EX-99.1 2 a11-6607_5ex99d1.htm EX-99.1

Exhibit 99.1

 

GRAPHIC

 

CHAPADA MINE AND SURUCA PROJECT

 

GOIAS STATE, BRAZIL

 

 

TECHNICAL REPORT

 

 

PURSUANT TO NATIONAL INSTRUMENT 43-101 OF

 

THE CANADIAN SECURITIES ADMINISTRATORS

 

 

PREPARED FOR

 

 

YAMANA GOLD INC.

 

 

Effective Date: March 7, 2011

 

PREPARED BY

 

Sergio Brandão Silva

 

P.Geo.,Exploration Director, Yamana Gold Inc

 

 

Greg Walker

 

P.Geo., Senior Manager, Resources Estimation, Yamana Gold Inc

 

 

Emerson Ricardo Re

 

MAusIMM, Corporative R&R Manager, Yamana Gold Inc.

 

 

Homero Delboni, Jr.

 

Senior Consultant of HDA Serviços S/S Ltda, Ph.D. in Mineral Processing Engineering

 

 

Raul Contreras

 

Senior Consultant, Resources Estimation, MAusIMM, Metálica Consultores S.A.

 

 

Renato Petter

 

MAusIMM, Technical Services Director, Yamana Gold Inc.

 



 

TABLE OF CONTENTS

 

1

SUMMARY

11

 

 

 

 

 

1.1

 

GENERAL

11

1.2

 

LAND CLAIMS

13

1.3

 

GEOLOGY AND MINERALIZATION

13

 

1.3.1

 

Local Geology

13

 

1.3.2

 

Deposit Types

14

 

1.3.3

 

Mineralization

14

1.4

 

DRILLING

15

 

1.4.1

 

Chapada Drilling

15

 

1.4.2

 

Suruca Drilling

16

1.5

 

MINERAL RESOURCES

16

 

1.5.1

 

Mineral Resources Chapada

16

 

1.5.2

 

Mineral Resources Suruca

17

 

1.5.3

 

Mineral Resources Chapada and Suruca

18

1.6

 

MINERAL RESERVES

18

 

1.6.1

 

Mineral Reserves Chapada

18

 

1.6.2

 

Mineral Reserves Suruca

19

 

1.6.3

 

Mineral Reserves Chapada and Suruca

20

1.7

 

MINE SCHEDULE

20

 

1.7.1

 

Mine Schedule Chapada

20

 

1.7.2

 

Mine Schedule Suruca

21

 

1.7.3

 

Mine Schedule Chapada and Suruca Integrated

21

1.8

 

SURUCA METALLURGICAL TESTWORK

25

 

1.8.1

 

Oxide Characterization

25

 

1.8.2

 

Suruca Sulphide Characterisation

25

1.9

 

PROCESS AND PLANT DESIGN

26

1.10

 

PROJECT IMPLEMENTATION

27

1.11

 

ECONOMIC RESULTS

28

 

1.11.1

 

Suruca Economic Results

28

 

1.11.2

 

Integrated cashflow Chapada + Suruca

32

1.12

 

CONCLUSIONS AND RECOMMENDATIONS

34

 

 

 

 

 

2

INTRODUCTION

35

 

 

 

3

PROPERTY DESCRIPTION AND LOCATION

36

 

 

 

 

 

3.1

 

LAND CLAIMS

37

3.2

 

EXPLORATION AND MINING ACTIVITIES BY “GARIMPEIRO”

40

 

 

 

 

 

4

ACCESSIBILITY, CLIMATE, LOCAL RESOURCE, INFRASTRUCTURE AND PHYSIOGRAPHY

41

 

 

 

 

 

4.1

 

ACCESSIBILITY

41

4.2

 

TOPOGRAPHY, ELEVATION, VEGETATION AND PHYSIOGRAPHY

41

4.3

 

CLIMATE AND PRECIPITATION

41

4.4

 

LOCAL RESOURCES AND INFRASTRUCTURE

41

 

 

 

 

 

5

HISTORY

42

 

 

 

 

 

5.1

 

CHAPADA

42

5.2

 

SURUCA

43

 

 

 

 

 

6

GEOLOGICAL SETTING

44

 

2



 

6.1

 

REGIONAL GEOLOGY

44

6.2

 

LOCAL GEOLOGY

46

6.3

 

PROPERTY GEOLOGY

47

6.4

 

STRUCTURAL

50

 

 

 

 

 

7

DEPOSIT TYPES

51

 

 

 

 

 

7.1

 

CU-AU PORPHYRY SYSTEM

52

7.2

 

EPITHERMAL SYSTEM

53

7.3

 

AU HIGH SULPHIDATION SYSTEM

54

7.4

 

BRASILIANO OROGEN FLUIDS

54

 

 

 

 

 

8

MINERALIZATION

55

 

 

 

 

 

8.1

 

CHAPADA

55

8.2

 

SURUCA

55

 

 

 

 

 

9

EXPLORATION

60

 

 

 

 

 

9.1

 

CHAPADA

60

9.2

 

SURUCA

61

 

9.2.1

 

Exploration until 1997

61

 

9.2.2

 

Exploration by Yamana from 2008 to Present

61

 

 

 

 

 

10

DRILLING

63

 

 

 

 

 

10.1

 

CHAPADA

63

10.2

 

SURUCA

66

 

10.2.1

 

Drilling by Yamana from 2008 to present

66

 

10.2.2

 

Diamond drilling methods

66

 

10.2.3

 

Drillhole patterns

66

 

10.2.4

 

Drillhole collar surveys

66

 

10.2.5

 

Downhole surveys

66

 

10.2.6

 

Drillhole preservation

67

 

 

 

 

 

11

SAMPLING METHODS AND APPROACH

67

 

 

 

 

 

11.1

 

CHAPADA

67

11.2

 

SURUCA

68

 

11.2.1

 

Sampling by Mineração Alonte (Santa Elina) from November 1996 to December 1996

68

 

11.2.2

 

Sampling by Yamana from April 2008 to present

68

 

11.2.3

 

Core sampling

68

 

11.2.4

 

Core logging

69

 

11.2.5

 

Density determinations

69

 

 

 

 

 

12

SAMPLE PREPARATION, ANALYSIS AND SECURITY

70

 

 

 

 

 

12.1

 

CHAPADA

70

12.2

 

SURUCA

71

 

12.2.1

 

Sample preparation, analysis and security by Yamana from April 2008 to August 2010 — Suruca Project

71

 

12.2.2

 

Laboratory

71

 

12.2.3

 

Sample preparation

71

 

12.2.4

 

Sample analysis

71

 

12.2.5

 

Sample security and chain of custody

72

 

 

 

 

 

13

DATA VERIFICATION

72

 

 

 

 

 

13.1

 

CHAPADA

72

 

13.1.1

 

Santa Elina Quality Control/Quality Assurance Program

72

 

13.1.2

 

IMC Data Verification and Reviews

73

13.2

 

SURUCA

74

 

13.2.1

 

Re-sampling of Mineração Alonte (Santa elina) drillhole core by Yamana

74

 

3



 

 

13.2.2

 

Yamana quality control measures

74

 

13.2.3

 

Certified standard samples

75

 

13.2.4

 

Blank samples

76

 

13.2.5

 

Duplicate drillhole core samples (field duplicates)

77

 

13.2.6

 

Inter-laboratories Pulp Check

78

 

13.2.7

 

Internal laboratory quality control measures

79

 

13.2.8

 

Independent statement on sample preparation, analysis and security

79

 

 

 

 

 

14

ADJACENT PROPERTIES

79

 

 

 

15

MINERAL PROCESSING AND METALLURGICAL TESTING

80

 

 

 

 

 

15.1

 

METALLURGICAL TESTING

80

 

15.1.1

 

Chapada Metallurgical Testing

80

 

15.1.2

 

Suruca Metallurgical Testing

83

15.2

 

PROCESS DESIGN CRITERIA — RUN OF MINE

86

 

15.2.1

 

Oxide Plant Process Description

88

 

15.2.2

 

Sulphide Plant Process Description

91

 

 

 

 

 

16

MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES

104

 

 

 

 

 

16.1

 

MINERAL RESOURCE ESTIMATE

104

 

16.1.1

 

Chapada

104

 

16.1.2

 

Suruca

119

16.2

 

MINERAL RESERVE ESTIMATE

126

 

16.2.1

 

Chapada

126

 

16.2.2

 

Suruca

138

 

 

 

 

 

17

OTHER RELEVANT DATA AND INFORMATION

141

 

 

 

 

 

17.1

 

SURUCA HYDROGEOLOGICAL STUDY

141

17.2

 

TAILINGS DAM

142

17.3

 

PRESENT DAM SITUATION AND RAISING NEEDS

143

17.4

 

GENERAL LAYOUT OF CHAPADA PROJECT MINE AND SURUCA PROJECT

144

 

 

 

 

 

18

INTERPRETATION AND CONCLUSIONS

146

 

 

 

19

RECOMMENDATIONS

147

 

 

 

 

 

20

DATE AND SIGNATURE PAGE

151

 

 

 

21

ADDITIONAL REQUIREMENTS FOR TECHNICAL REPORTS ON DEVELOPMENT PROPERTIES AND PRODUCTION PROPERTIES

152

 

 

 

 

 

21.1

 

MINING OPERATIONS

152

 

21.1.1

 

Chapada

152

 

21.1.2

 

Suruca

156

21.2

 

RECOVERABILITY

163

21.3

 

PRODUCTION SCHEDULING INTEGRATED

164

21.4

 

CONTRACTS

166

21.5

 

ENVIRONMENTAL CONSIDERATIONS

166

 

21.5.1

 

Chapada

166

 

21.5.2

 

Suruca

167

21.6

 

FINANCIAL ANALYSIS

169

 

21.6.1

 

Suruca Financial Analysis

169

 

21.6.2

 

Chapada and Suruca Financial Analysis

199

 

 

 

 

 

22

CERTIFICATES OF QUALIFIED PERSONS

205

 

 

 

 

 

APPENDIX A

212

 

4



 

LIST OF FIGURES

 

Figure 1.1: General Layout of the Suruca & Chapada Project

12

 

 

Figure 1.2 Figure: Chapada - Suruca Geological Map

14

 

 

Figure 1.3: Suruca Project schedule

28

 

 

Figure 1.4: Economic and technical parametres

30

 

 

Figure 1.5: Suruca Project NPV Sensitivity Analysis

31

 

 

Figure 1.6: Suruca IRR Sensitivity Analysis

32

 

 

Figure 3.1:General Area Map

36

 

 

Figure 3.2:Project Location Map

37

 

 

Figure 3.3: Chapada Project exploration claim outlines and roads

38

 

 

Figure 3.4: Mining and Exploration Concessions

38

 

 

Figure 6.1: Geological Map of Chapada- Suruca region

45

 

 

Figure 6.2: Geological map of Chapada - Suruca region with the localization of Chapada pit and Suruca designed pit (based on Suruca resource data)

47

 

 

Figure 6.3: Geological Map of Suruca Project

48

 

 

Figure 6.4: Stratigraphic correlation

49

 

 

Figure 6.5: Sketch of structural geology in Chapada - Suruca region

51

 

 

Figure 7.1: Sketch of Chapada system (Silitoe, 2008)

52

 

 

Figure 7.2: Location of Chapada Mine (Cu-Au), Suruca Project (Au-Ag+/-Zn) and Hidrotermalito (Au)

53

 

 

Figure 8.1: Suruca orebodies with strike length of 1,900 metres and and 800 metres of down dip to surface

56

 

 

Figure 8.2: Cross Section showing the oxide and sulfhide ore bodies dipping 25o to northwest

56

 

 

Figure 8.3: Graphics of Au x Zn and S x Au to sericitic halo and propylitic halo. The sericitic halo don´t have direct relationship with zinc and neither with S, contrasting with propylitic halo that have direct relationship with Zn and S.

57

 

 

Figure 8.4: Selective sample (black square) in high grade assays of Suruca. The picture on the left shows high contents of sulphides (esphalerite+galena+pyrite) with a lower grade than interval, and the picture on the right quartz shows veinlets with grades higher than interval.

58

 

 

Figure 8.5: Geological map of Suruca Project with executed drill holes. The red shell represents the drill that intercepted high grade values, always associated to folded quart-veinlet. The southwest portion of the high grade shell still open

59

 

 

Figure 9.1: Location of drill holes program in Suruca Project

63

 

 

Figure 10.1: Cross Section 27

65

 

 

Figure 13.1: Suruca standard sample results for gold, period between June, 2009 to August, 2010 tolerance is 10% > 2 -/+ STDEV, General Failure - ALS CHEMEX = 2.30%

76

 

 

Figure 13.2: Suruca blank sample results for gold, between June, 2009 to August, 2010. Blank limit is 0.025ppm (5 times mininum detection limit)

77

 

5



 

Figure 13.3: Suruca Project duplicates core sample precision plot for Au, between June, 2009 to August, 2010

78

 

 

Figure 13.4: Suruca Project check samples precision plot for Au, betwen June, 2009 and August, 2010 in Check inter-Lab (ALS Chemex and Acme)

79

 

 

Figure 15.1: Suruca Oxide Process Flowsheet

101

 

 

Figure 15.2: Chapada Treatment Plant - Existing Process Flowsheet

102

 

 

Figure 15.3: Chapada Treatment Plant - Recommended Process Flowsheet

103

 

 

Figure 16.1:

Quarterly Accuracy versus Grid Spacing for Au

107

 

 

Figure 16.2:

Annual Accuracy versus Grid Spacing for Au

107

 

 

Figure 16.3 Comparison of Copper Grades

114

 

 

Figure 16.4 Comparison of Gold Grades

114

 

 

Figure 16.5 Tonnage — Grade Curve

117

 

 

Figure 16.6: Mineral Processing Recovery Simulator

129

 

 

Figure 16.7: Multirun and Benefit Function Validation

131

 

 

Figure 16.8: Geotechnical Sectors of the Pit

132

 

 

Figure 16.9: Pit Design — Geometric Parametres

133

 

 

Figure 16.10: Base topography Dec. 31, 2010 without stocks and waste dumps

133

 

 

Figure 16.11: Final Pit Design

134

 

 

Figure 16.12: Chapada Mine 3D view of general arrangement including the dump areas for waste dump and stockpiles

135

 

 

Figure 16.13: Ultimate Pit Limit Oxide

140

 

 

Figure 16.14: Ultimate Pit Limit Sulphide

141

 

 

Figure 17.1: General Layout Chapada Project Mine & Suruca Project

145

 

 

Figure 21.1: Inter-Ramp Angles by Zone

152

 

 

Figure 21.2: In pit crusher 3D view, July 2012

153

 

 

Figure 21.3: In pit crusher 3D view layout operation, July 2012

153

 

 

Figure 21.4: Mine Haulage Distances

155

 

 

Figure 21.5: Pit Phase Design

157

 

 

Figure 21.6: Phase 1

157

 

 

Figure 21.7: Phase 2

158

 

 

Figure 21.8: Phase 3

158

 

 

Figure 21.9: Phase 4

159

 

 

Figure 21.10: Phase 5

159

 

 

Figure 21.11: Operating Final Pit vs Ultimate Pit Optimization

160

 

 

Figure 21.12: Operating Final Pit vs Ultimate Pit Optimization (Section)

160

 

 

Figure 21.13: Line Production Schedule

161

 

6



 

Figure 21.14: Waste Dump Location

163

 

 

Figure 21.15: Suruca Project NPV Sensitivity Analysis

174

 

 

Figure 21.16: Suruca Project IRR Sensitivity Analysis

174

 

 

Figure 21.17: Chapada and Suruca Project NPV Sensitivity Analysis

201

 

7



 

LIST OF TABLES

 

Table 1.1: Chapada Drilling by Date and Company

15

 

 

Table 1.2: Suruca Executed holes per year

16

 

 

Table 1.3: Chapada Mineral resources estimate as of December 31, 2010

17

 

 

Table 1.4: Suruca Mineral resources estimate as of December 31, 2010

17

 

 

Table 1.5: Chapada and Suruca Mineral Resources Estimate as of December 31, 2010

18

 

 

Table 1.6: Chapada Mineral Reserve as of December 31, 2010

19

 

 

Table 1.7: Suruca Probable Mineral Reserve, Effective Date December 2010

19

 

 

Table 1.8: Chapada and Suruca Mineral Reserves

20

 

 

Table 1.9: Chapada Mine schedule

22

 

 

Table 1.10: Suruca Mine schedule

23

 

 

Table 1.11: Processing Plant Production Plan — Chapada/Suruca

24

 

 

Table 1.12: Suruca Project Sensitivity NPV x Discount Rate

30

 

 

Table 1.13 : Suruca Project NPV Sensitivity Analysis (discount rate 5% p.y.)

31

 

 

Table 1.14: Suruca Project IRR Sensitivity Analysis

31

 

 

Table 1.15: Chapada mine and Suruca Project Cash Flow

33

 

 

Table 3.1: Mineral tenure status

39

 

 

Table 6.1:Events and structural features of Brasiliano deformation in the property area

51

 

 

Table 9.1: Historical Drill holes executed in Suruca Project by other companies

61

 

 

Table 9.2: Exploration works in Chapada Project (including Suruca)

62

 

 

Table 10.1: Chapada Drilling by Series

63

 

 

Table 10.2: Chapada Project Drilling by Date and Company

64

 

 

Table 10.3: Showing the holes executed per year

66

 

 

Table 11.1: Distribution of Sample Lenghts

67

 

 

Table 11.2: Specific gravity conversion

70

 

 

Table 13.1: Comparison of Nomos and Geolab With Cone for Copper Assays

73

 

 

Table 13.2: Comparison of Nomos and Geolab With Cone for Gold Assays

73

 

 

Table 13.3: Comparison of Old and New M Series Drilling

74

 

 

Table 13.4: Report failure of standards, totaling 2.3% of total standards

75

 

 

Table 13.5: Total blank samples and report of three failures

76

 

 

Table 13.6: Average grade of gold for original samples and duplicate samples

77

 

 

Table 13.7: Comparison of average grade of gold between samples of interlab check

78

 

 

Table 15.1: Lakefield Projected Metallurgy

81

 

 

Table 15.2: Oxide Process Design Criteria — Heap Leach Operation

86

 

8



 

Table 15.3: Sulphide Process Design Criteria — Modified Maraca Treatment Plant

87

 

 

Table 16.1: Mineral Resources - Net of Mineral Reserves

104

 

 

Table 16.2: Mineral Resources - Including Mineral Reserves

105

 

 

Table 16.3: Quarterly and Annual Accuracies at Different Grid Spacings

108

 

 

Table 16.4 Comparison of Copper Grades

114

 

 

Table 16.5 Comparison of Gold Grades

114

 

 

Table 16.6 Summary of Correlation Coefficient

116

 

 

Table 16.7: Tonnage block model at different Cu cut grades

116

 

 

Table 16.8: Suruca estimation domains

120

 

 

Table 16.9: Back transformed variogram model parametres for Au

122

 

 

Table 16.10: Suruca block model parametres

123

 

 

Table 16.11: Densities applied to the Mineral Resource models

123

 

 

Table 16.12: Mineral resources estimate

125

 

 

Table 16.13: Economic Parametres for Chapada Mine Design

126

 

 

Table 16.14: Chapada Mineral Reserve as of December 31, 2010

127

 

 

Table 16.15 Economic Parametres for Chapada Mine Design

128

 

 

Table 16.16 : Chapada Mine production Schedule

137

 

 

Table 16.17: Suruca Project Probable Mineral Reserve, Effective Date December 2010

138

 

 

Table 16.18: Ultimate Pit Input Parametres

139

 

 

Table 16.19: Ultimate Pit Results

140

 

 

Table 21.1 Chapada Current Mining Equipment Contractor Fleet

154

 

 

Table 21.2 Mine Major Equipment Fleet Requirement

155

 

 

Table 21.3: Planned Suruca Project Phases

160

 

 

Table 21.4: Mine Production Schedule

162

 

 

Table 21.5: Processing Plant Production Plan — Chapada/Suruca

165

 

 

Table 21.6: Suruca Project Gold Production

171

 

 

Table 21.7: Additional Gold recovered

171

 

 

Table 21.8: Suruca Project Financial Parametres

172

 

 

Table 21.9: Suruca Project Sensitivity NPV x Discount Rate

173

 

 

Table 21.10: Suruca Project NPV Sensitivity Analysis (discount rate 5% p.y.)

173

 

 

Table 21.11: Suruca Project IRR Sensitivity Analysis

174

 

 

Table 21.12: Suruca Project Cross NPV Sensitivity Analysis (discount rate 5% p.y.)

175

 

 

Table 21.13: Suruca Project Cross IRR Sensitivity Analysis

176

 

 

Table 21.14: Suruca Project Capital Cost Summary: Oxide + Sulphide Phase 1 in MMIC

178

 

 

Table 21.15: Suruca Project Capital Cost: Oxide (without working capital)

179

 

9



 

Table 21.16: Suruca Project Capital Cost: Sulphide Phase 1 (without working capital)

180

 

 

Table 21.17 — Suruca Project Capital Cost: Sulphide Phase 2 (without working capital)

181

 

 

Table 21.18: Suruca Project Total Cash Cost Summary (a)

183

 

 

Table 21.19: Suruca Project Mine Cost Details

184

 

 

Table 21.20: Suruca Project Plant and Other Cash Cost Summary (a)

185

 

 

Table 21.21: Suruca Project Oxide Plant Cash Cost Summary (a)

186

 

 

Table 21.22: Suruca Project Oxide Plant 2014 Labour Cost Details (a)

187

 

 

Table 21.23: Suruca Project Oxide Plant 2014 Supplies, Power and Maintenance Details

187

 

 

Table 21.24: Suruca Project Oxide Plant Other Cash Cost 2014 Summary

188

 

 

Table 21.25: Suruca Project Oxide Plant Other Cash Cost 2014 Labor Details (a)

188

 

 

Table 21.26: Suruca Project MMIC Recovery Increase (CIL/Phase 1) Other Cash Cost Summary (US$) (a)

189

 

 

Table 21.27: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Labour Cost Details (a)

190

 

 

Table 21.28: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Consumables/Supplies and Power Data Details

190

 

 

Table 21.29: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Maintenance and Other Costs

191

 

 

Table 21.30: Suruca Project Sulphide/Phase 2 Plant Cash Cost Summary (a)

191

 

 

Table 21.31: Suruca Project Sulphide/Phase 2 Plant 2017 Labour Cost Details (a)

191

 

 

Table 21.32: Suruca Project Sulphide/Phase 2 Plant 2017 Consumables/Supplies, Power and Maintenance Data Details

192

 

 

Table 21.33: Suruca Project Sulphide/Phase 2 2017 Other Cash Cost

192

 

 

Table 21.34: Suruca Project Sulphide/Phase 2 Other Cash 2017 Labour Details (a)

193

 

 

Table 21.35: Working Capital

195

 

 

Table 21.36: Suruca Project Financial Statement

197

 

 

Table 21.37: Suruca Project Cash Flow

198

 

 

Table 21.38: Chapada and Suruca Project Financial Parametres

199

 

 

Table 21.39: Chapada and Suruca Project Sensitivity NPV x Discount Rate

200

 

 

Table 21.40: Chapada and Suruca Project NPV Sensitivity Analysis (discount rate 5% per year)

200

 

 

Table 21.41: Chapada Project and Suruca Project Cross NPV Sensitivity Analysis (discount rate 5% p.y.)

202

 

 

Table 21.42: Chapada Project and Suruca Project Financial Statement

203

 

 

Table 21.43: Chapada Project and Suruca Project Cash Flow

204

 

10



 

1                      SUMMARY

 

1.1                     General

 

Yamana Gold Inc. (‘Yamana’), through its Brazilian subsidiaries, owns the Chapada copper and gold deposit, and Suruca gold deposit, incorporates three distinct phases or components to the project, accord with the pre-feasibility study of the Suruca gold deposit. These are i) the processing of Suruca oxides via conventional heap leach processing (the “Oxides Phase”); ii) the production of additional gold from the Chapada ore following modifications to the Chapada processing plant (“Phase I Sulphides”); and iii) the processing of Suruca sulphides through new processing facilities to be added to the Chapada plant (“Phase II Sulphides”).

 

The purpose of this technical report is to present the integration between Chapada operation and Suruca’s project pre-feasibility study and update the mineral resources and reserves for Chapada and Suruca integrated. It has been prepared by Yamana with the input from the following companies: Metalica Consultores S.A. (report integration and auditing of mineral reserves), AMEC Minproc Engenharia e Consultoria for the processing plant, associated infrastructure and mine design; VOGBR Recursos Hídricos & Geotecnia for waste pile and geomechanical study, Geoconsultoria S/C Ltda for the tailings disposal; Mineral Engenharia e Meio Ambiente (‘Mineral’) for the environmental studies; and Schlumberger Water Services for hydrogeological study at Suruca Project.

 

The integration between Chapada operation and Suruca pre-feasibility study not only considers the gold recovered from the Suruca oxide and sulphide ores, but also additional gold recovered from Chapada ore as a result of a plant upgrade.

 

The Chapada Project is located in northern part of Goias State, approximately 320 kilometres north of the state capital Goiania and 270 kilometres northwest of the national capital of Brasilia.  The property is accessible via the paved federal road BR-153.  The Suruca project is located 6 km northeast of the Chapada mine.

 

Yamana is mining the copper-gold ores of Chapada by conventional open pit methods (2007 was the first year of commercial production).  Processing is carried out in a conventional copper sulphide flotation plant which is designed to process about 22 million tonnes per year of ore. The plant produces a copper-gold concentrate that is shipped to smelting and refining facilities.

 

The Suruca Project includes two distinct basic ore types: Oxide ore and Sulphide ore. The production plan that was completed by AMEC was based on a two stage plan. The first step is to send only oxidized material to the heap leach pad located adjacent to the Suruca pit. The second step is to send sulphide material to the Chapada concentrator plant. The plan indicates that all of the oxidized material will be exhausted by 2017. Subsequently, the sulphide ore will be sent to a primary crusher and then to the concentrator located in the Chapada mine.

 

This report is in metric units. Tonnes mean metric tonnes and ktonnes denotes 1000 metric tonnes. Metal grades of gold are in grams per metric tonne. Koz is an abbreviation for 1000 troy ounces since gold prices are quoted in troy ounces on world markets. Copper metal is reported in US pounds since prices are commonly quoted in those terms. Mlbs is an abbreviation for 1 million US pounds of copper.

 

11



 

Figure 1.1: General Layout of the Suruca & Chapada Project

 

 



 

1.2                     Land Claims

 

The Chapada Project is divided into 16 claims totalling 18,921.37 hectares. The project claims are held in the name of Mineração Maraca Indústria e Comércio S/A. The Suruca Open Pit will be inserted into the following claims: 860.708/2009 and 860.595/2009, totalling 845.75 hectares.

 

1.3                     Geology and Mineralization

 

1.3.1                                 Local Geology

 

The Suruca Project was grouped from the base to the top as: amphibolite (“ANF”), Intermediate metavolcanic rocks (MVI) and metassediments (MTS). There are several intrusions of quartz diorite porphyry (“QDP”) that occur preferentially in the intermediate metavolcanic rocks (“MVI”) and Metassediments (MTS). The hydrothermal alteration overprints the lithologies and is characterized by inner and outer halos: i) Inner halo occur in the intermediate rocks, metassediments and diorites with strong and pervasive sericitic alteration (“MVA”); ii) outer halo is characterized by propylitic halo that occur mainly in the amphibolites.

 

All these rocks are covered by thick (average of 30m) lateritic profile. The lateritic profile is represented by a typical immature lateric terrain that was subdivided from the base to the top in: coarse saprolite, saprolite, mottled zone or argillic zone, lateritic duricrust and pisolitic soils (products of alteration of duricrust).

 

Figure 1.2 shows the geological map of Chapada - Suruca region with the location of Chapada Mine pit and Suruca Project designed.

 



 

Figure 1.2 Figure: Chapada - Suruca Geological Map

 

GRAPHIC

 

1.3.2                     Deposit Types

 

The mineralization in Chapada Project is currently interpreted as porphyry and epithermal system associated to Island Arc stage (864 Ma) overprinted by remobilization of orogenic fluids during Brasiliano events (630 — 580Ma) (Silitoe, 2008 and Espada, 2010 — Internal report). The porphyry and epithermal system can be separated into three distinctive mineralizations, based on the style of hydrothermal alteration, metal association: i) Cu-Au porphyry system represented by Chapada Mine; ii) Au High Sulphidation represented by HS (Hidrotermalito) Project; iii) Au (Ag-Pb-Zn) Intermediate Sulphidation represented by Suruca Project.

