the resources and reserves remaining in the Santa Rita Vein system (Table 6-6). These resource estimates cannot be relied upon, have not been verified by the qualified person, nor are they NI 43-101 compliant resource estimates. The qualified person has not done sufficient work to classify the historical estimates as current mineral resource and is not treating the historical estimates as current mineral resources.

Table 6-6: Historic Santa Rita Resources Calculated by CRM (Cavey, 1999)

Resource Category Tonnes Ag (g/t) Pb (%) Zn (%) Sb (%)
Positive 18,600 398 3 3.5 3
Probable 76,700 225 3.3 4.3 2.6
Possible 71,200 n/a n/a n/a n/a
Tailings 20,000 90 n/a n/a n/a

6.3.2        Quaterra/Blackberry 2009 and 2010 resource estimates

Quaterra and Blackberry contracted Caracle Creek to complete 43-101 compliant resources on the Nieves Property (Stone, 2009, 2010). The results are summarized in Table 6-7 and Table 6-8. Caracle Creek is not treating these resources as current; the resource within this report is the current resource on the Nieves Property.

Table 6-7: 2009 Resource Estimate for the Concordia vein system at a 60 g/t cutoff grade

Category Tonnes Ag (g/t) Au (g/t) Ag (oz)1 Au (oz)1
Indicated 2,897,571 110.231 0.126 10,269,203 11,701
Inferred 2,256,596 96.562 0.115 7,005,797 8,373
1ounces calculated using 31.103 g/t

Table 6-8: 2010 resource estimate for the Concordia and Gregorio North areas at a 45 g/t cutoff grade


Vein

Zone (Class)
Resource
Tonnes (t)1

Au (g/t)2

Ag (g/t)2

Au (oz)3

Ag (oz)3
Concordia La Quinta (Indicated) 4,590,000 0.1 103.4 14,757 15,259,171
Concordia La Quinta (Inferred) 10,516,000 0.08 85.5 27,048 28,907,758
San Gregorio North (Inferred) 4,005,000 0.15 79.4 19,315 10,223,998
1 tonnes have been rounded up to the nearest 1,000.
2gold is reported to 2 decimal places and silver to 1 decimal place
3 ounces calculated using 31.103 g/t

     
M3-PN120008
7 January 2014
Revision 2
48



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

7

GEOLOGICAL SETTING AND MINERALIZATION

   
7.1

REGIONAL GEOLOGY

The Nieves Property lies on the western flank of the Central Altiplano in Mexico, just east of the Sierra Madre Occidental ranges (Figure 4-1). Basement rocks underlying the western Altiplano are a Mesozoic assemblage of marine sedimentary and submarine volcanic rocks belonging to the Guerrero Terrane (Simmons, 1991) that sit unconformably on Precambrian continental rocks. In the Nieves area, the boundary between the Guerrero Terrane rocks and younger Jurassic-Cretaceous sedimentary sequences (interpreted to be the Caracol Formation on the Property) is unclear.

The late Cretaceous to early Tertiary Laramide Orogeny folded and thrust faulted the basement rocks throughout the area and preceded the emplacement of mid-Tertiary plutons and related dykes and stocks (Ruvalcaba-Ruiz and Thompson, 1988). Mesozoic marine rocks are host to the San Nicolas VMS deposit (Wendt, 2002).

Unconformably overlying the Mesozoic basement rocks in the western Altiplano are units from the late Cretaceous to Tertiary, Sierra Madre Occidental magmatic arc (Figure 7-3). These rocks consist of a lower assemblage of late Cretaceous to Tertiary volcanic, volcaniclastic, conglomerate and locally limestone rocks, the “lower volcanic complex” and a Tertiary (approximately 25-45 Ma) “upper volcanic supergroup” of caldera related, rhyolite ash-flow tuffs and flows. Eocene to Oligocene intrusions occur throughout the Altiplano and are related to the later felsic volcanic event. Locally, these two units are separated by an unconformity (Ruvalcaba-Ruiz and Thompson, 1988).

A late NE-SW extensional tectonic event accompanied by major strike-slip fault movement affected the Altiplano starting approximately 35 Ma ago. This extension was most intense during the Miocene and developed much of the basin and range topography currently exhibited in the area. Subsequent erosion of the ranges has covered most of the valleys.

7.2        PROPERTY GEOLOGY

Rocks underlying the Nieves Property are of two distinct ages: (1) Mesozoic “argillite” (interpreted to represent a calcareous finely bedded turbidite flysch) as belonging to the Caracol Formation overlain by (2) Tertiary rhyolitic volcaniclastic rocks separated by a presumably Tertiary age basal conglomerate and conglomeratic sandstone sequence. At Nieves, the Caracol Formation is isoclinally folded with an axial plane cleavage. Nieves veins parallel the cleavage.

7.2.1      Mesozoic Rocks

The most common rock types underlying the Nieves Property form a thick sequence of fine laminar grey to dark green argillite beds up to 1m thick that hosts the silver mineralization (Figure 7-1. These rocks have been assigned to the Caracol Formation of the late Cretaceous age. Argillite beds are more abundant to the south in the Santa Rita area and to the west in the Concordia area. The Caracol Formation is isoclinally folded with an axial plane cleavage, fold axes strike east-northeast to east and beds strike east- west and dip steeply south to near vertical.

     
M3-PN120008
7 January 2014
Revision 2
49



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 7-1: Sedimentary layers in argillite

(Photo from Doris Fox)

7.2.2      Tertiary Clastic Rocks

On the east side of the Nieves Property the Caracol Formation is overlain unconformably by a 1 to 10m thick conglomerate composed of rounded to sub-rounded limestone boulders 2 to 20 cm in diameter in a grey to brown sandstone groundmass. Above the limestone conglomerate there is up to 130m of conglomeratic sandstone with thin bands of calcareous conglomerate which was intersected in drill hole QTA-18 (Figure 7-2). These units dip shallowly.

     
M3-PN120008
7 January 2014
Revision 2
50



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 7-2: Surface Expression of Clastic Sediments on the Property

(Photo from Doris Fox)

7.2.3      Tertiary Volcanic Rocks

In drill hole QTA-18 (Phase I) 46 m of rhyodacitic to andesitic welded tuff occur above the conglomerate and conglomeratic sandstone. A thin 1.5 to 2 m unit of grey to dark grey basalt occurs above the tuff and is in turn overlain by at least 56 m of porphyritic rhyolite flows striking north-northwest and dipping northeast. These porphyritic rhyolite flows underlie a prominent north trending ridge on the east side of the Property and are the host rock for manganese-calcite veins and breccia mineralization previously exploited by local miners (Figure 5-3 shows the ridge).

7.2.4      Structural Geology

The oldest structures on the Nieves Property are the folds which affect the Mesozoic argillite beds. These structures are likely related to compression during the Laramide Orogeny in the Cretaceous. Thrust faults are also common features of structures attributed to the Laramide Orogeny and several have been suspected to occur on the Nieves Property.

     
M3-PN120008
7 January 2014
Revision 2
51



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Post-Laramide structures are in all cases brittle in nature and affect both the Mesozoic Caracol Formation sedimentary rocks and the Tertiary volcanic and sedimentary rocks. These structures include: (1) faults that strike 330o to 000o and dip moderately northeast to east with east plunging slicken-sides, (2) faults that strike 170o to 180o and dip steeply to the west, and (3) major vein structures that strike 240o to 270o and dip 60o to 90o to the south. A late vertical fault structure striking 020o to 030o offsets the major mineralized structures and offsets the Concordia from the San Gregorio vein systems.

     
M3-PN120008
7 January 2014
Revision 2
52



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 7-3: Geology map of the Nieves Property

     
M3-PN120008
7 January 2014
Revision 2
53



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

7.3

MINERALIZATION

   
7.3.1

Alteration and Styles of Mineralization

Generally, Mesozoic Caracol Formation rocks proximal to mineralized zones exhibit a weak bleaching halo that results from the oxidation of 2% to 5% disseminated pyrite throughout these rocks. Pyrite and thin calcite veinlets occur adjacent to mineralized zones in a pyrite-carbonate alteration assemblage called P-C type (pyrite-carbonate).

A local, more intense alteration assemblage includes weak to moderate sericite replacing thin calcite veinlets and weak to advanced fine-grained quartz replacing calcite, associated with an increase in fine grained pyrite. This alteration type, described as QSPC (quartz-sericite-pyrite-carbonate) is present in close proximity to the mineralized structures in some drill holes. Stibnite rosettes are commonly associated with the sericite veinlets.

Silicification, mainly of sandstone beds, occurs in a few zones on the Nieves Property as in the hill located north of the Santa Rita vein. Weak chlorite alteration of tuffs and conglomeratic sandstone occurs in drill hole QTA-18 in the manganese mine area within the Tertiary rhyolitic rocks on the east side of the Property (Figure 7-3).

Four types of mineralization have been identified on the Nieves Property and are described below.

7.3.2      Jasperoid Structures

Jasperoid structures located to the northwest of the Concordia-Dolores vein system are characterized by silicified tan to black coloured rocks with abundant thin jasper, fine grained quartz micro-breccia and veinlets with up to 5% disseminated pyrite. These jasperoid structures are 1 to 12 m wide, strike northwest and dip southwest. Locally, jasperoid bodies are anomalous in gold, arsenic and antimony with erratic silver, lead and zinc values.

Possibly a related mineralization style to the jasperoid structures are silica breccia veins that are typically composed of small silicified rock fragments in a saccaroidal quartz groundmass.

7.3.3      Iron Carbonate Veins

Iron carbonate veins include mostly calcite and scarce rhodochrosite with hairline to 10 cm wide pyrite veinlets which are abundant up to hundreds of meters away from partially to totally replaced quartz veins. Some veinlets contain stibnite and silver sulphosalts and are abundant in surface alteration halos as well as above and below mineralized material intercepts in drill core. Low grade silver often is associated with this type of veinlet.

7.3.4      Carbonate-Quartz-Sulphide Veins

Carbonate-quartz-sulphide veins are the most economically important veins and consist of calcite that is partially to totally replaced by grey to white, chalcedonic, fine-grained quartz veins and veinlets (Figure 7-4). These veins are from centimetres to 1.5 m wide with up to 50% sulphide minerals. Sulphides include pyrite, stibnite, sphalerite, galena, chalcopyrite and the silver sulphosalts: proustite, pyrargyrite, jamesonite and scarce tetrahedrite. The best grades of silver, gold, lead and zinc occur in these veins and past production has come primarily from this vein type.

     
M3-PN120008
7 January 2014
Revision 2
54



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 7-4: Carbonate- Quartz-Sulphide Mineralized Veins 7.3.5 Calcite-Manganese-Oxide Breccias and Veins

These mineralized structures which may be 5 to 10 m wide and up to 150 m long include breccias formed by sub-angular volcanic fragments in a clay-altered sandy groundmass (Figure 7-5). Thin veinlets of ferro-manganese oxides form stockwork zones of clay-altered volcanic rocks and occur along the borders of the breccia bodies in the Manganese mine area (Figure 7-3).

     
M3-PN120008
7 January 2014
Revision 2
55



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 7-5: Mineralized Oxide-Breccia in Core

(photo by Doris Fox)

7.3.6      Mineralized Zones

On the Nieves Property there are three major east to east-northeast striking silver vein systems, the California, Concordia- San Gregorio-Dolores, and Santa Rita veins systems (Figure 7-3). In addition to these silver mineralized systems there is an east-northeast to east-southeast striking manganese breccia system hosted by rhyolitic rocks on the east side of the Property. Local miners have worked on all of these areas, previously.

7.3.7      California Vein System

The California vein is marked by a shaft and series of small open cuts aligned 250° to 255° over a distance of 300 m. Only thin and discontinuous quartz-oxide veinlets outcrop near the workings. The California vein system shows a large 150-600m wide alteration zone extending about 2,700 m along strike. Local stockwork zones contain thin calcite veinlets in part weakly replaced by quartz-oxide veinlets. The California vein was intercepted in Kennecott hole NV08 in two intervals at depths of 108 m and 116.0 m that returned assays of 367 g/t silver over 2 m and 795 g/t silver over 2 m respectively. Recent drilling increased the length of known mineralization along the California vein system to approximately 550 m and mineralization remains open to the east. The total width of the mineralized zone may extend up to 130 m, suggested by assay results from drill hole QTA-130, which intersected several mineralized veins between 22 and 158.9 m grading between 79 g/t over 8 meters to 235 g/t over 2 m. The true width of the mineralized zone is not known.

     
M3-PN120008
7 January 2014
Revision 2
56



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

7.3.8      Concordia- San Gregorio-Dolores Vein System

The Concordia- San Gregorio -Dolores vein system has a known strike length, in mine workings of nearly 1.8 km in two system of veins, (1) the 240º-260° striking Concordia-San Gregorio vein and (2) the 260°-270º striking Dolores splay. Both veins dip from 60º southward to near vertical. The Concordia-San Gregorio-Dolores system is composed of carbonate to quartz-sulphide veins and varies in width from tens of centimetres up to 1.5m. The most recent drill program extended the total length of the known mineralized zone along the Concordia vein to approximately 1,300 meters. The true width of the mineralized zone along the Concordia vein ranges between 40 and 100 m.

The San Gregorio vein appears to be the continuation of the Concordia structure, assuming approximately 50 m of left lateral offset from a north trending fault that presumably follows the San Gregorio arroyo. The San Gregorio vein structure can be traced in some small open cuts for about 500 m to the northeast at an azimuth of 250° to 260°. Surface samples from 10 to 40 cm wide calcite to quartz veins with oxides returned silver assays of up to 954 g/t.

The Dolores vein is interpreted to be a splay of the Concordia vein, strikes at 260º to 270° and is traced for nearly 500 m on surface by numerous small open cuts and at least five shafts. A stockwork zone of thin calcite to quartz and oxides veinlets in the hanging wall extends on surface for up to 250 m across strike from the main vein and along strike for an additional 350m from the last workings on the vein. Surface samples of some of the thin stockwork veinlets from this zone returned silver assays of up to 553 g/t.

The Concordia and Dolores veins appear to intersect to the west of the Rosario Shaft in an area of abundant calcite and lesser quartz veinlets. This area was evaluated on the surface by two long trenches separated by 85 m, with 2 m wide channel samples collected 10 to 20 cm below the surface. No results were available to the author.

The Gregorio North area is located north of the San Gregorio vein, in the Gregorio Hill area and it is probably part of the Concodia-San Gegorio-Dolores vein system. The recent drill program was successful in extending the length of the mineralized zone to approximately 1,200 m. The true width of the mineralized zone in the Gregorio North area ranges between 100 and 200 meters.

7.3.9      Santa Rita Vein System

The Santa Rita vein system, located in southern portion of the Property, strikes 230° to 260° and can be recognized in shafts and in short drifts for over 500 m. Last production during 1970-1985 came from the lower levels of the mine which was deepening to 9 levels reaching a depth of 282m. The Santa Rita vein contains a series of veinlets in the footwall that form a wide stockwork zone in an area of 100 x 100 m centered on a small silica altered hill north of the main Santa Rita drift. A sub-parallel vein also occurs about 100 m southwest of the main Santa Rita vein.

     
M3-PN120008
7 January 2014
Revision 2
57



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Quaterra hole QTA-16 tested the Santa Rita vein at a depth of 350m and intercepted a 3.1m interval that averages 71.44 g/t silver, 0.56% lead and 0.91% zinc. QTA-37 also appears to have cut the Santa Rita vein system at 416 m depth where it encountered a 5.90 m zone that averaged 104 g/t silver, 0.23% lead, and 0.55% zinc.

In the phase VII and VIII drill program, a total of 15 drill holes systematically tested the Santa Rita vein system over 500 along strike, the total length of mineralization was extended to approximately 750 m and remains open to the west. Drilling suggests the presence of several parallel vein systems. The apparent width of the mineralized zone along the Santa Rita vein system may be up to 340 meters, suggested by drill hole QTA-25 that intersected several mineralized veinlets over 340 meters with grades ranging from 129 g/t over 1.2 meters to 405 g/t over 0.29 meters.

Recent mapping on the West Santa Rita area identified two groups of narrow, sub-parallel 2 to 30 centimeter wide calcite-quartz veinlets, some of which contain strong gold and silver mineralization. The first group of veinlets has an east-northeasterly trend and extends 120 to 200 meters along strike with a width of 100 meters. The best results include 8.11 ppm gold over 0.2 meters, 253 ppm silver over 0.4 meters, 4,460 ppm lead and 2,690 ppm zinc over 0.4 meters.

7.3.10     Manganese Mineralization

Various small pits and drifts sunk on calcite-manganese-oxides breccias and stockwork veinlets hosted in volcanic rocks occur 1 km east of the Concordia-Dolores- San Gregorio vein system on the eastern side of the Nieves Property (Figure 7-3).

The stockwork zone is flanked to the north and south by two breccia structures formed by sub-angular volcanic fragments in clay altered sandy groundmass with irregular ferroan calcite and manganese oxides of possible hydrothermal origin. The north breccia structure is 150 m long by 5 to 10 m wide, trends 290 to 300 and dips 75° to south. The southern breccia is 115 m long by 7 m wide, trends 070 and dips 75° to the north.

A second zone of calcite-manganese-oxide breccia occurs 230 m south of those described above. It is 150 m long by 5 m wide, trends 075 and dips 67o north. Surface and underground rock samples from this area were anomalous in silver, arsenic, antimony, tungsten, molybdenum and cobalt. Drill hole QTA-18 tested the depth extent of these structures but intersected no significant mineralization.

     
M3-PN120008
7 January 2014
Revision 2
58



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

8

DEPOSIT TYPES

Silver mineralization on the Nieves Property is best classified as low-sulphidation epithermal mineralization and is the primary exploration target. Several other styles of mineralization are found within the ages of rocks observed on the Nieves Property and are potential secondary exploration targets.

8.1        EPITHERMAL HIGH-GRADE SILVER VEINS

Within the Altiplano Region of Mexico, epithermal silver veins are the dominant deposit type with world- class examples such as Pachuca, Zacatecas, Fresnillo, and Guanajuato. The closest of these world class examples is the Fresnillo Deposit owned and operated by Peñoles, located 90 km to the south of the Nieves Property. Several styles of silver mineralization occur in the Fresnillo Deposit including (1) mantos and chimneys, (2) stockworks (Cerro Proaño area), (3) disseminated ores in areas of propylitic alteration, and (4) veins that show vertical mineralogical zonation (e.g. the Santo Niño vein). The veins are currently being mined by Peñoles and they are actively exploring for more of these mineralized structures (Garcia et al. 1991).

In the Santo Niño Vein the high-grade silver mineralization averaging 769 g/t silver, 0.56 g/t gold, 0.99% zinc, 0.5% lead, 0.03% copper; (Gemmel et al. 1988) is hosted in a single fault structure that locally bifurcates or is separated into en-echelon offset structures. It is between 0.5 to 4m wide, averaging 2.5m wide, and extends for over 2.5 km. Typically in these veins, the high-grade silver (gold) zone is constrained in elevation within the vein structure to up to 500m vertically, or between 180 to 750m depths (Garcia et al. 1991), below which the veins becomes dominated by base-metal sulphides and progressively lower in precious metal content (Garcia et al. 1991). A model for the formation of the Fresnillo fissure veins was proposed by authors such as Buchanan (1981) and modified and incorporated into the low-sulphidation epithermal model over the last 20 years (e.g. Corbett 2002; Corbett and Leach 1998; Hedenquist et al. 1996, Simmons et al. 1988). The low-sulphidation epithermal model predicts that the Fresnillo epithermal veins: (1) formed in rifting or tensional environments; (2) formed along normal or strike-slip fault structures; (3) are mineralogically zoned vertically; (4) have the highest precious metal zones within boiling horizons (likely related to paleo-water tables); and, (5) are in faults that diffuse as they near the surface and are accompanied with intense acid-sulphate alteration (advanced argillic and silicification) that cap the systems (Figure 8-1).

The geology of the Fresnillo District (Table 8-1) has been well studied and appears to be very similar to the geology observed on the Nieves Property. The Nieves Property and the Fresnillo District are underlain by a Jurassic-Cretaceous turbidite flysch sequence (Nieves; appears to be an argillite) and greywacke (Fresnillo) units that have been overlain by Tertiary volcanic rocks. Tertiary volcanism in this region is attributed to have occurred in conjunction with extensional tectonics associated with major strike-slip motion on north to northwest trending faults. In the Fresnillo District, epithermal fluids ascended along steeply dipping extensional fault structures generally oriented east-west (Simmons et al. 1988). On the Nieves Property, there are several north to north-northwest trending mapped faults as well as the main vein orientations which have a roughly east-west orientation, very similar to the mineralized veins and structures in the Fresnillo District.

