10. Percentage-of-Completion Changes in Estimates (Notes)
9 Months Ended
Sep. 30, 2015
Changes in Estimates for Systems Business [Abstract]  
Changes in project estimates
10. Percentage-of-Completion Changes in Estimates

We recognize revenue for certain systems business sales arrangements under the percentage-of-completion method. The percentage-of-completion method of revenue recognition requires us to make estimates of net contract revenues and costs to complete our projects. In making such estimates, management judgments are required to evaluate significant assumptions including the amount of net contract revenues, the cost of materials and labor, expected labor productivity, the impact of potential variances in schedule completion, and the impact of any penalties, claims, change orders, or performance incentives. If estimated total costs on any contract are greater than the net contract revenues, we recognize the entire estimated loss in the period the loss becomes known. The cumulative effect of the revisions to estimates related to net contract revenues and costs to complete contracts are recorded in the period in which the revisions to estimates are identified and the amounts can be reasonably estimated.

Changes in estimates for systems business sales arrangements accounted for under the percentage-of-completion method occur for a variety of reasons including but not limited to (i) changes in estimates to reflect actual costs, (ii) construction plan accelerations or delays, (iii) module cost forecast changes, and (iv) other cost related change orders. Changes in estimates could have a material effect on our condensed consolidated statements of operations. The table below outlines the impact on gross profit of the aggregate net changes in systems business contract estimates (both increases and decreases) for the three and nine months ended September 30, 2015 and 2014 as well as the number of projects that comprise such aggregate net changes in estimates. For purposes of the following table, we only include projects with changes in estimates that have a net impact on gross profit of at least $1.0 million during the periods presented. Also included in the table is the net change in estimate as a percentage of the aggregate gross profit for such projects.
 
 
Three Months Ended
September 30,
 
Nine Months Ended
September 30,
 
 
2015
 
2014
 
2015
 
2014
Number of projects
 
5

 
4

 
8

 
10

Increases (decreases) in gross profit resulting from net changes in estimates (in thousands)
 
$
10,521

 
$
9,499

 
$
51,133

 
$
3,214

Net change in estimate as a percentage of aggregate gross profit for associated projects
 
2.0
%
 
0.6
%
 
3.0
%
 
0.2
%