 

1.3.3                     Mineralization

 

The primary copper-gold mineralization at the Chapada mine is epigenetic. Copper is principally present as chalcopyrite with minor amounts of bornite. Fine grained gold is closely associated with the sulphide mineralization and was likely contemporaneous with copper. Copper mineralization occurs as finely disseminated crystals, elongated pods, lenses along foliation, crosscutting stringers, and coarse clots in occasional late stage quartz veins or pegmatites. The copper mineralization and grade are somewhat better in the central zone of the deposit along the anticline axis than in the surrounding anticlinal limbs. However, copper mineralization is pervasive over a broad area. Gold mineralization is more uneven spacially and may have been remobilized by post mineral low temperature alternation events.

 

14



 

The Suruca ore body has outlined a resource with a strike length of 1,900 metres and 800 metres of down dip from surface.  The main direction is N40°E, dipping 20 to 30°NW, controlled by the foliation S1.

 

The Suruca ore body is characterized by oxide and sulphides ores. The oxide ore comprises12,2 % of the total ore in the deposit and is associated to weathering surface with width between 35 to 40 metres depth with an average gold grade of 0.41 g/t Au. The oxide ore is characterized by soil, mottled zone, fine saprolite and coarse saprolite.

 

Ore body at the Suruca Project sulphide ore is characterized by fresh sulphides and rocks and occurs in four orebodiesreferred to as Suruca 1, Suruca 2, Suruca 3 and Suruca 4 that represent only spatial occurrence of mineralization.

 

·                  Suruca 1:  Is the upper ore body and represents 1.1% of the deposit, with average gold grade of 0.36 g/t Au;

 

·                  Suruca 2: Is the main ore body representing 80.3% of the deposit, with an average gold grade of 0.40 g/t Au. This ore body has four internal waste bodies (Waste 1, Waste 2, Waste 3 and Waste 4);

 

·                  Suruca 3: Is deeper than Suruca 2 and comprises 1.1 % of the deposit, with an average gold grade of 0.47 g/t Au;

 

·                  Suruca 4: Is the deepest ore body and comprises 5.8% of the deposit with average gold grade of 0.41 g/t Au. This ore body has an internal waste (Waste 5).

 

The hydrothermal alteration in Suruca sulphide ore is associated with sericitic and propylitic alteration halo. The proportion is about 44% in the sericitic and 37% in propylitic. The sericitic alteration is characterized by sericite, +/- biotite and carbonate with pyrite, galena, spharelite and some chalcopyrite. The propylitic alteration is characterized by epidote, chlorite, carbonate and pyrite.

 

1.4                     Drilling

 

1.4.1                     Chapada Drilling

 

The drillhole database consists of 856 diamond core drillholes that represent 67,314 metres of drilling and 47,939 sample intervals.  The drilling consists of two hole series, short CHD series holes that were drilled to test saprolite material and longer M series holes.

 

Table 1.2 is excerpted from the report “Executive Summary Report - Chapada Project”, dated June 25, 1997, by Santa Elina, and summarizes the drilling by date and company.

 

Table 1.1: Chapada Drilling by Date and Company

 

Date

 

Companies

 

No. of Holes

 

No. of Metres

 

1976

 

INCO

 

6

 

919

 

1976-1979

 

INCO/Eluma

 

78

 

10,573

 

1979-1981

 

Eluma/Noranda

 

86

 

11,140

 

1989

 

Eluma

 

6

 

569

 

1995

 

Santa Elina

 

416

 

6,631

 

1996

 

Santa Elina/Echo Bay

 

264

 

37,482

 

TOTAL

 

 

 

856

 

67,314

 

 

15



 

The drilling has delineated the main deposit areas at a spacing of 100 metres by 50 metres, with a tighter 50 meter pattern in the central portion of the deposit.

 

680 of the 856 holes were drilled in the 1995-1996 campaigns. These were NQ or NX size core holes. All collar locations were surveyed. Angle holes (only 5% of the drilling) were down-hole surveyed, but down-hole surveys were not done for the vertical holes. The “longer” M series holes only tended to be about 150 metres long due to the shallow nature of the deposit so significant deviation in hole orientation is not expected.

 

There is also documentation of several reverse circulation holes drilled for condemnation purposes. There were also some early S series holes in the saprolite material.

 

1.4.2                     Suruca Drilling

 

A total of 131 drill holes / 27,374.17 metres were completed at the Suruca Project by Yamana in 2008, 2009 and 2010, summarized as follows:

 

Table 1.2: Suruca Executed holes per year

 

Date

 

Companies

 

N.0 of Holes

 

N.0 of Metres

 

2008

 

Yamana Gold Inc.

 

7

 

439.5

 

2009

 

Yamana Gold Inc.

 

21

 

6,457.82

 

2010*

 

Yamana Gold Inc.

 

103

 

20,476.85

 

TOTAL

 

 

 

131

 

27,374.17

 

 


*Holes for Metallurgical Testing: 11 holes/1,014 metres.

 

1.5                     Mineral Resources

 

1.5.1                     Mineral Resources Chapada

 

Emerson Ricardo Re, MAusIMM, Resource and Reserves Corporative Manager of Yamana Gold Inc., is the qualified person for mineral resources. Raúl Contreras, Metalica Consultores S.A, is the qualified person for mineral reserves. Table 1.3 is an estimate of mineral resources remaining, after 2010 mining, including the mineral reserves.

 

16



 

Table 1.3: Chapada Mineral resources estimate  as of December 31, 2010

 

Mineral Resources - Including Mineral Reserve

 

 

 

Resource

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained

 

Resource Category

 

Ktonnes

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Measured/Indicated Resource

 

 

 

 

 

 

 

 

 

 

 

Measured Mineral Resource

 

233,015

 

0.258

 

0.186

 

1,307

 

1,394

 

Indicated Mineral Resource

 

479,738

 

0.211

 

0.119

 

2,228

 

1,839

 

Measured/Indicated Resource*

 

712,753

 

0.226

 

0,141

 

3,535

 

3,233

 

Inferred Mineral Resource

 

 

 

 

 

 

 

 

 

 

 

Inside Design Pit

 

0

 

0.000

 

0.000

 

 

 

Outside Design Pit

 

96,147

 

0.185

 

0.094

 

392

 

289

 

Inferred Resource

 

96,147

 

0.185

 

0.094

 

392

 

289

 

 


Notes:

(1) Mineral Resources estimated using the limits of block models;

(2) Mineral Reserve estimated at $900/oz gold price and $2.50/lb copper price;

(3) 3.53 $/t NSR cutoff for Open Pit.

* For copper grade we don´t include the oxide stockpile because process is different

 

Note that Table 1.3 shows mineral resources, inclusive of mineral reserves. Measured and indicated mineral resources are 712.753 million tonnes at 0.225% copper and 0.141 g/t gold.

 

Inferred resources have separate line items for resources inside versus outside the final pit design. There are no inferred resources inside the current pit design amount to 0.0 million tonnes. The total inferred mineral resource is 96.147 million tonnes at 0.185% copper and 0.069 g/t gold.

 

1.5.2                     Mineral Resources Suruca

 

Table 1.4 illustrates the mineral resource estimate for the Suruca Project. This estimate was performed by Yamana technical staff, under the supervision of Greg Walker, P.Geo, who acted as qualified person under Canadian rules. Indicated and inferred resources are based on a 0.2 g/t cutoff for oxides and a 0.3 g/t cutoff for sulphides are summarized as follows:

 

Table 1.4: Suruca Mineral resources estimate as of December 31, 2010

 

 

 

 

 

Indicated

 

Inferred

 

Ore

 

Cufoff

 

Au (g/t)

 

kt
(x1000)

 

koz
(x1000)

 

Au (g/t)

 

kt
(x1000)

 

koz
(x1000)

 

Oxide

 

0.2

 

0.48

 

19,247

 

298

 

0.39

 

3,755

 

47

 

Sulphide

 

0.3

 

0.50

 

132,114

 

2,127

 

0.39

 

5,423

 

68

 

Oxide and Sulphide

 

 

 

0.50

 

151,361

 

2,425

 

0.39

 

9,178

 

115

 

 

17



 

1.5.3                     Mineral Resources Chapada and Suruca

 

The Mineral resource estimate for the Suruca Project and Chapada mine integrated is reported in the Table 1.5.

 

Note that Table 1.5 shows mineral resources, inclusive of mineral reserves. Measured and indicated mineral resources are 864.114 million tonnes at 0.226% copper and 0.204 g/t gold.Total inferred mineral resource is 105.325 million tonnes at 0.185% copper and 0.069 g/t gold.

 

Table 1.5: Chapada and Suruca Mineral Resources Estimate as of December 31, 2010

 

Mineral Resources Chapada + Suruca - Including Mineral Reserve

 

 

 

Resource

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained

 

Resource Category

 

Ktonnes

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Measured/Indicated Resource

 

 

 

 

 

 

 

 

 

 

 

Measured Mineral Resource Chapada

 

233,015

 

0.258

 

0.186

 

1,307

 

1,394

 

Indicated Mineral Resource Chapada

 

479,738

 

0.211

 

0.119

 

2,228

 

1,839

 

Indicated Mineral Resource Suruca

 

151,361

 

 

 

0.500

 

 

 

2,425

 

Measured/Indicated Resource*

 

864,114

 

0.226

 

0.204

 

3,535

 

5,657

 

Inferred Mineral Resource

 

 

 

 

 

 

 

 

 

 

 

Infered Mineral Resource Chapada

 

96,147

 

0.185

 

0.094

 

392

 

289

 

Infered Mineral Resource Suruca

 

9,178

 

 

 

0.390

 

 

 

115

 

Inferred Resource

 

105,325

 

0.185

 

0.119

 

392

 

404

 

 


Notes:

(1) Mineral Resources estimated using the limits of block model;

(2) Mineral Reserve estimated at $900/oz gold price and $2.50/lb copper price;

* For copper grade we don´t include the oxide stockpile of Chapada

 

1.6                     Mineral Reserves

 

1.6.1                     Mineral Reserves Chapada

 

The estimation of mineral reserves was performed by Yamana Technical Services and audited by Metálica), who also updated the mineral reserves estimates herein presented.

 

The Table 1.6 shows the mineral reserves for the Chapada mine as of December 31, 2010 based on a long range mine plan and plant production schedule developed by Yamana. The total proven and probable mineral reserves is 368.7 million ore tons at 0.26% total copper and 0.18 g/t gold.

 

The mineral reserves are based on long term realized copper and gold prices of $2.50 per pound and $900 per ounce respectively. The NSR value represents net revenue per ton ore net of smelting, refining, concentrate freight, gold royalties, and copper sales taxes.

 

18



 

Table 1.6: Chapada Mineral Reserve as of December 31, 2010

 

Chapada Mineral Reserve as of December 31, 2010

 

 

 

Ore

 

NSR

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained

 

Reserve Class

 

Ktonnes

 

(US$/t)

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Proven Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore

 

140,160

 

13.84

 

0.296

 

0.209

 

915

 

943

 

Existing Mill Stockpile

 

1,214

 

16.78

 

0.356

 

0.301

 

10

 

12

 

Low Grade Stockpiles (Existing)

 

26,391

 

11.50

 

0.246

 

0.201

 

143

 

170

 

Total Proven Mineral Reserve

 

167,765

 

13.49

 

0.289

 

0.209

 

1,068

 

1,125

 

Probable Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore

 

200,951

 

10.35

 

0.244

 

0.148

 

1,081

 

957

 

Total Probable Mineral Reserve

 

200,951

 

10.35

 

0.244

 

0.148

 

1,081

 

957

 

Total Proven and Probable Mineral Reserve

 

368,716

 

11.78

 

0.264

 

0.176

 

2,149

 

2,082

 

 


Notes:

(1)- Total Pit Material 473,599 Ktonnes, Strip Ratio 0.39 to 1;

(2)- Mineral Reserve estimated at $900/oz gold price and $2.50/lb copper price;

(3) - 3.53 $/t NSR cutoff for Open Pit.

 

1.6.2                     Mineral Reserves Suruca

 

Mineral reserves for the Suruca Project are classified in accordance with the 2005 CIM Definition Standards for Mineral Resources and Mineral Reserves, and are estimated based on a gold price of US$900/oz. Mineral reserves evaluated by AMEC are summarized in Table 1.7.

 

The block model used in includes only indicated and inferred resources. The pit optimization was completed using only indicated resources. Inferred blocks were classified as waste material. Total reserves amount to approximately 1.1 million ounces, broken down as follows:

 

Table 1.7: Suruca Probable Mineral Reserve, Effective Date December 2010

 

 

 

 

 

Probable Reserves

 

 

 

 

 

 

 

Tonnes

 

 

 

Contained Metal (oz)

 

Suruca Project

 

Cutoff

 

(tx1000)

 

Au (g/t)

 

Au (oz x 1,000)

 

Oxide

 

0.2

 

16,331

 

0.510

 

268

 

Sulphide

 

0.3

 

44,124

 

0.553

 

784

 

Total

 

 

 

60,455

 

0.541

 

1,052

 

 


Notes:

(1)          All mineral reserves are categorized as probable.

(2)          Reserves are estimated using a US$ 900/oz gold price and economic function that includes operating costs, metallurgical recoveries and selling costs has been applied.

(3)          Rounding as required by reporting guidelines may result in apparent differences between tonnes, grade and contained metal content.

(4)          Tonnage and grade measurements are in metric units. Gold ounces are reported as troy ounces.

 

19



 

1.6.3                     Mineral Reserves Chapada and Suruca

 

The Table 1.8 shows the mineral reserves for Chapada mine and Suruca Project integrated as of December 31, 2010, based on a long range mine plan and plant production schedule of Chapada and the pre-feasibility study of the Suruca project, developed by Yamana and AMEC respectively. Total proven and probable mineral reserves is 429.18 million ore tons at 0.26% total copper and 0.23 g/t gold.

 

Table 1.8: Chapada and Suruca Mineral Reserves

 

Chapada + Suruca Mineral Reserve as of December 31, 2010

 

 

 

Ore

 

Copper

 

Gold

 

Copper
Containd

 

Gold
Contained

 

Reserve Class

 

Ktonnes

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Proven Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore Chapada

 

140,160

 

0.296

 

0.209

 

915

 

943

 

Existing Mill Stockpile Chapada

 

1,214

 

0.356

 

0.301

 

10

 

12

 

Low Grade Stockpiles (Existing) Chapada

 

26,391

 

0.246

 

0.201

 

143

 

170

 

Total Proven Mineral Reserve

 

167,765

 

0.289

 

0.209

 

1,068

 

1,125

 

Probable Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore Chapada

 

200,951

 

0.244

 

0.148

 

1,081

 

957

 

Open Pit Ore Suruca

 

60,455

 

 

 

0.541

 

 

 

1,052

 

Total Probable Mineral Reserve

 

261,406

 

0.244

 

0.239

 

1,081

 

2,009

 

Total Proven and Probable Mineral Reserve

 

429,171

 

0.262

 

0.227

 

2,475

 

3,134

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Pit Material 555,829 Ktonnes, Strip Ratio 1.30 to 1.

 

 

 

 

 

 

 

 

 

 

 

 

1.7                     Mine Schedule

 

1.7.1                     Mine Schedule Chapada

 

The tonnage and grade distribution from the mining phases was used to develop mining production schedule. The topography as of the end of 2010 was incorporated into the phase tonnages for the calculation of the updated schedule.

 

Table 1.9 shows the Chapada mine production schedule:

 

·                  During the life of mine (19 years) an amount of 368.72 Mt of ore reserves are sent to plant, including the processing of the materials of stocks.

 

·                  The average grades sent to plant are 0.264% CuT and 0.176 Au g/t.

 

·                  The mine requires a maximal removal of 60 Mtpy, during the life of mine 657.8 Mt of rock will be removed, representing an overall stripping ratio of 0.78. Re-handling of 194.0 Mt low grade stocks is included.

 

20



 

The planned gold and copper production for the life of mine, including all phases of the Project, with the topography as of the end of 2010, is summarized in the Table 1.9 below.

 

1.7.2                     Mine Schedule Suruca

 

Ore from the Suruca Project will be mined as an open pit. Contracted mining was considered, using 10 m3 excavators and 100 tonne trucks. Drilling and blasting estimates are based on the current contractors pricing. The production plan, for oxide and sulphide ore, over a ten year mine life, amounts to approximately 60.5 million tones, as shown in the below, at an average waste/ore ratio of 1.36.:1

 

1.7.3                     Mine Schedule Chapada and Suruca Integrated

 

The planned gold and copper production for the life of the Chapada mine and Suruca Project, including all three phases of the project, based on the pre-feasibility production levels, is in Table 1.11 below.

 

21



 

Table 1.9: Chapada Mine schedule

 

Yamana Gold

Name of Asset

 

Chapada

 

Status

 

Operating

 

Date

 

December 31, 2010

 

PRODUCTION

 

Unit

 

Total

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Ore Feed Chapada

 

kt

 

368.716

 

21.555

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.500

 

14.000

 

14.000

 

14.000

 

14.000

 

14.400

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.261

 

Copper Grade

 

%

 

0,264

%

0,431

%

0,371

%

0,308

%

0,298

%

0,290

%

0,305

%

0,330

%

0,316

%

0,321

%

0,360

%

0,257

%

0,202

%

0,190

%

0,189

%

0,185

%

0,180

%

0,185

%

0,174

%

0,180

%

Copper Recovery

 

%

 

85,3

%

86,8

%

87,1

%

86,1

%

86,0

%

85,9

%

86,4

%

86,9

%

86,6

%

87,6

%

84,1

%

84,1

%

84,3

%

84,4

%

84,2

%

83,9

%

84,0

%

84,0

%

84,0

%

84,0

%

Copper Contained

 

Mlb

 

2.149

 

205

 

180

 

150

 

144

 

141

 

148

 

127

 

98

 

99

 

111

 

79

 

64

 

92

 

92

 

90

 

87

 

90

 

85

 

68

 

Copper Production

 

Mlb

 

1.840

 

178

 

157

 

129

 

124

 

121

 

128

 

111

 

84

 

87

 

93

 

67

 

54

 

78

 

77

 

75

 

73

 

75

 

71

 

58

 

Gold Grade

 

g/t

 

0,176

 

0,330

 

0,304

 

0,243

 

0,228

 

0,210

 

0,199

 

0,220

 

0,199

 

0,200

 

0,240

 

0,169

 

0,129

 

0,100

 

0,098

 

0,098

 

0,097

 

0,106

 

0,091

 

0,093

 

Gold Recovery

 

%

 

62,2

%

60,7

%

60,8

%

58,8

%

64,8

%

63,0

%

62,1

%

63,7

%

61,8

%

76,0

%

64,9

%

61,9

%

61,6

%

61,3

%

60,6

%

61,1

%

61,1

%

61,1

%

61,1

%

61,1

%

Gold Contained

 

koz

 

2.082

 

229

 

215

 

172

 

161

 

149

 

140

 

124

 

90

 

90

 

108

 

76

 

60

 

71

 

69

 

69

 

69

 

75

 

64

 

52

 

Gold Production

 

koz

 

1.299

 

139

 

131

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

Waste + Stock Low Grade

 

kt

 

289.113

 

38.838

 

32.000

 

32.000

 

32.000

 

32.000

 

32.000

 

16.500

 

20.000

 

20.000

 

20.000

 

13.775

 

 

 

 

 

 

 

 

 

Waste

 

kt

 

132.488

 

18.448

 

24.441

 

19.026

 

13.853

 

18.308

 

17.810

 

6.327

 

9.007

 

4.711

 

5

 

552

 

 

 

 

 

 

 

 

 

Low Grade Ore + Oxide

 

kt

 

156.625

 

20.390

 

7.559

 

12.974

 

18.147

 

13.692

 

14.190

 

10.173

 

10.993

 

15.289

 

19.995

 

13.223

 

 

 

 

 

 

 

 

 

Low Grade Reclaiming

 

kt

 

194.001

 

 

 

 

 

6.757

 

11.000

 

9.400

 

10.500

 

6.000

 

6.000

 

4.000

 

21.000

 

21.000

 

21.000

 

21.000

 

21.300

 

21.300

 

13.744

 

 

 

 

Strip Ratio (REM)

 

 

 

0,78

 

1,80

 

1,45

 

1,45

 

1,45

 

1,45

 

1,45

 

0,94

 

1,43

 

1,43

 

1,43

 

0,98

 

 

 

 

 

 

 

 

 

Haulage profile (DMT)

 

m

 

1.607

 

2.033

 

1.706

 

1.614

 

1.457

 

1.501

 

1.537

 

1.944

 

1.919

 

1.750

 

1.715

 

1.491

 

1.146

 

1.489

 

1.390

 

1.370

 

1.329

 

1.350

 

1.350

 

1.350

 

Total mine move

 

kt

 

657.829

 

60.393

 

54.000

 

54.000

 

54.000

 

54.000

 

54.000

 

34.000

 

34.000

 

34.000

 

34.000

 

27.775

 

14.400

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.261

 

 



 

Table 1.10: Suruca Mine schedule

 

 

 

 

 

Mineral to Plant

 

Mineral to Stock

 

 

 

 

 

 

 

 

 

 

 

Oxide

 

Sulphide From Mine

 

Sulphide From
Stock

 

Total Sulphide

 

Total to Plant

 

Sulphide

 

Waste

 

Total

 

Year 

 

Day

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au(gr/t)

 

kt

 

Au(gr/t)

 

kt

 

kt

 

ktpd

 

2013

 

365

 

3,000

 

0.580

 

 

 

 

 

 

 

 

 

 

 

 

 

3,000

 

0.580

 

 

 

 

 

3,579

 

6,579

 

18

 

2014

 

365

 

4,000

 

0.531

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.531

 

1,154

 

0.596

 

5,281

 

10,435

 

29

 

2015

 

365

 

4,000

 

0.477

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.477

 

1,041

 

0.563

 

9,559

 

14,600

 

40

 

2016

 

365

 

4,000

 

0.535

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.535

 

3,146

 

0.491

 

11,104

 

18,250

 

50

 

2017

 

365

 

1,331

 

0.321

 

2,830

 

0,470

 

1,670

 

0.528

 

4,500

 

0,491

 

5,831

 

0.452

 

 

 

 

 

12,596

 

18,427

 

50

 

2018

 

365

 

 

 

 

 

6,405

 

0,510

 

1,595

 

0.528

 

8,000

 

0,514

 

8,000

 

0,514

 

 

 

 

 

10,250

 

18,250

 

50

 

2019

 

365

 

 

 

 

 

6,727

 

0.537

 

1,273

 

0.528

 

8,000

 

0.535

 

8,000

 

0.535

 

 

 

 

 

10,250

 

18,250

 

50

 

2020

 

365

 

 

 

 

 

7,583

 

0.530

 

417

 

0.528

 

8,000

 

0.530

 

8,000

 

0.530

 

 

 

 

 

10,250

 

18,250

 

50

 

2021

 

365

 

 

 

 

 

7,614

 

0.568

 

386

 

0.528

 

8,000

 

0.566

 

8,000

 

0.566

 

 

 

 

 

6,097

 

14,097

 

39

 

2022

 

365

 

 

 

 

 

7,624

 

0.658

 

 

 

 

 

7,624

 

0.658

 

7,624

 

0.658

 

 

 

 

 

3,264

 

10,888

 

30

 

Total

 

3,650

 

16,331

 

0.510

 

38,783

 

0.556

 

5,341

 

0.528

 

44,124

 

0.553

 

60,455

 

0.541

 

5,341

 

0.528

 

82,230

 

148,026

 

41

 

 

23



 

Table 1.11: Processing Plant Production Plan — Chapada/Suruca

 

Yamana Gold

Name of Asset

 

Chapada and Suruca

 

Status

 

Operating and Project

 

Date

 

December 31, 2010

 

PRODUCTION

 

Unit

 

Total

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Ore Feed Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Copper Grade

 

%

 

0.264

%

0.431

%

0.371

%

0.308

%

0.298

%

0.290

%

0.305

%

0.330

%

0.316

%

0.321

%

0.360

%

0.257

%

0.202

%

0.190

%

0.189

%

0.185

%

0.180

%

0.185

%

0.174

%

0.180

%

Copper Recovery

 

%

 

85.3

%

86.8

%

87.1

%

86.1

%

86.0

%

85.9

%

86.4

%

86.9

%

86.6

%

87.6

%

84.1

%

84.1

%

84.3

%

84.4

%

84.2

%

83.9

%

84.0

%

84.0

%

84.0

%

84.0

%

Copper Contained

 

Mlb

 

2,149

 

205

 

180

 

150

 

144

 

141

 

148

 

127

 

98

 

99

 

111

 

79

 

64

 

92

 

92

 

90

 

87

 

90

 

85

 

68

 

Copper Production

 

Mlb

 

1,840

 

178

 

157

 

129

 

124

 

121

 

128

 

111

 

84

 

87

 

93

 

67

 

54

 

78

 

77

 

75

 

73

 

75

 

71

 

58

 

Gold Grade

 

g/t

 

0.176

 

0.330

 

0.304

 

0.243

 

0.228

 

0.210

 

0.199

 

0.220

 

0.199

 

0.200

 

0.240

 

0.169

 

0.129

 

0.100

 

0.098

 

0.098

 

0.097

 

0.106

 

0.091

 

0.093

 

Gold Recovery

 

%

 

62.2

%

60.7

%

60.8

%

58.8

%

64.8

%

63.0

%

62.1

%

63.7

%

61.8

%

76.0

%

64.9

%

61.9

%

61.6

%

61.3

%

60.6

%

61.1

%

61.1

%

61.1

%

61.1

%

61.1

%

Gold Contained

 

koz

 

2,082

 

229

 

215

 

172

 

161

 

149

 

140

 

124

 

90

 

90

 

108

 

76

 

60

 

71

 

69

 

69

 

69

 

75

 

64

 

52

 

Gold Production

 

koz

 

1,299

 

139

 

131

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

Ore Feed Suruca Oxides

 

kt

 

16,331

 

 

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.511

 

 

 

 

 

0.580

 

0.531

 

0.477

 

0.535

 

0.321

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

85.0

%

 

 

 

 

85.0

%

85.0

%

85.0

%

85.0

%

85.0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

228

 

 

 

 

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore Feed Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.553

 

 

 

 

 

 

 

 

 

 

 

 

 

0.491

 

0.514

 

0.535

 

0.530

 

0.566

 

0.658

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

626

 

 

 

 

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

 

 

 

 

 

 

 

Total Ore Feed

 

kt

 

429,171

 

21,555

 

22,000

 

25,000

 

26,000

 

26,000

 

26,000

 

23,331

 

22,000

 

22,000

 

22,000

 

22,000

 

22,024

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Suruca Oxides

 

kt

 

16,331

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

2,152

 

139

 

131

 

149

 

162

 

146

 

146

 

147

 

161

 

178

 

179

 

163

 

166

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

 

24



 

1.8                     Suruca Metallurgical testwork

 

1.8.1                     Oxide Characterization

 

A summary of the oxidized ore studies are as follows:

 

·                  The characterization studies carried out by University of São Paulo using mineral liberation analysis (“MLA”) indicated the following: free gold particles 3.7% (greater than 37 microns), 55% of the gold associated with hydroxides of iron, 31% of the gold associated with silicates, 10% of the gold associated with other minerals and the gold grains have an average size of 8 microns.

 

·                  Cyanide leaching of the whole of ore sample at 100% passing 840 and 150 microns indicated gold recoveries of 75.9% and 89% respectively.

 

·                  Physical characterization test work indicated a Bond Work Index (BWi) value of 16.6 kWhr/tonne for a product grind size of 74 microns indicating that the Suruca oxide sample tested is moderately hard from the perspective of conventional ball mill grinding. Drop Weight Index (DWi) testing indicated that the sample tested was extremely friable.

 

·                  Gravity characterization test work was carried out by Knelson Research Laboratories. A conventional gravity recoverable gold (“GRG) test indicated a gravity recovery of 35.4% recovery. Leaching of the gravity concentrate with cyanide indicated a leach recovery of a 99%. This is compared to direct leaching of the ore crushed to less than 147 microns which gave a cyanide leach recovery of 93.6%.

 

·                  Flotation test work conducted on the oxide samples produced poor results with an overall flotation and leaching recovery of the flotation concentrates produced of approximately 30% of the feed gold content.

 

·                  Column leach tests conducted were positive. 92% of the contained gold was recovered from the oxide sample submitted in a period of 52 days leaching. The sodium cyanide consumption was calculated to be 0.44 Kg/tonne using a Portland cement addition rate of 18 Kg/t. The agglomerated sample was also strongly agglomerated based on the promising “slump” tests results indicating 0% slump with no pooling or channelling  noted during the testing.

