XML 131 R107.htm IDEA: XBRL DOCUMENT v3.24.0.1
Subsequent Events (Details)
$ in Millions
1 Months Ended
Dec. 31, 2023
USD ($)
item
Data Center Joint Venture  
Subsequent Events  
Ownership percentage in joint ventures 20.00%
Data Center Joint Venture | Blackstone Inc. [Member]  
Subsequent Events  
Ownership percentage in joint ventures 80.00%
Data Center Joint Venture  
Subsequent Events  
Joint venture amount | $ $ 7,000
The number of hyperscale data center campuses develop through joint venture 4
Number of data centers 10
Potential IT load capacity in number of megawatts 500
Data Center Joint Venture | Blackstone Inc. [Member]  
Subsequent Events  
Joint venture amount | $ $ 7,000
The number of hyperscale data center campuses develop through joint venture 4
Amount of investment to acquire interest in joint venture | $ $ 700