     
M3-PN120008
7 January 2014
Revision 2
59



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

8.2        OTHER DEPOSIT TYPES IN THE DISTRICT

The Altiplano Region contains several other deposit types such as Carbonate Replacement Deposits (e.g. San Martin, Charcas), Volcanogenic Massive Sulphide deposits (San Nicolas), Sedex (Francisco I. Madero) and Stockwork deposits (Real de Angeles) (Wendt 2002) (Table 8-2). These other deposit types are generally hosted within the Mesozoic rock units that underlie the Tertiary volcanic rocks and as the Mesozoic rocks are the dominant rock type underlying the Nieves Property, these other deposit types are possible secondary exploration targets.

Figure 8-1: Schematic cross section of a typical rift related epithermal low-sulphidation system (after Corbett 2004)

     
M3-PN120008
7 January 2014
Revision 2
60



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 8-1: Stratigraphy and associated mineralization in the Fresnillo District (modified from Ruvalcaba-Ruiz and Ruiz, 1988, Wendt 2002)

 
     
M3-PN120008
7 January 2014
Revision 2
61



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 8-2: Major Altiplano Mineralized Material Deposits (after Wendt 2002)

 
     
M3-PN120008
7 January 2014
Revision 2
62



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

9

EXPLORATION

   
9.1

GEOPHYSICAL WORK

   
9.1.1

2011

In April 2011, Quaterra contracted Mira Geoscience AGIC (Advanced Geophysical Interpretation Centre) to invert ground magnetic data from the Nieves Property. The purpose of the project was to advance geological understanding of the magnetic characteristics of the low magnetic anomaly identified in the ground geophysical survey completed by Zonge in 2003 (see section 6.2.4). The results of this data inversion indicated that the geophysics model was poorly constrained due to insufficient data particularly along the western edge of the magnetic low anomaly. In December, 2011, Zonge International was contracted to conduct additional ground magnetometer surveying along 14 N-S lines with a spacing of 200 m between lines (Job No. 11191). The data from this survey indicates the magnetic low extends an additional 1200 meters west for a total E-W length of 2200m. Zonge was then retained to model the magnetic low and they concluded the magnetic low is best explained by a reversely polarized source body at a depth of 800 m (1150 m elevation) below ground surface with spatial dimensions of 2600 m NE-SW and 1800 m NW-SE.

In June and July 2011, Quaterra contracted Zonge International to conduct IPR surveys along 9 lines (Job No. 11112) consisting of 6 lines over the Santa Rita vein and its western extension; 2 lines to evaluation the eastern extension of the California vein and 1 line to evaluate the area beneath Tertiary volcanic rocks further east. The results of this survey indicate the Santa Rita vein extends 700 m west of the historic workings, appears to become two veins rather than a single vein, and the strike of the veins change from NE-SW to nearly E-W. The two lines on the California vein also suggest the vein extends only a very short distance to the east. The line over the Tertiary volcanic rocks was able to penetrate the volcanic rocks but did not detect anomalous IP response.

9.1.2      2012

At the end of 2011 realization that the geophysical response of several of the vein systems including the Santa Rita, Dolores, Nino and Orion veins extended to the western edge of the existing survey coverage, a decision was made to conduct additional geophysical surveying to better define the extend and character of these vein systems. In the first quarter of 2012 Quaterra retained Zonge International (Job No. 11190) to conduct a survey consisting of six lines, a total of 28.4 line-kilometers, of vector CSAMT and CSIP and nine follow-up lines of pole-dipole IPR totaling 16.5 line-kilometers (Figure 9-1). The six lines of vector CSAMT/CSIP were spaced 400 meters apart and covered 1,000 hectares west of the main veins in the area of the enigmatic magnetic low.

Nine anomalous zones were detected and validated with IP lines using 50 meter dipole spacings. Most of the anomalies appear to be westward extensions of mineralized veins previously drilled, including the Dolores, Santa Rita, Niño and Orion veins.

     
M3-PN120008
7 January 2014
Revision 2
63



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The anomalies were followed up by mapping and sampling (see section 9.2). The most interesting area identified to date is West Santa Rita, located 1,000 to 1,200 meters west of the central portion of the main Santa Rita mine and over 500 meters from Quaterra’s nearest drill hole on line 7700E. The IP and resistivity results are shown along lines 6800E and 7200E (Figure 9-2, Figure 9-3 and Figure 9-4).

In addition the data also indicates the Nino vein extends well to the west from its previously known geophysical extent a strike length of 1,500 m along which no drilling has been done. Outcrop in the area is sparse but at least one sample from a fault zone coinciding with the anomalous IP zone defining the Nino vein is anomalous in gold and silver.

     
M3-PN120008
7 January 2014
Revision 2
64



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 9-1: Geology and location of drill holes and geophysical survey lines (red lines) in the Santa Rita area

     
M3-PN120008
7 January 2014
Revision 2
65



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 9-2: Geology and location of channels, samples and geophysical survey lines in the West Santa Rita area

     
M3-PN120008
7 January 2014
Revision 2
66



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT


Figure 9-3: Pole-Dipole Resistivity/IP data along Line 6800 in the West Santa Rita Area

     
M3-PN120008
7 January 2014
Revision 2
67



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 9-4: Pole-Dipole Resistivity/IP data along Line 7200 in the West Santa Rita Area

9.2        MAPPING AND SAMPLING

Mapping and sampling was completed to follow up the geophysical anomalies. The most interesting area was identified in West Santa Rita in the southern part of the Nieves Property (Figure 9-1 and Figure 9-2). Mapping identified two groups of narrow, sub-parallel 2 to 30 centimeter wide calcite-quartz veinlets, some of which contain strong gold and silver mineralization. The first group of veinlets has an east-northeasterly trend and extends 120 to 200 meters along strike with a width of 100 meters.

The second group of veinlets is located approximately 200 m north of the first group, has an easterly trend and 60 to 80° dip to the south and extends 300 meters along strike with an 80 meter width.

     
M3-PN120008
7 January 2014
Revision 2
68



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

A total of 39 rock chip samples contain gold values ranging from <0.05 ppm to 8.11 ppm (over 0.2 meters), with six of the samples above 2 ppm gold. Silver values range from <0.02 ppm to 253 ppm (over 0.4 meters), with seven samples at or above 29 ppm silver. Lead and zinc range from 2 ppm and 7 ppm to 4,460 ppm lead and 2,690 ppm zinc over 0.4 meters, respectively. Pathfinder elements like mercury and antimony report assays up to 32 ppm and 2280 ppm, respectively, suggesting that the veinlets may represent high level leakage, an idea supported by the presence of geophysical anomalies (chargeability highs and resistivity lows) starting at a depth of 50 to 100 meters below surface (see section 9.1).

     
M3-PN120008
7 January 2014
Revision 2
69



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10

DRILLING

   
10.1

DRILLING PROGRESS

Between March 2010 and October 2011, Quaterra completed Phase VII and Phase VIII drill programs. B.D.W. International Drilling of Mexico S.A. de C.V. was contracted to perform the drilling.

Drill holes were located using a RTK Trimble (model R8), double frequency GPS with precision to 1 cm. Down hole survey readings were recorded on average approximately every 50 m using an Eastman Single Shot instrument. Survey results have been corrected for magnetic declination (+9º).

When completed, drill holes are capped with an approximately 45 cm square concrete slab with the drill hole number etched into it for permanent identification (Figure 10-1).

Figure 10-1: Typical Drill Hole Cap and Marker

(photo by Doris Fox)

     
M3-PN120008
7 January 2014
Revision 2

70




NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10.1.1      Phase VII

Phase VII diamond drill program on the Nieves Property in Zacatecas, Mexico commenced on March 2010 and was completed at the end of February 2011. Twenty-eight NQ holes were drilled comprising 7759 m (Figure 10-3 and Table 10-1).

The phase VII drill program was designed to test numerous IP anomalies on several separate vein systems that appeared similar to other anomalies associated with known mineralization. Fourteen drill holes were drilled on the Gregorio North area, two holes were drilled on the Dolores area, six holes were drilled on the Concordia area, four holes were drilled on the California area and two holes were drilled on the Santa Rita area (Table 10-1 and Figure 10-2). All drill holes in Phase VII drill program were drilled with a 340° azimuth and -60° or -55° dip. True thicknesses are approximately 80% of intercept width.

The average overburden depth is 4.34 m with a maximum overburden depth of 20.5 m in drill hole QTA115.

     
M3-PN120008
7 January 2014
Revision 2
71



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-1: Summary of drill holes in Phase VII drill program

 
     
M3-PN120008
7 January 2014
Revision 2
72



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 10-2: Areas of mineralization on the Nieves Property

     
M3-PN120008
7 January 2014
Revision 2
73



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10.1.2      Phase VIII

Phase VIII drill program commenced in June, 2011 and was completed in October, 2011. Forty-five NQ holes were drilled comprising 10,788.25 m (Figure 10-3 and Table 10-2). Phase VIII drill program was designed to test extensions and shallower parts of the La Quinta-Concordia and Gregorio North vein systems.

Five drill holes were drilled on the Gregorio North area, 2 holes were drilled on the Concordia East area, 12 holes were drilled on the Concordia West area, 5 holes were drilled on the La Quinta area, 3 holes were drilled on the Concordia West/Gregorio North/Orion area, 2 holes were drilled on the Disquito Orion East area, located south of Orion East and northwest of the Concordia vein, 2 holes were drilled on the California area, 13 holes were drilled on the Santa Rita area and 1 hole was drilled on the Mariana vein, located southwest of the Jasperoide Grande vein (Figure 10-2).

All drill holes in Phase VII drill program were drilled with an azimuth between 320° and 340° and a dip between -60° or -50°. True thicknesses are approximately 80% of intercept width. The average overburden depth is 2.09 m with a maximum overburden depth of 6.25 m in drill hole QTA181.

Table 10-2: Summary of Drill Holes in Phase VIII Drill Program

 
     
M3-PN120008
7 January 2014
Revision 2
74



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
75



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 10-3: Location of drill holes in Phase VII and VIII drill programs

     
M3-PN120008
7 January 2014
Revision 2
76



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10.2        SAMPLING PROCEDURES

Core boxes were collected from the drill site and brought to the core storage facility on the Nieves Property for logging and sampling by the project or assistant geologists on a semi-daily basis. The drill core was washed, photographed and core recovery estimated. Rock types, alteration minerals, textural and structural features, veining, and mineralized zones were documented. Sample intervals were selected and measured, marked with permanent marker and given a sample number and sample tag by the geologists (Figure 10-4). From this point, technicians were given the core to split, using a core saw, into halves where one half of each interval was placed with the sample tag into a sample bag and marked with the sample number. The other half was placed back into the core box in its original position and the core boxes were then stacked on racks and stored in order and by hole number in their core storage facility.

The geologists visually selected sample intervals based on the presence of quartz-carbonate veins, silicification or the presence of sulphide minerals. The rock surrounding any significant mineralized zones was also sampled for several metres above and below the mineralization. Samples were placed into individual plastic bags marked with a unique sample identification number and with a sample tag placed into the bag. Sample ID numbers and meterages were also written on the core trays. Samples were then packaged into sealed sacks and taken by ALS employees to ALS Minerals Laboratories in Guadalajara, Mexico for preparation.

A total of 2884 samples were analyzed in Phase VII drill program, not including standards and blanks (Table 10-3). The length of samples in Phase VII ranges from 0.05 to 3 m; the average length is 1.51 m. 83 blanks and 45 standards were also sent for analysis. No core duplicates were included.

A total of 4876 samples were analyzed in Phase VIII drill program, not including QC samples (standards, blanks and core duplicates) (Table 10-4). The length of samples in Phase VIII ranges from 0.05 to 2.25 m; the average sample length is 1.69 m.

     
M3-PN120008
7 January 2014
Revision 2
77



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 10-4: A) Core tray marked with hole ID, depth to-from of core and box number; B) typical sample ID marking in core box; C) Locked core storage 1 of 5; D) Core storage.

     
M3-PN120008
7 January 2014
Revision 2
78



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-3: Phase VII Sampling Details

     
M3-PN120008
7 January 2014
Revision 2
79



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-4: Phase VIII Sampling Details

     
M3-PN120008
7 January 2014
Revision 2
80



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10.3        DRILL DATA AND DRILLING RESULTS

Phase VII and Phase VIII drill programs were very successful at increasing the size of the known mineralized zones along most of the major vein systems on the Nieves Property. Drill highlights are summarized in Table 10-5, Table 10-6 and Table 10-7.

The best intersections include 149 g/t Ag and 0.11 g/t Au over 31.25 m, which includes 6320 g/t Ag and 1.82 g/t Au over 0.25 m in drill hole QTA123 along the Concordia West vein, 104 g/t Ag over 19 m, including 6410 g/t Ag over 0.1 m and 5960 g/t over 0.1 m in drill hole QTA137 along the California vein, and 152.2 g/t Ag and 0.12 g/t Au over 57 m in drill hole QTA144 in the Concordia West area (Table 10-5, Table 10-6 and Table 10-7).

10.3.1      Concordia

A total of 28 drill holes were drilled along the Concordia vein system, which includes the Concordia East, La Quinta and the Concordia West areas.

Twenty drill holes were drilled in the Concordia West area, extending the mineralized zone approximately 200 m to the west. Most of the drill holes (QTA119, QTA120, QTA123, QTA131, QTA139, QTA143, QTA144, QTA153, QTA157, QTA168, QTA170 and QTA172) intersected significant mineralization, but holes QTA131, QTA139, QTA166 and QTA167 did not intersect significant mineralization (Table 10-5, Table 10-6 and Table 10-7). Mineralization remains open to the west.

     
M3-PN120008
7 January 2014
Revision 2
81



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The Concordia East area was tested with three drill holes (QTA136, QTA151 and QTA183), two of which intersected high grade mineralization extending the mineralized zone 200 m east of the La Quinta area.

The total length of the known mineralized zone along the Concordia vein system was extended to approximately 1300 meters. Stockwork style mineralization, typical of Concordia vein, has now been intersected on a minimum spacing of 100 m over a total strike length of 1000 m. Holes QTA140, QTA141, QTA142, QTA152, QTA154, QTA176, QTA178, QTA179, QTA180 and QTA182 intersected low to moderate grade Ag mineralization at shallow depth, suggesting the presence of mineralization up- dip, near surface (Table 10-6 and Table 10-7).

10.3.2      California

A total of 6 drill holes (QTA127, QTA128, QTA130, QTA137, QTA155 and QTA156) were drilled along the California vein system. QTA130 intersected several shallow, stockwork style mineralization (Table 10-5). Holes QTA137 and QTA155 were drilled near the east end of previously known mineralization and intersected high grade mineralization (Table 10-5 and Table 10-6). QTA127, drilled to the west of the known mineralized zone, did not intersect significant mineralization.

Recent drilling increased the length of known mineralization along the California vein system to approximately 550 m and mineralization remains open to the east.

10.3.3      Gregorio North

A total of 18 holes were drilled along the Gregorio North vein system. Holes QTA112 to QTA118, QTA122, QTA132, QTA133 and QTA134 traced the Gregorio North vein for an additional 500 m to the west (Table 10-5). The grade and thickness of the vein decreases to the west, indicated by drill holes QTA122, QTA133 and QTA134. The two best holes (QTA115 and QTA116) are located on the east end of the Gregorio North vein. Holes QTA135 and QTA138 intersected weak mineralization in the vein 100 and 200 m further to the east.

Phase VII and VIII drill programs were successful in doubling the strike length of the Gregorio North vein, extending the strike length of the vein to approximately 1200 m.

10.3.4      Santa Rita

A total of 15 drill holes systematically tested the Santa Rita vein system over 500 along strike, the total length of mineralization was extended to approximately 750 m and remains open to the west. Drilling suggests the presence of several parallel vein systems.

Most of the drill holes intersected significant mineralization (Table 10-6 and Table 10-7). Low grade Ag mineralization was intersected in holes QTA161 and QTA169. Holes QTA124 and QTA126, drilled east of the known mineralization on the Santa Rita vein, intersected weak mineralization.

     
M3-PN120008
7 January 2014
Revision 2
82



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

10.3.5      Other areas

Two holes (QTA121 and QTA125) intersected weak mineralization on the Dolores vein (Table 10-5). QTA129 drilled at Orion failed to return any mineralization (Table 10-5). Hole QTA184 was drilled along the Mariana vein, but failed to intersect significant mineralization.

Table 10-5: Drill Highlights of Phase VII Exploration Program

(Continued on next page.)

     
M3-PN120008
7 January 2014
Revision 2
83



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
84



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-6: Drill Highlights of Phase VIII Exploration Program from Hole QTA140 to QTA 169

 
     
M3-PN120008
7 January 2014
Revision 2
85



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
86



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
87



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 10-7: Ag and Au Drill Highlights in Phase VIII Drill Program from Hole QTA170 to QTA184

 
     
M3-PN120008
7 January 2014
Revision 2
88



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
89



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

11

SAMPLE PREPARATION, ANALYSES AND SECURITY

   
11.1

SAMPLE SECURITY

Core boxes are delivered to the core logging facility from the drill twice per day. The core is logged onsite and core samples are selected and marked by the logging geologist. No minimum or maximum sample lengths are used; the sample length is determined by the geologist based on presence and intensity of mineralization. The start and end of a sample and the sample ID are marked by the geologist on the side of the core box using a red permanent marker. The end of the box with the hole number is also marked with a red "X"; for easy visual recognition in core storage. The marked core boxes are taken to the onsite core cutting area and the core is split into two halves using a water-cooled circular diamond saw (Figure 11-1). One half of the core is taken for analysis and the remaining half is left in the box for future reference and stored in the locked core storage facility. After a sample is cut, each sample is placed immediately in a plastic sample bag with a pre-printed sample tag supplied by the lab in booklets of 50 sequential, numerical tags. The depth to and from of the core sample are marked in the sample tag booklet. The sample bags are stapled shut and set aside. Once a significant number of samples have been bagged, the samples are placed in rice bags with predetermined standards, duplicates and blanks. Blank and duplicate sample tag ID's are recorded in the core box following the core sample

Two to three times per month during the drill program, the samples were picked-up at the core logging facility in Nieves by an ALS Minerals operated transport truck. The truck transported the samples directly to the ALS prep lab in Guadalajara, Mexico. While waiting for the ALS truck to arrive, samples in rice bags are stored inside the locked core storage facility.

     
M3-PN120008
7 January 2014
Revision 2
90



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 11-1: Core Cutting and sample prep area at core logging / core storage facility

(Photo by Doris Fox)

11.2

QA/QC PROCEDURES

   
11.2.1

Frequency of QC samples

In Phase VII, the 3069 samples sent for analysis included 83 blanks (3% of samples) and 45 standards (1% of samples) (Table 11-1). No core duplicates were included. Out of 44 jobs sent to the lab, no external standards were inserted into 9 of the jobs and no external blanks and standards were inserted into 13 jobs.

The frequency of insertion of the quality control samples in Phase VII drill program is adequate for this stage of the project, but the number of quality control samples and the frequency of their insertion should be higher in the future for a systematic monitoring of assay quality. According to Sketchley (1998), 10% to 15% of quality control samples should be included with every sample batch. Every 20 sample should include 1 standard, 1 blank and 1 duplicate.

     
M3-PN120008
7 January 2014
Revision 2
91



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-1: Frequency of QC Samples in Phase VII Drill Program

     
M3-PN120008
7 January 2014
Revision 2
92



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

In Phase VIII, the 5315 samples sent for analysis included 132 external blanks (2% of samples), 130 external standards (2% of samples) and 177 core duplicates (3%) (Table 11-2). The frequency of QC samples improved in Phase VIII drill program, compared to Phase VII drill program, following recommendations given by Caracle Creek in August, 2011.

     
M3-PN120008
7 January 2014
Revision 2
93



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-2: Frequency of QC Samples in Phase VIII Drilling Program

 
     
M3-PN120008
7 January 2014
Revision 2
94



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

11.2.2      Blanks and standards

The source of blank material is a gravel (consisting of barren rocks) quarry located approximately 15 km to the west of the Nieves property and it is supplied by a local farmer by pick-up truck in bulk. The blank samples are prepared by Quaterra geotechs. The blank material is purposely put in plastic sample bags in weights heavier than most samples so that the sample weight can be used to help identify blanks when data is returned from the lab. Blank material is stored outside the core storage facility in sample bags within watertight plastic 45 gallon drums. Standard material is stored in the field office in 2L plastic jugs. The only external standard used is a custom made standard (KM 2653) prepared by Smee & Associates Consulting Ltd. Table 11-3 summarizes the standard information for Ag and Au.

The standard is characterized as a Provisional (not certified) standard for Au with a relative standard deviation between 5% and 15% and caution must be exercised when assessing the accuracy of data (Smee, 2010).

The analytical method used in the round robin of standard KM 2653 for Ag is four-acid digestion followed by instrument finish and for Au is fire assay and instrument finish.

     
M3-PN120008
7 January 2014
Revision 2
95



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-3: Characteristics of Customized Standards Inserted in Phase VII and VIII Drill Programs

Standards are used to check the accuracy of the analysis. The rules for the standards and blank samples include:

  1.