 

1.8.2                     Suruca Sulphide Characterisation

 

A summary of the sulphidised ore studies are as follows:

 

·                  The characterization studies carried out by University of São Paulo using mineral liberation analysis indicated the following: free gold particles 26% (greater than 37 microns), 59% of the gold associated with sulphides, predominantly Pyrite, 9% of the gold associated with silicates, 4 to 6% of the gold associated with tellurides; and the gold grains have an average size of 3 microns.

 

·                  Cyanide leaching of the whole of ore sample at 100% passing 75 microns indicated a gold recovery of 88%. Technological characterization of the sample indicated a total gold recovery of 76.9% for a sample less than 300 microns in size;

 



 

·                  Physical characterization test work indicated a Bond Work Index (BWi) value of 15.4 kWhr/tonne for a product grind size of 74 microns indicating that the Suruca sulphide sample has a moderately to high hardness from the perspective of conventional ball mill grinding. Drop Weight Index (DWi) testing indicated that the sulphide ore is very competent in nature;

 

·                  Gravity characterization test work was carried out by Knelson Research Laboratories. A conventional GRG test indicated a gravity recovery of 35.2% recovery. Leaching of the gravity concentrate with cyanide indicated a leach recovery of a 95%. This is compared to direct leaching of the ore crushed to less than 109 microns gave a cyanide leach recovery of 82.3%;

 

·                  Flotation testing was conducted in two separate stages. The stage 1 results utilising locked cycle testing indicated gold recoveries of 82% and 85% when leaching the flotation concentrates produced. The second set of flotation tests indicated 82% recovery for flotation and 85% leach gold recovery of the concentrate produced at a grind size p80 of 75 microns.

 

1.9                     Process and Plant Design

 

The Chapada Project was designed to process an average of 22 million tons of ore per year.

 

The gold is associated with copper minerals such as copper and iron sulphide, showing predominantly chalcopyrite and pyrite. Other sulphide also occurs, like calcosite, covelite, bornite.

 

The unit operation of process are: comminution (crushing and milling), classification (screening and hydrocyclones), concentration (flotation), solid-liquid separation (thickening and filtering).

 

The comminution process begins with primary crushing circuit, composed of two crushers in parallel. The double roller crusher (“MMD”) receives more friable material and Jaw crusher is feed with highest hardness material. The run of mine ore was crushed until 80% of the particles are reduced below 150 mm diameter. The crushed ore is transported by conveyor to stockpile and later to second stage of comminution.

 

The second stage is composed by semi autogenous mill, followed by a vibrating screening, pebbles crusher, ball mill, and three batteries of hydrocyclones. Overflow produced by hydrocyclones feeds the flotation.

 

The flotation circuit is composed of 18 cells and a flotation column which is divided as follows:

 

·                 4 cells rougher,

 

·                 2 rougher-scavengers,

 

·                 4 scavenger,

 

·                 6 cleaners,

 

·                 2 cleaner scavenger.

 

The flotation column works in a closed circuit with vertical mill (Vertimill) and a battery of hydrocyclones.

 

The concentrate produced by the column flotation is thickened, filtered and sent by road trucks.

 

26



 

Based on the metallurgical testwork results from the Suruca Project, the following structure was adopted:

 

·                  Oxide ore: conventional heap leach;

 

·                  Maracá plant — phase 1: Carbon in leach (“CIL”) and gravity concentrator installation to add 10% in average in the gold recovery rate;

 

·                  Maracá plant — phase 2: Installation of a third mill and additional flotation cells to increase 10% in the recovery rate and to feed Suruca sulphide ore in 2017.

 

Ore from the Suruca Project will be treated and incorporated into the Chapada mine total gold production through two separate processes. Firstly, the oxide ore will be processed using conventional heap leaching technology. Approximately 16.3 million tonnes of oxide ore will be processed over five years with annual gold production expected to average 45,600 ounces. This production is projected to begin in 2013. After oxide ore exhaustion, the sulphide ore  from the Suruca Project will be processed in the existing Chapada treatment plant following some plant modifications as described in the previous paragraph. Approximately 44.1 million tones of sulphide ore will be treated over six years with annual gold production expected to average 104,500 ounces per year. The production from the sulphide ore from the Suruca Project is projected to begin in 2017. In total then, Suruca should contribute a total of approximately 855,000 ounces of gold to Chapada mine gold production resulting in a revised production profile. In addition to the production outlined above, gold recovered from the Chapada mine will increase by approximately 218, 000 ounces over the project mine life. This increase is a result of plant modifications (sulphide phase I) which are projected to increase gold recoveries by 10%.

 

1.10              Project Implementation

 

The Suruca Project development schedule shown in Figure 1.3 is divided in three steps as follows:

 

·                  Suruca oxides

 

·                  Suruca sulphide and Chapada

 

·                  Phase I (CIL implementation + Gravity concentration in Chapada Project’s Plant):

 

·                  Phase II (Sulphide ore in Chapada plant with the implementation of mill circuit + flotation to treat the tailing of rougher cells):

 

27



 

Figure 1.3: Suruca Project schedule

 

 

1.11              Economic Results

 

1.11.1              Suruca Economic Results

 

The main objective of the pre-feasibility study of Suruca Project is to evaluate the economic viability of the Suruca Project development and implementation.

 

The project Project is to achieve an average annual gold sale of:

 

·                  46 koz/year of oxide ore gold from 2013 to 2017, generating a total of 228 koz;

 

·                  104 koz/year of sulphide ore gold from 2017 to 2022, generating a total of 626 koz;

 

·                  14 koz/year of gold generated from the increased recovery of gold at the Chapada mine where the sulphide ore will be processed. The Carbon in Leach system (“CIL”) used in the sulphide ore processing will be implemented at the beginning of the project, increasing the recovery of gold from 2013 through 2029 generating and additional 230 koz during that period;

 

·                  Based on current reserves, total project gold sales as a result of the suruca project development, based on existing reserves is estimated at 1,084 koz.

 

Project construction for oxide ore from the Suruca Project and increase in gold recovery for the Chapada mine will take place in 2011 and 2012 and the production phase of the project will start at the beginning of 2013.

 

The gold recovery rate increase  at the Chapada mine will happen in two stages:

 

1.             The first stage is associated with the carbon in leach (‘CIL”) plant and gravity concentrator implementation at the beginning of the project (Phase 1), adding 10% to the average recovery rate and;

 

28



 

2.             The second stage occurs on completion of the sulphide plant at the Suruca Project in 2016 (Phase 2), adding, an additional 10% to the recovery rate.

 

The cash flow analysis was completed by Yamana based upon data generated in the pre-feasibility study.

 

The main assumptions related to the base case are:

 

·                  Gold price equal to US$ 1,300/oz in 2013 and US$ 1,100/oz in subsequent years

 

·                  Rate of Exchange equal to Real (R$ ) 1.80/US$

 

·                  Sale Tax (CEFEM): 1% of annual sales value

 

·                  Investment made with 100% own capital

 

·                  Third party mine operation

 

·                  Processing plant operated by Yamana

 

·                  Discount rate of 5% in real terms per year

 

·                  Interest on equity equal to 10% per year (annual “Selic” rate of the Brazil Central Bank)

 

·                  Use of the following incentives: Special Regime for Acquisition of Capital Assets by Exporting Companies (RECAP) and drawback incentive for international supplies acquisition.

 

·                  Depreciation: according the present Brazilian legislation

 

·                  Income tax of 25% plus Social Contribution of 9% generating a total income tax of 34%

 

·                  Residual value composed by assets sells, tax credit recover of 70% for states taxes (the federal tax credits is recovered in the life project) and working capital return.

 

The following table shows the technical and economic parametres used in the study, as well the economic results for the phased development.

 

29



 

Figure 1.4: Economic and technical parametres

 

 

 

OXIDES

 

SULPHIDES

 

 

ITENS

 

Mton

 

Grade

 

Koz

 

Mton

 

Grade

 

Koz

 

GOLD RECOVERY INCREASE

INDICATED RESOURCE

 

19.3

 

0.48

 

298

 

132.1

 

0.5

 

2.127

 

 

INFERRED RESOURCE

 

3.8

 

0.39

 

48

 

5.4

 

0.39

 

68

 

MARACÁ PLANT

MINERAL RESERVES

 

16.3

 

0.510

 

268

 

44.1

 

0.553

 

784

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

METALLURGICAL RECOVERIES

 

85%

 

80%

 

10% - 2013 - 2017
20% - 2017 - 2029

GOLD RECOVERED

 

228 koz

 

626 koz

 

230

MINE THROUGHPUT

 

4.0 Mtpy

 

8.0 Mtpy

 

22.0 Mtpy

AVERAGE ANNUAL PRODUCTION

 

46 Koz

 

104 koz

 

14 koz

LIFE OF MINE (years)

 

5

 

6

 

17

MINING METHOD

 

HEAP LEACH

 

GRAVITY + FLOTATION+ CIL

 

GRAVITY+FLOTATION+CIL

CAPEX (Without working capital)

 

US$ 59 M

 

US$ 125 M (Phase 2)

 

US$ 39 M (Phase 1)

SUSTAINING CAPITAL (With closure and mine development)

 

US$ 12.4 M

 

US$ 74.2 M

 

 

PLANT OPEX

 

US$ 3.35/t

 

US$ 3.27/t

 

MINE OPEX

 

US$ 2.22/t

 

US$ 3.54/t

 

G&A and Other

 

US$ 0.44/t

 

US$ 0.22/t

 

TOTAL CASH COST

 

US$ 6.01/t

 

US$ 7.03/t

 

US$ 0.39/t

TOTAL CASH COST

 

US$ 431/oz

 

US$ 496/oz

 

US$ 584/oz

 

 

 

 

 

 

 

AVERAGE CASH COST 1

 

US$ 479/oz

 

 

AVERAGE CASH COST 2

 

US$ 501/oz

NET PRESENT VALUE (5%)

 

US$ 117 M

IRR

 

15.0%

EXCHANGE RATE

 

1 us$ = R$ 1.80

SELLING PRICE

 

US$ 1,300/oz in 2013 and US$ 1,100/oz onwards.

 

TOTAL GOLD PRODUCTION:

 

 

 

 

 

 

 

Koz Au

 

 

OXIDES SURUCA

 

228

 

 

SULPHIDES SURUCA

 

626

 

 

GOLD REC. INCREASE MARACÁ

 

230

 

 

TOTAL

 

1.084

 

 

 

The discount rate sensitivity analysis is present in the Table 1.12.

 

Table 1.12: Suruca Project Sensitivity NPV x Discount Rate

 

Sensitivity Analysis - NPV x Discount Rate to the Firm

 

Discount Rate

 

NPV

 

15,00

%

184.120

 

12,50

%

18.143.413

 

10,00

%

41.961.762

 

7,50

%

73.882.126

 

5,00

%

117.180.852

 

0,00

%

259.946.288

 

 

Table 1.13 and Table 1.14 present the sensitivity analysis for the 5% net present value (“NPV”) of the project and the internal rate of return (“IRR”) respectively, Figure 1.5 and Figure 1.6 show the results graphically. For example, a 10% price change impacts the projects NPV and after-tax IRR by approximately US$ 61.0 million (US$ 117.2 million — US$ 56.2 million) and 5.2% (15.0% - 9.8%) respectively.

 

30



 

Table 1.13 : Suruca Project NPV Sensitivity Analysis (discount rate 5% p.y.)

 

Net present value of the cash flow to the firm

 

 

 

 

 

Opex and

 

 

 

 

 

 

 

other

 

Capex and

 

 

 

Sale prices

 

expenses

 

sustaining

 

-30%

 

-77.862.067

 

205.247.285

 

168.795.289

 

-20%

 

-6.581.141

 

176.113.333

 

151.791.735

 

-10%

 

56.227.793

 

146.824.413

 

134.740.287

 

0%

 

117.180.852

 

117.180.852

 

117.180.852

 

10%

 

176.209.718

 

86.777.139

 

98.921.112

 

20%

 

234.333.135

 

56.226.025

 

80.756.360

 

30%

 

291.461.892

 

25.208.987

 

62.292.397

 

 

Figure 1.5: Suruca Project NPV Sensitivity Analysis

 

 

Table 1.14: Suruca Project IRR Sensitivity Analysis

 

IRR TO THE FIRM

 

 

 

 

 

Opex and

 

 

 

 

 

 

 

other

 

Capex and

 

 

 

Sale prices

 

expenses

 

sustaining

 

-30%

 

-1,2

%

22,1

%

25,0

%

-20%

 

4,4

%

19,9

%

21,0

%

-10%

 

9,8

%

17,5

%

17,7

%

0%

 

15,0

%

15,0

%

15,0

%

10%

 

19,9

%

12,5

%

12,7

%

20%

 

24,6

%

9,8

%

10,8

%

30%

 

29,1

%

7,1

%

9,2

%

 

31



 

Figure 1.6: Suruca IRR Sensitivity Analysis

 

 

According to this analysis, the Suruca Project is more sensitive to price, followed by operating expenditure (OPEX) variation, and then by capital expenditure (CAPEX) /sustaining

 

The worst scenario occurs when the price drops down 30% (average near US$ 777/oz) and when the IRR fall to — 1.2% p.y.

 

An increase of 30% in OPEX and CAPEX reduces the IRR for 7.1% p.y. and 9.2% p.y, respectively.

 

1.11.2              Integrated cashflow Chapada + Suruca

 

The cashflow Chapada Mine and Suruca Project is shown in Table 1.15.

 

32



 

Table 1.15: Chapada mine and Suruca Project Cash Flow

 

ID

 

Description

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Net Profit

 

63.648

 

50.441

 

155.057

 

72.069

 

24.821

 

34.004

 

10.059

 

-29.230

 

3.579

 

22.864

 

6.203

 

11.107

 

-23.048

 

-20.757

 

-21.717

 

-20.061

 

641

 

-15.881

 

-15.198

 

-75.083

 

-11.452

 

-11.452

 

210.613

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Interest on Equity

 

 

 

3.652

 

12.110

 

20.940

 

10.205

 

10.411

 

16.660

 

12.927

 

 

 

1.565

 

608

 

856

 

302

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

90.237

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Depreciation & Amortization

 

24.288

 

30.881

 

41.095

 

53.331

 

57.295

 

66.482

 

76.156

 

75.103

 

69.088

 

69.695

 

41.910

 

37.367

 

29.195

 

25.937

 

23.430

 

18.309

 

7.336

 

6.636

 

4.207

 

2.310

 

 

 

 

 

760.049

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

Investments

 

-35.985

 

-80.572

 

-85.308

 

-22.059

 

-68.306

 

-130.513

 

-23.799

 

-15.364

 

-30.230

 

-8.551

 

-8.294

 

-2.899

 

-10.279

 

-1.216

 

-1.326

 

-1.417

 

-1.326

 

-1.326

 

-548

 

 

 

 

 

 

 

-529.318

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1

 

Capex

 

 

 

-28.819

 

-67.245

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-96.065

 

4.2

 

Sustaining

 

-35.985

 

-51.752

 

-18.063

 

-22.059

 

-68.306

 

-130.513

 

-23.799

 

-15.364

 

-30.230

 

-8.551

 

-8.294

 

-2.899

 

-10.279

 

-1.216

 

-1.326

 

-1.417

 

-1.326

 

-1.326

 

-548

 

 

 

 

 

 

 

-433.253

 

4.3

 

Initial Working Capital

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

Working Capital Variations

 

-3.310

 

18.384

 

22.965

 

19.731

 

20.662

 

-4.842

 

7.976

 

13.472

 

-5.047

 

-6.687

 

18.778

 

4.211

 

16.649

 

639

 

1.040

 

1.609

 

-2.609

 

4.837

 

8.031

 

39.077

 

-5.040

 

 

 

170.525

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.

 

Tax balance

 

-1.155

 

-6.299

 

-4.848

 

-3.930

 

-5.582

 

-7.316

 

-3.244

 

-5.910

 

-6.644

 

-5.492

 

-5.076

 

-3.639

 

2.544

 

2.683

 

2.698

 

2.685

 

2.706

 

2.706

 

5.331

 

26.448

 

 

 

 

 

-11.334

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.1

 

Capex/Long Term Tax Balance

 

-538

 

-4.005

 

-2.993

 

-127

 

-3.013

 

-7.368

 

-560

 

-642

 

-1.325

 

-317

 

-264

 

-125

 

-140

 

-59

 

-25

 

-37

 

-36

 

-36

 

-36

 

15.153

 

 

 

 

 

-6.494

 

6.2

 

Opex/Short Term Tax Balance

 

-617

 

-2.294

 

-1.855

 

-3.803

 

-2.569

 

52

 

-2.683

 

-5.268

 

-5.319

 

-5.175

 

-4.812

 

-3.514

 

2.684

 

2.742

 

2.722

 

2.722

 

2.742

 

2.742

 

5.367

 

11.295

 

 

 

 

 

-4.841

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

 

Project Residual Value

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

52.073

 

 

 

 

 

52.073

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash Flow (c)

 

47.485

 

16.488

 

141.070

 

140.082

 

39.095

 

-31.774

 

83.809

 

50.998

 

30.745

 

73.395

 

54.128

 

47.002

 

15.363

 

7.286

 

4.124

 

1.126

 

6.748

 

-3.029

 

1.822

 

44.824

 

-16.492

 

-11.452

 

742.845

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net Present Value:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Interest Rate (%

 

US$ 000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15,0%

 

383.852

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12,5%

 

418.795

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10,0%

 

460.459

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7,5%

 

510.699

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5,0%

 

572.016

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Zero

 

742.845

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Payaback Calculation:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Discount Rate:

 

5,0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Years count starting zero

 

 

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

19

 

20

 

21

 

 

 

 

 

· Years count based on operation

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

19

 

20

 

21

 

22

 

 

 

 

 

· Discounted Cash Flow (zero base)

 

47.485

 

15.703

 

127.955

 

121.008

 

32.163

 

-24.896

 

62.539

 

36.243

 

20.809

 

47.311

 

33.230

 

27.481

 

8.555

 

3.864

 

2.083

 

542

 

3.092

 

-1.322

 

757

 

17.739

 

-6.216

 

-4.111

 

 

 

 

 

· Accumulated Discounted C.F.

 

47.485

 

63.189

 

191.144

 

312.151

 

344.315

 

319.419

 

381.958

 

418.202

 

439.011

 

486.322

 

519.552

 

547.033

 

555.588

 

559.452

 

561.535

 

562.077

 

565.168

 

563.847

 

564.604

 

582.342

 

576.127

 

572.016

 

 

 

 

Description

 

Factors

 

Units

 

Gold Price

 

1.100

 

US$/oz

 

Copper Price

 

2.50

 

US$/lb

 

Operating Costs

 

8.91

 

US$/t

 

Mining Costs (ore + Waste)

 

2.88

 

US$/t

 

Process Plant Costs

 

4.90

 

US$/t

 

Other Cash Costs

 

1.13

 

US$/t

 

Capital Cost

 

111,91

 

US$/oz

 

Mine Operational Capex

 

4,27

 

US$/oz

 

Plant Capex

 

107,65

 

US$/oz

 

Sustaining Operational

 

41,46

 

US$/oz

 

Reclamation & Closure

 

25,28

 

US$/oz

 

 

33



 

1.12              Conclusions and Recommendations

 

Based on profitable economic results of the Suruca Project, assuming a discount rate of 5% the Suruca Project has net present value (NPV) is US$ 117 million, it is recommended that the feasibility study including basic engineering be carried on.

 

The feasibility study will be split into oxides and sulphide studies, in order to simplify the permitting process and accelerate the oxides heap leaching implementation.

 

It is recommended that exploration drilling Projected to extend the deposit south be continued and that the in pit inferred resources be upgraded to increase mineral reserves.

 

34



 

2                      INTRODUCTION

 

Yamana and its wholly-owned subsidiary Mineração Maracá Industria e Comércio S.A. requested the preparation of this technical report concerning the Suruca Project in Goias State, Brazil.

 

The purpose of this technical report is to present the results of the pre-feasibility study regarding geology, mineral resources and mineral reserves, life-of-mine plan, metallurgy, processing plant and economic analysis and update mineral resources and mineral reserves at the Chapada Project.

 

Greg Walker, P.Geo., Senior Manager, Resources Estimation of Yamana is the qualified person for mineral resources at Suruca Project, Emerson Ricardo Re, MAusIMM, Resource and Reserves Corporative Manager of Yamana is the qualified person for mineral resources at Chapada mine, Sergio Brandão, P. Geo. of Yamana is the qualified person for Exploration and QA/QC, Raúl Contreras, Senior Engineer of Metálica Consultores S.A. is the qualified person for mineral reserves, Homero Delboni, Jr., Senior Consultant of HDA Serviços S/S Ltda, Ph.D. in Mineral Processing Engineering is the qualified person for processing plant.

 

Tabela 2.1: Responsibilities of each chapter

 

Author

 

Responsible for section/s

Sergio Brandão Silva

 

3: Property description and location; 4: Accessibility, climate, local resource, infrastructure and physiography; 5: History; 6: Geological setting; 7: Deposit types; 8: Mineralization; 9: Exploration; 10: Drilling; 11: Sampling methods and approach; 12: Sample preparation, analyses and security; 13: Data verification

Greg Walker

 

16.1: Suruca Mineral resource estimate

Emerson Ricardo Ré

 

16.1: Chapada Mineral resource estimate

Raúl Contreras G.

 

16.2: Mineral reserve estimate; 21.1: Mining operations

Homero Delboni Jr

 

15. Metallurgical testing and Mineral processing

Renato Petter

 

1: Executive Summary, 2: Introduction, 14:Adjacent Propoerties, 17: Other relevant data and Informartion, 18: Interpretations and Conclusions, 19: Recommendations, 21.2: Recoverabillity, 21.3: Production Scheduling Integrated, 21.4: Contracts, 21.5: Environmental, 21.6: Financial Analysis

 

This report is in metric units. Tonnes mean metric tonnes and ktonnes denotes 1000 metric tonnes. Metal grades of gold are in grams per metric tonne. Koz is an abbreviation for 1000 troy ounces since gold prices are quoted in troy ounces on world markets.  Copper metal is reported in US pounds since prices are commonly quoted in those terms. Mlbs is an abbreviation for 1 million US pounds of copper.

 

35



 

3                      PROPERTY DESCRIPTION AND LOCATION

 

The Suruca Project is located in the Alto Horizonte municipality in the state of Goias, Brazil, at approximately 14º 11’ 44” S, 49º 20’ 19”W and 375m of altitude.

 

Figure 3.1:General Area Map

 

GRAPHIC

 

36



 

Figure 3.2: Project Location Map

 

GRAPHIC

 

3.1                     Land Claims

 

The Chapada Project is divided into 16 claims totalling 18,921.37 ha. The details of the property claims are shown in Figure 3.3 and Figure 3.4. The project claims are held in the name of Mineração Maraca Indústria e Comércio S/A. In Brazil, property boundaries are filed electronically with the Departamento Nacional de Produção Mineral (DNPM), rather than physically marked.

 

The Suruca Open Pit will be inserted into the following claims: 860.708/2009 and 860.595/2009, totalling 845.75ha. Figure 3.4 shows the concession boundaries.

 

37



 

Figure 3.3: Chapada Project exploration claim outlines and roads

 

 

Figure 3.4: Mining and Exploration Concessions

 

 

38



 

Table 3.1: Mineral tenure status

 

DMPM 
Process N
o

 

City -
State

 

Area(hectares)
Exploration
Claim

 

DNPM
Exploration
Permit N.
o

 

Permit
Grating DOU
(3 Years)

 

Renewal
Appication

 

Renewal
Approval

 

New
Renewal
Application

 

Final
Report
Submission

 

Final
Report
Aproval

 

Application
for Mining
Concession

 

N.o Mining
Concession

 

Grantting
of mining
Concession
(DOU)

 

Status

808.923/1974

 

Alto Horizonte

 

3,000.00

 

316

 

8/3/1976

 

23/6/1976

 

1/8/1978

 

****

 

****

 

30/7/1979

 

18/10/1979

 

2394

 

11/12/1979

 

Mining Concession

860.931/1994

 

Alto Horizonte

 

571.78

 

1510

 

29/7/1987

 

****

 

****

 

****

 

****

 

27/7/2000

 

17/10/2001

 

351

 

26/10/2009

 

Mining Concession

860.158/1994

 

Alto Horizonte

 

967.70

 

9370

 

10/10/2006

 

6/8/2009 (3 years)

 

19/11/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.273/2003

 

Alto Horizonte

 

978.91

 

2620

 

23/4/2003

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.239/2007

 

Alto Horizonte

 

1,917.31

 

3016

 

23/4/2007

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.854/2007

 

Alto Horizonte

 

1,405.96

 

3702

 

13/5/2008

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.240/2007

 

Alto Horizonte

 

1,528.98

 

3742

 

9/5/2007

 

4/3/2010 (3 years)

 

29/6/2010

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.255/2007

 

Alto Horizonte

 

1,974.16

 

3018

 

23/4/2007

 

19/2/2010 (3 years)

 

****

 

19/2/2010

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.093/2009

 

Alto Horizonte

 

400.00

 

11193

 

16/9/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.595/2009

 

Alto Horizonte

 

516.25

 

7686

 

14/7/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.708/2009

 

Alto Horizonte

 

329.50

 

7687

 

14/7/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.074/2009

 

Alto Horizonte

 

1,959.50

 

11186

 

16/9/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.075/2009

 

Alto Horizonte

 

631.97

 

11187

 

16/9/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

860.177/2009

 

Alto Horizonte

 

999.23

 

13795

 

30/11/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.078/2009

 

Alto Horizonte

 

1,740.12

 

11188

 

16/9/2009

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

861.088/2004

 

Alto Horizonte

 

1,998,29

 

329

 

11/1/2005

 

6/11/2007 (3 years)

 

9/7/2008

 

****

 

****

 

****

 

****

 

****

 

****

 

Exploration Permit

 

39



 

Under the Brazilian Mining Code of 1967, activities may be allowed according to three types of licenses:

 

·                  Applications for prospecting

 

·                  Exploration permits

 

·                  Mining concessions

 

The exploration leases held at the Suruca Project are covered by exploration permits granted by the DNPM. The exploration permits covering a maximum area of 2,000 ha for gold properties may be initially granted for three years, renewable for no longer than an additional three years. An annual tax based on the size of the area and the term of the license must be paid to maintain the exploration lease in good standing. At the end of the three year period, the license holder must submit a report to the DNPM detailing the results of all exploration activities and a preliminary assessment of the economic and technical viability of any deposits found. The license holder may then apply to the DNPM for a mining concession within a one year time frame, along with the required environmental licenses.

 

Yamana has stated that no environmental permits are required at this stage of permitting.

 

Chapada permit

 

A substantial amount of environmental study, analysis and regulatory review was made for the Chapada Project.  In November, 1996, Geomina Consultants, from Goiânia, State of Goiás, Brazil, developed an Environmental Impact Study. This report was used for public comment and as support for application for permits. Yamana obtained the three environmental permits required for mine operations in Brazil: 1) the first environmental license (LP) was issued in December 1999; 2) the construction license (LI) was issued in April 2001 and it was renewed twice in April 2003 and April 2006; and 3) the operation license was published in November 2006, and it is valid until April 2008. The operation of the Chapada Project started up in November 2006.

 

On December 2007, Chapada Project submitted to the State of Goiás Environmental Agency all necessary documents to obtain the operational environmental license renewal. The license renewal was issued in September 2009 and is valid until March 2011.

 

The Chapada mine posseses all the licenses (operation, deforest, water use permit, etc) needed to operate.

 

3.2          Exploration and mining activities by “garimpeiro”

 

The Suruca small miners old works (“Garimpo”) are located about 3 Km to east of Alto Horizonte. It is characterized by an elongated excavation, N30oE with 600m, average width of 50m and 10m average depth (locally reached 18m). According verbal information of miners who worked there in the 1980’s about 200 kg of gold was mined. Currently the “garimpo” is disabled.

 

40



 

4                      ACCESSIBILITY, CLIMATE, LOCAL RESOURCE, INFRASTRUCTURE AND PHYSIOGRAPHY

 

4.1                     Accessibility

 

The Suruca Project e Chapada mine property are located in the northern part of Goiás State, approximately 320 kilometres north of the state capital Goiania and 270 kilometres northwest of the national capital of Brasilia.

 

Access to the Project from Brasilia is along BR-153 (Belem/Brasilia) up to Campinorte (GO) and then GO-465 (Campinorte/Santa Terezinha) in the west direction to Alto Horizonte. Close to Alto Horizonte there is one airstrip 800 metres long (Chapada Airport), which can be used by small aircraft. Figure 3.1 shows the location of the projects within Brazil and Figure 3.2 shows the location of the project within the region.

