XML 23 R9.htm IDEA: XBRL DOCUMENT v2.3.0.15
Vessels
9 Months Ended
Sep. 30, 2011
Vessels [Abstract] 
Vessels
Note 3.  Vessels

a. Vessel and Vessel Improvements

At September 30, 2011, the Company's operating fleet consisted of 44 dry bulk vessels. In January, February, May, two in July, August and September, the Company took delivery of the Thrush, Nighthawk, Oriole, Owl, Petrel, Puffin and Roadrunner, respectively.

In May 2011, the Company decided to sell the Heron, a 2001-built Supramax, and reached an agreement to sell the vessel for $22,572,000, after brokerage commissions payable to a third party.  The Heron was not available for delivery until the third quarter. On July 26, 2011 the Company sold the vessel and realized a net loss of $509,076.

Vessel and vessel improvements:
     
     
Vessels and Vessel Improvements, at December 31, 2010
 $1,509,798,249 
Purchase of Vessel Improvements
  928,341 
Delivery of Newbuild Vessels
  324,943,067 
Disposal of Vessel
  (22,494,172)
Depreciation Expense
  (50,893,485)
Vessels and Vessel Improvements, at September 30, 2011
 $1,762,282,000 
 
b. Advances for Vessel Construction

As of September 30, 2011, the Company took delivery of seven vessels, the Thrush, Nighthawk, Oriole, Owl, Petrel, Puffin, and Roadrunner and sold the Heron. In 2010 the Company took delivery of twelve newly constructed vessels, the last two Japanese-built vessels, the Golden Eagle and Imperial Eagle, in January and February 2010, respectively, and ten Chinese-built vessels including the Thrasher, Crane and Egret, in January 2010, the Avocet in February 2010, the Gannet Bulker, Grebe Bulker and Ibis Bulker in April, May and June, respectively, the Jay and Kingfisher in July and the Martin in August. In 2009 the Company took delivery of four newly constructed vessels. Two vessels from the Japanese shipyard, the Crested Eagle and Stellar Eagle, delivered in January and March 2009, respectively and two vessels from the Chinese shipyard, the Bittern and Canary, delivered in October and December 2009, respectively. In 2008 the Company took delivery of three vessels, the Wren and Woodstar were delivered by the Chinese shipyard in June and October 2008, respectively, and the Crowned Eagle, the first of the Company's five Japanese built vessels, was delivered in November 2008.

As of September 30, 2011, the Company had its last Supramax vessel under construction at a shipyard in China. This vessel was delivered on October 19, 2011. The total cost of the construction was $36,650,000 of which the Company has advanced $14,660,000 in progress payments. The Company incurred additional costs relating to the construction, including capitalized interest, insurance, legal, and technical supervision costs.

Advances for Vessel Construction:
     
     
Advances for Vessel Construction, at December 31, 2010
 $191,477,225 
Progress Payments
  143,387,165 
Capitalized Interest
  2,575,417 
Legal and Technical Supervision Costs
  9,796,060 
Delivery of Newbuild Vessels
  (324,943,067)
Advances for Vessel Construction, at September 30, 2011
 $22,292,800