The standard is considered a failure when it returns a value that falls outside ±3 standard deviation.

     
  2.

The standard is marked as a “warning” when it returns a value between ±2 and ±3 standard deviation. If three or more adjacent standards are on the same side of the Au mean value and fall between ±2 and ±3 standard deviation, then all standards are classified as failure. This may indicate a bias in the laboratory.

     
  3.

A blank sample greater than the maximum acceptable value, which is typically three times the detection limit, is a failure. A failure in the blanks indicates a contamination during sample preparation in the laboratory.

11.2.3      Duplicates

Core duplicates were inserted only in Phase VIII drill program. Lab duplicates were inserted in the laboratory.

Core and laboratory duplicates are used to check the precision of the analysis: analytical errors, sample preparation errors and nugget effect. The original values versus the duplicate values are plotted and compared. If the R2 value of the correlation line is greater than 0.95%, all the duplicates pass. A duplicate is considered a failure when there is a large difference between the original and duplicate analyses and the value of the analysis falls outside the 0.95% confidence interval.

11.3        SAMPLE PREPARATION

Samples were shipped to ALS Minerals Lab in Guadalajara, Mexico for preparation, then to ALS Minerals Vancouver, B.C. for analysis (Quaterra Resources Inc. webpage: www.quaterra.com). All ALS laboratories in North America are registered to ISO 9001:2008, and have received ISO 17025 accreditations for specific procedures (ALS Minerals website: www.alsglobal.com).

     
M3-PN120008
7 January 2014
Revision 2
96



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The samples were weighed, logged into the ALS Minerals system, fine crushed to 70%-2 mm or better, split using a riffle splitter and pulverized to 85% passing 75 microns or better.

11.4        ANALYTICAL METHODS

Silver was analyzed with two methods including aqua regia digest and a combination of ICP-AES (Inductively Coupled Plasma – Atomic Emission Spectroscopy) finish and fire assay and gravimetric finish. Gold was analyzed with fire assay and gravimetric finish (Table 11-4). The rest of the elements were analyzed with aqua regia digestion and ICP-AES finish.

In the aqua regia digest and ICP-AES finish, the samples are digested in aqua regia in a graphite heating block (ALS Minerals website: www.alsglobal.com). After cooling, the solution is diluted to 12.5 ml with deionized water, mixed and analyzed by ICP-AES. The results are corrected for inter-element spectral interferences.

In the fire assay and gravimetric finish, the samples are decomposed with fire assay fusion, during which the sample is fused with a mixture of lead oxide, sodium carbonate, borax, silica and other reagents to produce a lead button, which is cupelled to remove the lead (ALS Minerals website: www.alsglobal.com). The remaining gold and silver bead is separated in dilute nitric acid, annealed and weighed as gold. Silver is determined by the difference in weights.

Table 11-4: Description of Analytical Methods for Ag and Au

11.5        QA/QC PROCEDURES IN ALS MINERALS LABS

ALS Minerals inserted internal standards (Table 11-5), blanks and duplicates in every job at regular intervals.

For every 50 samples prepared, ALS Minerals inserts an additional split from the coarse crushed material to create a pulverizing duplicate, which is processed and analyzed in a similar manner to the other samples in the submission (ALS Minerals website: www.alsglobal.com).

     
M3-PN120008
7 January 2014
Revision 2
97



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-5: List of Internal Lab Standards Inserted by ALS Minerals

(Continued on the next page.)

     
M3-PN120008
7 January 2014
Revision 2
98



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

11.6

CHECK ASSAYS

   
11.6.1

Phase VII

A total of 158 samples from Phase VII were sent for check assays to Skyline Assayers and Laboratories of Tucson, Arizona. The samples included 145 rejects from ALS Minerals, 3 quarter core duplicates and their rejects from ALS Minerals, 4 blanks and 3 standards. The standard was the same customized standard inserted with the original assays (KM2653) (Table 11-3). The check assays are addressed also in Section 12.2.4.

The analytical methods of check assay samples are summarized in Table 11-6. All Skyline laboratories have received ISO 17025 accreditations for the analytical methods used for the check assays (Skyline website: http://www2.skylinelab.com). Table 11-7 summarizes the properties of lab standards inserted by Skyline.

     
M3-PN120008
7 January 2014
Revision 2
99



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-6: Analytical Methods of Check Assays at Skyline

Table 11-7: Summary of Lab Standards Used by Skyline for Phase VII Check Assays

11.6.2      Phase VIII

A total of 127 samples from Phase VIII drill program were sent to AGAT Laboratories of Sudbury, Canada for preparation and sent to AGAT Laboratories of Mississauga, Ontario for analysis. The samples included 127 pulp rejects from ALS, 7 blanks, 4 silver standards and 3 gold standards. AGAT Laboratories is accredited and certified for ISO 9001 and ISO/IEC 17025 accreditations.

     
M3-PN120008
7 January 2014
Revision 2
100



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 11-8: Summary of external standards inserted in the check assay samples for Phase VIII drill program

Analytical methods of check assays for Ag and Au at AGAT are the same as the analytical methods of the original samples (Table 11-9).

Table 11-9: Analytical Methods of Check Assays for Ag and Au at AGAT Laboratories

The names of the laboratory standards were not provided by AGAT, but the laboratory QC data indicates that internal standards were inserted for both Ag and Au. Five types of silver standards were inserted ranging from 116 and 811 g/t Ag in value. Two types of gold standards were inserted with values 0.922 and 5.865 g/t Au.

     
M3-PN120008
7 January 2014
Revision 2
101



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

12

DATA VERIFICATION

   
12.1

CARACLE CREEK SITE VISIT

A property site visit was conducted by D. Fox of Caracle Creek on March 11th and 12th, 2012. Several drill sites, artisanal pits, the core storage facility, geological logging area, sample cutting area and field office were all visited while onsite.

The property was accessed by toll highway from Zacatecas to Nieves. From Nieves, the property and core logging facility were accessed by dirt road. A network or narrow dirt roads and trails criss-cross the property from the logging facility to the drill sites and abandoned artisanal pits and shafts.

The compound containing the core logging and core storage facility contained within a chain link fence with locked gate preventing vehicle access (Figure 12-1 and Figure 12-2). Once inside the gated compound, the individual storage rooms are locked and prevent access to the core logging and core cutting areas. The onsite geology office is a separate building within the compound and is also kept locked. The main working office is located in the town of Nieves within a locked house compound and also serves as a field house for the geologists. Paper and digital maps, cross-sections and long sections are stored in the Nieves field house office.

Figure 12-1: Core storage and logging compound

     
M3-PN120008
7 January 2014
Revision 2
102



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-2: Core storage by hole and depth

Several drill sites from the Phase VII and VIII drill programs were visited. The drill programs were completed before the site visit so it was not possible to see a drill in operation on the property. The drill sites are marked with a cement slab with the drill hole ID marked on the top (Figure 10-1). Using a handheld GPS the coordinates of three drill hole markers were recorded to compare with Quaterra’s coordinates. The coordinates matched to within the error of the handheld GPS.

Table 12-1: Verification of Drill Hole Locations

Drilling activities are supported by the town of Nieves and Fresnillo. Drills are supplied by BDW drilling of Guadalajara and holes are drilled using HQ size core rods, reducing to NQ in deeper holes if conditions warrant. Standard drilling practices, such as marking the ends of 3m runs with wooden depth marker blocks are followed. Water for drilling is supplied by a deep water well at the logging compound pumped to the drill up to 1 kilometer away (Figure 12-3). Drilling activities greater than 1 kilometer from the compound are supplied water from the well by water truck into an onsite or nearsite sump.

     
M3-PN120008
7 January 2014
Revision 2
103



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-3: Water well at logging compound

Claims in Mexico are staked as corner points from a known government located survey marker. The Nieves property is a series of claims each registered from the same central government survey monument (Figure 12-4 and Figure 12-5). The monument was visited by Ms. Fox during the site visit. A secondary “back-up” marker registered with the government is located approximately two (2) meters from the main monument in the event the main monument is destroyed. Historically claim stakers were required to mark each of the corners of the claim with a separate claim-holder monument. This practice has been abandoned, however there are many monuments of various age scattered across the Nieves property as a testament to the long history of exploration on the property.

     
M3-PN120008
7 January 2014
Revision 2
104



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-4: Federal survey claim marker monument

Figure 12-5: Federal survey claim marker with datum peg showing date, datum and federal identification number

Abandoned pits and shafts are visible from the main access road that runs from the logging compound south to the Santa Rita mill. Pits at Dolores, Concordia and Santa Rita were visited (Figure 12-6 and Figure 12-7). All pits and shafts are unmarked and no security fencing is present. The sides of the pits and shafts are unstable and the mineralized zone cannot be safely accessed. The extension of the mineralization cannot be traced at surface. No surface expression of the mineralization intersected in core exists on the property. Three samples from stockpiles alongside the pits were collected to verify the presence of mineralization in or around the abandoned workings (Table 12-2).

     
M3-PN120008
7 January 2014
Revision 2
105



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-6: Dolores vein looking down the shaft

     
M3-PN120008
7 January 2014
Revision 2
106



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-7: Concordia Shaft

Since no surface expression of the mineralization exists, the site visit focused on examination of core stored at the logging facility. A total of seven drill holes from Phase VIII were reviewed The mineralized intersections were identified from cross-sections, and intervals for review were laid out in the core logging area. The assay results for the intervals were reviewed and random samples were selected for quarter splitting and cut by the Quaterra geotechs. Only some of the quarter samples were then selected for check assays and the rest of the cut samples remained in the core boxes in core storage. The selected samples were a mix of low, moderate and high grade to best verify the quality and accuracy of ALS Chemex. Core samples are summarized in Table 12-3.

The samples were bagged and tagged by Ms. Fox and placed in rice bags and then wooden boxes for transport while onsite. The samples remained with Ms. Fox during her visit and were transported by her to DHL in Zacatecas for shipment to Canada. The samples were shipped directly to the CCIC office in Sudbury, Canada. The samples were assigned a CCIC Sample ID and sent to AGAT Laboratories in Sudbury, Ontario for preparation and Mississauga, Ontario for analysis.

     
M3-PN120008
7 January 2014
Revision 2
107

NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 12-2: Surface Samples Collected on the Site Visit

Table 12-3: Quarter Core Samples Selected on the Site Visit

(Continued on Next Page)

     
M3-PN120008
7 January 2014
Revision 2
108



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The assay results of the site visit samples are shown in Table 12-4. Surface samples 51642 to 51644, collected near the Santa Rita and Concordia veins, returned high Ag values, verifying the presence of mineralization in the veins. The assays of the selected quarter core samples returned values reasonably well comparable to the original assays, considering the highly variable nature of the mineralization.

Table 12-4: Assay Results of the Site Visit Samples Compared to the Original Samples

 
     
M3-PN120008
7 January 2014
Revision 2
109



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

One drill hole, QTA-144, was reviewed in its entirety to compare logging descriptions and listed lithologies with actual core. The logging descriptions, lithologies and to-from depths were consistent with observations from the core. The sample intervals were marked on the sample boxes. During logging, the geologist photographs the core to maintain a complete record in the event core is destroyed. The core photos are digitally stored in the Nieves geology office by hole number and depth.

12.2

QUALITY CONTROL

   
12.2.1

External blank and standard

The results of the external blank and standard for Phase VII and VIII are summarized in Table 12-5. The control charts for standard and blank for Ag analyzed with both methods are shown on Figure 12-8 to Figure 12-15. The control charts for Au are in Appendix 3 of the report.

Table 12-5: Failure Rates of External Blank and Standard Analysis in Phase VII and VIII

Silver assays analyzed with the ME-ICP41 method are biased high (Figure 12-8 and Figure 12-12) and Ag assays analyzed with the ME-GRA21 method are biased low (Figure 12-9 and Figure 12-13). These biases show no correlation with time suggesting a systematic, not a temporary problem.

The failure rates of customized standard KM 2653 is high for Ag analyzed with both methods and very high for Au in both phases of drilling.

The main reason for the high failure rate of Ag with both methods is the difference in the analytical methods between that used to certify the standard and that used to analyze the drill core. The standard is certified for 4 acid digestion and instrument finish and Ag in the Nieves project was analyzed with aqua regia digestion and instrument finish and fire assay and gravimetric finish.

There are several reasons for the high failure rate of the standard for Au. One of them is the difference in methodology. The standard was analyzed for certification with fire assay and instrument finish and Au in the Nieves project was analyzed with fire assay and gravimetric finish.

     
M3-PN120008
7 January 2014
Revision 2
110



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The other reason for the high failure rate of the standard for Au is that the standard is classified as a provisional (not certified) standard for Au with an RSD (relative standard deviation) between 5 and 15%, therefore it should be used with caution when assessing the accuracy of data (Smee, 2010).

Also, the detection limit for Au is 0.05 ppm and the Au grade of standard is 0.062 ppm, which is very close to the detection limit, within the acceptable interval for a blank sample (3 times the detection limit).

The failure rates of the blank are acceptable for both Ag and Au in both phases of drilling.

Figure 12-8: Control chart of standard KM2653 for Ag analyzed with ME-ICP41 method in Phase VII

     
M3-PN120008
7 January 2014
Revision 2
111



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-9: Control chart of standard KM2653 for Ag analyzed with ME-GRA21 method in Phase VII

     
M3-PN120008
7 January 2014
Revision 2
112



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-10: Analytical results of blank samples for Ag with ME-ICP41 method in Phase VII

Figure 12-11: Analytical results of blank samples for Ag with ME-GRA21 method in Phase VII

     
M3-PN120008
7 January 2014
Revision 2
113



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-12: Control chart of standard KM2653 for Ag analyzed with ME-ICP41 method in Phase VIII

Figure 12-13: Control chart of standard KM2653 for Ag analyzed with ME-GRA21 method in Phase VIII

     
M3-PN120008
7 January 2014
Revision 2
114



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-14: Analytical results of blank samples for Ag with ME-ICP41 method in Phase VIII

Figure 12-15: Analytical results of blank samples for Ag with ME-GRA21 method in Phase VIII

     
M3-PN120008
7 January 2014
Revision 2
115



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

12.2.2      Laboratory standards

The performance of the laboratory standards were also checked due to the high failure rates of external standards. The failure rates of the laboratory standards are summarized in Figure 12-6.

Table 12-6: Failure Rates of Laboratory Standards for Phase VII and VIII

Internal standards OREAS-45C and OREAS-45P have very high failure rates probably due to the matrix of these standards, which is ferruginous soil which does not match the matrix of the drill core samples (Table 11-5).

The slightly high failure rate of standard OREAS-67A for Ag is probably caused by a difference in analytical methods. OREAS-67A is certified for 4 acid digestion and AAS, OES or MS finish (Table 11-5) and the samples were analyzed with fire assay and gravimetric finish.

The reason of the high failure rate of standard SQ28 for Ag (16% and 47.06%) is probably also due to different analytical methods. Standard SQ28 is certified for instrument finish (AAS or ICP-ES), but the samples were analyzed with gravimetric finish (Table 11-5).

Overall, the results of internal standards are acceptable. There is at least one standard for every analytical method used for Ag and Au that performed adequately.

     
M3-PN120008
7 January 2014
Revision 2
116



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

12.2.3      Duplicates

The failure rates of pulp duplicates in Phase VII are summarized in Table 12-7. The failure rates of pulp and core duplicates in Phase VIII are summarized in Table 12-8. Duplicate plots for silver are shown in Figure 12-16 to Figure 12-21.

The failure rates of all duplicates are within acceptable limits. The failure rates of core duplicates are slightly high, which may be indicative of the style of mineralization characterized by narrow veinlets.

Table 12-7: Failure Rates of Duplicates in Phase VII

Table 12-8: Failure Rates of Duplicates in Phase VIII

 
     
M3-PN120008
7 January 2014
Revision 2
117



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-16: Pulp duplicate versus original plot for Ag analyzed with ME-ICP41 method

Figure 12-17: Pulp duplicate versus original plot for Ag analyzed with ME-GRA21 method

     
M3-PN120008
7 January 2014
Revision 2
118



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-18: Pulp duplicate versus original plot for Ag analyzed with ME-ICP41 method

Figure 12-19: Pulp duplicate versus original plot for Ag analyzed with ME-GRA21 method

     
M3-PN120008
7 January 2014
Revision 2
119



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-20: Core duplicate versus original plot for Ag analyzed with ME-ICP41 method

Figure 12-21: Core duplicate versus original plot for Ag analyzed with ME-GRA21 method

     
M3-PN120008
7 January 2014
Revision 2
120



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

12.2.4      Phase VII check assays (Skyline)

The failure rates of the external blank and standard for Ag and Au are summarized in Table 12-9. The failure rates of blanks are acceptable for Au and Ag analyzed with the FA-03 method and too high for Ag analyzed with the TE-2 method (Table 11-6).

The failure rates of the external standard are too high for Au and Ag analyzed with both methods, similar to the original assays by ALS. The reasons for the high failure rates are the same as the reasons for high failure rates in the original analysis (see Section 12.2.1) .

Table 12-9: Check Assay Failure Rates of External Blanks and Standards in Phase VII Drill Program

The failure rates of laboratory standards are summarized in Table 12-10. The failure rates for Ag are within the acceptable limits for both methods (Table 11-7). The failure rate of Au is too high.

Table 12-10: Check Assay Failure Rates of Laboratory Standards in Phase VII

The results of the check assays were compared to the original assays from ALS (Table 12-11). The Ag assays compare reasonably to the original assays with an R2 value of 0.9518 for Ag analyzed with ICP and 0.9842 for Ag analyzed with the gravimetric method (Figure 12-22 and Figure 12-23).

     
M3-PN120008
7 January 2014
Revision 2
121



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The Au check assays compare a bit poorly to the original Au assays with most of the failures in the lower grades, which is probably also due to the poor choice of analytical method.

Table 12-11: Failure Rates of Check Assays Versus Original Assays in Phase VII

Figure 12-22: Plot of check assays versus original assays for Ag analyzed with ICP

     
M3-PN120008
7 January 2014
Revision 2
122



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-23: Plot of check assays versus original assays for Ag analyzed with gravimetric method

12.2.5      Phase VIII check assays (AGAT)

The failure rates of blanks and standards for both silver and gold are acceptable (Table 12-12). The check assays also compare reasonably to the original assays (Table 12-13, Figure 12-24 and Figure 12-25) for silver analyzed with both methods and for gold.

Table 12-12: Check Assay Failure Rates of External Standards in Phase VIII

 
     
M3-PN120008
7 January 2014
Revision 2
123



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 12-13: Failure Rates of Check Assays Versus Original Assays in Phase VIII

Figure 12-24: Plot of check assays versus original assays for Ag analyzed with ICP

     
M3-PN120008
7 January 2014
Revision 2
124



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 12-25: Plot of check assays versus original assays for Ag analyzed with gravimetric method

12.2.6      QA/QC of phases IV, V, and VI and gold reassay results

Due to the high failure rates in phases VII and VIII, the QC procedures and results of phases IV to VI were also reviewed. In the previous phases standard CDN-SE-1 was used for Au and Ag (Table 12-14). The standard performed very well for silver (~6% failure rate), but the failure rate for gold was very high (43 to 47%) (Table 12-15). For this reason, approximately 5% of the samples from phases IV to VII were reanalyzed for gold at AGAT Laboratories with fire assay and gravimetric method and some samples were reanalyzed with fire assay and ICP-OES finish as well. Since the comparison between the two methods was reasonable (R2 value 0.9859 and 5% failure rate) and the amount of gold is very small at Nieves, the gold assays were included in the resource calculation.

Table 12-14: Characteristics of Standard CDN-SE-1

Standard
Name
Prepared by Element Value
(ppm)
Standard
deviation
Analytical method
CDN-SE -1 CDN Resource Laboratories Ltd. Ag 712 28.5 fire assay or 4 acid digestion and ICP finish
CDN-SE -1 CDN Resource Laboratories Ltd. Au 0.48 0.017 Fire assay and AA or ICP finish
           

     
M3-PN120008
7 January 2014
Revision 2
125



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 12-15: QC Results for Au and Ag in Phases IV, V and VI

Standard
Name
Element Analytical
Method
Phase IV Phase V Phase VI
Number
of
Analysis
Failure
Rate
Number
of
Analysis
Failure
Rate
Number
of
Analysis
Failure
Rate
Blank Ag ME-ICP41 0   0   82 17%
Blank Ag ME-GRA21 0   0   82 1%
Blank Au ME-GRA21 0   0   82 1%
CDN-SE -1 Ag ME-GRA21 47 6% 107 6% 42 7%
CDN-SE -1 Au ME-GRA21 47 43% 107 47% 42 43%
                 

12.2.7      Conclusions and Recommendations

The QP’s opinion is that the quality of the data is adequate at this stage of the project and can be used in 3D modelling for the purpose of resource estimation.