 

4.2                     Topography, elevation, vegetation and physiography

 

The average elevation of the project is approximately 300 metres above sea level. The topography is characterized by low rolling hills, with large contiguous flat areas. The sites chosen for waste disposal, the plant, and other ancillary facilities are suitable for the current operation.

 

The vegetation there is referred to as Cerrado, a tropical savannah eco-region which comprises a diverse variety of low tropical trees, shrubs, and native grasses, most of which have been cleared and serves as cattle grazing land owned by local landowners.

 

The main river is Rio dos Bois and there are four small creeks called Mutuzinho, Goncalves, Seriema and Suruca. A lateritic mantle related to the peneplain is common in the region and is 5 to 30 metres thick.

 

4.3                     Climate and Precipitation

 

The region has a tropical climate characterized by two well defined seasons.The rainy season from November to March and the dry season from April up to October with an annual average rainfall of 1500mm. The average annual temperature is about 22°C. Exploration activities are usually not interrupted by climatic conditions, except when there are brief electrical storms.

 

4.4                     Local Resources and Infrastructure

 

Local economic activity is mainly agro-pastoral but there are some small scale mining activities related to gold in alluvium and quartz veins, and for clay used to make bricks.

 

The most important towns in the region are Uruaçu, Campinorte, Porangatu and Mara Rosa. All of them have good infrastructure to support field activities. The town of Alto Horizonte is located only 3 km west of the Suruca Project.

 

The municipality of Alto Horizonte has a population of 3,116habitants and the nearby towns (within 50 km) as Campinorte has 9,697 habitants, Mara Rosa 10,409 habitants and Uruaçu

 

41



 

33,382 habitants (Source IBGE 2007). These cities could provide key resources for manpower, schools, housing, health services, communications and other resources that may be necessary for the project.

 

5                      HISTORY

 

5.1                     Chapada

 

The Chapada Project´s deposit was discovered during 1973 by the Canadian company, INCO Ltda. (“INCO”) followed up with geochemical, geophysical, trenching, and initial drilling.  The sequence of project ownership and exploration is summarized below.

 

1975-1976

 

INCO completes a 2000m x 500m grid drilling program. Parsons-Eluma Projetos e Consultoria S/C, a Brazilian copper company acquires a 50% interest in the project.

 

 

 

1976-1979

 

INCO and Parsons-Eluma completes 200m x 100m drill grid. A 92m deep shaft is completed with 255m of crosscuts for exploration and metallurgical sampling.

 

 

 

1979-1979

 

Mining concession Number 2394 covering 3,000 hectares is issued to Mineracao Alonte by the Departamento Nacional da Producao Mineral.

 

 

 

1980-1981

 

Soil drilling was completed in the future plant, tailing ponds, and potential water dam areas.

 

 

 

1981

 

Feasibility study completed by Parsons-Eluma.

 

 

 

1994-1995

 

A 4500m drilling program re-evaluates a near surface gold deposit. A preliminary feasibility study was completed by Watts, Griffis and McQuat.

 

 

 

May 1994

 

Mineração Santa Elina Industria e Comercio S/A acquires the Chapada deposit through a subsidiary Mineracao Maraca.

 

 

 

July 1994

 

Echo Bay acquires an initial interest in Santa Elina by purchasing 5% of the outstanding shares from Sercor.

 

 

 

Dec 1994

 

Santa Elina completes its initial public offering.

 

 

 

Sep 1995

 

Santa Elina and Echo Bay approve the Chapada Project joint venture. Santa Elina issues about 3% of the outstanding shares to Echo Bay. Echo Bay receives the option to acquire 50% interest in the project.

 

 

 

May 1996

 

Santa Elina is privatized and Sercor and Echo Bay become equal owners of the company.

 

 

 

Dec 1996

 

Santa Elina completes an in-fill drilling program

 

 

 

Dec 1997

 

Independent Mining Consultants, Inc. reviews the Echo Bay model and completes a mine feasibility study.

 

42



 

Jan 1998

 

Kilborn Holdings Inc., now SNC-Lavalin Group Inc., completes the Chapada Project Bankable Feasibility Study (the 1997 study referenced in this document).

 

 

 

Nov 1999

 

The initial environmental license was issued (LP)

 

 

 

Apr 2001

 

The construction license was issued .

 

 

 

May 2000

 

PINUS acquires 100% of Mineracao Maraca.

 

 

 

2003

 

The project was acquired by Yamana.

 

 

 

2004

 

Yamana engaged Hatch Limited, Independent Mining Consultants, Inc. and other consultants to progress various aspects of the feasibility of developing the property. The study was completed in August 2004

 

 

 

2004

 

Yamana secured $100 million in debt financing for the construction of the Chapada Project in October. A formal construction decision was made in December.

 

 

 

2005

 

Plant construction and mine waste stripping commence.

 

 

 

2006

 

Construction completed during the fourth quarter of 2006 with concentrate production in November.

 

 

 

2007

 

Commercial production declared on February 11, 2007.

 

 

 

2007

 

Yamana re-started exploration program with 9 holes/1924 metres of diamond drill holes in east Chapada deposit for check extension mineralization intercepted for old drill executed in 1996 by joint venture Santa Elina-Echo Bay and for test easter sinclinal using model of mineralization associate volcanogenic massive sulphide.

 

 

 

2008

 

Yamana commenced work on the mine expansion at Chapada mine initially to increase production from 16 Mtpy to 20 Mtpy and subsequently to 24 Mtpy.

 

 

 

2010

 

Yamana developed exploration drill holes on the south west area of the main pit and infill hole to support mineral resource reclassification. No resource estimation was developed using the new set of drilling.

 

5.2                     Suruca

 

The Suruca Project has been explored by different companies since the 1970’s and in the 1980’s was exploited by garimpeiros. See below the summary activities:

 

·                  Suruca was worked by several companies : Inco/Eluma (1980 to 1981), Cominco (1987 to 1988), WMC (1993 to 1994) and Santa Elina/Echo Bay (1996 to 1997);

 

·                  1980’s exploited by “Garimpeiros”;

 

·                  In 2008 Yamana began exploration work with geological mapping, chip sampling and shallow drilling (Suruca South);

 

·                  In 2009 Yamana completed further drilling in a magnetic anomaly and the Suruca Garimpo with positive results.

 

43



 

6                      GEOLOGICAL SETTING

 

6.1                     Regional Geology

 

The geological setting of Suruca Project comprises tonalitic/dioritic orthogneisses and narrow NNE-striking metavolcano-sedimentary belts so called Mara Rosa Magmatic Arc (Figure 7.1). The crystallization of plutonic rocks showed Neoproterozoic age with two main stages: the older between 890 and 790 Ma and the younger at 670—600 Ma. The Brasiliano event (630-550 Ma) was responsible for the deformation and metamorphism in greenschist to amphibolite-facies conditions.

 

In the Chapada—Mara Rosa area, the medium to coarse-grained metaplutonic rocks of dioritic to tonalitic composition rocks locally show well-preserved plutonic textures such enclaves and porphyritic textures. They are geochemically very primitive, with SiO2 contents lower than 60%, and a calcic to calc-alkaline character,characterized by low Rb, Nb, Y, Zr and REE contents.They are regarded as similar to M-type granitoids of immature island arcs.U—Pb isotopic data have demonstrated, however, that the tonalitic and associated mafic magmatism took place in two distinct time intervals: the older, between 884 and 807 Ma, and the younger, and apparently more voluminous stage, between ca. 640 and 622 Ma. Nd isotopic data indicate the very primitive nature of the original magma, with TDM model ages mostly between 0.9 and 1.1 Ga and eNd(T) values between + 3.0 and + 4.6.

 

The supracrustal rocks form three individual NNE-striking belts, known as the eastern, central and western belts. These belts are separated by orthogneiss (Figure 6.1).The three belts are composed of metabasalts, intermediate and felsic metatuffs, finegrained metagraywackes, garnet—mica schists, metacherts, iron formations, quartzites and metaultramafic rocks. U—Pb zircon data for small elongated bodies of mylonitic granites in the Posse Gold Mine yield a crystallization age of 862 Ma. Titanites from the same sample yield a metamorphic age of 632 Ma that represent the peak of metamorphism.

 

Amphibolites of the volcano-sedimentary sequence are either tholeiitic, rich in Mg, Ni and Cr and similar to boninites, or are calc-alkaline. The amphibolites represent fragments of oceanic crust and the latter are related to arc magmatism. These amphibolites are chemically similar to modern-arc tholeiites and are interpreted as having originated in a back-arc setting.

 

Metasedimentary rocks represented by feldspathic garnet—mica schists and fine-grained biotite gneissesare abundant in the supracrustal belts, especially in the western belt. The Sm—Nd isotopic compositions ofthese rocks give TDM model ages mostly in the range between 0.9 and 1.2 Ga. This indicates that they are the product of erosion of the arc rocks, with little contribution from older sources. The placement of the original sediments must have taken place far from any old continental source area and probably happened in an intraoceanic setting.

 

44



 

Figure 6.1: Geological Map of Chapada- Suruca region

 

GRAPHIC

 

The last magmatic event is represent by tardi to pos - tectonic granitic (e.g., the Faina, Angelim, Estrela and Amador granites) as well as gabbro—dioritic bodies (eg, Diorite close to Chapada). The granite bodies include mainly biotite granites and two mica leucogranites, with local granodioritic facies.The mafic intrusions are dioritic and, to a lesser extent, gabbroic in composition and very commonly display magma mixing structures. The Precambrian geological evolution of the Mara Rosa arc ended, therefore, with an important bimodal magmatic event,

 

45



 

which has been interpreted to be associated with final uplift and collapse of the Brasiliano Orogen.

 

6.2                     Local Geology

 

In the context of Mara Rosa volcano sedimentary sequence the Chapada mine and Suruca Project deposit are inserted in Eastern Belt. Arantes (1991) defined the Eastern Belt in the Mara Rosa region composed by metavolcanic and metasedimentary rocks divided from bottom to top into four units:

 

Amaro Leite Unit: represented by a thick package of metasediments, predominantly metagraywackes interlayered with mafic tuffs;

 

Araras Unit: dominantly composed of mafic to intermediate metatuffs with subordinate intercalations of metagraywackes, felsic metavulcanics and cherts, the thickness of this Unit reaches 1300 metres;

 

Posse Unit: composed predominantly of metatuffs metalapilli-tuffs and rhyolite composition exhibiting gneissic texture. This unit has about 400 metres thick;

 

Carambolas Unit: consists of a sequence of mafic metavolcanic and metatuffs interlayered with intermediate metavulcanics rocks, and the package has a thickness of about 1200 metres.

 

The Eastern Belt in Chapada-Suruca region comprises a thick package of amphibolites succeeded by volcanic and vulcanoclastic rocks and on the top metasedimentary rocks. The metavulcano-sedimentary are intruded by metaplutonic rocks of dioritic to quartz-diorite composition (can be related to M-type granitoids of immature island arcs). These intrusions are associated to magmatic fluids responsible for Cu — Au and Au mineralization was also formed by the hydrothermal alteration. Tardi-tectonic body is represented by unmineralized and little-deformed diorite porphyry in SE of Chapada pit. Pos-tectonic granites are represented by pegmatites that are exclusive of Chapada mine.

 

U-Pb data provided age of 884.9±9.4 Ma for kyanite-epidote-muscovite-biotite feldspathic schist, which represents the crystallization age of volcanic rocks, considered the protolith of association metavolcanosedimentary rocks, and an age of 864.9±5.6 Ma for biotite gneiss, corresponding to the age of crystallization of igneous protolith.

 

The Cu-Au deposit at the Chapada mine comprised of products of hydrothermal alteration of Cu- Au porphyry system, these alteration are: biotitization (potassification) represented by biotite schist (BFS), biotite microcline bearing gneiss (GNS);sericitization represented by pyrite-quartz-sericite schist (SQS); advanced argillic alteration represented by kyanite bearing schists (SKQS) and kyanite quartzite (SQZT);and rocks products of propylitic alteration such epidote-rich rock (epidosite),besides unaltered rocks represented by amphibolites with calc-alkaline affinity, volcanoclastic represented by metatuffs and lapilli tuffs and metasedimentary rocks represented by garnet biotite schist, staurolite sillimanite biotite schist muscovite schists, biotite muscovite schist and metagraywacke (Figure 7.2).

 

46



 

Figure 6.2: Geological map of Chapada - Suruca region with the localization of Chapada pit and Suruca designed pit (based on Suruca resource data)

 

GRAPHIC

 

6.3                     Property Geology

 

The Suruca Project (Figure 6.3) was grouped from the base to the top as: Amphibolite (“ANF”), Intermediate Metavolcanic rocks (“MVI”) and Metassediments (“MTS”), there are several intrusions of Quartz Diorite porphyry (“QDP”) that occur preferentially in the intermediate metavolcanic rocks (“MVI”) and Metassediments (“MTS”).The hydrothermal alteration overprints the lithologiesand is characterized by inner and outer halos: i) Inner halo occurs in the intermediate rocks, metassediments and diorites with strong and pervasive sericitic alteration (MVA); ii) outer halo is characterized by propylitic halo that occurs mainly in the amphibolites.

 

47



 

Figure 6.3: Geological Map of Suruca Project

 

GRAPHIC

 

The stratigraphy of the Suruca Project and Chapada mine region is comparable with the Carambolas Unit in the Mara Rosa region, except in Suruca Project region, where the top of the stratigraphy has a thick layer of metasediments and in Chapada mine tuffs and lapilli tuffs occur (Figure 6.4).

 

All these rocks are covered by thick (average of 30m) lateritic profile. The lateritic profile is represented by a typical immature lateric terrain that was subdivided to base to the top in: coarse saprolite, saprolite, mottled zone or argillic zone, lateritic duricrust and pisolitic soils (products of alteration of duricrust).

 

The lithology units of Suruca Project are characterized as follows: Amphibolites (“ANF”),Intermediate Metavulcanics (“MVI”), Metasedimentary (‘MTS”),Quartz porphyry Diorite (“QDP”) and altered Metavulcanics (“MVA”).

 

48



 

Figure 6.4: Stratigraphic correlation

 

GRAPHIC

 

Amphibolites (“ANF”): The amphibolites represent metavolcanic mafic rocks characterized by the following lithological terms: amphibolite; garnet-amphibolite, quartz Amphibolite. Propylitic alteration changesthe composition of this rock to epidote-amphibolite, hornblende quartz epidosite.They are presented with fine to medium-grained, greenish and often with a gneissic banded and/or nematoblastic texture.

 

Intermediate Metavulcanic (“MVI”): Intermediate metavolcanic is characterized by amphibole-biotite gnaisse, amphibole-sericite-biotite schist, muscovite-epidote-biotite schist, garnet-epidote-quartz-muscovite-biotite schist. In general this unit is associated with propylitic halo that generate a pervasive cloritization and epidotizaition, when showing strong sericitization.

 

Metassedimentary (“MTS”): Metassediments rocks are characterized by garnet-biotite schist or garnet-biotite-epidote-muscovite-quartz schist. These rocks were possibly as pelitic or psamo-pelitic rocks. This unit can be overprinting by sericite or propylitic hydrothermal halo.

 

Quarzt Diorite porphyry (“QDP”): Characterized by intrusive quartz diorite porphyry, can occur with isotropic or sheared texture.The quartzdiorite sheared lost the igneous features and is represented by mylonitc schist with strong sericitization and sulphides. The isotropic quartz diorite is generally related to propylitic alteration.

 

Altered Metavulcanics (“MVA”): Altered Metavolcanic rocks are characterized by carbonate-muscovite-chlorite schist, plagioclase-biotite-quartz schist, carbonate-epidote-muscovite-quartz schist, epidote-quartz-muscovite schist, carbonate-biotite-epidote-quartz-muscovite schist, albite-muscovite-quartz-carbonate-epidote schist. All this schist presents a high contents of sulphides represented by pyrite, galena, sphalerite, chalacopyrite. This unit is product of sericitic hydrothermal alteration from MVI or QDP.

 

49



 

6.4                     Structural

 

The Goias Magmatic Arc has two main tectonic features (Figure 6.5):(i) large-scale high-angle thrust to reverseshear zones (Rio dos Bois Fault), developed during the Brasiliano Orogeny and separating the Neoproterozoic sequence from the Archaean granite—greenstone terrains of the Crixa´s—Hidrolina area in the south and from the Mesoproterozoic Serra da Mesa metasedimentary sequence in the east; (ii) extensive NNE-trending, vertical dextral strike—slip shear zones Transbrasiliano lineaments.

 

The Chapada mine and Suruca Project are included throughout the deformational Rio dos Bois System Faults, associated with formation of the Magmatic Arc Brasiliano orogenic cycle. The observed deformations in the field were ranked in four phases, following deformities criteria such as penetrate of the foliation, deformation regime, metamorphic facies and structures developed for each event associated referred to as D1, D2, D3 and D4 that are summarized in Table 6.1 and illustrated in Figure 6.5.

 

The D1 deformation phase is characterized by ductile deformation, compressive and progressive, in medium to high amphibolite facies, which generated intrafoliation isoclinal F1 folds, recumbent, eventually transposed generating boudins. The foliation is penetrative in the direction of N40°E to N50°E, dipping low to moderate angle (15° to 30°) to NW, with fold axis bending (Lb1) to N40-50°E and which often show thinning of the flanks and thickening of the hinge.

 

The stage D2 is coaxial and progressive to D1 and is characterized by the foliation S2 with direction N20-30°E and dip with moderateangle (40° to 50°) to the NW.The F2 folds are asymmetric with axis (LB2) direction N-15°-25°E. Retrometamorphism occurred at this stage at greenschist facies.

 

Phase D3 is characterized by brittle-ductile deformation, with the Lb3 axis directed N45°W, marked by open folds and spaced fracture cleavage (S3). The interference with the D3-D1//D2 generated a pattern of dome-basin, generating a double dip of LB1 and LB2to NE or SW.

 

Phase D4 is represented by a brittle-ductile tensional tectonics, which are generated oblique and normal faults with reactivation of lineaments (mostly in N-S or E-W direction), which may be filled by quartz, carbonates and epidote (Copy+Py). In this phase, only stretch lineations (L4) and discrete foliation along the faults (S4) are generated.

 

50



 

Table 6.1: Events and structural features of Brasiliano deformation in the property area

 

Event

 

Phases

 

Foliation(S)

 

Lineation
(L)

 

Folds (F)

 

Metamorphism

 

 

 

D1

 

S1

 

Lb1

 

F1

 

Amphibolite

 

Brasiliano
(Neoproterozoic)

 

D2

 

Sm; S2

 

Lx;Lb2

 

F2

 

Greenschist

 

 

D3

 

S3

 

Lb3 -

 

F3

 

Low Green schist

 

 

 

D4

 

S4

 

L4

 

 

 

 

 

 

Figure 6.5: Sketch of structural geology in Chapada - Suruca region

 

GRAPHIC

 

7                      DEPOSIT TYPES

 

The mineralization in the Chapada mine is currently interpreted as a porphyry and epithermal system associated with an island arc stage (864 Ma) overprinted by remobilization of orogenic fluids during Brasiliano events (630 — 580Ma) (Silitoe, 2008 and Espada, 2010 — Internal report).The porphyry and epithermal system can be separated into three distinct mineralizations, based on the style of hydrothermal alteration,and metal association: i) Cu-Au porphyry system represented by Chapada Mine; ii) Au High Sulphidation represented by HS (Hidrotermalito) Project; and iii) Au (Ag-Pb-Zn) Intermediate Sulphidation represented by Suruca Project (Figure 7.1).

 

51



 

Figure 7.1: Sketch of Chapada system (Silitoe, 2008)

 

GRAPHIC

 

7.1                     Cu-Au porphyry system

 

The Chapada orebody is a typical system prior to extensive modification during the D1 deformation event. The characteristics of the copper-gold porphyry mineralization are:

 

·                  Association copper, gold and molybdenum;

 

·                  Transposed remnants of A-type quartz, D-type sericite-bordered pyrite and anhydrite veinlets are still recognizable in the biotite-rich gneiss and schist, which is interpreted as a former zone of biotitic alteration;

 

·                  The best copper and gold values are found in biotite-rich metamorphic rocks containing disseminated chalcopyrite and magnetite, but little pyrite: a typical situation in porphyry copper-gold deposits;

 

·                  The hydrothermal alteration of potassic (biotitite), sericitic, propylitic and argillic fit with the alteration of younger Cu-Au system.

 

The biotite-plagioclase gneiss (“GNS”) biotite schist (“BFS”, Figure 7.2) hosts most of the copper-gold ore and with the lower-grade mineralization are believed to correspond to a standard biotitic alteration zone prior to the intense contractional deformation under amphibolite facies metamorphic conditions. Granular A-type quartz veinlets with magnetite and chalcopyrite characterize biotitic alteration zones and, notwithstanding the intense deformation, are still identifiable in the biotite-rich gneiss and schist at Chapada.

 

The upper parts of biotite alteration zones are commonly overprinted by sericitic alteration, either as a stockwork of D-type veinlets or in more pervasive form the transposed muscovite veinlets are thought to represent a D-type event, whereas the sericitequartz schist (“SQS”) in the southern part of the pit is considered as a former sericitic zone (Figure 7.2).

 

52



 

Figure 7.2: Location of Chapada Mine (Cu-Au), Suruca Project (Au-Ag+/-Zn) and Hidrotermalito (Au)

 

GRAPHIC

 

The quartz-muscovite-kyanite schist (“SQKS”) being a metamorphosed argillic alteration zone. The propylitic system is represented by the association of epidote+chlorite+carbonate in ANF and MVI rocks of Mara Rosa Sequence.

 

7.2                     Epithermal system

 

There are two other prospects adjacent to the Chapada mine with characteristics of epithermal deposits that may be similar to a copper-gold porphyry model. The first prospect is Suruca Project that has style of gold-zinc mineralization associated with sericite-chlorite-epidote-carbonate (-biotite) argillic to the propylitic alteration seen at Suruca could fit in the intermediate-sulphidation epithermal type (IS). The second prospect is Hidrotermalite Project that is an extensive belt of kyanite-muscovite-quartz rocks that occur approximately 4 km to the east of

 

53



 

the Chapada mine open pit. This belt can only be interpreted as the metamorphosed product of an advanced argillic (AA) lithocap.

 

The Lepanto-Vitoria in the Philippines is an example of this model of primary mineralization with copper-gold porphyry, intermediate sulphidation and high sulphidation is deposit of Au (Ag-Pb-Zn) Intermediate Sulphidation System.

 

The style of gold-zinc mineralization associated with sericite-chloritecarbonate (MVA, Figure 7.2) and propylitic alteration (ANF and MVI) propylitic seen at Suruca could fit in the intermediate-sulphidation epithermal type (IS). These types of epithermal deposits are generated distally from, but roughly at the same time as, porphyry systems. They result from more evolved, less corrosive fluids and/or more reactive mafic wall rocks that will buffer acid high-sulphidation fluids to produce sericite-illite-carbonates (notably manganese-bearing carbonates) argillic assemblages - going outwards into smectite-chlorite and epidote-chlorite - instead of the more acid advanced argillic alterations - alunite+/kaolinite+/-vuggy silica - seen where high-sulphidation fluids hit more felsic rocks. The characteristics of intermediate sulphidation mineralization are:

 

·                  IS deposits which typically contain base metals (Zn, Pb and Mn) together with gold and silver;

 

·                  The high manganese content (e.g. ~1000-1500 ppm in hole SU-11) broadly associated with the Suruca mineralization is also typical of IS systems and is likely due to former presence of rodocrosite or manganese-rich calcite in the pre-metamorphic alteration assemblage. High manganese is seen e.g. in holes and in thin sections;

 

·                  The distance of 4  kilometres between Chapada and Suruca is within the normal distance range between porphyry and genetically related IS systems;

 

·                  The presence of iron-poor sphalerite is typical of IS system.

 

7.3                     Au High Sulphidation system

 

The AA lithocap was presumably overlying the nearby Chapada Project´s copper-gold porphyry system in the pre-deformation geometry of the magmatic-hydrothermal system. The lithocap at Chapada mine hosts anomalous to ore-grade gold values associated with abundant sulphide boxwork and relict pyrite that, given its advanced argillic alteration, must therefore represent a high-sulphidation gold system (HS).

 

The alteration rocks are represented by aluminum- and K-rich kyanite-muscovite-quartz (SQKS, Figure 7.2) assemblages that must result from the metamorphism of clay+/-alunite rich alteration. The other are quartzite and kyanite quartzite (SQZT, Figure 7.2) that represented silicified hydrothermal breccias or as vuggy to massive silica, this host most of Au mineralization as well as the sulphides of high sulphidation state (covellite, enargite).

 

7.4                     Brasiliano Orogen Fluids

 

The disseminated, low grade character at the mineralization at the Chapada mine and Suruca Project is relatively unusual for porphyry and IS deposits, which tend to occur more frequently as vein systems or breccia pipes. We believe that the deformation, mainly D2 phase, was responsible for epigenetic hydrothermal processes, associated with Rio dos Bois shear zone at the end of the Brazilian Orogeny, between 600 and 560 Ma.

 

54



 

The epigenetic hydrothermal fluids are responsible for the remobilization of Au and base metals in both system (Chapada mine and Suruca Project). Chapada is characterizated by the transformation of magnetite-biotite gneiss to biotite schist (biotitization) and in Suruca the dissemination of the mineralization in propylitc halo that is not usual in IS system. In the HS system appears that the epigenetic fluids not remobilize metals due to the low reactivity of the silicified rocks.

 

8                      MINERALIZATION

 

8.1                     Chapada

 

The primary copper-gold mineralization at the Chapada mine is epigenetic. Copper is principally present as chalcopyrite with minor amounts of bornite.  Fine grained gold is closely associated with the sulphide mineralization and was likely contemporaneous with copper.

 

Copper mineralization occurs as finely disseminated crystals, elongated pods, lenses along foliation, crosscutting stringers, and coarse clots in occasional late stage quartz veins or pegmatites. The copper mineralization and grade are somewhat better in the Central Zone of the deposit along the anticline axis than in the surrounding anticlinal limbs. However, copper mineralization is pervasive over a broad area.  Gold mineralization is more uneven spacially and may have been remobilized by post mineral low temperature alternation events.

 

8.2                     Suruca

 

The Suruca Project´s orebody has outlined a resource with a strike length of 1,900 metres and 800 metres of down dip from surface.  The main direction is N400E and dipping 20 to 300NW controlled by foliation S1 (Figure 8.1).

               

55



 

Figure 8.1: Suruca orebodies with strike length of 1,900 metres and and 800 metres of down dip to surface

 

GRAPHIC

 

The orebody is characterized by oxide and sulphides ores (Figure 8.2). The oxide ore consists of about 11.7 % of the deposit and is associated with a weathering surface with a width between 35 to 40 metres depth with average gold of 0.41g/t Au. The oxide ore is characterized by soil, mottled zone, fine saprolite and coarse saprolite.

 

Figure 8.2: Cross Section showing the oxide and sulfhide ore bodies dipping 250 to northwest

 

GRAPHIC

 

56



 

The sulphide ore is characterized by fresh sulphides and rocks and occurs in four orebodies (“Suruca 1’’, “Suruca 2’’, “Suruca 3’’ and “Suruca 4’’) that represent only spatial occurrences of mineralization. The ore bodies are detailed below:

 

·                  Suruca 1: the upper ore body and represents 1.1% of the deposit, with an average gold grade of 0.36 g/t Au;

 

·                  Suruca 2: the main ore body with 80.3% of deposit, with average gold grade of 0.40 g/t Au. This ore body has four internal waste bodies called of Waste 1, Waste 2, Waste 3 and Waste 4;

 

·                  Suruca 3: deeper than Suruca 2 with 1.1 % of the deposit, with average gold grade of 0.47 g/t Au;

 

·                  Suruca 4: the deepest ore body with 5.8% of the deposit and with average gold grade of 0.41 g/t Au. This ore body has an internal waste (Waste 5”).

 

The hydrothermal alteration in sulphide ore is associated with sericitic and propylitic alteration halo. The proportion is about 44% in the sericitic and 37% in propylitic. The sericitic alteration is characterized by sericite, +/- biotite and carbonate with pyrite, galena, spharelite and some chalcopyrite. The propylitic alteration is characterized by epidote, chlorite, carbonate and pyrite. The expectation is that most of mineralization was contained in sericitic halo. The high proportion in the propylitic halo is not normal. This can be a strong evidence that a system of Au-Zn-Ag was remobilized by epigenetic fluids along structures. The two types of ore have different features: the sericitic may be related to zinc, but the high values of gold always have an “envelope” of zinc. The propylitic halo has a direct relationship between gold and zinc. To confirm this relationship we also utilized the assay results with graph of Au x Zn (Figure 8.3).The Suruca Project was submitted to a strong metamorphism and deformation that caused Au, Ag and zinc remobilization.

 

Figure 8.3: Graphics of Au x Zn and S x Au to sericitic halo and propylitic halo. The sericitic halo don´t have direct relationship with zinc and neither with S, contrasting with propylitic halo that have direct relationship with Zn and S.

 

GRAPHIC

 

57



 

The study case of elements of mineralization showed that the high grade values of gold are related to folded quartz vein/veinlets with sericitic and biotite alteration, instead of the samples with high sulphides concentrations (Figure 8.4). The second generation of quartz veins/veinlets with sulphides (esphalerite+galena+pyrite), carbonates and epidote shown grades intermediates, but with correlation between zinc and gold.

 

The high grades are compelling evidence that main mineralization pre-date the event of deformation, so high grade of gold remains in epithermal features and is not associated with a structural control (Figure 8.5).

 

Figure 8.4: Selective sample (black square) in high grade assays of Suruca. The picture on the left shows high contents of sulphides (esphalerite+galena+pyrite) with a lower grade than interval, and the picture on the right quartz shows veinlets with grades higher than interval.

 

GRAPHIC

 

58



 

Figure 8.5: Geological map of Suruca Project with executed drill holes. The red shell represents the drill that intercepted high grade values, always associated to folded quart-veinlet. The southwest portion of the high grade shell still open

 

GRAPHIC

 

59



 

9                      EXPLORATION

 

9.1                     Chapada

 

A summary of the exploration history was provided in the Micon International Ltd Technical Report on the Chapada Copper dated July 2003 and the more recent Independent Mining Consultants, Inc report dated March 2008.

 

Additional copper-gold anomalies have been identified along the general trend defined by the northwest strike of the Chapada Project deposit. Exploration of the roughly 50km trend has been undertaken by Yamana predecessors with geophysical, geochemical, and drill sampling means with some success.

 

The Chapada Project’s mineralization was discovered in 1973 during a regional program of stream sediment sampling.  Follow up work by INCO was conducted during 1974 and 1975 that included detailed stream sediment surveys, soil geochemistry, geophysics, trenching and broadly spaced initial Project drilling.

 

There are few outcrops in the Chapada Project area due to the laterite-saprolite cover. Consequently, deposit definition required extensive diamond drill exploration.  Development drilling of the deposit occurred in several campaigns from 1976 through 1996 by INCO, Parsons-Eluma, Eluma- Noranda, Santa Elina, and Santa Elina-Echo Bay.  Section 11 describes the accumulated drill hole database that now amounts to 856 drill holes.

 

In 2007, Yamana re-started the exploration program with 9 holes totaling 1924 metres of diamond drill holes in east Chapada Project deposit for check extension mineralization intercepted for old drill executed in 1996 by the joint venture Santa Elina-Echo Bay and for test easter sinclinal using model of mineralization associate volcanogenic massive sulphide.

 

An early 2008 consultancy by Richard Sillitoe defined a genetic model of mineralization with typical porphyry copper-gold system (Cu-Au-Mo association), that underwent intense isoclinal folding and amphibolite facies metamorphism during continental collision at the end of the neoproterozoic. However, the original mineralogy may not have been so profoundly changed, because of the stability of minerals like quartz, anhydrite, pyrite, chalcopyrite, magnetite and biotite under amphibolite facies conditions. The economic mineralization is structurally controlled by the axial zone of an asymmetric D2 anticlinal fold, due to remobilization chalcopyrite. Sillitoe highlights that porphyry copper-gold deposits worldwide have a strong tendency to occur in clusters, with as many as a dozen discrete centers being known from some districts (e.g. Northparkes, New South Wales, Australia). The marker is quartz-muscovite-kyanite schist horizon is believed to be a former advanced argillic lithocap.

 

The goal of exploration is the discovery of another ore body in Chapada Project district and the evaluation of the extension of resources of the Chapada Project deposit. To reach these objectives, a regional geological map, a detailed geological map of the open pit, a regional cross section and a geological model of mine were produced. Additionally, old drill holes were re-logged, chip/soil samples were taken and 5530 metres of diamond drill holes near the Chapada Project deposit were drilled. The next step is a geophysics survey with IP and Magnetic, followed by checking the exploration drill holes.

 

60



 

During 2010, Yamana developed an exploration program on the south-west pit area. The south-west area was the target of 16 drill holes. The infill drilling program was conducted by a mine team that developed 10 drill holes in the north-east area. The samples of both exploration and infill program were analyzed in a commercial and accredited laboratory. Internal QAQC was managed by Yamana staff to maintain the criteria to be applied during the previous drilling programs.

 

Is important to highlight that neither exploration’s nor infill’s new drilling dataset were used to review the resource estimation.

 

9.2                     Suruca

 

9.2.1                     Exploration until 1997

 

The Suruca Project has been explored by different companies since the 1970’s: INCO/Eluma (1980 to 1981), Cominco (1987 to 1988), WMC (1993 to 1994) and Santa Elina/Echo Bay (1996 to 1997), but most of the past exploration was focused in oxide mineralization. The old database has only exploration works done by Santa Elina/Echo bay and some reports about location reverse circulation drilling by WMC.

 

An Exploration Report of Santa Elina/Echo Bay (1997) reported a total of 120 holes/4050 metres having been drilled in three programs executed by the following companies:

 

Table 9.1: Historical Drill holes executed in Suruca Project by other companies.

 

Companies

 

Holes

 

Metrage (m)

 

Eluma

 

4

 

649.3

 

EDEN/COMINCO

 

7

 

623.6

 

WMC

 

91

 

2,241.0

 

Santa Elina

 

18

 

536.4

 

Total

 

120

 

4,050.3

 

 

The results of all drilling programs (4050m - mostly in saprolite), indicate in the saprolite zone a consistency of low grade gold zones (0.1 to 0.5 g/t Au), with  high grade interceptions  between 0.5 to 6.0 g/t Au. The potential resources identified by Santa Elina were 11Mt @ 0.56 g/t Au, totalling 199.4 Koz Au.

 

9.2.2                     Exploration by Yamana from 2008 to Present

 

In 2008, Yamana’s exploration team re-started the exploration activities in Chapada working with new mineralization model for region associated to deformed/metamorphosed copper-gold porphyry systems. Preliminary work done in conjunction with Richard Sillitoe, a consultant, together with the detailed geological mapping of the Chapada Project’s early pit, assisted the understanding of the regional geological model. After this new exploration model integrated the old data, it was initiated the geological mapping with focus in hydrothermal halos and structures, sampling (soil, chip, auger,…) and shallow drill holes in south Suruca Project. In 2009,

 

61



 

Yamana’s claims were renewed and it re-started geophysics survey (IP and Mag) and exploration drilling. Table 9.2 details the exploration works:

 

Table 9.2: Exploration works in Chapada Project (including Suruca)

 

Activities

 

Total

 

Drilling (m)

 

41,766

 

Soil Samples

 

1,377

 

Chip Samples

 

2,543

 

RAB Drilling

 

1,307

 

Auger Drilling (m)

 

280

 

Ariel Magnetic Survey (Km)

 

2,200

 

IP Survey (km)

 

16

 

 

The exploratory drill holes SU-11, SU-13 and SU-15 intercepted the first positives results: SU-11: 81.0m @ 1.22 g/t Au (112.0m) and 28.0 m @ 1.20 g/t Au (203.0m), SU-13:  6.0 m @ 1.35 g/t Au (7.0m) and 55.4 m @ 0.41 g/t Au (83.6m) and SU-15: 74.7 m @ 0.87 g/t Au (52.5m), 39.7 m @ 0.37 g/t Au (140.3m), 30.0 m @ 0.55 g/t Au (203.0m) and 20.0 m @ 0.35 g/t Au (248.0m).

 

In late 2009 and early 2010 the drilling program was planned to delineate the Suruca Project’s ore body with grid 400x200 metres and after detailed to grid 200x200 metres. This phase extended the strike length to 2100 metres, a width of 1000 metres and a depth of 500 metres. An infill program of grid 100x100 metres was done in north portion of deposit (between lines L500S and L1500S) and with 1000 metres strike length, a width of 800 metres and depth of 300 metres (Figure 9.1).

 

62



 

Figure 9.1: Location of drill holes program in Suruca Project

 

GRAPHIC

 

10               DRILLING

 

10.1              Chapada

 

The drillhole database consists of 856 diamond core drillholes that represent 67,315 metres of drilling and 47,939 sample intervals.  The drilling consists of two hole series, short CHD series holes that were drilled to test saprolite material and longer M series holes. Table 10.1 summarizes the drilling by series.

 

Table 10.1: Chapada Drilling by Series

 

Drilling Series

 

No. of Holes

 

No. of Metres

 

No. of Intervals

 

CHD Series

 

416

 

6,630

 

7,731

 

M Series

 

440

 

60,685

 

40,208

 

Total

 

856

 

67,315

 

47,939

 

 

Table 10.2 is excerpted from the report “Executive Summary Report - Chapada Project”, dated June 25, 1997, by Santa Elina, and summarizes the drilling by date and company.

 

63



 

Table 10.2: Chapada Project Drilling by Date and Company

 

Date

 

Companies

 

No. of Holes

 

No. of Metres

 

1976

 

INCO

 

6

 

919

 

1976-1979

 

INCO/Eluma

 

78

 

10,573

 

1979-1981

 

Eluma/Noranda

 

86

 

11,140

 

1989

 

Eluma

 

6

 

569

 

1995

 

Santa Elina

 

416

 

6,631

 

1996

 

Santa Elina/Echo Bay

 

264

 

37,482

 

TOTAL

 

 

 

856

 

67,314

 

 

The drilling has delineated the main deposit areas at a spacing of 100 metres by 50 metres, with a tighter 50 meter pattern in the central portion of the deposit.

 

680 of the 856 holes were drilled in the 1995-1996 campaigns. These were NQ or NX size core holes.  All collar locations were surveyed.  Angle holes (only 5% of the drilling) were down-hole surveyed, but down-hole surveys were not done for the vertical holes. The “longer” M series holes only tended to be about 150 metres long due to the shallow nature of the deposit so significant deviation in hole orientation is not expected.

 

Figure 10.1 shows a cross section of the drilling through the central portion of the orebody. The Chapada Project deposit is essentially flat lying and the holes are mostly vertical, so mineral intercepts represent true thicknesses.

 

There is also documentation of several reverse circulation holes drilled for condemnation purposes.  There were also some early S series holes in the saprolite material.

 

64



 

Figure 10.1: Cross Section 27

 

GRAPHIC

 

65



 

10.2              Suruca

 

10.2.1              Drilling by Yamana from 2008 to present

 

The qualified person for drilling at the Suruca Project is Sergio Brandão. A total of 131 drill holes / 27,374.17 metres were executed in Suruca Project in this period (Table 10.3).

 

Table 10.3: Showing the holes executed per year

 

Date

 

Companies

 

N.0 of Holes

 

N.0 of Metres

 

2008

 

Yamana Gold Inc.

 

7

 

439.5

 

2009

 

Yamana Gold Inc.

 

21

 

6,457.82

 

2010*

 

Yamana Gold Inc.

 

103

 

20,476.85

 

TOTAL

 

 

 

 

 

27,374.17

 


*Holes for Metallurgical Testing: 11 holes/1,014.09m.

 

10.2.2              Diamond drilling methods

 

The drilling methods used in this Project were diamond drillholes.

 

Drillholes were collared in soil at HW diameter, changed to HQ diameter at the top of the saprolite surface, and changed to complete the hole at NQ diameter once fresh rock is encountered. The rod interval is 3 metres.

 

The wire line method was used in the diamond drilling operation.

 

10.2.3              Drillhole patterns

 

In north portion of the Suruca Project deposit, between lines L500S and L1500S, the grid drilling is 100 by 100 metres and south portion. Between L1500S and L2300S, the grid drilling is about 200 by 200 metres. Most holes have azimuth 130 degree and dip 60 degrees with some holes with azimuth of 310 degree.

 

10.2.4              Drillhole collar surveys

 

Diamond drillholes were designed by a geologist. Collar surveys are taken using a total station. Coordinates are collected in UTM coordinates, SAD 69 Brazil datum, 22 South zone.

 

10.2.5              Downhole surveys

 

Downhole surveys are taken by the drilling contractor upon completion of the drillholes. The drillholes with inclination between 45 to 85 degrees have been surveyed every 3metres downhole using a Reflex Maxibor II or Devicom Deviflex electronic surveying instrument, in the sub-vertical drillholes, was used PeeWee or EZ-Shot instrument. All holes were surveyed, of which 51.74% were surveyed using Devicom Deviflex instrument, 45.86% using Maxibor II electronic instrument and only 2.40% using PeeWee instrument. Generally, the drillholes show

 

66



 

deviation below 5% and no significant deviation issues have been encountered in the drilling to date.

 

10.2.6              Drillhole preservation

 

After drilling is concluded the collars of holes are cased and protected at the surface with a cement block, and are affixed with a metal tag stamped with the drillhole number, final depth, inclination, azimuth, and start and end of drilling dates.

 

11               SAMPLING METHODS AND APPROACH

 

11.1              Chapada

 

This section as well as the following sections on “Sample Preparation, Analyses, and Security”, and “Data Verification” describe the procedures used by Santa Elina during the 1995 and 1996 drilling campaigns.  The information on earlier drilling campaigns is not readily available.  The early campaigns account for only 21% of the drillholes and 34% of the metres drilled.  Also, a statistical comparison of the early and recent drilling results conducted by IMC indicates that the early results are consistent with the new drilling.

 

The distribution of sample lengths is as follows:

 

Table 11.1: Distribution of Sample Lenghts

 

Less than 1 metre

 

15

%

 

 

 

 

1 metre

 

7

%

 

 

 

 

Between 1 and 1.5 metres

 

18

%

 

 

 

 

1.5 metres

 

42

%

 

 

 

 

Between 1.5 and 2 metres

 

9

%

 

 

 

 

2 metres

 

6

%

 

 

 

 

Greater than 2 metres

 

3

%

 

 

 

 

TOTAL

 

100

%

 

It can be seen that the most common sample interval is 1.5 metres. One and two metres intervals were also used for some of the drilling. There was also a tendency to make sample intervals slightly longer or shorter to match lithologic contacts, resulting in the variation in lengths.

 

The Micon report states that overall core recovery averaged 95%; neither IMC nor Hatch has reviewed the core recovery data.

 

Micon concluded that the sampling procedures used by Santa Elina have provided representative samples of the deposit being tested. Micon reported that they were not aware of any drilling, sampling or recovery factors that could materially affect the accuracy of the results

 

67



 

obtained. The Chapada Project database, which incorporates all drilling performed since 1976, contains 47,939 individual sample intervals.

 

All core drilled by Santa Elina was logged. The logging included rock type, degree of oxidation, degree of alteration, estimated percentage of sulphides, and the presence of additional minerals.

 

11.2              Suruca

 

11.2.1              Sampling by Mineração Alonte (Santa Elina) from November 1996 to December 1996

 

There is no information available regarding the sampling method and approach during this period.

 

11.2.2              Sampling by Yamana from April 2008 to present

 

The qualified person for the sampling method and approach at the Chapada Project is Mr.Sergio Brandão.

 

The drillhole core intersections from Yamana’s drilling programmes are stored under an open sided roofed structure at the exploration camp while the drillhole core intersections from Mineração Alonte are stored in Alto Horizonte City. The drillhole core from the CRD sequence drilled by Mineração Alonte is no longer available as the remaining half core was re-analysed by Yamana.

 

The drillhole core is stored in wooden core boxes with a nominal capacity of approximately 4 metres for NQ or NQ2 sized drill core and 3 metres for HQ or HW sized core. The drillhole number, Project name, box number, and downhole depths are stamped onto an aluminium tag and affixed to the edge of the box. Wooden downhole core depth markers are placed in the core box by the driller and affixed with an aluminium tag stamped with the depth, the length of the interval, and the length of the recovered sample.

 

Approximately three staff geologists are responsible for logging drillhole cores. Drillhole core logging and sampling is done at Yamana’s exploration camp.

 

11.2.3              Core sampling

 

When the drillhole core is received at the sampling shed, the entire length of the drillhole is checked and marked for lithological contacts. Samples are marked down the entire length of the hole at 1 metre intervals, except at lithological contacts where the sample is selected to respect lithological boundaries. A red square marked on the box with a pen indicates the start and end of the sample interval, after the paper sample number tags are plasticized and stapled to the core box next to the corresponding sample.

 

Samples are selected down the entire length of the drillhole core, sawn in half with an electric diamond bladed core saw, and sampled prior to logging. Half core samples are selected by a Yamana geology technician or by a trained sampler. The samples are then placed in a

 

68



 

numbered plastic bag along with a paper sample tag, and tied closed with a piece of string. Sample weight is approximately 3.5 kilograms. Six to eight samples are placed in a larger plastic bag, loaded onto a truck owned and driven by a locally based transport company, and driven to the ALS Chemex laboratory sample preparation facility in Goiânia, State of Goiás. After the samples have been crushed and pulverised, the samples are sent by the ALS Chemex laboratory for analysis in Lima, Peru.

 

11.2.4              Core logging

 

After sampling, the geologist completes a graphic log and logs the core in detail for lithology, structure, mineralization and alteration. Codes are assigned for the oxidation state, consistency and alteration including alteration halo, sulphides, silicification, biotite, sericite, epidote, amphibolite, garnet, carbonate, rodocrosite, chlorite, and kyanite content. Angles of structures such as foliation and faults are recorded, although drillholes are not oriented.  Sample intervals and sample numbers are also recorded on the exploration hole log. When the drillhole is an infill, the core is quickly logged, according to the alteration halos with fewer details, and no structural drawings.

 

Core sample recovery is not recorded by the geologist, although a record of the drillhole recovery on a run by run basis is recorded manually by the driller. This information is typed by a geological technician into a digital file for each hole. The recovery in the mineralized zones is generally very good, on average better than 95%.

 

11.2.5              Density determinations

 

The geologist selects about four samples of each alteration halo for each drillhole for density determination by two different methods after the drillhole has been sampled and logged.

 

The first method used is the water displacement method which is performed  in the logging shed. This method uses half core samples between 8 cm and 12 cm long selected, weighed indoors, coated with vaseline to prevent water impregnation or vaseline, and placed in a plastic beaker containing 500 ml of water to determine the volume of water displacement. The density value is measured using the formula:

 

Density = Weight of Samples (g)/(displaced water volume (ml) — original water volume (ml))

 

The second method, which is gravimetric, is done in a laboratory. This method uses pulverized samples selected by geologists to check the first method. A prepared sample (3.0g) is weighed into an empty pycnometer. The pycnometer is filled with methanol and then weighed. From the weight of the sample and the weight of the methanol displaced by the sample, the specific gravity is calculated according to the formula below:

 

Specific Gravity = Weight of sample (g)/weight of solvent displaced (g) x Specific gravity of solvent

 

After that, the specific gravity is converted to density using the formula:

 

Density = Specific gravity x density of water (at temperature (t0C)

 

Factors for converting specific gravity to density are tabulated below:

 

69



 

Table 11.2: Specific gravity conversion

 

Factors for converting specific gravity to density are tabulated below:

 

Temp (ºC)

 

Density (g/cm3)

 

Temp (ºC)

 

Density (g/cm3)

 

19

 

0.9984

 

23

 

0.9975

 

20

 

0.9982

 

24

 

0.9973

 

21

 

0.998

 

25

 

0.997

 

22

 

0.9978

 

26

 

0.9968

 

 

A total of 955 density analyses are available, representing around 3% of the samples collected thus far. The density determinations have been taken in fresh, mixed and oxidised material, collecting data in all mineralized weathered zones, lithologies and alteration halos.

 

12               SAMPLE PREPARATION, ANALYSIS AND SECURITY

 

12.1              Chapada

 

The core samples were sawed in half, with one half submitted for sample preparation and assay and the other half retained for reference.  The entire half core is first crushed to less than ¼ inch by a jaw crusher and then to less than one millimeter in a roll crusher.  This product is split into three parts, two of which are saved. One of the splits is then pulverized to -150 mesh to provide 500 grams of the final pulp.

 

The gold analysis utilized a 30 gram sample that was fire assayed by atomic absorption. The total copper analysis utilized a 0.25 gram sample that was dissolved with a four acid digestion (hydrochloric, nitric, hydrofluoric, and perchloric). This was evaporated and analysed for copper by atomic absorption.

 

Geolab in Belo Horizonte, Brazil was used for most of the Santa Elina assays.  Another Brazilian lab, Nomos, was used for the shallow saprolite holes drilled in 1995. Geolab was founded in 1967 and is now part of the ALS Chemex laboratories group, although this was not the case in 1996. The ALS Chemex laboratories group has obtained ISO 9002 certification. The analytical procedures used by Nomos were similar to the Geolab procedures, including the four acid digestion for total copper.

 

Usually the jaw crushing and roll crushing stages were done at the Chapada Project’s sample preparation facility at Alto Horizonte.  During times of peak drilling however, some half core was sent to Geolab.

 

It is reported that the chain of custody of the samples is as follows.  Core was placed in wooden storage boxes at the rig, under the supervision of the geotechnicians. The core boxes were transported to the secure sample preparation facility at Alto Horizonte.  The core was then logged for geotechnical characteristics and marked longitudinally for sawing in half.  Sawing took place a few blocks from the sample preparation facility due to noise considerations.  The sawn core was replaced in the core boxes and returned to the sample preparation facility where it was logged by geologists.  The core was then divided into sample lengths for the sample preparation procedures described above.

 

70



 

The sample preparation and assaying have been performed using procedures that are accepted as standard in the mining industry.  The security procedures are also reasonable given the high volume of samples and relatively low mineral concentrations of the samples.

 

As of this writing, the half core, coarse rejects, and pulps from the 1995-1996 drilling campaigns are still located at the core storage facility at Alto Horizonte.  The sample preparation equipment has been removed.  It was reported to IMC that the sample preparation personnel at the site were under contract from the Geolob Laboratory and were not Santa Elina personnel.

 

In the opinion of the authors of this report, the sampling, sample preparation and assaying procedures, have resulted in representative samples of the Chapada Project deposit.

 

12.2              Suruca

 

12.2.1              Sample preparation, analysis and security by Yamana from April 2008 to August 2010 — Suruca Project

 

The qualified person for the sample preparation, analysis and security at the Chapada Project is Mr. Sergio Brandão.

 

12.2.2              Laboratory

 

Diamond drill core samples are prepared by ALS Chemex in Goiânia/GO - Brazil and analysed by ALS Chemex in Lima - Peru. The laboratory in Peru is accredited with ISO 9000:2008 in the preparation and the chemical analysis process of mining exploration samples.

 

The five percent (5%) of analysed samples are selected by Yamana for interlab check and shipped by ALS Chemex to Acme Laboratory in Santiago.

 

12.2.3              Sample preparation

 

Upon receipt of the sample submission, each sample bag is weighed and then dried at 100°C for about 8 to 12 hours. The entire sample is then crushed to 90% passing <2 mm (10 mesh), split to 0.5 kilograms in a riffle splitter, and pulverised to 95% passing 150# (mesh). Samples are then split again to 50 grams using a rotating splitter / Spatula. The crusher and pulveriser are cleaned between each sample. Each fraction retained is returned to Yamana.

 

12.2.4              Sample analysis

 

All samples are analysed by fire-assay. Since the beginning of the Suruca Project study until the hole SU_28, Atomic Absorption assay for copper were requested for all samples. Yamana determined there isn’t significant grade of copper around the gold mineralized zone.  Additional 48 elements ICP, with an opening by aqua regia, analysis are also performed for all samples in order to obtain the hydrothermal alteration element assemblages. Yamana determined that no significant difference existed between ICP and AA in copper low grade.

 

71



 

12.2.5              Sample security and chain of custody

 

Samples are transported from the drill rig to Yamana’s core storage facilities at the Chapada Project exploration camp by the drilling contractor, where a Yamana geologist marks up sample intervals and assigns sample numbers to the core. The half core sample is selected, cut and sampled by a Yamana geology technician or by a trained sampler, placed in a numbered plastic bag along with a paper sample tag, and tied closed with a piece of string. Sample weight is approximately 3.5 kilograms. Six to eight samples are placed in a larger plastic bag, loaded onto a truck owned and driven by a locally based transport company, and driven to the laboratory sample preparation facility in Goiânia. After the samples have been crushed and pulverised, they are sent by the laboratory for analysis in Lima, Peru.

 

ALS CHEMEX stores all pulps and coarse rejects for three months and then transport them back to the Chapada Exploration Project where all samples are stored in the core storage facility for the life of the project. Yamana intends to build a storage facility for old drillhole cores, coarse rejects and pulps.

 

13               DATA VERIFICATION

 

13.1              Chapada

 

13.1.1              Santa Elina Quality Control/Quality Assurance Program

 

In 1996 Echo Bay became actively involved in the drilling and sampling program for the Chapada Project. A rigorous quality control program was commenced making use of standards, blanks, and duplicate assays to monitor results. Geolab was selected as the primary assay laboratory.  A large number of samples were also sent to various labs in North America for check assays.

 

IMC reviewed several reports from K.A. Lovstrom, a consulting geochemist from the United States, describing the quality control program.  IMC also received the data file of all the quality control assays.  IMC reviewed all the available data. The author believes that the quality control program was sufficient to ensure consistent and relatively high quality assays for the Chapada Project.

 

Data comparing the Nomos lab with the Cone lab in the United States for the CHD holes and Geolab with Cone for the M series holes is summarized on Table 13.1 and Table 13.2. There appears to be small differences in results between the Brazilian labs, Nomos and Geolab, and the Cone laboratory in the United States.  For copper, Cone is lower than both the Brazilian labs; Cone is 5.99% lower than Nomos and 6.62% lower than Geolab.  For gold, Cone is 4.9% lower than Nomos and 2.13% higher than Geolab.

 

72



 

Table 13.1: Comparison of Nomos and Geolab With Cone for Copper Assays

 

CHD Series Holes:

 

Number

 

Mean (%Cu)

 

Std. Dev. (%Cu)

 

 

 

 

 

 

 

 

 

Nomos

 

398

 

0.267

 

0.254

 

 

 

 

 

 

 

 

 

Cone

 

398

 

0.251

 

0.236

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

-5.99

%

-7.09

%

 

M Series Holes:

 

Number

 

Mean (%Cu)

 

Std. Dev. (%Cu)

 

 

 

 

 

 

 

 

 

Geolab

 

1299

 

0.423

 

0.342

 

 

 

 

 

 

 

 

 

Cone

 

1299

 

0.395

 

0.317

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

-6.62

%

-7.31

%

 

Table 13.2: Comparison of Nomos and Geolab With Cone for Gold Assays

 

CHD Series Holes:

 

Number

 

Mean (g/t)

 

Std. Dev. (g/t)

 

 

 

 

 

 

 

 

 

Nomos

 

396

 

0.204

 

0.378

 

 

 

 

 

 

 

 

 

Cone

 

396

 

0.194

 

0.358

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

-4.90

%

-5.29

%

 

M Series Holes:

 

Number

 

Mean (g/t)

 

Std. Dev. (g/t)

 

 

 

 

 

 

 

 

 

Geolab

 

1297

 

0.376

 

0.782

 

 

 

 

 

 

 

 

 

Cone

 

1297

 

0.384

 

0.843

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

2.13

%

7.80

%

 

13.1.2              IMC Data Verification and Reviews

 

IMC randomly selected 31 drillholes from the Chapada drillhole database to audit the procedures.  The 31 holes represent about 3.6% of the drillholes and about 5% of the holes with significant mineralization and covered all the drilling campaigns since 1979.  IMC requested assay certificates and geology logs for the holes to compare with the assays in the computer database.  The available hard copy data was compared with the assay database to verify that the database was assembled in a proper fashion.

 

Overall, the authors believe that the database management procedures are reasonable and that no serious errors or omissions occurred in assembling the database. The audit trail for the Santa Elina/Echo Bay data meets the industry standards. The available quality control for the older drilling is not as complete as the new drilling; it should, however, be noted that the deposit has largely been re-drilled by newer holes and comparisons between the old and new drilling is possible as will be discussed next.

 

IMC compared the old (pre Santa Elina/Echo Bay) M series drillholes with the recent M series holes.  There is an approximate 350 metres by 350 metres area in the center of the deposit that

 

73



 

contains a mix of both types of data. Table 13.3 shows the comparison for assays in this area. For copper, the new drilling is 6.38% higher than old drilling. For gold, the new drilling is 3.46% lower than old.  It is interesting to note that the comparison of new with old drilling is about the same magnitude and direction as Cone versus Geolab.