The quality control review indicates that there were no major problems in the core shack such as sample mix ups or contamination. The slightly high failure rate of core duplicates in Phase VIII is probably an indication of the nature of the mineralized material that is characterized by narrow veinlets.

The failure rates of external standard (KM2653) are high for silver in phases VII and VIII, but this is due to the different analytical method and not the poor quality of the data, which is suggested by the performance of the laboratory standards. Also, silver analyzed with the ME-ICP41 method is slightly biased high and silver analyzed with the ME-GRA21 method is slightly biased low, but these biases are not always consistent with the laboratory standard, suggesting that the problem is with the external standard. In the previous phases silver was analyzed with the same methods and a commercially available certified standard (CDN-SE-1) was used and performed well for silver, which also suggests that the reason for the high failure rates for silver is the poor choice of external standard.

The failure rates for gold are very high in phases VII and VII and high in the previous phases. The reason for the high failure rates is the poor choice of standards (different analytical methods) and poor choice of analytical method. The average gold value in phases at Quaterra is 0.058 g/t including all data and 0.22 g/t including only data above the detection limit, therefore gravimetric method should not be used to analyze gold.

Despite the high failure rates of gold standards, the QP’s conclusion is that the quality of the Au assay data is adequate to include Au in the resource calculation at this stage of the project, especially because the grade of Au is fairly low and it is not the main commodity at Quaterra. Also, Au analyzed with ICP- OES and gravimetric method is comparable.

It is recommended that in the future drill programs a different external standard is used to check the quality of silver assays, which has similar certified value as the silver grades at Nieves, is certified for the same analytical method and has similar matrix.

     
M3-PN120008
7 January 2014
Revision 2
126



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

It is also recommended that the analytical method for gold is changed to fire assay and instrument finish (AAS or ICP) and a certified standard with a low grade value, same analytical method and similar matrix is inserted.

The frequency of the quality control samples should also be increased to include one standard, one blank and one core duplicate with every twenty samples.

     
M3-PN120008
7 January 2014
Revision 2
127



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

13        MINERAL PROCESSING AND METALLURGICAL TESTING

The Nieves Project will produce a silver flotation concentrate. The concentrate will be shipped offsite for further processing.

This report section describes the samples used and the test work performed to evaluate the metallurgical aspects of the project. The interpretation of the test work is also discussed. Estimated consumption of reagents and other consumables is presented.

The metallurgical test work performed to date is limited, but M3 considers it sufficient to support a preliminary economic assessment level study.

In 2010, the project group performed certain mineralogical examinations and metallurgical testing to provide data for evaluating the project, and to establish preliminary criteria for the design of a processing facility.

A master composite sample was prepared for preliminary testwork for the Nieves project. Preliminary testwork included: mineralized material characterization using standard analytical techniques and QEMSCAN bulk mineral analysis; mineralized material hardness; and open circuit kinetic rougher and batch cleaner tests. Preliminary tests to determine process alternatives included: gravity concentration; and cyanidation.

The test results are reported in the following documents:

  1.

G&T Metallurgical Services Ltd., Kamloops, B.C., Canada, June 30 2010, Metallurgical Assessment of the Nieves Project, KM2653.

     

2.

G&T Metallurgical Services Ltd., Kamloops, B.C., Canada, August 30, 2010, Supplemental Metallurgical Testing of the Nieves Project, Zacatecas, Mexico, KM2740.

13.1        MINERALOGY

The chemical and mineral contents of the master composite sample prepared for metallurgical testing, taken from Reference 1 above, are shown in the following table. Standard analytical techniques and QEMSCAN Bulk Analysis were used.

Table 13-1: Chemical and Mineral Composition – Master Composite 1

  Symbol Units Master Composite 1
Element      
Silver Ag g/t 79
Copper Cu % 0.08
Lead Pb % 0.14
Zinc Zn % 0.1
Iron Fe % 4.12
Sulfur S % 1.81
Mineral      
Silver Sulfide AgS % 0.07

     
M3-PN120008
7 January 2014
Revision 2
128



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  Symbol Units Master Composite 1
Chalcopyrite Cp % 0.02
Sphalerite Sp % 0.2
Galena Ga % 0.12
Goethite Goe % 2.49
Pyrite Py % 3.04
Quartz Qz % 30.8
Micas Mi % 20
Feldspars Fs % 18.3
Others - % 25

13.2        METALLURGICAL SAMPLES

Coarse crush ‘reject’ material from selected core intervals in 12 holes was composited. One Master Composite was prepared for mineralogy and metallurgical testing, as well as a single Bond ball mill work index test.

Table 13-2: Composite Sample Details

Coarse crush "reject" core material
Composite sample details (silver as determined by ALS during the exploration program)
Hole Sample From (m)  To (m) Ag (g/t)  Weight (kg)   Ag, g    
QTA96 568216 74 76 64 6.1   390.4    
QTA97 568304 77 79 150 7.4   1110.0    
QTA98 568364 54 56 34.5 6.9   238.1    
QTA99 568438 68 70 112 7.6   851.2    
QTA100 568534 104 106 84.5 6.8   574.6    
QTA101 568633 122 124 42.1 7.3   307.3    
QTA102 568700 114 116 101 6.2   626.2    
QTA102 568711 124 126 70.4 7.3   513.9    
QTA103 568775 134 136 86.8 7.6   659.7    
QTA104 568871 130 132 123 7.2   885.6    
QTA105 568985 170 172 30.1 7   210.7    
QTA106 569055 120 122 77 7.4   569.8    
QTA107 569122 146 148 146 7.5   1095.0    
QTA108 569198 84 86 31.2 6.5   202.8    
        83.4 98.8   8235.3    
Note : Independent Technical Report 17Sep2010 pg 65

Fourteen crushed mineralized material samples were received at G&T weighing approximately 99 kilograms. The samples were combined to form Master Composite 1. The samples were stage crushed to minus 6 mesh, homogenized and split into 2 kilogram charges. Representative samples were removed and assayed.

     
M3-PN120008
7 January 2014
Revision 2
129



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

G&T Test KM2653 - June 3, 2010
Assayed Head - Master Composite 1
 Cu (%) Pb (%)   Zn (%) Fe (%) S (%) Ag (g/t) C (%)
0.08  0.14 0.1 4.12 1.81 79 2.52

13.3        COMMINUTION TESTING

A single Bond ball mill work index test was performed by G & T Resources in June, 2010 (Ref. 1) at 100% -106 µ (150 mesh) on Master Composite 1. The reported Wi was 10.8 kWh/tonne. This indicates a moderately soft mineralized material.

13.4        FLOTATION

For the master composite, three open circuit kinetic rougher tests were performed to evaluate the primary grind size and the reagent type and dosage. Results are discussed below: 90 to 95% of the silver in the feed was recovered into the rougher concentrate with a mass pull ranging from 12 to 22%.

Two primary grind sizes were tested, P80 = 104µ and P80 = 67µ.

A finer grind did not improve the silver recovery in these preliminary tests. Additional tests to coarsen the grind are recommended.

Reagent screening tests were run using potassium amyl xanthate (PAX) with and without Aerophine 3418A.

Results were best with a combination of PAX and 3418A. Additional reagent optimization tests are recommended.

     
M3-PN120008
7 January 2014
Revision 2
130



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 13-1: Rougher Flotation Silver Performance

Three cleaner tests were performed to evaluate the effect of: (1) rougher concentrate regrind size and (2) pH of the slurry. Parameters for the cleaner tests included:

  • primary grind size P80 = 104µ
  • regrind size – 28µ, 23µ, 19µ
  • pulp pH – 8 and 10

Results are discussed below:

 

Three regrind grind sizes were tested. Test 4 was not reground P80 = 28µ, test 5 was reground to a P80 = 23µ, and test 6 was reground to a P80 = 19µ.

o

A finer grind did not appear to improve the silver recovery in these preliminary tests.

 

A single test was done with the pH of the cleaner circuit being adjusted to pH 10.

o

An increase in the final cleaner concentrate grade was obtained with no significant impact on recovery.


     
M3-PN120008
7 January 2014
Revision 2
131



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 13-2: Cleaner Flotation Silver Performance

Three additional cleaner tests were performed to evaluate the effect of: (1) rougher concentrate regrind size and (2) pH of the slurry.

Parameters for the additional cleaner tests included:

  • primary grind size P80 = 104µ
  • regrind size – 24µ, 19µ, 11µ
  • pulp pH – 10 and 11

Results are discussed below:

  • A single open circuit cleaner test was conducted at a primary grind of P80 = 104µ with the rougher concentrate reground to a P80 = 24µ. The cleaner circuit pH was 10. Final concentrate grade was 2,420 g/t silver with a recovery of 86%. Concentrate was analyzed using a Trace Mineral Search (TMS) with QEMSCAN and the mean projected diameter of the silver sulfides was determined to be 19 µ.

  • Based on the results of the TMS a second open circuit cleaner test was conducted with a regrind size P80 = 19µ. In addition, the slurry was conditioned to a pH of 11. Final concentrate grade was 7,200 g/t silver with a recovery of 67%.

  • A third open circuit cleaner test was conducted with a regrind size P80 = 11µ. The slurry was conditioned to a pH of 10. Final concentrate grade was 6,050 g/t silver with a recovery of 81%.

Further testing is required to improve selectivity and increase concentrate grade.

     
M3-PN120008
7 January 2014
Revision 2
132



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

For this study, based on the preliminary testwork, design parameters of 86% silver recovery with a final concentrate grade of 6,000 g/t will be used. The high recovery and high concentrate grade can likely be achieved through reagent and flotation optimization.

13.5        QUALITY OF CONCENTRATE

Concentrate from open circuit cleaner flotation tests was subjected to a minor element scan and a Trace Mineral Search (TMS) using QEMSCAN. The concentrate sample had elevated levels of antimony, arsenic, and fluorine. Pyrite was the dominant mineral (41%). Lead-antimony sulfide was the second most abundant mineral. Silver minerals accounted for 7.8% of the weight with freibergite being the majority. The concentrate analyzed had a silver grade of 6,050 gpt.

13.6        GRAVITY CONCENTRATION

A single gravity concentration test was performed on master composite 1. The sample was ground to a primary grind of P80 = 104µ. A Knelson concentrator was used as the first step of gravity. Concentrate from the Knelson concentrator was then hand panned for upgrading. Approximately 9% of the silver in the feed was recovered. No further gravity tests are planned.

13.7        CYANIDATION

A single whole mineralized material leach bottle roll test was performed on master composite 1. The sample was ground to a primary grind of P80 = 104µ. The tests parameters were: 33% solids (w/w), pH 11, 2 g/L NaCN, and 48 hour leach time. After 48 hours of leaching, 48% of the silver in the feed was recovered.

A second bottle roll test was performed on the gravity tail from both the Knelson concentrator and the hand panning. After 48 hours of leaching, 49% of the silver from the tailings was recovered. No further cyanidation tests are planned.

     
M3-PN120008
7 January 2014
Revision 2
133



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

14

MINERAL RESOURCE ESTIMATES

   
14.1

INTRODUCTION

Caracle Creek International Consulting (Caracle Creek) was retained by Quaterra Resources Inc. (Quaterra) to complete a mineral resource estimate update for their Nieves Property located in Zacatecas State, Mexico. The Nieves Property is a large, undeveloped, low grade Ag-Au deposit which has the potential to be mined by open pit.

The mineral resource reported herein is based on drilling information as of June 22nd, 2012. All of the drill hole data, including collars, assays, survey and lithology, were compiled into a database which links directly to the geological modelling and resource estimation software. The mineral resource estimation was evaluated using geostatistical block modeling methods constrained by a mineralised wireframe. GEMCOM’s GEMS resource modeling software V.6.3 was used to generate the block model and perform the grade estimation. Grades for Ag & Au were estimated using the inverse distance method of interpolation. The mineral resources have been estimated in conformity with the CIM “Mineral Resource and Mineral Reserves Estimation Best Practices” guidelines and were classified according to the CIM Standard Definition for Mineral Resources and Mineral Reserves (December 2005) guidelines. The mineral resources are reported in accordance with the Canadian Securities Administrators National Instrument 43-101. Independent, NI 43-101 compliant resources at the Nieves Property were estimated by Jason Baker P.Eng., a Geological Engineer with Caracle Creek. QA/QC was completed by Caracle Creek on the historic assays prior to incorporation in the 3D model (Section 12, Data Verification). Because of his education, project experience and affiliation to a recognized professional association, Mr. Baker is a “qualified person” independent of Quaterra Resources Inc. in accordance with NI 43-101 guidelines. Mineral resources were calculated for the Nieves Project by the methods described below. The Mineral Resource Statement reported for the Nieves Project is presented in Table 14-1 using a 15 g/t Ag cut-off grade.

Table 14-1: Mineral Resource Statement1 (Caracle Creek, June 22nd, 2012)

This report summarizes the methodology, data and validation techniques used by Caracle Creek in estimating the mineral resources for the Nieves Project.

     
M3-PN120008
7 January 2014
Revision 2
134



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

14.2

RESOURCE ESTIMATION METHODOLOGY

   
14.2.1

Resource Database, Preparation & Compositing

Drill hole collar coordinates and details were provided in MS Excel format by Quaterra Resources Inc. including assays, lithology and down hole survey. The resource estimate was calculated using data from 8 drill holes from programs of previous operators between 1995 and 1996, 10 drill holes drilled by Quaterra between 1999 and 2000, as well as 174 drill holes drilled by Quaterra and Blackberry between 2004 and 2012. QA/QC was completed by Caracle Creek on the assays prior to incorporation in the 3D model.

All of these data were compiled into a database which links directly to the geological modelling and resource estimation software. 3D wireframes (solids) representing the mineralized areas were constructed and used to constrain (domain) the tonnage and grade estimation. GEMCOM’s GEMS software V.6.3 was used to generate the 3D block model and perform the grade estimation (Table 14-2, Figure 14-1).

Table 14-2: Data used in estimating the mineral resources at Nieves

     
M3-PN120008
7 January 2014
Revision 2
135



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 14-1: Drill Hole Distribution of all holes at Nieves

The following section describes how the mineralized domains were used to constrain the resource estimation as well as how compositing and outliers were dealt with in this project. The results of the specific gravity analysis are also discussed.

14.2.1.1    Geological Modeling & Mineralized Domains

Geological modeling was performed by Caracle Creek using the raw drill hole data. A topography surface was created by Caracle Creek using the drill hole collar coordinates. The mineralized domain was constructed primarily from the Ag grade assay data. The mineralized domain was not constrained by lithology (Figure 14-1, Figure 14-2 and Figure 14-3).

     
M3-PN120008
7 January 2014
Revision 2
136



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 14-2: View of Topo & Mineralized Domain Looking NW

The La Quinta mineralized domain was defined using 99 drill holes and 5072 samples. The Gregorio North mineralized domain was defined using 25 drill holes and 1729 samples. The drill holes were drilled in a sectional pattern with a drill hole spacing ranging from 20 - 100 meters, in the La Quinta area, and 20 - 175 meters in the Gregorio North area (Figure 14-1). The mineralized domain was projected 100 meters beyond the last drill hole. Due to the potential for bulk open pit mining, a grade cut-off was not used when constructing the mineralized domain. However, if the last assay in the interval was less than 0.1 g/t Au, then it was not included in the mineralized domain unless it had a significant Ag grade component of 10 g/t Ag.

     
M3-PN120008
7 January 2014
Revision 2
137



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 14-3: Sectional view of mineralized domain showing Ag assays (looking NE)

14.2.1.2     Data Analysis & Compositing

All the raw assays within the mineralized domains were extracted from the database for statistical analysis. This included a total of 6789 assay intervals, of which over 98% had an assay interval length of 2.0 meters (Figure 14-4 and Figure 14-5). The remaining assay intervals were of varying lengths between 0.03 & 3.7 meters. Considering the assay data statistics, with respect to interval length, Caracle Creek chose to composite the data to 2m intervals. The estimation parameters set for the mineral resources were not allowed to interpolate through un-sampled intervals. An Ag value of 0.1 g/t was assigned to the missing intervals (Half Detection Limit).

     
M3-PN120008
7 January 2014
Revision 2
138



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Basic assay statistics were calculated for all raw assays within the mineralized domain. See Table 14-3 for the results.

     
M3-PN120008
7 January 2014
Revision 2
139



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 14-3: Summary of raw assay data statistics for all samples within the mineralized domain

Basic statistics were also calculated for the 2 m composites. See Figure 14-4 and Table 14-4 for the results.

Table 14-4: Summary of 2m composite data statistics for all samples within the mineralized domain

14.2.1.3    Grade Capping

Caracle Creek performed a capping analysis on the composited data using histogram plots and probability plots. Figure 14-6 shows the histogram plots for the Ag 2m composite data, including all outliers. Based on this analysis Caracle Creek capped the Ag composites at 1100.0 g/t.

     
M3-PN120008
7 January 2014
Revision 2
140



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 14-6: Histogram showing Ag composite grade distribution for the La Quinta area

14.2.1.4    Specific Gravity

Specific Gravity (SG) for the Concordia (La Quinta) area was determined using 173 SG samples within the mineralized domain. The block model was populated with SG values using these 173 SG samples via inverse distance interpolation. There were only 16 SG samples available for the Gregorio North area, therefore, the average of those samples (2.83) was assigned to each block. The tonnage for each block was calculated as follows: Block volume (10m × 10m × 5m) × (SG) × (the proportion of the block within the solid)

14.2.2        Variography

Caracle Creek did not evaluate the 3D spatial distribution of Au or Ag using variograms.

14.2.3        Block Model

The block model definitions for Nieves are shown in Table 14-5. Partial percents were used as part of the volume estimation. The block volumes were adjusted using the partial percents based on the proportion of the block that was inside the wireframed solids representing the mineralization. The block model origin coordinates are represented by the Maximum “X”, Maximum “Y” and Minimum “Z”. Positive rotation is clockwise about any axis. Based on the anticipated mining methods, the size of the mineralized domain and the drill hole spacing, Caracle Creek chose a block size of 10m × 10m × 5m. The model was rotated 38° counterclockwise from north.

     
M3-PN120008
7 January 2014
Revision 2
141



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 14-5: Block model definitions for Nieves

14.2.3.1    Grade Estimation Strategy

Grade estimation was based on Inverse Distance (power of 2) using two passes. The first pass was the most restrictive in terms of search radius, the minimum/maximum number of samples required as well as the minimum number of holes required. The second pass was less restrictive under the same terms. The first pass populated approximately 40% of the blocks, with the rest of the blocks within the mineralized domain being populated by the second pass. The search ellipse radius and orientation were chosen based on the drill hole spacing. Table 14-6 summarizes the parameters used in the grade estimation. Table 14-7 shows the block model.

Table 14-6: Nieves Block Model Parameters

     
M3-PN120008
7 January 2014
Revision 2
142



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 14-7: Plan View Showing Block Model 14.2.4 Resource Model Validation

The validity of the block model was evaluated using four techniques. 1) Caracle Creek constructed a parallel estimation model for Ag & Au using an inverse distance method of estimation (power of five). The results were within 10% deviation in total tonnes and Ag grade to that of the original model. 2) Statistical comparisons were made between the interpolated blocks from the inverse distance squared model and the 2m composites (Table 14-7). 3) The reported total block model tonnage and grade were also compared to a sectional volume method of estimation, which does not involve block modeling. A weighted average of all Au assays within the mineralized domain was calculated along with the volume of the mineralized domain. The results were within 10% to that of the original block grade estimation. 4) The interpolated block grades were visually checked on section and level plans and compared to the composited data.

     
M3-PN120008
7 January 2014
Revision 2
143



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 14-7: Ag Block Model vs. 2m Composite Statistical Analysis

14.2.5      Mineral Resource Classification

Based on the study reported herein, delineated mineralization at the Nieves Project is classified in part as mineral resource according to the following NI 43-101 definitions:

“In this Instrument, the terms "mineral resource", "inferred mineral resource", "indicated mineral resource" and "measured mineral resource" have the meanings ascribed to those terms by the Canadian Institute of Mining, Metallurgy and Petroleum, as the CIM Standards on Mineral Resources and Reserves Definitions and Guidelines adopted by CIM Council on December 11, 2005, as those definitions may be amended from time to time by the Canadian Institute of Mining, Metallurgy, and Petroleum.” “A Mineral Resource is a concentration or occurrence of natural solid, inorganic or fossilized organic material in or on the Earth's crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge.”

Mineral resources are not mineral reserves as economic viability of the Property has not yet been shown. The terms Measured, Indicated and Inferred are defined in NI 43-101 as follows:

“A 'Measured Mineral Resource' is that part of a Mineral Resource for which quantity, grade or quality, densities, shape, physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.”

     
M3-PN120008
7 January 2014
Revision 2
144



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

"An 'Indicated Mineral Resource' is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics, can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed."

"An 'Inferred Mineral Resource' is that part of a Mineral Resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes."

The estimated tonnages for the mineralized domain at Nieves are classified as Indicated & Inferred resources, as described in the following section. Blocks were classified as indicated if they were populated during pass 1. All blocks populated during pass 2 were classified as inferred.

14.3        MINERAL RESOURCE STATEMENT

Mineral resources for Nieves were classified by Mr. Jason Baker, P.Eng, an appropriate independent qualified person. Classification was done in accordance with the CIM Standard Definition for Mineral Resources and Mineral Reserves (December 2005) guidelines. The mineral resources for the Nieves Project are reported at a cut-off grade of 15 g/t Ag. The Mineral Resource Statement for the Nieves Project is summarized in Table 14-8.

Table 14-8: Mineral Resource Statement1 (Caracle Creek, June 22nd 2012)

The block model tonnage and grade were calculated at various cut-off grades in order to demonstrate the sensitivity of the resource estimate with respect to reporting cut-off grade. The results are shown in Table 14-9. It should be stressed to the reader that the figures presented in Table 14-9 are not to be misconstrued as a mineral resource as they are intended for the sole purpose of demonstrating the sensitivity of the resource estimate with respect to reporting cut-off grade.

     
M3-PN120008
7 January 2014
Revision 2
145



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 14-9: Block Model Quantities and Grades Reported at Various Cut-off Grades

Mineral resource estimates for the Nieves Project presented in this report are effective as of the 22nd day of June, 2012 (Table 14-8).

14.4        ISSUES THAT COULD AFFECT THE MINERAL RESOURCE

There are no known factors related to permitting, legal, title, taxation, socio-economic, environmental, and marketing or political issues which could materially affect the mineral resource at the time of reporting.

     
M3-PN120008
7 January 2014
Revision 2
146



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

15          MINERAL RESERVE ESTIMATES

This section is not required for a Preliminary Economic Assessment.

     
M3-PN120008
7 January 2014
Revision 2
147



16

MINING METHODS

   
16.1

OPEN PIT MINE PLAN

The Nieves silver deposit contains mineralization at or near the surface and is distributed in continuous veins that is ideal for open pit mining methods. The method of material transport evaluated for this study is open pit mining using two16.5 -m3 front end shovels as the main loading units with a 12.2 -m3 front end loader as a backup loading unit. The mineralized material will be loaded into 90-tonne haul trucks and transported to the primary jaw crusher, which will be set up at the toe of the waste dump. The plan assumes that the project operator owns, operates, and maintains all equipment. The general site layout, including pits, waste dumps, the crusher site, infrastructure, and tailings pond, is shown on Figure 1-2.

Mineralized material production is planned at a nominal rate of 10,000 tonnes per day (tpd), equivalent to 3.65 million tonnes per annum with a 10 year mine life. Mining is planned on a 7 day per week schedule, with two 12 hour shifts per day. Other mining schedules may prove to be more effective, but are not expected to significantly change project economics. Peak mineralized material and waste production is estimated at 94,000 tpd during the first year and then slowing to an average rate of 62,000 tpd. The average life of mine stripping ratio is 5.36:1 waste-to-mineralized material, using a 21.3 g/t AgEq cutoff. Lower grade material is stockpiled using 30.5 g/t AgEq cutoff in order to improve project economics which results in a maximum low grade stockpile of 2.8 million tonnes. Other cutoff scenarios using 19.4, 21.3, 23.7, 26.7 and 30.5 g/t were evaluated during the study but the chosen scenario resulted in the best IRR and NPV. Table 16-1 below lists the resources used in the mine production plan. The mine plan is preliminary in nature and includes inferred mineral resources that are considered too geologically speculative at this time to have the economic considerations applied to them to be categorized as mineral reserves.

Table 16-1: Resources Inside Pit Design



Pit Phase


Classification
Mineralized
Material Tonnes X
1,000

Ag
(g/t)

Au
(g/t)

AgEq
(g/t)


Ag (oz)


Au (oz)


AgEq (oz)
Phase 1 Indicated 10,617 65.2  0.06 67.4 22,268,479 19,608 23,009,813
Phase 1 Inferred 1,139 38.4  0.03 39.6 1,405,732 1,203 1,450,498
 
Phase 2 Indicated 8,872 57.5  0.04 58.9 16,394,161 11,869 16,801,719
Phase 2 Inferred 2,215 46.2  0.03 46.9 3,287,717 1,830 3,339,898
 
Phase 3 Indicated 8,114 52.8  0.04 54.0 13,777,644 9,335 14,085,645
Phase 3 Inferred 4,402 52.7  0.03 53.5 7,463,505 3,830 7,564,356
 
Total All Phases Indicated 27,603 59.1  0.05 60.7 52,440,284 40,811 53,897,177
Total All Phases Inferred 7,756 48.8  0.03 49.5 12,156,954 6,863 12,354,752

1) Prepared by Jeff Choquette, P.E., Mining Engineer, an independent Qualified Person within the meaning of NI43-101, using a reporting cut-off grade of 21.3 g/t AgEq.
2) AgEq values were calculated using a $26/oz silver price $1375/oz Au price, 81% Ag recovery 80% Au recovery, 95% metal payable, 1.5 oz/t Ag deduct and 0.05/oz Ag deduct, $1/oz silver refining charge and $10/oz Au refining charge $300/wet tonne treatment charge and a $50/wet tonne shipping charge.

     
M3-PN120008
7 January 2014
Revision 2
148



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

16.1.1      Pit Optimization

In order to evaluate the optimal mineralized material throughput rate for the current resource model on the Nieves Silver Project a series of Whittle optimizations were completed. The first step involved the calculation of an AgEq value for use in the pit optimizations. The AgEq calculation was based on $1,375 gold and $26 silver. The calculation includes metal recoveries, expected smelter charges and refining. Table 16-2 below shows the parameters use in the AgEq calculation.

Table 16-2: AgEq Calculation Parameters




Metal


Price
US$/oz.


Recovery
%

Smelter
Payable
%

Smelter
Deduct
oz./t

Refining
charge
US$/oz.
Smelter
Treatment
Charge
$/wmt conc.
Concentrate
Shipping
Charge
$/wmt conc.
Ag
Au
$26
$1,375
81%
80%
95%
95%
1.5
0.05
$1
$10
$300
$50

To assist in determining the optimal throughput a series of pit shells from 5 ktpd to 20 ktpd on 2.5 ktpd increments were run. For each processing rate 29 pit shells were generated based on a silver price starting at $8.32/oz. and ending at $52.00/oz. using $1.56 increments. The base mine operating costs for each case were then factored for the benches below the surface elevation by adding $0.0205 for every 5 meters in depth. Pit slopes were run at 43 degrees for all sectors which will allow room for insertion of haulage ramps and safety benches in the pit design stage. Table 16-3 shows the pit optimization parameters.

Table 16-3: Pit Optimization Parameters

Area Parameter
Mining
Operating
AgEq Price
Initial Capital
Discount rate
Pit Slopes
Base cost for processing rate -plus $0.0205 per 5m bench below surface.
Base operating cost for processing rate, plus G&A and environmental.
$8.32 to $52.00 based on $1.56 increments (29 pits shells)
Varies with process rate.
5%
43 degrees

The initial capital, mineralized material processing plus G&A and mining costs were given a different value for each processing rate. The initial capital cost estimate started from the 15 ktpd process rate. The capital was then factored based on the change in processing rates to the power of 0.75. The mineralized material processing plus G&A and mining costs also used the preliminary costs estimates for a 15 ktpd case but used a factor to the power of 0.2. Table 16-4 below lists the different capital and base operating costs used for each processing rate.

The NPV for each pit shell in each case was then calculated using the initial capital estimate for each processing rate and a 5% discount rate. The best NPV results from each set of optimizations was then assembled and graphed to determine the optimal processing rate. Based on these results the optimal processing rate for the current status of the project is 10 kptd. Table 16-4 shows a summary of the NPV’s for the different processing rates. Note that the NPV’s are preliminary results based on the rough pit shells and don't included any detail for pit ramps and safety benches included with a pit design.

     
M3-PN120008
7 January 2014
Revision 2
149



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 16-4: Optimization Capital and Operating Costs

Mineralized
Material
Processed
(tpd)



Initial Capex

Operating
Cost
$/ton

Base Mining
Cost
$/ton



NPV @ 5%
5,000 $131,607,401 $12.41 $1.12 $126,006,028
7,500 $178,381,067 $11.44 $1.03 $138,871,987
10,000 $221,336,384 $10.80 $0.98 $140,204,765
12,500 $261,658,785 $10.33 $0.93 $135,739,850
15,000 $300,000,000 $9.96 $0.90 $128,715,010
17,500 $336,768,410 $9.66 $0.87 $105,488,780
20,000 $372,241,944 $9.40 $0.85 $85,629,369

16.1.2      Pit Design

The Nieves open pit is planned in three pit phases designed on the Concordia zone. The San Gregorio zone resulted in some mining in the pit optimization studies but it was minimal so this zone was not included in the mine plan but may become viable with additional drilling. The $23.92/oz Ag pit shell resulted in the highest NPV in the optimization study for the 10 ktpd case and thus was chosen as the basis for the final pit design. Since there has not been a geotechnical study completed on the project a conservative inter-ramp pit slope of 45° was chosen. Haul roads are designed at a width of 25 meters, which provides a safe truck width (6.5 meters) to running surface width ratio of 3.85. Maximum grade of the haul roads is 10%, except for the lowermost few benches where the grade is increased to 14% and the ramp width is narrowed to 14 meters to minimize excessive waste stripping. The pit design criteria are presented in Table 16-5.

Table 16-5: Pit Design Criteria

Mine Design Criteria
Pit Design Criteria Parameter
Inter Ramp Angles 45 Degrees
Face Angles 65 degrees
Catch Bench Berm 9 m
Catch Bench Vertical Spacing 20 m
Minimum Turning Radius 25 m
Road Widths 25 m
Road Grade 10%
Road Widths Pit Bottom 14 m
Road Grade Pit Bottom 14%

     
M3-PN120008
7 January 2014
Revision 2
150



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The pits were designed in three phases in order to balance the required stripping throughout the mine life. The first phase is based on a $11.44/oz. Ag pit shell, phase two is based on a $17.68/oz. Ag shell and as mentioned previously the final design is based on a $23.92/oz. Ag pit shell. The pit designs phases are shown in Figure 16-1 to Figure 16-3.

     
M3-PN120008
7 January 2014
Revision 2
151



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 16-1: Phase 1 Pit Design

     
M3-PN120008
7 January 2014
Revision 2
152



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 16-2: Phase 2 Pit Design

     
M3-PN120008
7 January 2014
Revision 2
153



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Figure 16-3: Phase 3 Pit Design

     
M3-PN120008
7 January 2014
Revision 2
154



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

16.1.3      Waste Dump Design

The waste dump was designed near the pit ramp exit just south of the pit design. The dump was designed with a maximum slope angle of 2.5:1. The waste dump is designed with a capacity of 190 million tonnes to accommodate the mine plan. The location of the waste dump in relation to the other facilities is shown in Figure 1-2.

16.2        PRODUCTION SCHEDULE

The yearly mine production schedule is presented in Table 16-6. The production schedule is driven by the nominal mineralized material feed rate of 10,000 tpd. The production schedule has been calculated on a monthly basis for the first three years and then yearly for the remaining life of the mine. The schedule shows mineralized material being delivered to the mill during the first month of mining at a rate of 6,800 tpd with the mine being able to provide the required mill rate of 10,000 tpd starting in month six. Peak mineralized material and waste production is estimated at 94,000 tpd during the first year and then slowing to an average rate of 62,000 tpd. The average life of mine stripping ratio is 5.36:1 waste-to-mineralized material.

The mine schedule is preliminary in nature and includes inferred mineral resources that are considered too geologically speculative at this time to have the economic considerations applied to them to be categorized as mineral reserves. Thus, there is no certainty that the production profile concluded in the PEA will be realized. Actual results may vary, perhaps materially.

     
M3-PN120008
7 January 2014
Revision 2
155



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
156



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

16.2.1      Production Schedule Parameters

The mine production schedule is based on a 7 day per week schedule, with two 12 hour shifts per day. There are four crews planned to cover the rotating schedule. Each 12 hour shift contains a half hour down for blasting and miscellaneous delays, a half hour for shift start up and shutdown and an hour for lunch and breaks for a total of 10 effective working hours. Table 16-8 below shows typical yearly schedule parameters and hours scheduled.

Table 16-8: Mine Schedule Parameters

Mine Schedule  
Crews 4
Shifts/day 2
Hours/shift 12 hr.
Lunch, Breaks, etc 1 hr.
Blasting, Misc 0.5 hr.
Startup & Shutdown 0.5 hr.
Days/Year 365 days
Scheduled Hours/Year 8,760

The amount of equipment required to meet the scheduled tonnages is calculated based on the mine schedule, equipment availabilities, usages and haul and loading times for the equipment. Equipment mechanical physical availabilities start at 94% for the trucks, drills and loading units. For each year of production the mechanical physical availabilities decrease by one percent, the use of availability for all of the equipment is calculated at 83% based on the breaks and down time in the schedule parameters. An additional 85% efficiency factor is applied to all of the equipment for calculating the total units of equipment required. The Table 16-9 below shows the equipment availability parameters.

Table 16-9: Equipment Availabilities

Equipment
Availabilities
Year
1
Year
2
Year
3
Year
4
Year
5
Year
6
Year
7
Year
8
Year
9
Year
10
Physical Availability 94% 93% 92% 91% 90% 89% 88% 87% 86%  85%
Use of Availability 83% 83% 83% 83% 83% 83% 83% 83% 83%  83%
Efficiency 85% 85% 85% 85% 85% 85% 85% 85% 85%  85%

16.2.2      Drill and Blast Parameters

The design parameter used to define drill and blast requirements are based on a 200 mm blast hole on a 7.4m by 6.4m pattern in the mineralized material zones and a 7.7 m by 6.7 m pattern in the waste zones. Benches will be blasted and mined on 10m levels with 1.9m of sub-drill. Buffer rows and pre-shear are planned to allow for controlled blasting and minimize damage to the highwalls. The number of blast holes and blast hole drills required each month or year is calculated based on the parameters shown in Table 16-10 and used in calculating the operating costs. The majority of the mine life requires two rotary production drills, a third smaller drill is planned for pre-shear drilling.

     
M3-PN120008
7 January 2014
Revision 2
157



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 16-10: Drill and Blast Parameters

Production & Wall Control Blast Pattern Data   Production Pattern  
DRILLING & BLASTING PARAMETERS

Units
Mineralized
Rock
Waste
Rock
Wall Control Pattern
Buffer Buffer Preshear
             Tonnage Factor dmt/cubic meter 2.835 2.780 2.840 2.840 2.840
     Blast Pattern Details            
             Bench Height meters 10.00 10.00 10.00 10.00 10.00
             Sub Drill meters 1.90 1.90 1.00 1.25 0.00
             Diameter of Hole mm 200.00 200.00 200.00 200.00 114.00
             Staggered Pattern Spacing meters 7.40 7.70 3.70 7.40 1.40
             Staggered Pattern Burden meters 6.40 6.70 3.20 3.20 1.40
             Drill Equivalent Square Pattern meters 6.90 7.20 3.45 5.30 1.40
             Hole Depth meters 11.90 11.90 11.00 11.25 10.00
             Height of Stemming or Unloaded Length meters 4.00 4.00 9.00 6.00  
     Material Quantity            
             Volume Blasted/Hole cubic meters 476 518 119 281 20
             Tonnes Blasted/Hole tonnes 1,350 1,441 338 798 56
     Powder Factor            
             Percent Emulsion   30% 30% 30% 30% 30%
             Percent Anfro   70% 70% 70% 70% 70%
             Density of Powder g/cc 1.01 1.01 1.01 1.01 1.01
             Loading Density kg/m 31.67 31.67 31.67 31.67 10.29
             Powder/hole kg 250.17 250.17 63.33 166.25 5.01
             Powder Factor kg/t 0.185 0.174 0.187 0.208 0.090
             Powder Factor kg/bcm 0.525 0.483 0.532 0.592 0.256
Drill Productivities            
     Penetration Rate M/hr 40.00 40.00 35.00 35.00 25.00
             Penetration Rate M/min 0.67 0.67 0.58 0.58 0.42
     Cycle Time Estimate            
             Drilling Time minutes 17.85 17.85 18.86 19.29 24.00
             Steel Handling Time minutes 0.00 0.00 0.00 0.00 0.50
             Set up Time minutes 3.30 3.30 3.30 3.30 2.00
             Add Steel minutes 0.00 0.00 0.00 0.00 2.00
             Pull Rods minutes 0.50 0.50 0.50 0.50 2.00
             Total minutes 21.65 21.65 22.66 23.09 30.50
Drilling Factors for Wall Control            
             
     Wall Control Drill Holes Required Perimeter Blast          
             Pre-Shear Holes holes/meter   0.71      
             Buffer Holes - 2 Rows holes/meter   0.48      
             Material to Remove from Production Blast tonnes/meter   288.26      

16.2.3      Load and Haul Parameters

The design parameter used to define the loading and hauling requirements are shown in Table 16-11 below. The main loading units will be two 16.5 m3 front shovels with a 12.2 m3 front end loader as a backup unit. The shovels were chosen over front end loaders as the main loading unit because of their higher loading rate versus the loaders which will be advantageous given the short cycle times of the trucks. 90 tonne haul trucks are the main hauling unit, the shovel is calculated to require 3 passes to load the trucks and the loader will require 4 passes. 139 tonne trucks were also evaluated in the schedule but the 90 tonne trucks were found to be more cost effective than the 139 tonne trucks. Haulage profiles for the mineralized material and waste material from each pit phase were generated and used to calculate the truck cycle times which were used in the equipment requirement calculations.

     
M3-PN120008
7 January 2014
Revision 2
158



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 16-11: Load and Haul Parameters

Loading & Truck Match Calculation   16.5 CM Shovel 12.2 CM Loader


Mineralized
Material

Waste
Mineralized
Material

Waste
Bucket Capacity (heaped) cm 16.50 16.50 12.20 12.20
Bank Material Weight Dry kg/bcm dry 2835 2780 2835 2780
Bank Material Weight Wet kg/bcm wet 2906 2850 2906 2850
Bulk Factor (Swell Factor)   1.35 1.35 1.35 1.35
Loose Material Weight Dry kg/lcm dry 2,100.0 2,059.3 2,100.0 2,059.3
           
% Moisture   2.5% 2.5% 2.5% 2.5%
Bucket Fill Factor   0.90 0.90 0.90 0.90
Effective Bucket Capacity cm 14.85 14.85 10.98 10.98
Wet Material Weight (LCM) wmt/lcm 2.15 2.11 2.15 2.11
Dry Material Weight (LCM) dmt/lcm 2.10 2.06 2.10 2.06
Tonnes/Pass wmt 31.96 31.34 23.63 23.18
Truck Size Capacity (volume) cubic m heaped 60.0 60.0 60.0 60.0
Truck Size Capacity (tonnes) wmt 90.3 90.3 90.3 90.3
Theoretical Passes (volume) passes 4.04 4.04 5.46 5.46
Theoretical Passes (tonnes) passes 2.82 2.88 3.82 3.90
Actual Passes passes 3.0 3.0 4.0 4.0
Truck Load - Volume (volume) cm 44.6 44.6 43.9 43.9
Truck Load - Volume (tonnes) wmt 95.9 94.0 94.5 92.7
Truck Load for Productivity dmt 93.6 91.7 92.2 90.4
Truck Capacity Utilized (tonnes) by weight 106.2% 104.1% 104.7% 102.7%
Truck Capacity Utilized (volume) by volume 74.3% 74.3% 73.2% 73.2%
Average Cycle Time sec 35 35 55 55
Truck Spot Time sec 30 30 30 30
Load Time per Truck sec 135 135 250 250
Load Time per Truck minutes 2.25 2.25 4.17 4.17
Maximum Productivity trucks/hr 26.7 26.7 14.4 14.4
Insitu Volume/Hour bcm/hr 880.0 880.0 468.5 468.5
Tonnes/Hour dmt/hr 2,494.8 2,446.4 1,328.1 1,302.4

16.3        PREPRODUCTION DEVELOPMENT

The preproduction requirements at Nieves are minimal given the presence of mineable mineralized material near the surface. The mine will be able to provide 6,800 tpd of mineralized material to the mill during the first month of mining and will be at full capacity by month six. The terrain is fairly flat which will make the construction of initial haul roads fairly inexpensive. An estimated allowance of $2.5M has been included in the initial capital to cover the costs of the initial road construction and any clearing, or grubbing that may take place.