 

Table 13.3: Comparison of Old and New M Series Drilling

 

Copper:

 

Number

 

Mean (%Cu)

 

Std. Dev. (%Cu)

 

 

 

 

 

 

 

 

 

Old Drilling

 

2496

 

0.329

 

0.309

 

 

 

 

 

 

 

 

 

New Drilling

 

2703

 

0.350

 

0.311

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

6.38

%

0.65

%

 

Gold:

 

Number

 

Mean (g/t)

 

Std. Dev. (g/t)

 

 

 

 

 

 

 

 

 

Old Drilling

 

2460

 

0.231

 

0.284

 

 

 

 

 

 

 

 

 

New Drilling

 

2703

 

0.223

 

0.264

 

 

 

 

 

 

 

 

 

% Variance

 

 

 

-3.46

%

-7.04

%

 

In author’s opinion the database is of sufficient quality for a feasibility level study.

 

There is evidence that the recent copper analysis done at Geolab is about 6% high when compared with North American labs and the old drilling data.  There is also evidence that the recent gold assays are 2% to 3% low compared to North American labs and the old data.

 

13.2              Suruca

 

13.2.1              Re-sampling of Mineração Alonte (Santa elina) drillhole core by Yamana

 

A total of 18 diamond drill holes from Mineração Alonte (Santa Elina) (prefixed CDR) were re-analysed using Yamana’s procedures. The results assay was compatible with old results.

 

13.2.2              Yamana quality control measures

 

Yamana inserts certified standards and blank samples with drillhole core sample submissions. Yamana has formal procedures (Protocols) in place for describing the frequency and type of QA/QC submission, the regularity of analysis of QA/QC results, failure limits, procedures to be followed in case of failure, or for flagging failures in the QA/QC database.

 

The main purpose of the QA/QC Program is to monitor and control the quality, reliability and accuracy of data reported by commercial laboratories, which render services to Yamana, under the international standards of the NI 43-101 protocols and internal protocols.

 

74



 

13.2.3              Certified standard samples

 

Certified standards are used to measure the accuracy of analytical processes. Certified standards are composed of material that has been exhaustively analysed to accurately determine its gold grade within known error limits.

 

Yamana is procedure requires three standards for every 100 samples submitted to the laboratory. Standards of low, medium, high, and very high gold grades are supplied in pre-packaged plastic bags purchased from Geostats Sample and Assay Monitoring Service (Geostats”), in Australia. Geostats provides Yamana with the round robin assay results for both fire assay and aqua regia, and the expected standard deviation for assay results.

 

The report analyzed the results of 567 assays of standards (an actual submission frequency of three standards per 100 samples). A standard assay is considered to have failed it if is more than three standard deviations from the certified value of the standard. Failure rates for submitted standards are average (Table 13.4 and Figure 13.1), 10% > -/+2 STDEV (a little above = 5%). Assays show no tendencies to bias. The ALS laboratory has 13 failures, representing 2.30% of total standards. The failures have 5 negatives bias, 3 positive bias and 5 samples were lost in the fusion process.

 

Yamana continues with the ALS laboratory; failures continue, but are very few. Yamana continues to investigate by way of visits, meetings and audits, the reasons for the failure rate for certified standards at the Chapada Project.

 

Table 13.4: Report failure of standards, totaling 2.3% of total standards

 

LAB.

 

Standard value Au ppm

 

Standard Number

 

Failures

 

Samples

 

% Failure

 

Analisys

 

ALS

 

1.93

 

G303-3

 

2

 

58

 

3.4

%

Au-AA24

 

ALS

 

0.26

 

G303-8

 

1

 

147

 

0.7

%

Au-AA24

 

ALS

 

3.95

 

G397-6

 

5

 

65

 

7.7

%

Au-AA24

 

ALS

 

1.48

 

G900-2

 

0

 

10

 

0.0

%

Au-AA24

 

ALS

 

3.21

 

G900-5

 

0

 

5

 

0.0

%

Au-AA24

 

ALS

 

1.76

 

G901-2

 

0

 

24

 

0.0

%

Au-AA24

 

ALS

 

6.78

 

G907-8

 

0

 

48

 

0.0

%

Au-AA24

 

ALS

 

0.8

 

G998-6

 

3

 

66

 

4.5

%

Au-AA24

 

ALS

 

0.38

 

G998-9

 

0

 

10

 

0.0

%

Au-AA24

 

ALS

 

0.82

 

G999-1

 

2

 

134

 

1.5

%

Au-AA24

 

 

 

 

 

 

 

13

 

567

 

2.3

%

 

 

 

75



 

Figure 13.1: Suruca standard sample results for gold, period between June, 2009 to August, 2010 tolerance is 10% > 2 -/+ STDEV, General Failure - ALS CHEMEX = 2.30%

 

 

13.2.4              Blank samples

 

Blank samples are composed of material that is known to contain gold grades that are less than the detection limit of the analytical method in use (L/D ALS = 0.005 ppm). Analysis of blank samples is useful for determining if cross-contamination of samples is occurring in the sample preparation or analysis process.

 

Yamana’s procedure requires submission of three blank samples for every 100 samples submitted to the laboratory. Assay results from 653 samples (an actual submission frequency of three blank sample per 100 samples), in period from June 2009 to August 2010_Suruca Project, with 0.46% of the samples (03 samples) returning results above 0,025 ppm (5 times the detection limit), but below the limit from 5% out (Table 13.5 and Figure 13.2).

 

This rate of failure is very low and suggests that the laboratory maintains a very good cleaning procedures in respect of equipment. Yamana is investigating these results above of the limit with the analytical laboratory.

 

Yamana is inserting blank samples between or after samples believed to return high assay values, to check for sample contamination at the laboratory. In months with more than 5% of contaminated samples, batch reanalyse is required.

 

Table 13.5: Total blank samples and report of three failures

 

 

 

ALS_Au ppm

 

Blank-Suruca

 

Count

 

%

 

Total sent

 

653

 

100.00

%

Below Limit

 

650

 

99.54

%

Failures

 

3

 

0.46

%

 

76



 

Figure 13.2: Suruca blank sample results for gold, between June, 2009 to August, 2010. Blank limit is 0.025ppm (5 times mininum detection limit)

 

GRAPHIC

 

13.2.5              Duplicate drillhole core samples (field duplicates)

 

The duplicate samples are the same core samples that are sent two times. At the Chapada Project, where diamond drillhole cores are sampled by taking half of the core extracted from the ground, a duplicate sample is cut again by submitting 2 samples, each containing a quarter core. Field duplicates are submitted to measure the precision of the entire sampling, sample preparation, and analysis process. Field duplicates also provide a measure of the inherent variability of the deposits (the Nugget Effect”).

 

Yamana submits all duplicate drillhole core samples for analysis. It is selected at a frequency of one for every 20 samples.Between June 2009 and August 2010 a total of 1124 samples drillhole core duplicate samples were analyzed (Table 13.6 and Figure 13.3). These results show a small Nugget Effect and a good gold dispersion in mineralized zone.

 

Table 13.6: Average grade of gold for original samples and duplicate samples

 

Total
Results

 

Original Grade
Average

 

Duplicate Grade
Average

 

Difference
Average

 

1114

 

0.211 g/t Au

 

0.197 g/t Au

 

6.629

%

 

77



 

Figure 13.3: Suruca Project duplicates core sample precision plot for Au, between June, 2009 to August, 2010

 

 

13.2.6              Inter-laboratories Pulp Check

 

Selected pulp samples are splitted again from the pulverized portion and sent by ALS Chemex to SGS Geosol Lab (in January, 2010) and Acme Analitica (since February, 2010). Analysis of these pulps is useful for measuring the precision of the analytical process at both laboratories, as well as assuring better average of accuracy and control on assays.

 

Yamana’s procedure requires submission of 5% of samples for each batch submitted. Assay results for 1149 checked samples were analysed this year (Table 13.7 and Figure 13.4).The level of precision indicated by the checked sample results is good; most of the samples have a relative difference below ±25% and a moving average generally below ±20%. The grade average of total checked samples have a difference of only 1.569%.

 

Table 13.7: Comparison of average grade of gold between samples of interlab check

 

 

 

ORIGINAL

 

CHECK

 

DIFFERENCE

 

Average

 

0.335

 

0.329

 

-1.569%

 

Total Samples

 

1149

 

Ideal Limit of Difference - 10%

 

 

78



 

Figure 13.4: Suruca Project check samples precision plot for Au, betwen June, 2009 and August, 2010 in Check inter-Lab (ALS Chemex and Acme)

 

 

13.2.7              Internal laboratory quality control measures

 

ALS Chemex conducts internal quality control measures including analysis of blanks, standards, pulp duplicates, and repeat assays when a discrepancy is found for each work order. ALS Chemex provides the results of these assays on each assay certificate.

 

13.2.8              Independent statement on sample preparation, analysis and security

 

Sample security of diamond drill core samples for the Chapada Project is of industry standard. Analysis of certified standard assays indicates high accuracy and precision in the sampling and analysis of samples. Analysis of blank sample assays suggests an almost perfect cleaning of equipment. A thorough assessment of sampling precision is allowed with the duplicate core samples in order to guarantee the reliable results. The inter-laboratory checks are done along with three other controls, which assure best quality and control assay results, and show any important deviation in the laboratory protocols and practices.

 

14               ADJACENT PROPERTIES

 

Some copper and gold prospects, as well as former artisanal mining areas exist along the trend of the anomaly. Other companies with exploration rights in the area include subsidiaries of Vale S/A Corporation, Codelco do Brasil Corporation, Amarillo Mineração do Brasil Corporation, Mineração Brilhante Corporation and Ferlig - Ferro Liga Corporation.

 

79



 

15               MINERAL PROCESSING AND METALLURGICAL TESTING

 

15.1              Metallurgical Testing

 

15.1.1              Chapada Metallurgical Testing

 

In the author’s opinion, the sampling, sample preparation and assaying procedures, have resulted in representative samples of the Chapada Project deposit.

 

The following is from the Chapada Copper-Gold Project Goias State, Brazil prepared by Hatch and IMC in August 2004 and describes the metallurgical testing data available as of the date of the feasibility study.

 

There has been a significant amount of process testing completed on the Chapada Project by third parties. The results of this test work provide the basis to develop a straight-forward process flowsheet for treating the ore.  Test results indicate that a clean, predominately chalcopyrite concentrate can be produced with associated gold. Tests and design work indicate that a concentrate grade of 28% copper is achievable with acceptable recoveries of copper and gold.

 

The metallurgical testing has included the following major components:

 

a.             Mineralogic studies.

 

b.             Grinding and Bond Work index tests.

 

c.                                       Grind size versus flotation recovery studies including the evaluation of regrind after rougher flotation.

 

d.             Flotation studies to evaluate reagents, pulp density, pH, and residence time.

 

e.             Settling tests for thickener design.

 

Sufficient testing was completed such that Kilborn was able to develop a bankable feasibility design for the process plant in 1997.  The Kilborn flowsheet and plant design was used by Yamana’s predecessors to obtain an updated turnkey cost estimate for plant construction and operation.

 

The process testing history is summarized below:

 

Feb 1975:

INCO, “Flotation Tests on Project M” — Inco

 

 

April 1979:

“Report RT-91228-01-R1”, INCO — Parsons-Eluma Projetos e Consultoria S/C

 

 

May 1980:

“Report RT-91228-03-R1”, Eluma-Noranda RPT “Relatorio 13898”, Eluma-Noranda

 

 

Dec 1981:

METAGO, “Metallurgical Processing”, Eluma-Noranda

 

 

May 1982:

METAGO, “Report on Bench Scale Flotation”, Eluma-Noranda

 

 

Sep 1995:

METAGO, “Estudos de Processo para a Mineracao S. Elina”

 

80



 

Aug 1996:

MacPherson Consultants, “Proposed Grinding Circuite for Chapada

 

 

 

Ore”, Santa Elina — Echo Bay Mines.

 

 

Feb 1997:

LAKEFIELD RESEARCH, “Recovery of Copper and Gold from Samples of Chapada Ore- Progress Report N.1”, Santa Elina-EchoBay

 

 

Oct 1997:

AUGMENT, “Chapada Amenability Test Report”, Santa Elina-Echo Bay.

 

 

Nov 1997:

Billiton Process Research, “Report PR97/90 — Bacterial Oxidation of Chapada Concentrate” Echo Bay.

 

2004:       CIMM and HDA Services S/C Ltda. - SAG/Ball mill test work reports. The study regarding bacterial leaching of the concentrate is not being applied to the project at this time.  Conventional smelting of the concentrate is anticipated.

 

For the feasibility study, Hatch relied on the December 1981 metallurgical processing report, the 1997 Lakefield report and the 2004 CIMM / HDA Services S/C Ltda. report as the basis for the current flowsheets.

 

·                  The Parsons- Eluma report, from the 1981 / 1982 work, was carried out at the Metago facility in Goiana, Brazil.  The tests were carried out on bulk samples from the exploration shaft and crosscuts.  Locked cycle flotation tests were carried out. A primary grind of 55% -150 microns was selected, although it was noted that the test results were not particularly sensitive to grind. This report is only of value as a guide, as the flowsheet at that time was radically different to what is envisaged for the feasibility study. It included the production of separate pyrite and copper concentrates, preceded by multi stage crushing, and rod and ball milling.  Parsons-Eluma Projetos e Consultoria S/C reported that recovery was high, but no assessment of recovery and grade is provided in the report, other than a conclusion that a 28% Cu concentrate would be achieved, with a constant tail of 0.04% copper.

 

The Lakefield report of 1997 is a more comprehensive report, presented in a manner that allows some conclusions to be drawn. In addition, the Lakefield personnel involved in this work were still available for discussion and commentary.  Lakefield based their work on an aggressive bulk rougher flotation, regrinding of the rougher concentrate and cleaning to produce a high grade concentrate. On the basis of their work, Lakefield presented the projected metallurgy for Chapada as follows;

 

Table 15.1: Lakefield Projected Metallurgy

 

 

 

 

 

Assay

 

Distribution %

 

 

 

% wt

 

% Cu

 

g/t Au

 

Cu

 

Au

 

Feed

 

100

 

0.338

 

0.328

 

100

 

100

 

Cu Rougher Conc.

 

7.29

 

478

 

3.6

 

95.3

 

73.8

 

Cu Cleaner Conc.

 

1.09

 

28

 

18.5

 

90.2

 

61.6

 

Cu Cleaner Tail

 

6.2

 

0.3

 

0.71

 

5.1

 

12.2

 

Au Carbon

 

 

 

 

 

 

 

 

 

10.2

 

Final Tail

 

98.9

 

0.034

 

0.09

 

9.8

 

28.2

 

 

Gold recovery to cleaner concentrate was 61.6%.

 

81



 

The Lakefield work also found a relative insensitivity to grind between p80’s of 100 and 200mm. As with Parsons-Eluma, Lakefield also selected a p80 of 150 microns, with regrinding to finer than 50 microns to achieve the final concentrate grade.  The selection of a 28%Cu concentrate at a recovery of 90.2% copper was based on a relatively small number (4) of locked-cycle tests.

 

Hatch concurs with the 28% Cu concentrate grade, but have used the IMC life of mine recoveries of 88.6% for copper recovery and 54.6% gold recovery based on the life of mine head grades and the use of a fixed tails grade. This calculation of recovery is therefore more conservative than the Lakefield conclusions. If a test-work program were to be carried out now, current standards would probably include more samples taken from throughout the ore body, and would include a metallurgical mapping program. In addition, Hatch would recommend further tests to investigate the relatively low gold recovery.

 

In January 2004, under Yamana’s supervision, five large 4 metre diameter “shafts” were excavated at Chapada to obtain bulk samples for testing at the CIMM laboratory in Santiago for SAG (semi autogenous grinding) / Ball mill evaluation.  The shafts were excavated through the soft soil and overburden, and into the ore to a total depth of 30-40 metres.  The samples collected, over 100 tonnes, were shipped to CIMM in Santiago, and a SAG / Ball mill campaign conducted during February and March of 2004.

 

The tests indicated a work index of 15-16 kWh/t, which was somewhat higher than the values indicated in previous work (12-13 kWh/t).  These higher values were used, due to the quality of the samples and the reputation of CIMM, to develop the grinding circuit and size the main equipment, (mill and pebble crusher size and power, and SAG mill discharge screen).  The testwork was managed by HDA Services S/C Ltda. of Sao Paulo, and the results provided to Hatch. Only a limited amount of sedimentation and filtration work was carried out, by Hazen Research, Inc. in 1996.

 

In December 2008, HDA Serviços Ltda.prepared a comminution circuit report detailed below. Solid ore characterization program and comprehensive survey campaigns were the basis for simulations carried out for the expansion of Chapada Project grinding circuit. The former included the assessment of breakage characteristics and flotation performance of five individual ore types as occurring in the Chapada deposit, while the latter comprised two detailed surveys in the existing industrial grinding circuit.

 

The breakage characteristics of all five main ore types were assessed by high-energy comminution (DWT — Drop Weight Test), low-energy comminution (abrasion test) and ball milling (BWI — Bond Work Index). In all cases the ANX (amphibole schist) ore type indicated distinctive breakage characteristics, as compared to the other four ie. SRT (sericitic schist), QSRT (sericitic quartzite), GNS (gneiss) and BTO (biotite schist). Accordingly, testing results showed that ANX is a much more competent ore, while BTO and SRT were considered friable ore types. Both GNS and QSRT were classified as extremely friable in terms of resistance to high-energy comminution.

 

Even though the ANX indicated the highest value of bond work Index among the five ore type results, the differences were not as severe as those obtained for the high-energy resistance. Bond Work Index was within the12.01-14.44 kWh/t range for all five ore types.

 

Flotation testing indicated that highest copper and gold recoveries were obtained for samples ground at P80 within the 0.21-0.25 mm range for the SRT, QSRT, GNS and BTO ore types. Conversely, the ANX ore type indicated a finer grinding size corresponding to highest copper and gold recoveries, in this case at P80 equals to 0.15 mm.

 

82



 

The models developed on the basis of the current Chapada Project’s industrial operation were considered robust for simulating the entire grinding circuit, including all processing equipment such as SAG and ball mills, cone crushers, screens and cyclones, as well as HPGR (High Pressure Grinding Rolls). In particular, the HPGR model was calibrated on the basis of comprehensive testing program carried out at a selected manufacturer laboratory, in Germany.

 

On the basis of individual calibrated models, a base case was assembled, which consisted of a complete Chapada Project comminution circuit integrated within a simulator to represent the current circuit operation, under nominal conditions. Nominal capacity was here referred as 16 Mtpy which resulted in 2058 tph plant throughput.

 

During 2010, it was built an expansion project to achieve 22 Mtpy that was based solely on installed equipment at the Chapada Project’s grinding circuit. The existing mills (SAG and ball mill) were adjusted to operate under increased power draw mode, which resulted in the extra energy required for fragmentation P80 of 0.22-0.23 mm.

 

15.1.1.1             Chapada Treatment Plant Test Work Report

 

The report conducted by UIMIN recommended many physical additions to the existing Chapada Project treatment plant and changes to operating procedures in order to improve copper and gold recoveries in the Chapada Project’s plant. One of the requirements of the study was to look at the implications of introducing Suruca ores into the existing Chapada Project’s treatment plant for treatment of these ore in combination with the Maraca ores.

 

Pilot and bench scale testing of the plant was conducted on the Maraca ores and various recommendations were made in the report for both the existing operation and for future metallurgical test work.

 

The report considered the installation of additional milling and flotation capacity for the separate production of copper concentrates and pyrite concentrates. The production of a separate pyrite concentrate would allow for the treatment of the Suruca ore body and the separate production of copper concentrate and gold bullion on site.

 

15.1.2              Suruca Metallurgical Testing

 

15.1.2.1             Technological Characterisation of the Ore

 

The Suruca Project’s ore deposit can be broken into two distinct basic ore types;

 

·                  Suruca oxide ore; and

 

·                  Suruca sulphide ore.

 

There is a narrow transitional zone between the oxide and sulphide zones but for all intensive purposes, the characterisation of the ore will be either oxide or sulphide. Separate test work programs were initiated for the oxide and sulphide samples. The following programs were initiated:

 

·                  Characterisation — USP Laboratories;

 

83



 

·                  Physical Parametres Characterisation — HDA services Pty. Ltd.;

 

·                  Gravity and Leaching Studies — Knelson Research and Technology Centre;

 

·                  Exploratory Studies for Flotation and Leaching Steps 1 and 2 — John Clark, Yamana Metallurgy Department and Funmineral Laboratories; and

 

·                  Evaluation Studies of Heap Leaching — Kappes, Cassiday & Associates.

 

A draft metallurgical report was produced by Yamana in September 2010 summarising the tests conducted to date and results available. The draft report is entitled “Relatorio de Estudos Metalurgicos — Alvos de MMIC” and translates as “Metallurgical Study Report on Ore from the Maraca Region”.

 

At the Maraca site, improvements in the recovery of gold and copper from the existing Chapada Project’s treatment plant, were being investigated concurrently running bench and pilot scale testing on the various Maraca ore types. The study was completed by U. I Minerals (UIMIN) in July 2010 and was entitled “Review of & Recommendations for the Chapada Plant — Current and Future Developments”.

 

Three ore types were studies but only two ores were relevant in the context of the Suruca ore deposit:

 

·                  Suruca gold oxide; and

 

·                  Suruca gold sulphide.

 

 

 

Suruca Gold Sulphides

 

Suruca Gold Oxides

 

Gold Grade (g/t

 

0.57

 

0.45

 

 

 

 

 

 

 

Copper Grade (ppm)

 

156

 

246

 

 

 

 

 

 

 

Total Sulphur Grade (%)

 

1.68

 

0.11

 

 

15.1.2.1.1             Oxide Characterisation

 

A summary of the oxidised ore studies are as follows;

 

The characterisation studies carried out by USP using MLA analysis indicated the following;

 

·                  Free gold particles 3.7% (greater than 37 microns);

 

·                  55% of the gold associated with oxygen and hydroxides of iron;

 

·                  31% of the gold associated with silicates;

 

·                  10% of the gold associated with other minerals; and

 

·                  The gold grains have an average size of 8 microns.

 

·                  Cyanide leaching of the whole of ore sample at 100% passing 840 and 150 microns indicated gold recoveries of 75.9% and 89% respectively.

 

·                  Physical characterisation test work indicated a bond work index (BWi) value of 16.6 kWhr/tonne for a product grind size of 74 microns indicating that the Suruca oxide

 

84



 

sample tested is moderately hard from the perspective of conventional ball mill grinding. drop weight index (DWi) testing indicated that the sample tested was extremely friable;

 

·                  Gravity characterisation test work was carried out by Knelson Research Laboratories. A conventional GRG (gravity recoverable gold) test indicated a gravity recovery of 35.4% recovery. Leaching of the gravity concentrate with cyanide indicated a leach recovery of a 99%. This is compared to direct leaching of the ore crushed to less than 147 microns gave a cyanide leach recovery of 93.6%;

 

·                  Flotation test work conducted on the oxide samples produced poor results with an overall flotation and leaching recovery of the flotation concentrates produced of approximately 30% of the feed gold content;

 

·                  Column leach tests conducted were positive. 92% of the contained gold was recovered from the oxide sample submitted in a period of 52 days leaching. The sodium cyanide consumption was calculated to be 0.44 Kg/tonne using a Portland cement addition rate of 18 Kg/t. The agglomerated sample was also strongly agglomerated based on the promising “slump” tests results indicating 0% slump with no pooling or channelling noted during the testing.

 

15.1.2.1.2             Sulphide Characterisation

 

A summary of the sulphidised ore studies are as follows;

 

· The characterisation studies carried out by USP using MLA analysis indicated the following;

 

·                  Free gold particles 26% (greater than 37 microns);

 

·                  59% of the gold associated with sulphides, predominantly Pyrite;

 

·                  9% of the gold associated with silicates;

 

·                  4% to 6% of the gold associated with tellurides; and

 

·                  The gold grains have an average size of 3 microns.

 

·                  Cyanide leaching of the whole of ore sample at 100% passing 75 microns indicated a gold recovery of 88.0. Technological characterisation of the sample indicated a total gold recovery of 76.9% for a sample less than 300 microns in size;

 

·                  Physical characterisation test work indicated a Bond Work Index (BWi) value of 15.4 kWhr/tonne for a product grind size of 74 microns indicating that the Suruca sulphide sample tested has a moderately to high hardness from the perspective of conventional ball mill grinding. Drop Weight Index (DWi) testing indicated that the sulphide ore is very competent in nature;

 

·                  Gravity characterisation test work was carried out by Knelson Research Laboratories. A conventional GRG (Gravity Recoverable Gold) test indicated a gravity recovery of 35.2% recovery. Leaching of the gravity concentrate with cyanide indicated a leach recovery of a 95%. This is compared to direct leaching of the ore crushed to less than 109 microns gave a cyanide leach recovery of 82.3%;

 

·                  Flotation testing was conducted in two separate stages. The stage 1 results utilising locked cycle testing indicated gold recoveries of 82% and 85% when leaching the flotation concentrates produced. The second set of flotation tests indicated 82%

 

85



 

recovery for flotation and 85% leach gold recovery of the concentrate produced at a grind size p80 of 75 microns.

 

15.2              Process Design Criteria — Run of Mine

 

Based on the metallurgical test work results, the mine plan from AMEC and the fact that copper and gold grades in the nearby Maraca (Chapada) treatment plant are decreasing over time, the following strategy was adopted:

 

Treat the oxidised component of the Suruca Project’s ore using conventional heap leaching with agglomeration technology; and

 

Modify the existing Maraca treatment plant to improve recoveries of both copper and gold from both the Maraca and Suruca Project’s ore-bodies. The Maraca plant will be modified in response to the introduction of Suruca Project’s sulphide ore in 2017.

 

As a result of the separate oxide and sulphide treatment plants, two separate design process design criteria were developed.

 

These are detailed below in Table 15.2 and Table 15.3.

 

Table 15.2: Oxide Process Design Criteria — Heap Leach Operation

 

Item

 

Value

 

Average Annual Stacked Treatment Rate (tonnes)

 

4,000,000

 

Average Gold Grade Stacked (g/t)

 

0.477

 

Overall Plant Gold Recovery (%)

 

90.0

 

Average annual production of gold (oz)

 

55,209

 

Run of Mine (ROM) top size (mm)

 

600

 

Ore Moisture Content — Range (%)

 

5 to 8

 

Agglomerated Ore Moisture Content (%)

 

12 to 15

 

Apparent Density of ROM ore (t/m3)

 

1.4

 

Average Cement Addition Rate (kg/t)

 

15.0

 

Average Cyanide Addition Rate (kg/t)

 

0.10

 

Design Application Rate (litres/hour/m2)

 

10.0

 

Number of Leach Cycles

 

1

 

Application Period (days)

 

90

 

Design Application Volume (m3/tonne)

 

3.2

 

Life of Mine (LOM) (years)

 

6

 

 

86



 

Table 15.3: Sulphide Process Design Criteria — Modified Maraca Treatment Plant

 

Item

 

Value

 

Annual Treatment Rate (tonnes) — Plant

 

22,000,000

 

Annual Treatment Rate (tonnes) — Suruca

 

7,377,000

 

Annual Treatment Rate (tonnes) — Chapada

 

14,663,000

 

Integrated - Life of Mine (LOM) (years)

 

6

 

Proportion of Suruca Ore in Plant Feed Blend (%)

 

33.4

 

Proportion of Chapada Ore in Plant Feed Blend (%)

 

66.6

 

Gold Grade (g/t) — Plant

 

0.278

 

Gold Grade (g/t) — Suruca

 

0.553

 

Goid Grade (g/t) — Chapada

 

0.141

 

Gold Recovery (%) — Plant

 

69.4

 

Gold Recovery (%) — Suruca

 

79.8

 

Gold Recovery(%) Chapada

 

64.2

 

Gravity Gold Recovery (%) Plant

 

33.4

 

Flotation Gold Recovery (%) Plant

 

46.4

 

Annual production of gold (oz)

 

136,627

 

Copper Grade (%) — Plant

 

0.161

 

Copper Concentrate Grade (%) — Plant

 

23.65%

 

Copper Recovery (%) — Plant

 

84.8%

 

Copper Recovered (tonnes) Plant

 

30,048

 

Copper Concentrate (tonnes) Recovered

 

127,053

 

Crushing Circuit Operational Efficiency (%)

 

75

 

Comminution and Hydromet Operational Efficiency (%)

 

92

 

Operating Work Index Requirement — p80 of 75 µm (kWhr/t) - Plant

 

28.5

 

Flotation Circuit — Mass Pull to Copper Concentrate (%)

 

1,5

 

Flotation Circuit — Mass pull to Pyrite Concentrate Leach Circuit (%)

 

4,52

 

Cyanide Addition Rate (Kg/tonne of concentrate)

 

0,42

 

SMBS Addition Rate (Kg/tonne of concentrate)

 

0.75

 

Collector Addition Rate (Kg/tonne of new feed)

 

40

 

SAG Mill Grinding Media Consumption — 5” (g/t of new feed)

 

200

 

Ball Mill Grinding Media Consumption — 3” — (g/t of new feed)

 

300

 

Vert-Mill Mill Grinding Media Consumption — 1” — (g/t of new feed)

 

25

 

Pyrite Grinding Mill Media Consumption — 2” (g/t of new feed)

 

300

 

Total Grinding Media Consumption — Plant (g/t of new feed)

 

825

 

 

87



 

15.2.1              Oxide Plant Process Description

 

15.2.1.1             Crushing and Stacking

 

The crushing circuit consists of two MMD sizers in series and associated equipment. ROM material from the mine is fed to the first of the MMD sizers using either dump trucks or front end loaders. The ROM material is unloaded directly to the ROM bin through a 400 mm aperture fixed grizzly screen. The grizzly screen oversize is collected, broken with a mobile rock-breaker and fed to the ROM bin at a later time. Grizzly undersize material is then stored in the ROM bin and control fed to the MMD sizer via apron feeder. Material is pre-screened before the MMD sizer using a fixed screen with the undersize reporting directly to the crushed product conveyor. Material passing through the first MMD Sizer (625 model) passes directly to the second MMD Sizer (625 model) in series. MMD crusher product then combines with screen undersize and is conveyed to the crushed product stockpile. The crushed stockpile is covered with a plastic cover to prevent the crushed product being exposed to the rain. The covered stockpile can be accessed with a front end loader to clean out the bin and conveyors under the stockpile when required.