16.4        MINING EQUIPMENT

The initial mine production equipment will include two 16.5 m3 shovels. A 12.2 m3 front end loader will function as a backup loading unit and infill for production when needed. Initially thirteen 90 tonne haul trucks are required to meet the production schedule, during year two an additional truck will be added to meet production requirements and during year three five more trucks will be added for a total of nineteen trucks. Two production drills will also be purchased initially with a third pre-shear drill also purchased for wall control purposes. Table 16-12 lists the initial and total equipment requirements.

     
M3-PN120008
7 January 2014
Revision 2
159



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 16-12: Mine Production Equipment

Description # Initial Units # Total Units
16.5 m3 Front Shovel 2 2
12 m3 Loader 1 1
Production Drill 2 2
PreShear Drill 1 1
Haul Truck - 90t 13 19

Support equipment will consist of three dozers Cat D8, D9 and D10. A 16’ road grader will service the haul roads along with a 10,000 gallon water truck. A 0.9 m3 excavator will be purchased for scaling highwalls and other miscellaneous projects around the mine site. Six mobile light plants will be purchased for lighting the working areas during nighttime production. A maintenance service truck with a mobile crane will be purchased for field maintenance and a self-contained fuel lube truck will be purchased for infield fueling.

Table 16-13: Mine Support Equipment

Description # Initial Units # Total Units
16' Grader 1 1
Water Truck 1 1
448hp Dozer 1 1
347hp Dozer 1 1
580hp Dozer 1 1
Lube/Fuel/Service 3 3
Light Plants 6 6
Small Excavator 148 hp 1 1

16.4.1      Staffing

The required manpower for the mine department is calculated based on the equipment required to meet the production schedule. The yearly averaged manpower requirements are shown in Table 16-14 below. The average mine department personnel is expected to average 152 people.

     
M3-PN120008
7 January 2014
Revision 2
160



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 16-14: Mine Department Manpower

Manpower Summary LOM Average
Mining G&A  
       Mine Superintendent 1
       Mine Foreman 4
       Blasting Foreman 1
       Maintenance Superintendent 1
       Maintenance Foreman 4
                                                                 Mine Salaried 11
Drilling and Blasting  
       Driller 6
       Blaster 2
       Blaster Helper 2
                                               Drilling and Blasting 10
Loading  
       Loader Operator 4
       Shovel Operator 7
                                                                                 Loading 11
Hauling  
       Truck Driver 61
                                                                                 Hauling 61
Roads and Dumps  
       Dozer Operator 8
       Grader Operator 4
       Utility Operator 4
                                                                                 Support 16
Mine Maintenance  
       Lead Mechanic 4
       Heavy Equipment Mechanic 4
       Light Vehicle Mechanic 2
       Welder/Mechanic 8
       Apprentice 8
       Planner 2
       Electrician 2
                                       Total Mine Maintenance 30
                                 Total Mine OP Operations 140
Engineering and Geology  
       Sr Mining Engineer 1
       Jr Mining Engineer 1
       Chief Surveyor 1
       Surveyor 1
                                                                     Engineering 4
       Sr Geologist 1
       Ore Control Geologist 1
       Sampler 2
                                                                               Geology 4
                                       Total Mine OP Eng Geo 8
Total Mine Department 152

     
M3-PN120008
7 January 2014
Revision 2
161



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

17          RECOVERY METHODS

The design basis for the processing facility is 10,000 dry metric tons per day (DTPD) or 3,650,000 dry metric tons per year (DTPY) on an operating basis of 91% availability.

Design mineralized material grade to the process plant is estimated to average 32.0 gpt of silver and 0.04 gpt gold. The process plant design allows for sustained metal recovery of silver and gold. Figure 17-1 shows the site plan of the process area.

Figure 17-1: Process Area Site Plan

17.1        CRUSHING AND COARSE MINERALIZED MATERIAL STORAGE

Run of Mine (ROM) mineralized material will be trucked from the mine to the primary crusher where it will be dumped directly into the crusher dump pocket that feeds a jaw crusher. If required, ROM mineralized material may be dumped in a stockpile ahead of the primary crusher. A front end loader will be used to feed the crusher if needed. The crusher feed pocket will be designed to contain two truckloads of material.

ROM mineralized material will discharge from the crusher dump hopper onto a vibrating grizzly feeder. The feeder will discharge oversize mineralized material directly into a jaw crusher. Jaw crusher product will discharge onto the discharge conveyor. Undersize material that passes through the vibrating grizzly feeder will be combined with the jaw crusher product on the discharge conveyor. The discharge conveyor will discharge to the stockpile feed conveyor. The conveyor will transport the mineralized material to a coarse material stockpile.

     
M3-PN120008
7 January 2014
Revision 2
162



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

A hydraulic rock breaker located at the crusher will be provided for breaking oversize ROM material.

Crushing production rate will be monitored by a belt scale mounted on the stockpile feed conveyor.

A “wet spray” system will be installed to suppress dust in mineralized material feed streams, transfer points, and dump pocket. An air compressor and air dryer will be installed for operation and maintenance.

17.2        PRIMARY CRUSHED MINERALIZED MATERIAL RECLAIM

Primary crushed mineralized material will be discharged to a stockpile. The coarse mineralized material stockpile will have a 10,000 tonne live capacity. Dead storage may be recovered by bulldozer and/or a front end loader.

Three draw points under the coarse material stockpile will provide mineralized material to three reclaim feeders, two operating and one standby, located in a tunnel. The reclaim feeders will discharge onto the SAG mill feed conveyor. Each feeder will be capable of feeding up to 500 tonnes per hour of mineralized material to the SAG mill feed conveyor. The feeders will be variable speed and controlled to maintain a set point feed rate to the grinding circuit. One, two, or three feeders may be operated at any time. The control signal will be provided by a belt scale mounted on the conveyor downstream of the feed points. A metal detector will be installed over the SAG mill feed conveyor to remove tramp metal.

A “wet spray” system will be installed to suppress dust in mineralized material feed streams, transfer points, and dump pocket. In addition, cartridge type dust collectors will be installed for dust control.

17.3        GRINDING

The grinding circuit will be designed to process an average of 10,000 mtpd at 91% availability on a 24 hour per day, 365 days per year basis. Mineralized material will be ground to a final product size of 80% passing 104 microns in a semi-autogenous (SAG) primary and ball mill secondary grinding circuit.

Primary grinding will be performed in an 8.5 m diameter by 3.1 m (effective grinding length) long SAG mill with a 5,200 kW motor. The SAG mill will operate in closed circuit with a SAG mill discharge screen.

SAG mill discharge screen oversize will report to a series of two belt conveyors that will transport the oversize back to the SAG mill feed. The pebbles may be discharged directly to the SAG mill feed or they may be diverted to a pebble pile. SAG mill screen undersize will flow by gravity to the cyclone feed sump where it is combined with ball mill discharge.

Secondary grinding will be performed in a 5.0 m diameter by 10.1 m (effective grinding length) long ball mill powered by a 5,100 kW motor operated in closed circuit with hydrocyclones. The ball mill will discharge over a trommel screen. Ball chips will be rejected out the end of the trommel into a tote bin. Ball mill discharge will be combined with SAG mill discharge screen undersize in a grinding sump and will be pumped to hydrocyclones for classification. Combined slurry will be pumped using variable speed horizontal centrifugal slurry pumps to the primary cyclone cluster. Hydrocyclone underflow will report to the ball mill. Hydrocyclone overflow (final grinding circuit product) will flow by gravity to the rougher conditioner tank. Cyclone overflow will be sampled prior to rougher flotation.

     
M3-PN120008
7 January 2014
Revision 2
163



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

A belt weigh scale will monitor the SAG mill discharge screen oversize that will be returned to the mill. The belt scale on the SAG mill feed conveyor will provide a signal for adjusting belt feeder speeds and makeup water addition.

Flotation reagents may be added to the SAG mill feed and may be added to the cyclone feed sump prior to flotation.

The grinding and flotation circuit plant floor will be concrete on grade with containment walls to contain spills within the floor area. The floor will be sloped to sumps that will pump the contained liquids and solids back to the mill feed. Steel framed maintenance platforms with steel grating will be provided.

17.4        FLOTATION AND REGRIND

The flotation circuit will consist of one train of rougher cells and one train of cleaner cells.

The rougher circuit will consist of one train of eight 100 m3 tank type, forced air cells; with a drop between each cell and a conditioning tank ahead of the first cell. The eight cells will be used to float silver from the mineralized material. Rougher flotation is expected to occur at a natural pH.

The cleaner train will consist of: a regrind mill, regrind cyclones, a conditioning tank, and one train of fourteen flotation cells, seven first cleaner cells, four second cleaner cells, and three third cleaner cells.

Cyclone overflow at approximately 30% solids will flow by gravity from the primary grinding circuit to the rougher conditioning tank. Slurry from the conditioning tank will overflow by gravity to the first rougher flotation cell. Rougher flotation tailings from the final rougher cell will be pumped to a high-rate tailings thickener.

Rougher flotation concentrate will flow by gravity to the regrind cyclone feed pump box. The slurry will be pumped from the pump box using variable speed horizontal centrifugal pumps (one operating and one stand by) to the regrind mill hydrocyclone cluster, or may be bypassed directly to the cleaner conditioner tank. Underflow from the regrind cyclone cluster will be returned, by gravity, to the regrind mill. Cyclone overflow from the regrind mill cyclone cluster will flow by gravity to the cleaner conditioner tank via the cleaner feed sampler.

Rougher concentrate will be reground to a final product size of 80% passing 20 to 30 microns in the regrinding circuit. Reground or bypassed concentrate will flow by gravity from the cleaner conditioner tank to the first cleaner flotation cells. The first cleaner concentrate will be pumped using froth pumps (one operating and one standby) into the second cleaner flotation cells and the tailing will be pumped (one operating and one standby) back to the rougher circuit or may be bypassed directly to the tail thickener. The second cleaner concentrate will be pumped using froth pumps (one operating and one standby) to the third cleaner flotation cells. The third cleaner concentrate will be pumped using froth pumps (one operating and one standby) to a concentrate thickener. Cleaner flotation is expected to occur at an increased pH.

     
M3-PN120008
7 January 2014
Revision 2
164



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Automatic samplers will be provided to sample and monitor designated streams.

Flotation reagents may be added into the rougher conditioner tank and/or may be stage added to the rougher flotation cells. In addition, flotation reagents may be added into the cleaner conditioner tank ahead of each row and/or may be stage added as needed into the cleaner cells.

17.5        DEWATERING AND FILTRATION

Concentrate from the third cleaner flotation cells will be pumped to a concentrate thickener. Concentrate thickener overflow from will be pumped to the cyclone feed sump for re-use in the process or may be bypassed to the process water pond. Concentrate thickener underflow will be pumped (one operating pump and one standby) to an agitated storage tank and then to a pressure filter. Flocculant will be added as needed to aid in solids settling in the thickener. There will be a single concentrate filter.

Filter cake from the concentrate filter will drop onto a discharge conveyor that will feed a concentrate bin feed conveyor. Concentrate from the discharge conveyor may be bypassed to a bulk concentrate storage area. Concentrate from the bin feed conveyor will discharge to a bagging system. Bagged concentrate will be loaded by fork lift in trucks for shipping.

A truck scale will be located near the concentrate load out area.

A metal clad concentrate handling building will house the filter, thickener, concentrate packaging, electrical, and load out. The floor will be concrete on grade with curbs to contain spills within the floor area. The floor will be sloped to sumps and pumps that will pump the collected liquids and solids back to the process. Steel framed maintenance platforms with steel grating will be provided.

17.6        FLOTATION TAILING TREATMENT

The rougher flotation tailings will be pumped to a high rate tailings thickener. Flocculant and dilution water will be added to the thickener feed to aid in settling.

The withdrawal rate of settled solids will be controlled by a variable speed thickener underflow pump to maintain either thickener underflow density or thickener solids loading. Underflow from the tailing thickener will be pumped using three horizontal centrifugal slurry pumps (two fixed speed, one variable speed, three operating, three standby), at 50 to 65% solids, to the TSF.

     
M3-PN120008
7 January 2014
Revision 2
165



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The thickener overflow will be pumped, using fixed speed horizontal centrifugal pumps, to the process water pond.

The tails thickener, a high rate thickener, will be mounted on steel legs on foundations. A concrete containment area with slab on grade and cast-in-place curbs will contain rain runoff and process spills. A sump pump will transfer the containment water and/or spills back to the thickener.

17.7        REAGENT STORAGE AND MIXING

Reagents requiring handling, mixing, and distribution system include:

  • Collector(s)
  • Frother(s)
  • Flocculant
  • Antiscalant

The dry reagents will be stored under cover, then mixed in reagent tanks and transferred to distribution tanks for process use.

Liquid reagents will be off-loaded to storage tanks and transferred to distribution tanks for process use.

17.8        WATER SYSTEM

Water for will be supplied from a variety of sources over the life of mine (LOM).

Process water will be recycled from the tailings thickener and TSF. The reclaimed water will be pumped to the process water pond located close to the plant.

Make up water is introduced to the system to account for evaporation losses. Make up water will be pumped to a fresh/fire water tank. The fresh/fire water tank will supply the requirements for reagents, crushing area dust suppression, and for use as makeup water in material processing. In addition, fresh water will be delivered to the truck shop, the truck wash, and the warehouse, laboratory, and administration buildings. Fresh water will be supplied from wells. Water from the wells will be pumped to a Fresh water tank. The fresh water tank will supply the requirements for reagents, crushing area dust suppression, and for use as makeup water in material processing. In addition, fresh water will be available at the truck shop, the truck wash, and the warehouse laboratory, and administration buildings.

Potable water will come from the Fresh/Fire water tank. The water will be distributed from a 30 m3 capacity storage tank following treatment (filtering and chlorinating) in a potable water treatment plant.

     
M3-PN120008
7 January 2014
Revision 2
166



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

17.9        COMPRESSED AIR

An air compressor and air receiver will be installed for operation and maintenance at the primary crushing area. Plant air compressors will provide service and instrument air for grinding through the tailings operations. An air dryer will remove moisture in instrument air. Plant air and instrument air receivers will be provided.

Individual low pressure blowers will be located in the flotation area to provide air to the rougher flotation and cleaner flotation cells.

A tank mounted reciprocating air compressor will be installed for operation and maintenance at the truck shop.

     
M3-PN120008
7 January 2014
Revision 2
167



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

18

PROJECT INFRASTRUCTURE

   
18.1

TRANSPORTATION

The Nieves project will have convenient ground transportation for construction and operation of the project. Within close proximity is federal Mexican Highway “Cerraterra Federal 49” that runs northwest from Rio Grande to Juan Aldama Municipality. An existing paved road leads east 17 km from a turn off on highway east adjacent to the Nieves property.

No rail or port facilities are planned or required for this project.

18.2        POWER

Comisión Federal de Electricidad (CFE) is the regional supplier of power in Mexico. This power is carried largely on Mexico’s high voltage transmission systems.

Power for the project facilities will be provided from a connection to the local transmission grid that runs along Highway 49. A new substation would likely be required, along with a new 17 km 115 kV power line to the site.

18.3        WATER

The Nieves project will likely require 50 to 100 liters per second of fresh water to sustain operations. While no water exploration has been completed for the Nieves project to date, past experience in the area indicates that water is available in deep regional aquifers. It was a assumed that a water well field could be found within close proximity of the project.

18.4        TAILING STORAGE FACILITY

The Nieves project tailing storage facility (TSF) will be constructed utilizing downstream dam construction and located south of the processing facility. The TSF location was selected primarily because adjacent hills make it topographically accommodating to an economical tailing dam design. Tailing slurry will be pumped from the processing facility at 55% solids. Material will then be deposited utilizing a pipeline with spigots at strategic locations. Solids will settle in the dam and supernatant water will be recycled back to the processing facility.

A three year starter dam will be constructed as part of the original capital project that will hold 10.5 million tonnes of tailing. Starting in year three, the dam will be “raised” by adding material on top and downstream of the dam. This will allow the dam to hold more tailing material. The dam will be raised multiple times throughout the mine life. The costs for raising the dam are allocated in sustaining capital. The ultimate capacity of the dam is 35.4 million tonnes.

It is assumed for the purposes of this project that the tailing facility will be unlined. It was also assumed that the dam will be constructed of local borrow material and that the constructed side slopes will be 3 (horizontal) to 1 (vertical).

     
M3-PN120008
7 January 2014
Revision 2
168



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

19          MARKET STUDIES AND CONTRACTS

No marketing studies were completed for this study. It was assumed for the purposes of this PEA that concentrate can be sold to a Mexican smelter.

     
M3-PN120008
7 January 2014
Revision 2
169



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20

ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

   
20.1

ENVIRONMENTAL STUDY RESULTS AND KNOWN ENVIRONMENTAL ISSUES

This section contains the results of environmental studies and a discussion of any known environmental issues that could materially impact the project.

20.1.1

Environmental Characterization

   
20.1.1.1

Typical Weather Patterns at the Project Site

Typical weather patterns at the project site include the following:

  1.

Climate Type

     
 

According to Koppen’s classification modified by E. Garcia (1988), the typical weather in the project zone belongs to the dry climate group (BS), dry climate type (BS0) and partially dry climate type (BS1).

     
  2.

High Temperatures

     
 

The average temperature in January is around 12°C and rises to 23°C in August. The area has an average annual temperature of 17.9°C.

     
  3.

Precipitation

     
 

The annual proportional precipitation in the zone is 383.1 mm. The months of July and August are the rainiest, with rains between 84.9 and 86.4 mm respectively. March has historically been the driest month, with only 1.7 mm of rain.

     
 

The zone is not susceptible to hurricanes or tropical cyclones.

     
  4.

Air Quality

     
 

The project zone is located in the Santa Rita mining district, where there are many (sometimes very old) mining construction sites, waste rock areas and, leach pads that could imply impacts on the air quality of the zone.

20.1.2      Seismic Activity

The project will built in an area where there is no historical record of earthquakes. There have been no earthquakes reported in the last 80 years, and no ground accelerations from earthquakes are expected beyond the 10% of the gravity acceleration caused by earthquakes.

In general, all volcanoes in Mexico are located over 100 kilometers away from the project site. Therefore, if one of them became active, it would not represent a risk for the zone.

     
M3-PN120008
7 January 2014
Revision 2
170



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.1.3      Hydrologic and Underground Surface Information

According to the names given by the National Water Commission (CONAGUA), the project area is located in the R. Aguanaval hydrologic basin, below the hydrologic basin called Hydrologic RH36Dc Río Agua Naval-Río Grande. This represents an endorheic (or closed) basin that deposits its current water under the hydrologic basin RH36Db R. Aguanaval-P. Deriv. Sombreretillo.

Inside the project area are many intermittent creeks that only run when it is raining. Meanwhile, the municipality has one important river available, which is Rio Aguanaval or de Nieves. In Colonial times it had been named Rio de Medina, Río de Alonso López de Lois, de Urdiñola and later after the colonial times it was called Guanaval or Benaval. Currently the river is called Aguanaval or Nieves.

20.1.3.1    Underground Water

The project site is located on the aquifer named by the National Water Commission as 3217 El Palmar. It has an annual average recharge of 69.1 million m3, which represents a concessional underground water volume of 48.4 million m3 and an annual average underground water survey of 10.5 million m3.

20.1.4      Land Use and Vegetation

The project area is located in the Santa Rita mining district, where there are several old mining works, leaching pads, and waste rock dumps, with relative flat topography, covered by alluvial or rock materials. The vegetation on the site is primarily Creosote (Larrea tridentata), Texas Sage (Leucophyllum frutescens), A. Gray (Mimosa zygophylla), chaparro prieto (Castela texana), huizache (Acacia sp.) mesquite (Prosopis Grandulosa, nopaleras (opuntia sp.), tesajillo (Opuntia leptocaulis), Agave lechugilla and maguey (Agave sp.).

The fauna on site is typical for the Zacatecas desert; however, very rarely because of its proximity to buildings and human activities, the site fauna is represented by hares (Lepus sp.) rabbits (Sylvilagus audobony parvulus), roadrunners (Geococcxys californainus), house sparrow (Passer domesticus), rattlesnake (Crotalux sp.), and lizard (Family iguadinae).

20.1.5      Regiones Terrestres Prioritarias (RTP) or Priority/Protected Land Areas

The closest RTP is located more than 50 kilometers to the west of the project site.

20.1.6      Important Areas for the Conservation of Birds

AICA C62, called Sierra de Valparaíso, is located more than 50 kilometers directly south of where the Nieves project will be developed. At a similar distance, to the west, AICA NO-52 (Sierra de Organos) is located in the state of Durango.

     
M3-PN120008
7 January 2014
Revision 2
171



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.1.7      Regiones Hidrologicos Prioritarias (RHP) or Priority/Protected Hydrological Areas

The closest RHP, RHP-51 Camacho-Gruñidora, is located more than 25 kilometers to the west of the project site.

20.1.8      Natural Protected Areas

The project site is not located inside a Natural Protected area. The closest protected area is the National Park Sierra de Organos, in the municipality of Sombrerete, Zacatecas, at a distance of more than 60 km to the southwest of the project site.