 

Crushed product is then control fed to an agglomeration drum. Prior to the drum, cement is added in a controlled fashion based on the agglomeration drum feed rate and pre-set cement addition rate. In the agglomeration drum, a weak cyanide solution (barren pond solution) is added and mixed to produce agglomerates which are conveyed and stacked. A series of semi-portable conveyors runs the material outside the plastic lined pads. A further set of mobile conveyors transports the material down the centre of the pads to the stacking conveyor. All of the semi-mobile and mobile conveyors are covered to prevent further exposure to rainfall.

 

The crushed ore can also be fed to the agglomeration drum using a front end loader when the crushing plant is stopped. The wheel loader can enter under the plastic sheet to feed the conveyor underneath. At the end of the mobile and semi-mobile conveyor system the material is transferred to a cross conveyor and finally transfers to the heap leach stacker, which discharges the agglomerated material at a height of 8 metres. The agglomerated material is stacked on pads which are prepared using impermeable HDPE plastic. The pads are approximately 100 metres wide and 620 metres long.

 

15.2.1.2             Internal rate of returnigation

 

The pads have a slight inclination to allow collection of the internal rate of returnigation liquor at one end of the prepared pad. The heap leach pads are stacked from one end to the other, with the mobile conveyors progressively removed as the stacker moves up along the length of the pads. The heap leach pads are divided into three distinct phases:

 

·                  Active leaching

 

·                  Rinsing; and

 

·                  Idle ore (before leaching and after leaching and rinsing).

 

Once the stacking process is completed, the agglomerated ore is allowed to dry for a period of 1 to 4 days depending on the prevailing climatic conditions. Internal rate of returnigation lines are installed onto the top surface of the stacked ore. In the high rainfall months, a sprinkler

 

88



 

(wobbler) internal rate of returnigation system is used to promote evaporation and during the low rainfall months drip internal rate of returnigation is utilised to reduce evaporation rates.

 

A weak cyanide solution from the barren solution pond at basic pH levels (10 to 12) is then used to internal rate of returnigate the stacked ore. The weak solution filters through the agglomerated ore with the gold inherent in the ore leached into solution to produce a gold rich solution. The gold rich solution collects at the base of the pad and is diverted to the end of the pad and collected in a drainage system. The gold rich pregnant solution runs through a plastic lined drainage system to the pregnant solution pond.

 

Two other drains exist (3 in total). The second drain collects rinse water which is utilised to neutralise the cyanide in the heaps after cyanidation has been completed. The rinse water is directed to the emergency pond for re-use at a later time. The third drain is used to collect rainfall from the top of the heaps. Heaps which have been leached and rinsed are covered with HDPE plastic and the rain water (free of chemicals) is directed to a water collection dam which can be reclaimed during the drier months.

 

15.2.1.3             Solution Ponds

 

The process plant consists of 6 plastic lined HDPE ponds and 1 water collection pond. The 6 plastic lined ponds are as follows;

 

·                  Pregnant solution pond — Receives gold rich liquor from the active leaches. This solution is then pumped through the adsorption columns. In instances of high rainfall, the pregnant solution pond overflows in the barren solution pond;

 

·                  Barren solution pond — Receives solution from the adsorption columns once gold is removed onto activated carbon. Make-up water which is either water from the emergency pond or water collection dam and cyanide, is added to this pond during the drier months to maintain internal rate of returnigation solution volume application rates. Solution from the barren pond is pumped to the active leach and to the agglomeration drum using separate pumps. During the wet months during high rainfall periods internal rate of returnigation will cease whilst gold adsorption will continue. When the barren solution pond is full, solution overflows into the emergency solution pond;

 

·                  Carbon fines pond — At the completion of the carbon regeneration process, the regenerated carbon is screened to remove fine carbon. The fine carbon is directed to a small plastic lined pond. The overflow from the carbon fines pond runs into the barren solution pond;

 

·                  Emergency solution pond — The emergency solution pond prevents weak cyanide solutions from entering the environment. During the wet months the pond acts as an emergency containment system during periods of high rainfall events. This solution is then returned to the system for gold recovery. During the dry months the pond acts as a water reservoir and make-up pond. It receives water from the local river system and from the water collection pond. Water from the emergency pond is added to the barren solution pond using a pontoon pump arrangement in the emergency pond;

 

·                  Neutralisation ponds 1 and 2 — At the completion of the active leach process, weakly complexed cyanide within the heaps must be neutralised prior to reclamation. The ponds are small ponds which are used to internal rate of returnigate the inactive leach pads with copper sulphate and hydrogen peroxide. The first neutralisation pond is used to mix the copper sulphate and hydrogen peroxide. The second pond is the internal rate

 

89



 

of returnigation pond. Solution is pumped to the disused heaps. Solution return flows to the emergency pond. The solution is re-used at a later time;

 

·                  Water collection pond — The water collection pond or safety dam is a clay lined pond which receives water from the local river system (Rio dos Bois) and also rainfall run-off from plastic lining over the top of internal rate of returnigated and rinsed ponds. The water is reclaimed during the dry seasons and either runs into the environment naturally when full or is pumped/discharged to the environment when required.

 

15.2.1.4             Adsorption and Elution

 

Pregnant solution is sampled and then sent to the adsorption feed tank. The solution flows through 4 adsorption columns in series and flows by gravity from one adsorption column to the next. In each of the column is 6 x 12 mesh activated carbon at a concentration of approximately 24 grams per litre in solution or a total of 12 tonnes of carbon.

 

Barren or eluted carbon is added to the last adsorption column and pumped forward to the next adsorption column in a counter current mode. A sieve is installed on the discharge of each of the adsorption column to prevent the carbon flowing to the next adsorption column.

 

The total residence time in the adsorption columns is in the order of 25 minutes. The final liquor discharged from the final adsorption column containing a low concentration of gold is sent to the barren solution pond.

 

Loaded activated carbon is transferred to an acid wash tank where the loaded carbon is washed with a cold dilute hydrochloric acid solution to remove organic salts of calcium and magnesium from the loaded carbon surface prior to the elution process.

 

After acid washing, the carbon is washed and sent to the elution column to remove gold from the loaded carbon. The atmospheric Zadra process will be used to elute or desorb the contained gold from the loaded carbon. The Zadra desorption process consists of the desorption of the precious metal present in the loaded carbon by washing with a solution of NaCN and NaOH at high temperature (85 to 95º C) and at ambient pressure and requires around 24 hours to complete.

 

The gold removed from the loaded carbon cools in a flash cell and then reports to the two Mintek electrowinning cells in parallel. Gold in solution is removed onto stainless steel cathodes. The electrowon solution then flows to the solution tank below the electrowinning cells. The solution is then pumped to a gas heater and then continues on to the elution column for further elution. Once the solution returning from the elution column is below 1 ppm gold in solution the elution process is stopped. The eluted or barren carbon is then rinsed and sent to the carbon regeneration process.

 

Once per week, the stainless steel cathodes are rinsed off with a high pressure washer. The cathode sludge is then filtered, dried in an oven and then transferred to the barring furnace. Fluxes are added to the barring furnace which is then heated to around 1150oC. Gold is then poured into molds.

 

90



 

15.2.1.5             Utilities

 

Eluted carbon is sent to the thermal regeneration kiln to remove inorganic material which has loaded into the pores and onto the surface of the carbon such as naturally occurring oils.  The carbon is heated to between 650 and 750oC in a sealed and steam atmosphere. The regenerated carbon is then screened to remove fine carbon generated during the elution and regeneration process. Carbon oversize is cooled using water in a carbon storage hopper. The carbon fines report to the fine carbon settling pond.

 

New carbon is added to the process when carbon in circuit stocks drop. 500 kilograms bulk bags are used to maintain circuit stocks. Regenerated oversize carbon is then pumped to the last adsorption column.

 

As previously stated, hydrochloric acid is used to wash the activated carbon to remove particles of calcium and magnesium. The acid will be received as 1000 bulk drums and then pumped through to the acid mixing tank where it is mixed with water to a concentration of around 3% w/w HCl. The dilute solution is re-circulated through the acid wash hopper.

 

Sodium cyanide solution is used in the leaching process and in the desorption process. The sodium cyanide will be stored in 1 tonne bulker bags and will be mixed with fresh at a concentration of 30% solids w/w. The dosage of sodium cyanide will be in the order of 100 grams per tonne of ore stacked. Any gases generated will be removed through an exhaust fan. To ensure consistent cyanide addition rates and cyanide concentrations reporting to the active leach cells, a cyanide storage tank and dosing pump will be installed. Another pump is installed to dose cyanide into the solution dosing line going to the agglomeration drum. Cyanide will run by gravity to the elution storage tank.

 

Portland or “High Early” strength cement will be used in the agglomeration process for crushed ore with an average dosage equal to 15 grams per tonne of ore processed. The cement will be delivered in trucks equipped with air compressors and unloaded directly into 2 installed cement silos. These silos will be installed above the crushed product discharge conveyor and fed at a controlled onto the discharge conveyor using screw feeders.

 

Caustic soda or sodium hydroxide is used in the desorption of gold from loaded carbon. The caustic soda will be delivered in 25 kilograms bags and mixed in a tank and then transferred to a doing tank. From there, the solution is added to the elution circuit.

 

Liquefied gas will be used in the elution circuit and the gold room for heating and smelting. The project calls for a tank to be installed in the field to meet this need and to store enough LPG to supply the plant for two weeks continuously.

 

A fuel station installed in the field will be required for all light vehicles used in the plant, and for mobile plant equipment (front end loaders, excavators and rock breakers) as well as for the fleet of trucks and other mining equipment including scrapers and tractors. The facilities must have the capacity to supply all equipment for a period of one week continuously.

 

15.2.2             Sulphide Plant Process Description

 

An individual processing plant option for the Suruca Project’s ore body was initially considered for the treatment of the sulphide ore component. However, due to the relatively short life Suruca Project’s deposit life of mine (“LOM”) time span, the required annual throughput rate and low gold grades it was decided to look at other options for treatment. As the Chapada Project’s ore

 

91



 

body grades would be in decline at the commencement of the Suruca Project’s sulphides ore treatment, it was decided to treat the Suruca Project’s ores within the existing Chapada Project’s plant with modifications. The following treatment route described is based upon the recommendations made by UIMIN and additional requirements considered by AMEC Minproc.

 

15.2.2.1             Primary Crushing

 

Two types of ore will be fed to the Chapada Project’s treatment plant:

 

·                  Chapada ore and

 

·                  Suruca ore.

 

The Chapada Project’s ore will be crushed in the existing MMD 1000 sizer or the existing C200 single toggle jaw crusher depending on the hardness of the ore being treated. The MMD sizer will treat the finer softer ore bodies at Maraca (BTT-F, GNS and QRST) and the harder, coarser ores (ANX and BTT-M) treated through the jaw crusher.

 

The Suruca ore will be treated in two Lokotrack LT140 crushers situated adjacent to the Suruca open pit. These portable crushers are existing crushers and will be able to treat the 8 Mtpa of Suruca ore. The Lokotrack crushers are standard single toggle jaw crushers that are track mounted and portable.

 

The crushed ore from Suruca will then be either transported to the Chapada Project’s plant via an overland conveyor system between the two operations. The Suruca open pit is located approximately 7.5 kilometres from the Chapada Project’s plant. A study was developed to determine which option for ore transport will be chosen and the overland conveyor option revealed to be more economically viable.

 

The MMD Sizer has a fixed screen prior to crushing and has an individual feed ROM bin. Ore is fed using an apron feeder to the fixed screen. Oversize reports to the crushed ore feed conveyor below and the oversize passes through the MMD sizer and recombines with the screen undersize product. The material is then transported to the primary crushed ore stockpile. The C160 crusher has a fixed grizzly to remove oversize rocks and oversize rocks are removed, broken with a rock breaker and re-fed at a later time.

 

Material which passes through the grizzly is delivered at a controlled rate to the primary crusher via an apron feeder. The product reports to a fixed screen with the fines by-passing the primary crushing step. Oversize material retained on the feeder is fed to the C160 jaw crusher. Jaw crusher product is combined with feeder undersize material and conveyed to the same crushed product stockpile and combined with the MMD crushed product. It is anticipated that the crushed product from the Suruca Project’s deposit will be fed directly onto the jaw crusher product conveyor.

 

The existing crushed product stockpile has a live stockpile capacity of 30,000 tonnes or 15,800 m3 and total stockpile capacity of 200,000 tonnes or 107,300 m3. This stockpile will continuously feed the grinding circuit at a controlled rate. An external emergency stockpile will also be constructed and used during periods of extended crushing circuit downtime.

 

92



 

15.2.2.2             Grinding and Classification

 

Primary crusher product from the stockpile will be transported by fixed speed conveyor to an existing high aspect 34 foot diameter by 19 foot EGL SAG mill with 2 x 6250 kW drive motors fitted on individual pinions. A fixed weightometer will be installed on the conveyor at a point after the discharge of material from the stockpile feeders. The Primary SAG mill discharge product reports to an existing double deck vibrating screen with dimensions of 3 m x 6.1 metres and bottom deck apertures of 12 mm x 30 mm. A spare screen exists and in the event that one of the screens is offline for maintenance, the other screen can be rolled into position quickly.

 

Discharge screen (pebble) oversize is transported by conveyor to an existing HP800 crusher with the crushed pebbles re-fed to the SAG mill. Two crushers are installed with one crusher operating and the other crusher on standby in the event that the other crusher is undergoing maintenance. Due to the heavy pebble crusher duty, two crushers are required in order to maintain the grinding and classification circuit operating efficiency of greater than 92%.

 

Mill discharge will pass over a flat deck horizontal vibrating screen. The screen will have a polyurethane deck fitted with 12mm x 25 mm slot apertures in the direction of flow. Material will be separated into oversize and undersize components. The screen will be installed with high volume and pressure water sprays to remove fine slimes material from the surface of the screen oversize. Oversize material will passes to a chute and fall onto a conveyor located at the discharge of the screen. This conveyor will stop when pebble crusher maintenance is conducted. As a result, the rock load in the chute overflows into a concrete bay below. This material is then collected and transported to a stockpile and re-fed when pebble crusher maintenance is completed.

 

Material passing through the screen is combined with intensive cyanide leaching system tailings in the cyclone feed hopper. Additional water is also added to control cyclone feed density. Cyclone feed is pumped to the existing primary cyclone cluster consisting of 6 x 33-inch diameter hydro-cyclones for classification. It is anticipated that 5 of these cyclones will be operating during the treatment of the Suruca and Chapada ore. One cyclone will be maintained as a spare and be ready to be used in the event that maintenance is required for another of the cyclones.

 

Cyclone feed material is then classified into an overflow (fine material) and underflow (coarse material) stream. The entire underflow stream is then fed to a splitting hopper. During normal operation, the material will report to the new gravity circuit installed (referred to as primary gravity circuit). In the event that the gravity circuit is undergoing maintenance, the material will report directly to the feed of the ball mill.  Cyclone overflow flows by gravity directly to the flotation circuit. Cyclone underflow material reports to 2 new vibrating gravity feed screens 2.4 metres wide x 6.3 metres long with 1.7 mm x 10 mm aperture slots. Screen undersize from each of the screens reports to a single gravity concentrator. Screen oversize combines with cyclone underflow from the secondary cyclone classification bank and the gravity concentrator tail and reports to ball mill feed.

 

The existing ball mill is a 24 foot x 40 foot conventional overflow ball mill fitted with 2 x 6250 kW motors. Ball mill discharge is screened over a trommel. Trommel oversize runs into an pebble oversize concrete bunker whilst trommel undersize runs into the ball mill discharge hopper where the pulp combines with the tailings from the second set of new installed centrifugal gravity concentrators, screen oversize from the installed secondary gravity concentrator feed

 

93



 

screens and the residue from the installed intensive leach reactor treating all of the gravity concentrate produced.

 

Ball mill discharge hopper product is pumped to an existing set of cyclones (secondary cyclone classification). Two banks of cyclones are installed, one bank consisting of 8 x 32 inch cyclones and the other bank consisting of 8 x 32 inch cyclones. Cyclone underflow flows directly to ball mill feed whilst cyclone overflow flows by gravity to the flotation circuit.

 

A second set of new pumps is installed onto the ball mill discharge hopper. The pumps are used to direct feed to the second set of gravity concentrator feed screens. Three new vibrating screens of 2.6 metres wide x 6.4 metres long screens are installed above the ball mill discharge hopper. Screen oversize feeds to the ball mill discharge hopper whilst screen undersize feeds to 3 new centrifugal gravity concentrators. Gravity tails feed the ball mill discharge hopper whilst gravity concentrate reports to intensive leach reactor with the concentrate from the primary centrifugal gravity concentrators.

 

The installation of the gravity concentrators in these 2 separate locations ensures that gravity gold is captured as soon as it becomes liberated.

 

15.2.2.3             Gravity concentration

 

In both of the location points, the primary cyclone underflow and the secondary cyclone feed, the screen feed passes over a flat deck vibrating screen to remove oversize material. Polyurethane screen panels fitted will have slots of 1.7 mm x 10 mm in the direction of flow. The screens will have high pressure water sprays to adjust the density of the feed pulp to the concentrator and also remove sludge from the surface of larger rocks. Five new screens will be fitted, 2 in the primary cyclone underflow and 3 in the secondary cyclone feed location. Pulp feed rate and density to the concentrators will also be controlled so that material does not overflow from the top of the concentrator.

 

Two different types of gravity concentrators can be utilised for the duty, Knelson XD-48’s or Falcon SB5200 concentrators. Two concentrators will be installed in the primary cyclone location and three concentrators in the secondary cyclone feed location. The concentration of the feed pulp will be adjusted again inside the concentrator using additional water injected into the concentrator bowl to assist in separation of gangue minerals from coarse, fine and sulphide associated gold

 

The output of the gravity concentrators will be discharged once per hour (maximum) and an intensive cyanide leach reactor that follows will be sized to accommodate the amount of concentrate produced from all of the concentrators.

 

A new single centrifugal C4000 continuous gravity concentrator also fitted to the discharge of the new and second cleaner flotation bank to remove fine gold associated with flotation tailings prior to entering the concentrate leach circuit. The sulphide concentrate from the C4000 (around 10% of the feed mass) will then be fed to a batch continuous centrifugal concentrator which will be either a Falcon SB750 or Knelson XD20 concentrator. This will remove very fine gold particles from the pyrite concentrate stream. The batch concentrate will then report to the intensive leach reactor.

 

94



 

15.2.2.4             Intensive leaching

 

The concentrate from the 5 large (XD48 concentrators or equivalent) and 1 small (XD20 concentrator or equivalent) gravity concentrator will be discharged at a maximum of once per hour. The intensive leaching reactor that follows will be sized to accommodate the volume of concentrate from all 6 concentrators. Two types of intensive leaching reactors are being considered, a Consep Acacia CS 6000 reactor or Gekkos ILR 10000 BA reactor.

 

The reactors use cyanide for intensive leaching of gold from the concentrate into solution. Sodium hydroxide is used to control pH (around 11-12) during the leaching cycle, which can take between 3 and 12 hours to complete, depending on the size of the gold recovered into the concentrate and the quantity of gold recovered. Up to three batches of concentrate can be leached per day depending on the leaching rate for the concentrate. A cyanide concentration of 20,000 ppm or 2% by weight will be used during the leaching cycle.

 

After the leach cycle is completed, rich clarified pregnant solution is pumped to the new electrowinning circuit holding tanks. Solid tailings washed from the leach reactor will then be sent to the ball mill discharge hopper or dumped directly on the mill floor (pumped to the cyclone feed hopper using a sump pump).

 

15.2.2.5             Sequential Flotation

 

Existing Circuit

 

The existing Chapada Project’s flotation circuit is used for the extraction of copper concentrate with a gold by-product which is associated with both pyrite and chalcopyrite. In order to maintain copper grade specifications a reduction in gold recovery is noted. Existing copper and gold recoveries for the Chapada Project’s ore types average 86% and 62.5% respectively. Gold recoveries are reduced in order to maintain copper grades above 23% by weight.

 

The existing flotation circuit consists of the following:

 

·              6 x 160 m3 rougher cells;

·              4 x 160 m3 scavanger cells;

·              6 x 21.5 m3 cleaner cells; and

·              2 x 160 m3 pyrite scavenger cleaners;

·              1 x 4 m diameter x 10 m high column flotation cells.

 

The concentrate from the rougher cells is first cyclone classified in an existing bank of 4 x 20 inch cyclones with cyclone underflow ground in an existing VTM 1000 WB Vertical mill with 750 kW of available power. Cyclone overflow reports to the cleaner cells. Cleaner concentrate reports through to the column flotation cell with the column cell concentrate reporting through as final copper concentrate and column cell tail reporting back to the feed of the regrind classification cyclones.

 

Modifications

 

In the modified circuit an additional 4 x 20 inch cyclones bank and 6 x 21.5 m3 cleaner cells will be added. The 6 x 21.5 m3 cleaner cells are already installed on site but have being used for other applications. A sequential flotation step will be added to separate the chalcopyrite

 

95



 

concentrate from the pyrite concentrate. This will be accomplished using high pH to depress flotation of pyrite.

 

The rougher and scavenger concentrates will be combined and fed to the regrind mill cyclone feed hopper where lime is added. The cyclone feed pump then pumps to the existing 20 inch cyclones and to a new 20 inch cyclone bank of 6 units, with both cyclone banks underflows running to the existing VTM 1000 WB Verti-mill.

 

The two regrind cyclone banks overflows will then be split into two parallel streams of 6 x 21.5 m3 cleaner cells with an elevated pH. The concentrates produced will be chalcopyrite rich and low in pyrite concentration. The two concentrates produced from the cleaner banks will be combined and sent to the feed hopper which feeds the column flotation cell. Cleaner bank tail will report to a tank and is control fed to the C4000 continuous gravity concentrator. This material will be the gold pyrite concentrate.

 

The combined rougher-scavenger tail is fed to new banks of 76 (total) cyclones of 15 inch in open circuit. Cyclone overflow material reports directly to the final tails hopper whilst cyclone underflow reports to a new ball mill installed. Ball mill discharge will be pumped to 11 flash flotation cells 1200 tonnes per hour with flash concentrate reporting to a 6 x 200 m3 cleaner bank. The cleaner bank concentrate reports through to the feed to the regrind mill cyclone feed hopper and joins the cleaning bank circuit. This ball mill and flash circuit is to ensure that losses associated with coarse primary grinds are reduced. The tails from the Flash rougher and cleaner cells are combined and fed to a new banks of 62 (total) cyclones of 32 inch. Cyclone underflow runs back to the ball mill feed and cyclone overflow is directed to the existing pyrite scavenger cells. The pyrite scavenger concentrate runs back to the feed to the rougher flash flotation cell (ball mill discharge) whilst the tail runs and combines with the new cyclone banks overflow prior to the secondary ball mill and the detoxification tail from the pyrite concentrate leach circuit.

 

All of the tailings is pumped directly to the final tailings dam.

 

15.2.2.6             Copper Concentrate Thickening and Filtration

 

Column flotation concentrate combines and feeds to an existing 13 metres diameter high rate thickener. Concentrate underflow at 60% solids w/w is fed to an existing concentrate holding tank with 998 m3 of capacity prior to filtration.

 

Filtration is conducted in an existing Larox pressure filter model with 72 m2 of filter area, model number PF60/72 M145. The filtered copper concentrate is stored in a covered area to prevent moisture increase prior to shipment in bulk.

 

15.2.2.7             Pyrite Leaching and Adsorption (new circuit)

 

Tails from the centrifugal concentrators (continuous and batch) are sent to a new pre-leach thickener to increase the solids density from around 25% to 30% solids by weight to 50% solids by weight. The thickener will be a 20 metres diameter high rate thickener. If required additional lime pulp is also added to the entrance to the first leach tank and the pH adjusted to between 10 and 11. Pulp is oxidised using an air ejection device located at the base of the tank to increase the level of dissolved oxygen (DO) levels to between 10 and 20 ppm.

 

96



 

No pre-oxidation will be required due to the presence if dissolved oxygen in the previous flotation steps. It is anticipated that 6 new CIL tanks with activated carbon and interstage screens will be used air is injected at the base of the tank to retain DO levels above 10 ppm. The six CIL tanks in series will be used for a total residence time of 24 hours at nominal throughput rates.  The DO level of the final leach tank is maintained above 7 ppm and the level of cyanide maintained above 100 ppm free sodium cyanide in solution in the final CIL tank.

 

The CIL tanks will have an agitator, air injection, carbon transfer pump (with recessed impellor) and vertical Kemix type inter-stage screens fitted. The activated carbon (coconut charcoal 6 x 12 mesh) will be transported using the transfer pumps. The carbon is transported in a counter current direction to the flow of pulp. It will be necessary that the inter-stage screen area is sufficient to ensure that during periods of high rates of carbon transfer that the adsorption tanks do not overflow. The vertical Kemix type screens proposed can be removed and substituted with replacement screens using a permanent overhead crane that will be installed.

 

The loaded carbon is removed from the lead (first or second tanks) adsorption tank using a recessed impellor pump. The pulp reports to a 0.65 metres width x 1.55 metres length vibrating screen (activated carbon screen) with polyurethane panels (slot 710μm x 10mm) with water sprays fitted to remove sediment from the surface of the loaded carbon. Clean loaded carbon flows by gravity to the acid wash column located directly below the screen. Screen pulp returns back to the lead adsorption tank.

 

The pulp from the final CIL tank will flow over a new 0.90 metres width x 2.24 metres length vibrating screen (carbon safety screen) and report to a new post leach thickener, also a 20 metres diameter high rate thickener. Water will be added to the thickener to dilute the cyanide level in solution reporting to the detoxification circuit.

 

15.2.2.8             Acid wash and elution (new circuit)

 

Loaded carbon from the CIL circuit front tank is transferred to the acid wash hopper or column that is equal in size and volume to the elution column. The loaded carbon is washed with raw water to remove sludge and the overflow from the acid wash column flows by gravity to the detoxification circuit. When the wash is complete, an acid wash step with hydrochloric acid (3% - 6% concentration) is conducted at atmospheric pressure and temperature. Acid solution circulates through the loaded carbon bed to remove any inorganic salts present on the surface of the carbon. Excess solution from the acid wash cycle is diverted to the detoxification circuit. Raw water is then pumped through the loaded carbon bed to remove excess acid and increase the pH of the solution back to neutral. When the output water has reached neutral pH, loaded carbon will be transferred using an eduction water system to the top of elution column. Raw water will be added to the elution feed tank as and when required. When the carbon transfer process has been completed to the elution column, drainage will continue until the carbon has fully drained at which time the elution process commences.