20.2        REGULATIONS AND MANAGEMENT REQUIREMENTS (PERMITS/AUTHORIZATIONS)

This section contains an analysis of the regulations relevant to the development of the Nieves Project, as well as management requirements, including permits and authorizations.

The Nieves Project consists of carrying out work and activities related to the exploration, exploitation and mineral extraction/beneficiation reserved by the Federation in the terms of Article 27 of the Mexican Constitution and in the Mining Law, as well as the change in land use from forest land for this purpose.

By virtue of the aforementioned laws, it will be necessary to submit an environmental impact manifest (Manifiesto de Impacto Ambiental, or MIA) that relates to the possible impacts on the environment that the Nieves Project activities could cause.

20.2.1      Project Compatibility with Participatory Planning Instruments

Carrying out Nieves Project activities is compatible with the policies and guidelines set forth in federal and local plans and development programs. The authorizations and permits to be requested from the required authorities correspond to a project compatible with existing legal systems and environmental policy instruments.

  a)

The development of the Nieves study does not contravene any legal provision or policy which is explicitly in the laws, regulations and Official Mexican Standards, which are applicable in the field of pollution prevention and the use, preservation and restoration of natural resources.

     
  b)

In the case that negative impacts to the environment are detected during the course of the environmental impact assessment, the Company will determine the appropriate measures to prevent, mitigate, or compensate for any possible adverse environmental impacts resulting from the activities.

     
  c)

The Company must comply fully with the applicable legal systems, as well as with the environmental protection provisions that the Secretariat of the Environment and Natural Resources determines at the time that the Project is subject to evaluation.


     
M3-PN120008
7 January 2014
Revision 2
172



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.2.2      Viability Criteria

Because of the aforementioned requirements, the following list of declarations form the general criteria for viability applicable to the Nieves Project:

  1.

The project is not located in any other area that prohibits its execution, such as a protected natural area or an area of priority conservation.

     
  2.

The management of the species of plants, which are cataloged by the Mexican Official Norm NOM-059-SEMARNAT-2010 will be handled in accordance with the Rescue Program in the authorized areas ensuring their conservation. Additional effects on surfaces are not anticipated from the presence of the project’s catalog of natural elements.

     
  3.

Air quality will not be changed by the development of the mining project.

     
  4.

In the long term, the Company can mitigate the project implementation impacts on the land through the development of a Management Plan for soils, which will allow topsoil to be kept and later used during the reclamation and closure program.

     
  5.

The project's impact on surface and groundwater hydrology can be mitigated such that operating the project will have no impact on the ecological balance of the area’s environmental system.

     
  6.

Acid drainage will be prevented through the appropriate management of materials with sulfides. Drainage will be proportionately reduced, and the probability of acid generation will be low.

     
  7.

The Company will develop an environmental monitoring program with the purpose of monitoring the effectiveness of preventive measures, environmental mitigation and compensation.

     
  8.

As far as environmental risks are concerned, there will be a safety program provided that includes the actions, techniques and methodologies required to reduce the likelihood of the occurrence of unwanted events, as well as to reduce their impacts to the environment and to human health and safety.

     
  9.

To minimize the chance of environmental risks occurring, various measures will be applied, including the land stability analysis.

20.3        POTENTIAL SOCIAL & COMMUNITY REQUIREMENTS AND PLANS

This section contains a discussion of any potential social or community related requirements and plans for the project and the status of any negotiations or agreements with local communities.

     
M3-PN120008
7 January 2014
Revision 2
173



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.3.1

Background

   
20.3.1.1

Socio-economic environment

Nieves is the town with largest population in the Municipality, and it is located near to the proposed site location.

20.3.1.2    Demographics

According to the Census of Population and Housing 2010 developed by the National Institute of Geography and Computer Science (INEGI, from its Spanish acronym), the total population of Nieves is 5,653 people, of which 2,688 are men and 2,965 are women.

Nieves is considered a migrant city. Because the migratory flow is very high, this dynamic demographic causes depopulation of the communities and aging of its population.

20.3.2

Economy and Employment

   
20.3.2.1

Characteristics of the economically active population

Nieves has an economically active population of 1,978 people, of which 1,430 are men and 548 are women. There are 2,319 individuals who are not economically active, of which 558 are men and 1,761 are women.

The occupied population was established at around 1,896 people, of which 1,346 are male and 547 are female. The unemployed population totals 82 people.

20.3.2.2    Key economic processes, products and commercial activities of the municipality: The economic activity in Nieves and in general in the municipality is primarily agriculture. Specifically, livestock activities are extensively carried out in an area of 165,579 hectares.

The municipality has not had an industrial development, today having an onyx factory as well as a hulling mill that produces milk, cream and cheese.

As far as the natural conditions in or around the municipality, there are no locations for developing tourism.

Percentagewise, 16.3% of the economically active population is engaged in primary sector activities; 29.01% participate in the secondary sector, and 51.66% participate in the tertiary sector. This infers that the population develops their productive activities outside the town of Nieves.

     
M3-PN120008
7 January 2014
Revision 2
174



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.3.2.3    Marginalization

The indicators of social backwardness and lag in housing in the town of Nieves is found at a very low level. At the same time, there has been a breakthrough in the gloom of the lag in the indicators between 2005 and 2010.

20.3.2.4    Health

The institution that has greatest impact with their respective coverage in the insured population is the Instituto Mexicano del Seguro Social (IMSS, or Social Security) that covers 2,683 of the 4,155 rights holders. There are 1,486 residents without health insurance to health services. The Instituto de Seguridad y Servicios Sociales de los Trabajadores del Estado (“ISSSTE”) caters to 983 beneficiaries, and in both categories the IMSS provides service to 389 people.

20.3.2.5    Education

Elementary education infrastructure consists of three federal elementary schools that cater for close to 750 students with 42 teachers in the same number of classrooms.

It also has a federal technical secondary or middle school campus which is attended by more than 300 students, taught by 15 teachers in 11 classrooms.

Finally, Nieves is also has a technical agricultural secondary school and a normal high school. The population aged 15 and up with incomplete elementary school education amounts to 685 people and the average schooling grade level is 8.23.

20.3.2.6    Housing

In Nieves, the census found 1,379 households, of which 1,014 are male-headed households and 365 are female-headed households.

The average number of occupants per household is 4.1 people, with an average number of occupants per room of 0.97.

20.4        SOCIAL AND COMMUNITY NEEDS

As has been pointed out in previous paragraphs, the indicators of social backwardness and lag in housing in the town of Nieves is found to be very low. What can be inferred from this is that the income of the population enables them to maintain worthwhile housing conditions. Additionally, during the period between the years 2005 and 2010, efforts were made to combat the lag.

However favorable conditions may be with regards to the social backwardness indicators, there is a factor that explains this: the high rate of population migration is a factor that has led to Nieves being the main starter location of the population that goes toward the U.S. in Zacatecas (47.7% of the homes receive remittances from nationals living abroad). While more than 50% of the population still lives in Nieves, they are dedicated to the tertiary economic sector, since there is no industry in the town.

     
M3-PN120008
7 January 2014
Revision 2
175



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

That is to say, uprooting happens when the lack of local employment opportunity encourages potential workers to go abroad.

Therefore, the main social and community needs would need to be focused to address the following aspects:

  • Providing well-paid and long-term employment opportunities that allow the population to establish roots in the community and to build long-term projects for themselves and in the community, as well as other integral developments.

  • The aforementioned will also strengthen aspects of health, education, communication and infrastructure in the area, generating a regional development center.

  • Strengthening the identity of the Nieves residents through putting down roots.

20.4.1      Status of Agreements with the Community

According with the information provided by the Company, exploration activities made in the project area cover suburban land, small privately owned parcels (ranches) and municipal property.

With regard to the ejidos, there is an agreement with the ejido Nieves, which was signed with the representatives of the Ejido, including its commissariat. Beyond that, any other agreements with landowners have been made verbally without any formality.

It is desirable that in the future, and especially in the event that the project becomes profitable, that formalizing legal possession and occupation of the land be considered, in case outright acquisition of the land is not chosen.

As far as Ejidos are concerned, the land occupation agreements must have been worked out in compliance with requirements established by the Land Law so as to have legal certainty of being able to carry out project activities on the site, as well as for processing and acquiring permits/authorizations of any kind, especially for environmental issues or studies.

With regards to private property, the contract should be drawn up under the requirements established by the Civil Code of the State of Zacatecas.

The enterprise may take into account that one way to legally be able to occupy project area land is through the processing and acquisition of a decree for temporary occupation, as outlined in the terms of the Mining Law. This option should be analyzed according to the conditions under which one may negotiate for the occupation of the land.

     
M3-PN120008
7 January 2014
Revision 2
176



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

20.5        MINE CLOSURE

This section includes a discussion of mine closure (remediation and reclamation) requirements and costs. The main objectives for the recovery of the mine are:

  • Prepare the land for productive use in the long term and / or for the establishment of wildlife habitat.
  • Leave the mine areas stable and safe/secure.
  • Prevent erosion by reforestation of affected areas and to encourage and facilitate drainage.
  • Prevent environmental contamination, both present and future.

Having as general activities:

  • General dismantling of the infrastructure and the removal of machinery and equipment.
  • Detoxification and physical stabilization of the leach pads.
  • Restoration and Reforestation of areas disturbed by mining activity.

The list of the most important activities performed on the stage of closure/abandonment of the mine, depending on the mining work is as follows:

Pit

o

Removal of all types of explosives and cancellation of the permit;

o

Removal of equipment and support facilities;

o

Construction of berm and security fence around the pit;

o

Work surface runoff control;

o

Closure and restoration of roads; and

o

Scarification of soil and planting seeds.

     

Crushing plant

o

Dismantling of equipment and facilities;

o

Cleaning and waste disposal area;

o

Land grading and scarifying; and

o

Reforestation (planting seeds and plantations).

     

Waste dumps

o

Relaxation of slopes and soil scarification. According to NOM-155- SEMARNAT-2007;

o

Work surface runoff control;

o

Assessing the quality of exposed soil;

o

Establishment of herbaceous substrate; and

o

Establishment of tree substrate.

     

Leaching pad

o

Dismantling and removal of process equipment;

o

Detoxification process (irrigation with water or application of other treatment);


     
M3-PN120008
7 January 2014
Revision 2
177



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

o

Sampling to assess the quality of the solutions, according to NOM-155- SEMARNAT-2007;

o

Notification to CNA regarding usage or discharging solutions to environment;

o

Characterization of waste material and sludge neutralized in pools;

o

Filling of pools;

o

Smoothing of slopes in backyards and scarification of the soil. According to NOM-155-SEMARNAT-2007;

o

Establishment of herbaceous; and

o

Establishment of tree layer.

     

Processing plant

o

Decommissioning (first phase of the metallurgical process order);

o

Decommissioning (second phase, to neutralization);

o

Demolition of fixed works which are not of interest to owners of surface land;

o

Cleaning and proper disposal of waste;

o

Land grading and scarifying; and

o

Reforestation.

     

Support facilities (workshop, laboratory, etc.).

o

Dismantling of equipment and facilities;

o

Closure of septic tanks and trash;

o

Cleaning and waste disposal;

o

Cleaning and treatment of areas impacted by oil spills;

o

Scarification of the land; and

o

Planting native seeds.

     

Roads

o

Agree with the landowners which roads will remain;

o

Closure of inactive roads;

o

Land grading and drainage works; and

o

Scarification and planting native seeds.


     
M3-PN120008
7 January 2014
Revision 2
178



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

21          CAPITAL AND OPERATING COSTS

In general M3 based this capital cost estimate on its knowledge and experience of similar types of facilities and work in similar locations. Resources available to M3 included recent cost data collected for a nearby mining project now in the detailed engineering phase, and plant designs for similar process plants under construction, design or study in other locations.

To assist in the estimating, M3 used quantity estimates, and in some cases costs, supplied by specialist sub consultants, including Hard Rock Consulting.

21.1

CAPITAL COSTS

   
21.1.1

Process Plant & Infrastructure

   
21.1.1.1

Assumptions

The project is assumed to be constructed in a conventional EPCM format, i.e. Nieves will retain a qualified contractor to manage and design the project; bid and procure materials and equipment as agent for Nieves; bid and award construction contracts as agent; and manage the construction of the facilities as agent.

Nieves will order major material supplies (i.e., structural and mechanical steelwork) as well as bulk orders (i.e., piping and electrical). These will be issued to construction contractors on site using strict inventory control.

All costs to date by Owner are considered as sunk costs. Any costs incurred for this preliminary economic assessment, the upcoming pre-feasibility study and the completion of any future feasibility study (including field drilling and lab testing) are not included.

“Initial Capital” is defined as all capital costs through to the end of construction or the end of Year 1 of the mine life defined as the year in which commercial scale production starts. Capital costs predicted for later years are carried as sustaining capital in the financial model.

This is a capital sensitive project, so it is assumed that value engineering for the processing facility will be required to keep costs down. The capital estimate shown is on the low side of benchmark ranges evaluated.

It was assumed that no geo synthetic liner would be required for the Tailing Facility, and local borrow material is available.

All costs are in 2nd quarter 2012 US dollars.

21.1.1.2    Estimate Accuracy

The accuracy of this estimate for those items identified in the scope-of-work is estimated to be within the range of plus 30% to minus 30%; i.e., the cost could be 30% higher than the estimate or it could be 30% lower. Accuracy is an issue separate from contingency, the latter accounts for undeveloped scope and insufficient data (e.g., geotechnical data).

     
M3-PN120008
7 January 2014
Revision 2
179



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

The following is a summary of the approach used to estimate the costs in the project.

  • Processing Facilities: Costs for the processing facilities were developed by utilizing a major equipment list and benchmarking similar projects.

  • Infrastructure: Costs for power line was estimated based on a cost per kilometer for a similar installation. Other infrastructure costs were estimated based on similar projects.

  • Indirect: Indirect costs are based on standard percentages of direct level costs. EPCM, mobilization, commissioning, owner’s costs and first fills are included in indirect costs.

  • Contingency: Contingency was assumed to be 20% of the total contracted cost.

Table 21-1: Process & Infrastructure Capital Cost Estimate Summary

Description PEA Level Costs Cost Areas Include
Direct Level Costs    
Site General 11,000,000 Roads, plant site civil and misc project infrastructure
Primary Crusher and Stacking Conveyor 7,500,000 Primary Jaw crusher, stacking conveyor
Reclaim and Conveying 6,000,000 Reclaim tunnel and SAG feed conveyor
Grinding and Classification 22,000,000 Grinding mills, Building, hydrocyclones, pumps, etc.
Flotation and Regrind 13,000,000 Rougher and cleaner cells, regrind mills, samplers, etc.
Concentrate Thickening and Filtration 6,500,000 Concentrate thickeners, filters, and load out building
Reagent Storage 4,500,000 Tanks, Agitators, Flocculant Make Down, Dry Storage, etc.
Tailing Handling 4,500,000 Tailing thickener, piping and distribution to the tailing Impoundment
Tailing Impoundment 20,000,000 3 Year Starter Dam, No Liner, no Diversion
Power and Electrical 7,500,000 High voltage transmission line, upgrade of CFE infrastructure, and on site power transmission
Water Systems 4,000,000 Well Field, Fresh Water Distribution and Process Water Distribution Systems
Ancillary Facilities 9,000,000 Ancillary Buildings, Mine Support Facilities, Fueling, etc.
     
Total Direct Level Costs 115,500,000  
Indirect Costs    
Construction Contractor Camp and Bussing Costs 3,000,000 Cost to operate construction camp and bussing system for construction
Mobilization 577,500 Cost for contractors to mobilize to site.
EPCM 18,480,000 Engineering, Procurement and Construction Management
First Fills, Spares, Pre-Commissioning and Commissioning 4,042,500
Contingency 28,320,000 For unknown costs within current scope
Owner's Costs 17,325,000 Land tenure, owner's staff, legal, early staffing, training, site security, etc.
Total Indirect Level Costs 71,745,000  
Total Direct + Indirect Costs 187,245,000  

     
M3-PN120008
7 January 2014
Revision 2
180



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

21.1.1.3    Documents

Documents available to the estimators include the following:

  Design Criteria (No)
  Equipment List (Major Equipment)
  Equipment Specifications (No)
  Construction Specifications (No)
  Flowsheets (Yes)
  P&IDs (No)
  General Arrangements (PEA Level)
  Architectural Drawings (No)
  Civil Drawings (PEA Level)
  Concrete Drawings (No)
  Structural Steel Drawings (No)
  Mechanical Drawings (No)
  Electrical Schematics (No)
  Electrical Physicals (No)
  Instrumentation Schematics (No)
  Instrument Log (No)
  Pipeline Schedule (No)
  Valve List (No)
  Cable and Conduit Schedule (No)

21.1.2      Mine Capital Costs

The mine capital cost estimate for the Nieves Silver Project includes recent price quotes from projects using similar size equipment or from Cost Mine Handbooks. A breakdown of the total estimated mine capital cost is presented in Table 21-2. The preproduction development estimate of $2.5M is not included in the total below nor is the estimate for mine buildings and infrastructure which are included in the site infrastructure capital.

     
M3-PN120008
7 January 2014
Revision 2
181



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 21-2: Mine Capital Cost Estimate



Description

# Initial
Units
#
Additional
Units

# Total
Units


$/Unit
Initial
Capital
Cost
Sustaining
Capital
Cost
Total
Capital
Cost
16.5 m3 Front Shovel 2 0 2 $5,000,000 $10,000,000 $0 $10,000,000
12 m3 Loader 1 0 1 $2,125,000 $2,125,000 $0 $2,125,000
Production Drill 2 0 2 $950,000 $1,900,000 $0 $1,900,000
PreShear Drill 1 0 1 $750,000 $750,000 $0 $750,000
Haul Truck - 90t 13 6 19 $1,600,000 $20,800,000 $9,600,000 $30,400,000
16' Grader 1 0 1 $850,000 $850,000 $0 $850,000
Water Truck 1 0 1 $850,000 $850,000 $0 $850,000
448hp Dozer 1 0 1 $970,000 $970,000 $0 $970,000
347hp Dozer 1 0 1 $665,000 $665,000 $0 $665,000
580hp Dozer 1 0 1 $1,400,000 $1,400,000 $0 $1,400,000
Lube/Fuel/Service 3 0 3 $125,000 $375,000 $0 $375,000
Light Plants 6 0 6 $22,000 $132,000 $0 $132,000
Small Excavator 148hp 1 0 1 $190,000 $190,000 $0 $190,000
Misc Equip 1 0 1 $500,000 $500,000 $0 $500,000
Pickups 10 0 10 $40,000 $400,000 $0 $400,000
Equipment Rebuilds           $21,484,489 $21,484,489
Total         $41,907,000 $31,084,489 $72,991,489

21.2        SUSTAINING CAPITAL COST ESTIMATE

Sustaining capital costs were also evaluated for the project. Costs were estimated for future costs as shown in Table 21-3.

Table 21-3: Summary of Sustaining Costs (in Millions of $)

    Mining     Tailing     Total  
1 $  2.176   $  -   $  2.176  
2 $  1.671   $  -   $  1.671  
3 $  10.399   $  11.00   $  21.399  
4 $  2.430   $  -   $  2.430  
5 $  2.594   $  11.00   $  13.594  
6 $  2.567   $  -   $  2.567  
7 $  2.588   $  -   $  2.588  
8 $  2.524   $  11.00   $  13.524  
9 $  2.289   $  -   $  2.289  
10 $  1.847   $  -   $  1.847  
Total $  31.085   $  33.00   $  64.085  

Sustaining capital costs include indirect costs, but do not include contingency. All sustaining costs are in Q3, 2012 dollars.

21.3        OPERATING COST

The average Operating Costs over the life of the mine include mine, process plant, general & administration, and refining and treatment charges. These are included in Section 22. See Table 21-4 for more detail.

     
M3-PN120008
7 January 2014
Revision 2
182



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 21-4: Average Operating Cost Summary

Mining $  6.75  
       
Process Plant Operating Costs      
Labor $  0.51  
Maintenance Parts and Services $  0.70  
Power $  3.34  
Reagents $  2.20  
Steel Consumption $  2.29  
Supplies and Services $  0.40  
Total Process Plant $  9.43  
G&A Operating Costs $  1.41  
       
Total Operating Costs/ tonne milled $  17.59  

21.3.1      Mine Operating Costs

Mine operating cost estimates are based on scheduled production, equipment requirements, operating hours, hourly equipment operating costs, and manpower requirements. Cost factors are based on past project experience and equipment usage estimates from the Cat handbook and Cost Mine handbook. The total mine operating costs are estimated to average $1.10/tonne mined or $6.75/tonne milled. Mine wages and salaries are estimated from work on past projects in Mexico with similar size and location to Nieves. The scheduled hours are based on the 12 hour shift operating schedule averaged over the year with 3% scheduled overtime. During times of major equipment rebuilds 80% of the maintenance labor costs are distributed to the mine equipment and charged to sustaining capital. The remaining 20% remains in operating costs for routine maintenance items. The payroll burdens are estimated to be 35% of the total payroll amount. The required manpower for the mine department is calculated based on the equipment required to meet the production schedule. The yearly averaged manpower requirements are listed in Table 16-14.

Monthly required operating hours are calculated for each piece of equipment based on the production schedule, equipment availabilities, usages, and the load and haul parameters. Cost factors are based on past project experience and equipment usage amounts from the Cat handbook and Cost Mine handbook. The diesel fuel cost is estimated at $0.85/liter.

     
M3-PN120008
7 January 2014
Revision 2
183



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

22          ECONOMIC ANALYSIS

The Nieves project economics were completed using a discounted cash flow model. The financial indicators examined for the project included the Net Present Value (NPV), Internal Rate of Return (IRR) and payback period (time in years to recapture the initial capital investment). Annual cash flow projections were estimated over the life of the mine based on capital expenditures, production costs, transportation and treatment charges and sales revenue. The life of the mine is approximately 10 years.

This PEA is preliminary in nature and includes discussion of mineral resources including inferred mineral resources that are too speculative geologically to have economic considerations applied to them. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.

22.1        ASSUMPTIONS

Major assumptions in the cash flow model.

It was assumed that a smelter in Mexico could take and treat the concentrate; therefore, shipping costs were included at $50/tonne. If concentrate would be taken outside of Mexico, the shipping costs would increase.

22.2        PRODUCTION STATISTICS

Mine production is reported as mineralized material and waste from the mining options. The annual production figures were obtained from the mine plant.

This PEA is preliminary in nature and includes discussion of mineral resources including inferred mineral resources that are too speculative geologically to have economic considerations applied to them. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.

The life of mine mineralized material quantities and grade are presented in Table 22-1 below.

Table 22-1: Mine Production

Mineralized
Material
Ktonnes
Waste
ktonnes
Average Annual
Silver Grade (g/t)
Average Annual
Gold Grade (g/t)
35,359 189,591 56.822 0.042

Process Plant Production Statistics

The following products will be produced from the Process Plant:

         •          Flotation Concentrate in Super Sacks

The estimated recoveries for each metal are as follows:

     
M3-PN120008
7 January 2014
Revision 2
184



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  Silver 86%
  Gold 86%

Life of mine saleable production is presented in Table 22-2 below.

Table 22-2: Commodity Production

  Silver (koz) Gold (koz)
Metal Production 52,365 25

Smelter Return Factors

The process plant product will be shipped from the site to smelting and refining companies. The smelter and refining treatment charges will be subject to negotiation at the time of final agreement.

A smelter may impose a penalty either expressed in higher treatment charges, or in metal deductions to treat concentrates that contain higher than specified quantities of certain elements. It is expected that the concentrate will not pose any special restrictions on smelting and refining, and that the concentrates will be marketable to smelting and refining companies. The smelting and refining charges calculated in the financial evaluation include charges for smelting and refining these products. The off-site charges that will be incurred are presented in Table 22-3 below.

Table 22-3: Smelter Return Factors

         Payable Metal - Ag (%) 95.00%
         Payable Metal - Au (%) 95.00%
         Deduction Ag- ozs/t 1.5
         Deduction Au- ozs/t 0.05
         Smelter Treatment Charges - ($/t) 300
         Refining Charge - Ag ($/oz) 1
         Refining Charge - Au ($/oz) 10
         Transportation Charge ($/wt) 50

22.3        REVENUES

Annual revenue is determined by applying estimated metal prices to the annual payable metal before treatment, refinery and transportation charges for each operating year. Sales prices have been applied to all life of mine production without escalation or hedging.

The evaluation used a deck of prices with silver and gold prices calculated by M3 based on weighted average prices for NI 43-101 reporting purposes, 60% historical prices; 40% futures forecast prices. Metal prices used for this study were based on round numbers that were lower than the 60-40 weighted average.

     
M3-PN120008
7 January 2014
Revision 2
185



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Metal sales prices used in the evaluation $27.00/ounce and $1,300/ounce for silver and gold respectively.

22.3.1      Other

Salvage Value

An allowance of $5 million has been included in the cash flow analysis as a return of capital from the salvage and resale of equipment at the end of mine life.

Fees and Royalties

Royalties are calculated at 2% of the net smelter returns, plus an initial 2 Million dollar payment.

Income Taxes

Taxable income for income tax purposes is defined as metal revenues minus operating expenses, royalty, property and severance taxes, reclamation and closure expense, depreciation and depletion. Income tax rates for state and federal, all-in, are 28%.

22.4        FINANCIAL MODEL

This PEA is preliminary in nature and includes discussion of mineral resources including inferred mineral resources that are too speculative geologically to have economic considerations applied to them. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.

Table 22-4 shows the financial model for the project.

     
M3-PN120008
7 January 2014
Revision 2
186



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Table 22-4: Financial Model

 
     
M3-PN120008
7 January 2014
Revision 2
187



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
188



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
189



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

 
     
M3-PN120008
7 January 2014
Revision 2
190



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

23          ADJACENT PROPERTIES

The Nieves Property is not directly bordered by any other mining concessions

     
M3-PN120008
7 January 2014
Revision 2
191



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

24          OTHER RELEVANT DATA AND INFORMATION

No additional information or explanation is necessary to make this technical report more understandable.

     
M3-PN120008
7 January 2014
Revision 2
192



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

25          INTERPRETATION AND CONCLUSIONS

The Nieves project is located in a socially and economically stable part of the world where Mining is prevalent. The climate is moderate and local infrastructure is present. Topography for the project is favorable and will allow for economical construction. A state highway runs adjacent to the site, eliminating many logistical problems typically associated with mining projects. The permitting process in Mexico is well defined.

M3 reviewed Metallurgical data and test work provided by Quaterra. This data was used to develop the project flow sheets and design criteria. No unproven technologies are planned for the Nieves project. Many process plants of this size have been constructed in the past and this project can be constructed on a reasonable schedule.

Hard Rock Consulting notes that, as far as the mining plan is concerned, the Nieves silver project in its current state shows potential. The current plan only includes resources from the Concordia Vein; there is potential with additional drilling to expand the current pit to include the San Gregorio inferred resource which was not included in this study. There are also two other vein systems on the property: the California and Santa Rita, which with further exploration may be able to add to the project.

The project should proceed further to a pre-feasibility study.

     
M3-PN120008
7 January 2014
Revision 2
193



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

26

RECOMMENDATIONS

   
26.1

CARACLE CREEK RECOMMENDATIONS

The following work is recommended by Caracle Creek:

  1.

More SG sampling in the Gregorio North area to increase the confidence level of the tonnage estimate. Once achieved, it may be possible to add more indicated resource in this area.

     
  2.

Further infill drilling is recommended for the Gregorio North area as well as the westerly area of the Concordia (La Quinta). This can increase the amount of indicated resource at the same time possibly increase the grade.

     
  3.

Due to the anticipated mining method (bulk open pit mining) it is recommended that all intervals within the defined mineralized domain be sampled.

     
  4.

Exploration drilling in the West Santa Rita area to test the geophysical anomaly and the down dip extent of the mineralization identified on the surface.

     
  5.

Drill testing of the new geophysical targets in the other areas.

     
  6.

Drilling along the California vein system to determine the extent of the mineralization. Table 26-1 summarizes the budget for the recommended exploration program.

Table 26-1: Recommended Exploration Budget on the Nieves Property

26.2        HARD ROCK CONSULTING RECOMMENDATIONS

The following is recommended by Hard Rock Consulting:

  1.

The current mine plan contains a significant amount of indicated material, 78% of the material, with a small amount of additional drilling the project could be advanced to the pre-feasibility stage with the calculation of reserves.


     
M3-PN120008
7 January 2014
Revision 2
194



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

  2.

Continue the metallurgical testing and investigate the possibility to recover lead and zinc as there are significant amounts of each metal contained in the mineralized material.

26.3        M3 RECOMMENDATIONS

M3 recommends that the project proceed to a pre-feasibility study at a cost of approximately $3 million. Some additional recommendations with regards to metallurgical testwork are as follows.

26.3.1      Metallurgy

Complete additional metallurgical drilling to obtain data required to define process equipment. Further metallurgical testing will be necessary to confirm the silver recovery and reagent consumption. The metallurgical tests recommended for the next phase of testing include the following major activities.

26.3.1.1    Test Program Major Activities

Sample selection and additional:

  • Drilling
  • Mineralogy
  • Comminution
  • Flotation
  • Concentrate Dewatering
  • Variability testing
  • Physical properties
  • ARD and tailing characterization
  • Concentrate quality (marketing)

26.3.1.2    Metallurgical Test Program Schedule and Cost

Once core is available, the overall test program will require several months to one year to complete at a cost of approximately $1 million.

     
M3-PN120008
7 January 2014
Revision 2
195



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

27          REFERENCES

Buchanan, L.J., 1981: Precious metal deposits associated with volcanic environments in the Southwest; in Dickinson, W.R. and Payne, W.D., eds. Relations of tectonics to ore deposits in the southern Cordillera, Arizona Geological Society Digest, v. 14, p. 237-262. Cavey, G., 1999: Summary Report on the Nieves Property, Zacatecas, Mexico; Report for Quaterra Resources Inc.

Corbett, G.J., 2002: Epithermal Gold for Explorationists; AIG Presidents Lecture, AIG Online Journal April 2002, AIG website: www.aig.asn.au.

Corbett, G.J., 2004, Epithermal and porphyry gold – Geological models in Pacrim Congres 2004, Adelaide, The Australasian Institute of Mining and Metallurgy, p. 15-23.

Corbett, G.J., and Leach, T.M., 1998: Southwest Pacific rim gold-copper systems: Structure, alteration and mineralization; Economic Geology, Special Publication 6, 238 p., Society of Economic Geologists.

Dill, D.B., 1954: Nieves, Valencianna and Miguel Auza Silver Districts of Northwestern Zacatecas; Servicios Industriales Peñoles S.A. de V.V., Archio Oficina, Torreon, Coahila, Mexico.

Folinsbee, J. and Pojhan, A., 2010: Preliminary metallurgical testing on a global composite, Nieves project, Mexico, KM2653, p. 49.

G&T Metallurgical Services Ltd., 2010a. Metallurgical Assessment of the Nieves Project, KM2653. G&T Metallurgical Services Ltd., Kamloops, B.C., Canada, June 30 2010. G&T Metallurgical Services Ltd., 2010b. Supplemental Metallurgical Testing of the Nieves Project, Zacatecas, Mexico, KM2740. G&T Metallurgical Services Ltd., Kamloops, B.C., Canada, August 30, 2010.

Garcia, M.E., Querol, S.F. and Lowther, G.K., 1991: Geology of the Fresnillo mining district, Zacatecas; in: Salas, G.P., ed., Economic Geology, Mexico, Geological Society of America, Boulder, CO, DNAG Volume P-3, p. 383-394.

Gemmell, J.B., Simmons, S.F. and Zantop, H., 1988: The Santo Nino silver-lead-zinc vein, Fresnillo District, Zacatecas, Mexico; Part I Structure, vein stratigraphy, and mineralogy; Economic Geology, v. 83, no. 8, p. 1597-1618.

Hedenquist, J.W., Izawa, E, Arribas, A, and White N.C., 1996: Epithermal Gold Deposits: Styles Characteristics and Exploration; Society of Resource Geology, resource Geology Special Publication Number 1, Tokyo, Japan, 24 p.

     
M3-PN120008
7 January 2014
Revision 2
196



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

Long, S.D. 2008: Assay quality assurance-quality control program for drilling projects at the pre-feasibility to feasibility report level, third edition, Mining Consulting Group, Amec, Phoenix Arizona, unpublished report.

Ruvalcaba-Ruiz, D.C. and Thompson, T.B., 1988: Ore deposits at the Fresnillo Mine, Zacatecas, Mexico; Economic Geology, v. 83, no. 8, p. 1583-1596.

Simmons, S.F., 1991: Hydrologic implications of alteration and fluid inclusion studies in the Fresnillo District, Mexico; evidence for a brine reservoir and a descending water table during the formation of hydrothermal Ag-Pb-Zn orebodies; Economic Geology, v. 86, no. 8, p1579-1601.

Simmons, S.F., Gemmell, J.B. and Sawkins, F.J., 1988: The Santo Nino silver-lead-zinc vein, Fresnillo District, Zacatecas; Part II, Physical and chemical nature of ore-forming solutions; Economic Geology, v. 83, no. 8, p. 1619-1641.

Sketchley, D.A., 1998: Gold deposits: Establishing sampling protocols and monitoring quality control, Exploration and Mining Geology, v. 7, p.129-138.

Smee, B.W. 2008: Analytical quality control in mineral exploration and mining: compliance with NI 43-101 or “How to bulletproof your database and never fail an audit”, Smee and Associates Consulting Ltd, North Vancouver, unpublished report for Century Systems users conference.

Smee, B.W., 2010: Certificate of analysis, Quaterra standard KM 2653, Smee and Associates Consulting Ltd., Consulting Geochemistry/Geology, 2p.

Stone, M., 2009: Independent Technical Report, The Nieves Silver Project, Zacatecas, Mexico, 104p. Stone, M., 2010: Independent Technical Report, Nieves Property, Zacatecas State, Mexico, 116p.

Turner, T., 1999: The Nieves District, Zacatecas, Mexico, A geologic report; Report for Western Copper Holdings Ltd.

Wendt, C. J., 2002: The Geology and Exploration Potential of the Juanicipio Property, Fresnillo District, Zacatecas, Mexico; Technical Report for Mega Capital Investments. Wetherup, S. W., 2006: Independent Technical Report, Nieves Silver Project, Zacatecas, Mexico, 56p.

     
M3-PN120008
7 January 2014
Revision 2
197



NIEVES PROJECT
FORM 43-101 TECHNICAL REPORT

APPENDIX A: PEA CONTRIBUTORS AND PROFESSIONAL QUALIFICATIONS

     
M3-PN120008
7 January 2014
Revision 2
198


 


 


CERTIFICATE of QUALIFIED PERSON

I, Jeffery W. Choquette, P.E., do hereby certify that:

1.

I am currently employed as Principal Engineer by:

   

Hard Rock Consulting, LLC
10901 W Toller Dr., Suite 205
Littleton, CO 80127
U.S.A.

   
2.

I am a graduate of Montana College of Mineral Science and Technology and received a Bachelor of Science degree in Mining Engineering in 1995.

   
3.

I am a:


  Registered Professional Engineer in the State of Montana (No. 12265)
 

QP Member in good standing of the Mining and Metallurgical Society of America (No. 01425QP)


4.

I have practiced mining engineering and project management for 16 years. I have worked for mining and exploration companies for 16 years and as a consulting engineer for one and a half years.

   
5.

I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.

   
6.

I am responsible for the preparation of Sections 16, 25, 26 and portions of Sections 1, 25 and 26 of the technical report titled “Nieves Project, Form 43-101F1 Technical Report, Amended Preliminary Economic Assessment, Zacatecas, Mexico” dated October 31, 2012 and amended on January 7,2014(the "Technical Report").

   
7.

I have had no prior involvement with the property that is the subject of the Technical Report.

   
8.

As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the report not misleading.

   
9.

I am independent of Quaterra Resources Inc., applying all of the tests in section 1.5 of NI 43-101.

   
10.

I have read National Instrument 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form.



Dated this 7th day of January, 2014.

“signed” Jeffery W. Choquette


/s/ Jeffery W. Choquette  
Signature of Qualified Person  
   
   
   
Jeffery W. Choquette  
Print name of Qualified Person  


 


 


CERTIFICATE of QUALIFIED PERSON

I, Zsuzsanna Magyarosi, P.Geo., do hereby certify that:

1.

I am currently employed as Senior Geologist for the geological consulting firm of Caracle Creek International Consulting Inc. Canada (CCIC).

   

Caracle Creek International Consulting
25 Frood Road
Sudbury, Ontario, Canada, P3C 4Y9
Telephone: 705-671-1801
Email: zmagyarosi@caraclecreek.com

   
2.

I am a graduate of Brock University, St. Catharines, Ontario, Canada and received a B.Sc. degree in Geology in 1996. I am also a graduate of Carleton University, Ottawa, Ontario, Canada and received a M.Sc. degree in 1998 and a Ph.D. degree in 2002.

   
3.

I am a member of the Association of Professional Geoscientists of Ontario (Member #2031).

   
4.

I have worked on exploration projects worldwide including: Canada (Ontario, British Columbia, Yukon, Quebec and Newfoundland), Finland and have worked on gold, Ni- Cu-PGE and VMS deposits since 1996.

   
5.

I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.

   
6.

I am responsible for the preparation of Sections 5, 6, 7, 8, 9, 10, 11, 12, 15 and jointly responsible for Sections 25 and 26 (for geology) of the technical report titled “Nieves Project, Form 43-101F1 Technical Report, Amended Preliminary Economic Assessment, Zacatecas, Mexico” dated effective October 31, 2012 and amended January 7, 2014 (the "Technical Report").

   
7.

I have had no prior involvement with the property that is the subject of the Technical Report.

   
8.

As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the report not misleading.

   
9.

I am independent of Quaterra Resources Inc., applying all of the tests in section 1. 5 of NI 43-101.




10.

I have read National Instrument 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form.

Dated this 7th day of January, 2014.

“signed and sealed”  
Signature of Qualified Person  
   
   
Zsuzsanna Magyarosi  
Print name of Qualified Person  


CERTIFICATE of QUALIFIED PERSON

I, Jason Baker, P.Eng., do hereby certify that:

1.

I am currently employed as a Mining Engineer by:

   

Caracle Creek International Consulting Inc. 34 King Street East, 9th Floor Toronto, Ontario Canada M5C 2X8

   
2.

I am a graduate of Dalhousie University and received a Bachelor of Engineering degree in Mining Engineering in 2000.

   
3.

I am a:


  Registered Professional Engineer in the Province of Nova Scotia (APENS No. 9627)
  Registered Professional Engineer in the Province of British Columbia (APEGBC No. 37720)

4.

I have practiced mining engineering and project management for 13 years. I have worked for mining and exploration companies for 13 years and for Caracle Creek International Consulting Inc. for 2 years.

   
5.  
   

6.

I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43 -101.

   
7.

I am responsible for the preparation of Sections 14 and portions of Sections 1, 25 and 26 of the technical report titled “Nieves Project, Form 43-101F1 Technical Report, Amended Preliminary Economic Assessment, Zacatecas, Mexico” dated effective October 31, 2012 and amended on January 7, 2014 (the "Technical Report").

   
8.

I have had no prior involvement with the property that is the subject of the Technical Report.

   
9.

As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the report not misleading.

   
10.

I am independent of Quaterra Resources Inc., applying all of the tests in section 1.5 of NI 43-101.




11.

I have read National Instrument 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form.

Dated this 7th day of January, 2014.

“signed and sealed”  
Signature of Qualified Person  
   
   
Jason Baker  
Print name of Qualified Person  


CERTIFICATE of QUALIFIED PERSON

I, Doris M.Fox, M.Sc., P.Geo., PMP, do hereby certify that:

1.

I am currently employed as Senior Associate Geologist:

   

Caracle Creek International Consulting Inc.
34 King Street East, 9th Floor
Toronto, ON.

Canada, M5C 2X8

   
2.

I am a graduate of Saint Mary’s University and received a Bachelor of Science Double Major degree in Geology / Geography in 2000. I am also a graduate of McGill University and received a Master of Science degree in Earth Sciences in 2002.

   
3.

I am a:


  Registered Professional Geologist in good standing in the Province of Ontario (No. 1430)

4.

I have practiced mineral exploration and project management for 10 years. I have worked in academic research for 4 years.

   

5.

I have read the definition of “qualified person” set out in National Instrument 43-101 (“NI 43-101”) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.

   
6.

I am responsible for the preparation of Sections 12.1 (Site visit) and jointly responsible for sections 5, 7, 8, 10.2 (Sampling procedures), 11.1 (Sample security) and portions of Sections 1, 25 and 26 of the technical report titled “Nieves Project, Form 43-101F1 Technical Report, Amended Preliminary Economic Assessment, Zacatecas, Mexico” dated effective October 31, 2012 and amended on January 7, 2014 (the "Technical Report").

   
7.

I have had no prior involvement with the property that is the subject of the Technical Report.

   
8.

As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the report not misleading.

   
9.

I am independent of Quaterra Resources Inc., applying all of the tests in section 1.5 of NI 43-101.

   
10.

I have read National Instrument 43-101 and Form 43-101F1, and the Technical Report has been prepared in compliance with that instrument and form.



Dated this 7th day of January, 2014.

“signed and sealed”  
Signature of Qualified Person  
   
   
   
Doris M. Fox  
Print name of Qualified Person