 

The selected process is the AARL elution method. During the acid wash cycle, an elution pre-heating cycle commences. The cycle consists of pre-heating a concentrated solution of sodium hydroxide and cyanide (3% cyanide and 2% sodium hydroxide), which will be distributed in a primary heat exchanger system under pressure, until reaching a temperature of around 120°C. When this temperature is reached, the solution is pumped to the bottom of the elution column under pressure (certified pressure vessel). Once the column is filled with solution, this allows wetting of the loaded carbon within the column. During the elution cycle, the solution exits at the top of the column and passes through a secondary heat exchanger which will then be used to

 

97



 

heat the softened water entering during the following step. The rich pregnant solution then passes to electrowinning solution storage tanks. It is anticipated that two solution storage tanks will be installed. During the elution step, clean water then passes through the primary and secondary heat exchangers before entering the bottom of the elution column. The clean raw water will continue to remove gold from the surface of loaded carbon. This process will be continued as needed to achieve a barren carbon grade of 50 ppm or lower.

 

Once elution is complete, barren (eluted) carbon will be washed with softened raw water and this wastewater will be pumped to the CIL circuit final tanks so that any residual gold recovered during the cooling down process will be recovered onto activated carbon. Once the barren carbon has been washed with sodium hydroxide and cyanide and sufficiently cooled, it will be sent to the feed tank of the new carbon regeneration kiln.

 

The carbon will feed the horizontal gas kiln. The kiln will not use any external source of steam and, when exiting the column, the regenerated carbon will pass through a screen to remove fine particulates generated during the elution and regeneration processes. Screen oversize material falls into the kiln discharge tank where it is water educted to the final CIL tank. When the stocks of carbon, within the adsorption circuit, fall below the required level, new activated carbon is fed to the kiln discharge tank and then fed to the final adsorption tank.

 

15.2.2.9             Gold room and electrowinning (new circuit)

 

Solutions coming from the intensive leaching and elution processes are pumped into one of two electrowinning solution storage tanks. Three electrolytic cells will be installed with two in operation and one spare. The cells will operate in parallel.

 

Each cell box will have perforated stainless steel plate anodes and cathodes of stainless steel mesh. The spare cell box will allow the gold to be removed whilst the electrowinning process can continue. The electrowinning circuit will be designed so that the cycle will be completed in no more than 16 hours, with levels of gold in solution reduced to below 5ppm. The barren solution will then be pumped back into the CIL circuit through a sump pump.

 

The gold deposited on the cathodes is removed from the stainless steel wool by means of a high-pressure washer and washed in a tank below where it is drained of excess water. The moist electrowinning sludge or cake is then dried in a furnace until all of the moisture is removed. The dried cake is then feed to an A100-type gas smelting kiln manually. Fluxes will be added and the kiln will be heated to around 1,150°C.

 

15.2.2.10      Detoxification (new circuit)

 

Discharge pulp from the tailings of the adsorption circuit will be pumped to the INCO neutralization tank that will have a residence time of 1.2 hours at the nominal throughput rate and at a concentration of 45% solids w/w (1 hour at maximum throughput rates). A spare tank will be installed in the event that maintenance is required during normal operation.

 

Air will be added into the INCO tank to achieve a minimum level of 3ppm dissolved oxygen along with SMBS for generating SO² gas. Copper sulphate for copper ions (catalyst for the reaction of the weak acid dissociable (WAD) cyanide ions) will not be required at the pyrite concentrate will have sufficient dissolved copper levels in solution. If required, lime is added to maintain pH at around 8 which is ideal for the reaction described below.

 

98



 

The basic reaction is as follows:

 

CN- WAD + SO2 + O2 + H2O ®OCN- + H2SO4

 

Cyanide + Sulfur Dioxide + Oxygen + Water ® Cyanate + Sulfuric acid

 

The chemicals listed will be added in a controlled manner by an automatic control system to ensure that the above reaction occurs and acceptable levels of free and WAD cyanide are discharged to the tailings dam.

 

It is recommended that the INCO detoxification tank be agitated and maintained at a near-maximum level at all times to ensure maximum residence time, sufficient agitation and the avoidance of pulp by-passing through the tank without undergoing neutralization. Final neutralised waste is pumped to the TSF (tailing storage facility) for tailings storage and water recovery.

 

15.2.2.11      Air Generation and Distribution

 

Compressed air is supplied to the CIL tanks, INCO detoxification cyanide neutralization tank, for maintenance work and for plant instrumentation. The air requirement will be dependant on existing air requirements and anticipated air requirements. Both will require reservoir tanks and the plant instrument air will also require filters and dryers for use within the new plant and equipment. During maintenance periods, a portable diesel air compressor should be used to meet the demand as required.

 

15.2.2.12      Utilities

 

Liquefied gas will be used in the elution circuit and the gold room for heating and smelting. The project calls for a tank to be installed in the field to meet this need and to store enough LPG to supply the plant for two weeks continuously.

 

The main chemicals and consumables currently used in the sulphide flotation plant include the following;

 

·              Collector - PAX and SIPX

·              Frother — M28 and Flotanol D-14

·              Lime — hydrated lime

·              Flocculant — anionic polyacrylide

·              Grinding media 5, 3, 1 and 2 inch balls.

 

It is expected that there will be minor changes to the above systems due to the increased consumption of collector, lime, frother, flocculants and grinding media for the additional new equipment.

 

In addition to the above requirements there will need to be new systems related to the installation of the gold leach plant and associated equipment including:

 

·        Sodium cyanide mixing, storage and dosing facilities;

·        Hydrochloric acid mixing and dosing facilities;

·        Sodium hydroxide mixing, storage and dosing facilities;

 

99



 

·        SMBS mixing, storage and dosing facilities; and

·        Activated carbon storage facilities.

 

100



 

Figure 15.1: Suruca Oxide Process Flowsheet

 

 

101



 

Figure 15.2: Chapada Treatment Plant - Existing Process Flowsheet

 

 

102



 

Figure 15.3: Chapada Treatment Plant - Recommended Process Flowsheet

 

 

103



 

16               MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES

 

16.1              Mineral resource estimate

 

16.1.1              Chapada

 

Emerson Ricardo Re, MAusIMM, Resource and Reserves Corporative Manager of Yamana, is the qualified person for Chapada Project’s mineral resources. Raúl Contreras, Metalica Consultores S.A, is the qualified person for mineral reserves. Based on the Yamana methods, Table 16.1 and Table 16.1 were developed as an estimate of mineral resources remaining after 2010 mining net of the mineral reserve presented in Table 16.1.

 

The mineral resources statement is based on the block model validated by Metalica in 2008 and reported on the technical report dated February of 2009.

 

The model was constructed using 10 metres x 10 metres x 5 metres. parent cell size within the project field limits. Vertical sections were interpreted using 0.15% Cueq. grade shell that was based to estimation plan. Two sets of estimation were defined, within Cueq grade shell and outside Cueq grade shell. Also, the estimations were done for separated dataset of Oxide, Mixed and Sulphide rocks that were add for futures process.

 

Measured resources are reported with existing oxide stockpile that total 65.250 Ktonnes of ore that represent 269,000 gold ounces.

 

Table 16.1: Mineral Resources - Net of Mineral Reserves

 

Mineral Resources - Net of Mineral Reserve

 

 

 

Resource

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained

 

Resource Category

 

Ktonnes

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Measured/Indicated Resource

 

 

 

 

 

 

 

 

 

 

 

Measured Mineral Resource

 

61,785

 

0.176

 

0.108

 

239

 

214

 

Existing Oxide Stockpile

 

3,465

 

0.000

 

0.491

 

 

55

 

Indicated Mineral Resource

 

278,787

 

0.187

 

0.098

 

1,146

 

881

 

Measured/Indicated Resource*

 

344,037

 

0.185

 

0.104

 

1,385

 

1.150

 

Inferred Mineral Resource

 

 

 

 

 

 

 

 

 

 

 

Inside Design Pit

 

0

 

0.000

 

0.000

 

 

 

Outside Design Pit

 

96,147

 

0.185

 

0.094

 

392

 

289

 

Total Inferred Resource

 

96,147

 

0.185

 

0.069

 

392

 

289

 

 


Notes:

(1) Mineral resource estimated using the limits of block models;

(2) Measured and indicated mineral resource is only the resource outside of the current design pit.

(3) 3.53 $/t NSR cutoff for Open Pit

* Copper grade does not include the oxide stockpile

 

Note that measured and indicated resources are only those resources outside of the current final pit design.  Measured and indicated mineral resources are 344.037 million tonnes at 0.185% copper and 0.104 g/t gold.

 

104



 

Inferred resources have separate line items for resources that are both inside and outside the final pit design. Inferred resources inside the current pit design amount to 0.0 million tonnes.  Total inferred mineral resource is 96.147 million tonnes at 0.185% copper and 0.069 g/t gold. Table 16.2 shows mineral resources, inclusive of mineral reserves.  Measured and indicated resource on Table 16.2 is the sum of the proven and probable mineral reserve (Table 16.2) and the measured and indicated mineral resource on Table 16.1. Inferred resources are the same on Table 16.1 and Table 16.2.

 

Table 16.2: Mineral Resources - Including Mineral Reserves

 

Mineral Resources - Including Mineral Reserve

 

 

 

Resource

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained

 

Resource Category

 

Ktonnes

 

(%)

 

(g/t)

 

lbs. (mm)

 

oz. (000’s)

 

Measured/Indicated Resource

 

 

 

 

 

 

 

 

 

 

 

Measured Mineral Resource

 

233,015

 

0.258

 

0.186

 

1,307

 

1,394

 

Indicated Mineral Resource

 

479,738

 

0.211

 

0.119

 

2,228

 

1,839

 

Measured/Indicated Resource*

 

712,753

 

0.226

 

0.141

 

3,535

 

3,232

 

Inferred Mineral Resource

 

 

 

 

 

 

 

 

 

 

 

Inside Design Pit

 

0

 

0.000

 

0.000

 

 

 

Outside Design Pit

 

96,147

 

0.185

 

0.094

 

392

 

289

 

Inferred Resource

 

96,147

 

0.185

 

0.094

 

392

 

289

 

 


Notes:

(1) Mineral Resources estimated using the limits of block models;

(2) Mineral Reserve estimated at $900/oz gold price and $2.50/lb copper price and

(3) 3.53 $/t NSR cutoff for Open Pit.

* For copper grade we don´t include the oxide stockpile because process is different

 

16.1.1.1             Model Validation

 

Metálica carried out the block model validation to support the mine plan production and the definition of the ore reserves. The block model used is version 2010, which included new criteria for ore resources classification.

 

Validation was performed for the following variables:

 

1.- Category.

 

2.- Copper and gold grade.

 

3.- Cooper and gold grade correlation.

 

The review was referenced based on benches every 20 metres between 250 m.a.s.l. and 350 m.a.s.l.

 

105



 

16.1.1.2             Resource Classification

 

Yamana reviews the resouce classification of the Chapada Project’s mine deposit based on the procedure developed by Harry Parker. This methodology has been applied with success in different types of deposits around the world.

 

The procedure consists of using the grade estimation accuracy as a major resource classification criterion, as follows:

 

·                  Measured resources should have grades estimated with ±15% relative accuracy on a quarterly production panel at 90% confidence.

 

·                  Indicated resources should have grades estimated with ±15% relative accuracy on an annual production panel at 90% confidence.

 

Yamana conducted a grade spacing study using Datamine Studio 3® and simulated a single block to determine the kriging estimation error for various grid spacings on a quarterly production panel. For the Chapada Project’s mine, the current quartely production panel represent a total of 5.250 million tons of ore.

 

The relative estimation error (RSE”) was then estimated as:

 

RSE = σOK· CV

 

whereσOK is the standard deviation of the kriging estimation error (using a unit sill variogram model of the total composites of the Chapada Project’s Deposit), and CV is the coefficient of variation of the original Au composite data. Finally, the accuracy for each grid spacing on quarterly and annual production panels at 90% relative confidence levels (Q90 and A90, respectively) were estimated as:

 

Q90 = RSE · 1.645

 

A90 = Q90 · 1/√4

 

Quarterly and annual accuracy are compared with grid spacing on Figure 16.1 and Figure 16.2.  Detailed calculations are presented in Figure 16.3.

 

Yamana defined acceptable accuracy levels (±15% accuracy on quarterly and annual production at 90% confidence) are achieved with 90 m and 160 m spacings on average for measured and indicated resources, respectively.

 

Yamana support this methodology based on the knowledge of geology and the low variance of the mineral continuity. Consecutive results obtained with the reconciliation procedures applied during the last 4 years of the mine provide a solid base to sustain the current classification.

 

106



 

Figure 16.1:        Quarterly Accuracy versus Grid Spacing for Au

 

 

Figure 16.2:        Annual Accuracy versus Grid Spacing for Au

 

 

107



 

Table 16.3: Quarterly and Annual Accuracies at Different Grid Spacings

 

Au
Grid

 

Spacing
(m)

 

Normalized
OK Variance

 

Normalized
OK Std. Dev.

 

CV

 

RSE

 

Q90

 

A90

 

1

 

310

 

0.02632

 

0.162

 

1.91

 

0.3099

 

51

%

25

%

2

 

215

 

0.019799

 

0.141

 

1.91

 

0.2688

 

44

%

22

%

3

 

110

 

0.002791

 

0.053

 

1.91

 

0.1009

 

17

%

8

%

4

 

56

 

0.003087

 

0.056

 

1.91

 

0.1061

 

17

%

9

%

 

Finally, a conservative smooth wireframes were developed as follows:

 

For measured resources: blocks are printed as category 1 represents areas with consistently estimation and good continuity between sections.

 

For Indicated resources: category 2 represents blocks printed with variance obtained within the range of 160 m.

 

For Inferred resources: areas with category 3 represents blocks within the limit of ore interpreted by Yamana.

 

The wireframes were initially developed as polylines on vertical sections, and then extrapolated as solids using the predefined section thickness. The purpose of drawing smooth wireframes was to avoid the so-called spotted dogs areas with local and erratic classification patterns (Stephenson et al., 2006).

 

Finally, to classify the mineral resource, Yamana applied the single block method, which determines the kriging error for various grid spacing on a quarterly production panel. It´s a practical and reliable method supported by a real scenary of production, independent of grade estimation.

 

Metálica carried out a graphic review that matched information density (in-plant graphic representation of the boreholes) with its associated category.

 

Areas with high information density are expected to have blocks in the measured category, shifting from the indicated to the inferred category as information density diminishes.

 

The categories are presented below by bench:

 

108



 

· Bench 250

 

 

Note: CAT: (1) Measured, (2) Indicated and (3) Inferred

 

· Bench 300

 

 

Note: CAT: (1) Measured, (2) Indicated and (3) Inferred

 

109



 

· Bench 350

 

 

Note: CAT: (1) Measured, (2) Indicated and (3) Inferred

 

16.1.1.3             Grade model review

 

Model grades were compared with those shown by the bench-to-bench boreholes.

 

The review of Cu and Au grades compared the mean model values to the mean boreholes values, according to the bench selected.

 

The Chapada Project’s mine was found to have no data aggregation problems.

 

Boreholes provide information at different levels, thus the values used were selected according to the altitude of the selected bench leg plus 5 metres, corresponding to the altitude of the block model’s benches.

 

At the same time, one model per bench was selected in order to compare areas that had more available information.

 

The results are shown below:

 

110



 

· Bench 250

 

 

· Bench 300

 

 

111



 

· Bench 350

 

 

The Cu Grade is presented below by bench:

 

· Bench 250

 

 

112



 

· Bench 300

 

 

· Bench 350

 

 

113



 

The following tables summarize the comparison of mean boreholes grades with mean model grades:

 

Table 16.4 Comparison of Copper Grades

 

Bench

 

Cu_model

 

Cu_comp

 

Delta Cu

 

350

 

0.274

 

0.251

 

0.024

 

330

 

0.268

 

0.278

 

-0.010

 

310

 

0.317

 

0.301

 

0.016

 

290

 

0.351

 

0.332

 

0.019

 

270

 

0.342

 

0.335

 

0.008

 

250

 

0.299

 

0.267

 

0.032

 

Average

 

0.309

 

0.294

 

0.015

 

 

Figure 16.3 Comparison of Copper Grades

 

 

Table 16.5 Comparison of Gold Grades

 

Banco

 

Au_model

 

Au_comp

 

Delta Au

 

350

 

0.200

 

0.184

 

0.016

 

330

 

0.215

 

0.214

 

0.002

 

310

 

0.272

 

0.250

 

0.022

 

290

 

0.281

 

0.277

 

0.004

 

270

 

0.223

 

0.217

 

0.006

 

250

 

0.209

 

0.204

 

0.005

 

Average

 

0.233

 

0.224

 

0.009

 

 

Figure 16.4 Comparison of Gold Grades

 

 

114



 

16.1.1.4             Study of the correlation between Cu and Au grades

 

A bench-to-bench correlation analysis was carried out in order to identify the relationship between copper and gold grades. The analysis was based on data from composite boreholes.

 

 

 

 

115



 

Table 16.6 Summary of Correlation Coefficient

 

 

 

Correlation

 

Bench

 

Coefficient

 

350

 

0.51

 

330

 

0.55

 

310

 

0.80

 

290

 

0.80

 

270

 

0.81

 

250

 

0.94

 

 

16.1.1.5             Cubing model

 

The block model provided — with blocks measuring 10 metres x 10 metres x 5 metres — has the following tonnage at different cut grades.

 

Table 16.7: Tonnage block model at different Cu cut grades

 

Cut Cu grade (%)

 

Tonnage (Mt)

 

Mean Cu grade (%)

 

Mean Au grade (g/t)

 

0.0

 

6,720.93

 

0.033

 

0.021

 

0.1

 

812.77

 

0.215

 

0.124

 

0.2

 

355.87

 

0.307

 

0.191

 

0.3

 

150.24

 

0.396

 

0.253

 

0.4

 

51.97

 

0.497

 

0.331

 

0.5

 

17.72

 

0.607

 

0.413

 

0.6

 

6.47

 

0.722

 

0.520

 

0.7

 

2.67

 

0.835

 

0.640

 

0.8

 

1.25

 

0.939

 

0.749

 

0.9

 

0.66

 

1.022

 

0.817

 

 

116



 

Figure 16.5 Tonnage — Grade Curve

 

 

Block Model Origin:

 

·  North = 423,934.98

 

·  East =  674,447.88

 

·  Elevation = 50

 

·  Azimuth = 56°

 

Block Model Dimension:  DX/DY =10 e DZ=5m

 

Number of Blocks: NX = 400, NY= 220 e NZ = 71

 

Total Blocks: 6,248,000

 

Variables:

CAT

Resource Classification

 

 

 

 

CUPCT Copper

Grade (%)

 

 

 

 

AUPPM

Gold Grade (g/t)

 

117



 

16.1.1.6             Conclusions

 

Block Model

 

The resource model used by Yamana was built according to international standards and successfully reflects the true variability of grade within the deposit. The model can be used in the development of long-term production plans.

 

The block model is found to be sufficiently robust to define the respective mining reserves according to the mining plans to be carried out.

 

Resource Categorization

 

When plotted, the information density (boreholes) matches its respective definition. The criteria used by Yamana to define categories are in line with international standards of NI 43-101.

 

Cu and Au Grades

 

Depending on the selected benches, the mean block model grade tended to be above the mean borehole grade.

 

The average difference in copper grade is 0.015%, while the average difference in gold grades is 0.009 g/t. Nevertheless, this variation is low and falls within the ranges given by previous reconciliations made by Independent Mining Consultants, as shown in the tables below:

 

Comparison Jan 2007 – Dec 2007

 

 

 

Grade Cu

 

Grade Au

 

Y - Budget Mine Plan

 

0.470

 

0.441

 

Y - LR Reconcilation

 

0.495

 

0.450

 

IMC Volumetrics

 

0.482

 

0.459

 

 

 

 

 

 

 

 

 

0.026

 

-0.020

 

 

Comparison 2005 – 2007

 

 

 

Grade Cu

 

Grade Au

 

Y - Ore Control Model

 

0.488

 

0.523

 

Y - Long Range Model

 

0.469

 

0.545

 

IMC Volumetrics

 

0.456

 

0.549

 

 

 

 

 

 

 

 

 

0.028

 

-0.007

 

 

Cu and Au Correlation

 

The relationship between copper and gold grades is related to the depth of ore deposit bench, with the lower benches showing a more direct relationship.

 

Cubing Model

 

According to the model, the total resources include 355.87 Mt at 0.307 % CuT and 0.191 g/t Au at a cut grade of 0.2 % CuT. There is a reduction of approximately 50% with every 0.1% CuT increase in the cut grade.

 

118



 

16.1.2              Suruca

 

16.1.2.1             Disclosure

 

The mineral resource estimates reported in this section are preliminary and they were prepared by Thiago Vaz Andrade, Geologist, and supervised by Greg Walker, P.Geo., Senior Manager, Resources Estimation of Yamana and a Qualified Person as defined under NI 43-101. The work was peer reviewed by suitably qualified Yamana geologists.

 

16.1.2.1.1             Known issues that materially affect the September 2010 Mineral Resource

 

There are noissues that may materially affect the mineral resources in a detrimental sense. These conclusions are based on the following:

 

·                  The mineral and surface rights have secure title;

 

·                  There are no known marketing, political, or taxation issues;

 

·                  The project has local community support;

 

·                  There are no known infrastructure issues.

 

16.1.2.2             Assumptions, methods, and parametres for the September 2010 Mineral Resource Estimates

 

The estimates were prepared in the following steps:

 

·                  Data validation;

 

·                  Data preparation, including importation to various software packages;

 

·                  Validation of mineralization interpretations;

 

·                  Coding of drillhole data within mineralised and waste domains;

 

·                  Sample length compositing;

 

·                  Analysis of extreme data values and application of top cuts;

 

·                  Exploratory analysis of gold grades within the mineralised domains;

 

·                  Variogram analysis and modeling;

 

·                  Creation of block models and application of density values by domain;

 

·                  Estimation of gold grade into blocks using ordinary kriging;

 

·                  Validation of grade estimations against input sample data;

 

·                  Resource tabulation and resource reporting.

 

16.1.2.2.1             Data preparation

 

The number of drillholes used in the September 2010 Mineral Resource Estimate was 149, accounting 27,950m.

 

119



 

16.1.2.2.2             Drillhole data validation

 

Validation checks in Vulcan 3D software included searches for overlaps or gaps in sample and geology intervals, inconsistent drillhole identifiers, and missing data. A small number of errors were noted and corrections were made.

 

16.1.2.2.3             Data domaining, geological interpretation and modelling

 

The Suruca Project ore bodies have outlined a resource with a strike length of 1,900 metres and 800 metres down dip.  The main direction is N40º E and dipping 20 to 30º NW controlled by foliation S1. The hydrothermal alteration is associated to sericitic and propylitic alteration halo. The proportion is about 44% in the sericitic and 37% in propylitic.The Project is characterized by four ore bodies called Suruca 1, Suruca 2, Suruca 3 and Suruca 4. See below detailing of ore bodies:

 

·                  Suruca 1:  It is the upper ore body with an average length of 7.5 metres.The gold grade average is 0.36 g/t;

 

·                  Suruca 2: It is the main ore body representing more than 80% of the deposit with lengths about 180 metres. It grade has an average of 0.40 g/t Au. This ore body has four internal waste bodies called Waste 1, Waste 2, Waste 3 and Waste 4;

 

·                  Suruca 3: Deeper than Suruca 2, this ore body has lengths about 2 metres and it gold grade average is 0.47 g/t;

 

·                  Suruca 4: The deeper ore body with lengths of about 5 metres has a gold grade average of 0.41 g/t Au. This ore body has an internal waste called Waste 5.

 

All other samples, including discontinuous zones of mineralisation, were not wireframed and were coded as lying within the waste domain.

 

Surfaces of saprolite and oxidation were created for the purpose of applying density codes to the model. The saprolite strings were snapped between the fine saprolite and coarse saprolite. The oxidation strings were snapped between the mix and fresh rocks.

 

For the construction of the wireframes, a cut-off of 0.2 g Au/t was used, considering the main hydrothermal alterations (sericitic and propylitic). For internal waste, it used composites with 5 metres length below 0.2 g Au/t.

 

A contact plot analysis, which compared grades between the ore bodies and waste along equal distances from the contact, was made and showed that all grade shells have hard boundaries.

 

The Suruca Project estimation domains are shown in Table 16.8.

 

Table 16.8: Suruca estimation domains

 

Mineralisation

 

Domain code

Waste

 

99

Waste 1

 

11

Waste 2

 

22

Waste 3

 

33

Waste 4

 

44

Waste 5

 

55

 

120



 

Mineralisation

 

Domain code

Suruca 1

 

1

Suruca 2

 

2

Suruca 3

 

3

Suruca 4

 

4

 

16.1.2.2.4             Sample compositing

 

The drillhole sample lengths were composited to ensure that the samples used in statistical analysis and estimations have a similar support (i.e., length). The sample drillhole length vary depending on the length of intersected hydrothermal alteration features. In geologically similar units, samples are selected at 2.5 metres length. Sample lengths were examined and composited accordingly to the most frequently sampled length interval which was 1 meter for all domains in all deposits. The composited and raw sample data were compared to ensure that no sample length loss or metal loss had occurred.

 

The Vulcan 3D software composite run length process was used to composite the samples within the estimation domains, (meaning that composites do not cross over the mineralised domain boundaries). The run length process was set to a value of 2.5 to allow adjusting of the composite length. This is done to ensure equivalent sample support.

 

16.1.2.2.4.1             Drillhole core recovery treatment

 

There are no significant core recovery issues at Suruca Project.

 

16.1.2.2.5             Extreme value treatment

 

Gold composite grades were examined on a domain basis for each ore body to identify the presence and nature of extreme grade values. This was done by examining the sample histogram and the cumulative frequency plot. If required, top cut thresholds were determined by examination of the same statistical plots and by examination of the effect of top cuts on the mean and variance of the sample data.

 

16.1.2.2.6             Data declustering

 

Descriptive statistics of sample populations within a domain may be biased by clustering of sample data in particular areas of the domain. At the Suruca Project deposit, declustering was not used.

 

16.1.2.2.7             Variography

 

16.1.2.2.7.1             Continuity analysis

 

Continuity analysis refers to the analysis of the spatial correlation of grade values between sample pairs to determine the direction of the major axis of spatial continuity. As the mineralised domains have a long and relatively flat shape oriented to the northest, only orientations within the plane of the domain were considered.

 

121



 

16.1.2.2.7.2             Variogram modeling

 

The variography in the Suruca Project deposit was made for two different sample populations, one for the sap+oxidated rocks and other for the fresh rocks. The nugget for both populations was found by modeling down hole omni-directional variograms. Semivariograms were modeled for each sample population. Figure 16.9 gives the back transformed variogram model parametres used in the estimation of the Suruca Project deposit.

 

Table 16.9: Back transformed variogram model parametres for Au

 

Deposit

 

Domain

 

Az.

 

Pl.

 

Dip

 

C0

 

C1

 

Ranges (m)†

 

C2

 

Ranges (m)†

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Suruca

 

Sap+Oxi

 

67.5

°

0

 

4

°

0.020

 

0.027

 

99, 88, 4.9

 

0.031

 

197, 98, 7.2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Suruca

 

Fresh

 

40

°

0

 

29

°

0.034

 

0.059

 

121, 85, 20

 

0.007

 

148, 125, 49

 

 


Note:  ranges for major, semi and minor axes, respectively; structures two and three are modelled with a spherical model.

 

16.1.2.2.8             Estimate parametres

 

Ordinary kriging is a grade estimation technique that takes a standard map file and, using the information derived from a variography study and a geological interpretation of the ore body, uses classical kriging to interpolate grade values to each of the nominated cells of a block model.

 

16.1.2.2.8.1             Block size selection

 

Block sizes were selected according to the average drillhole spacing and the dimensions of the mineralised envelopes, leading to a selection of blocks with dimensions of 10 metres easting, 10 metres northing and 5 metres elevation.

 

16.1.2.2.8.2             Sample search parametres

 

The following search strategy was selected to perform the estimations:

 

·                  A search range equal to the maximum variogram range.

 

·                  A minimum of 3 samples per estimate.

 

·                  A maximum of 24 samples per estimate.

 

·                  A maximum of 8 samples per octant.

 

Two search ellipses were employed. A first search equal the maximum variogram range was used to perform an estimate. If the minimum number of required samples were not encountered in the first search ellipse, a second search equal twice the maximum variogram range was used wherever the first search did not encounter the minimum number of required samples to perform an estimate.

 

16.1.2.2.9             Block model set up

 

To Suruca Project deposit, the block model has a bearing of 40° of X axis around the Z axis, following the left hand rule, on the origin point. This point is an arbitrary point used to define the start of the offsets in the scheme and the pivot for the rotations. The origin point, offsets and

 

122



 

rotations are used in conjunction with the parent scheme to define the position in space of the block model.

 

Table 16.10 gives the block model parametres for the Suruca Project’s mineral resource models. The UTM coordinate of the origin point is 682200 E / 8428200 N / -100 elevation.

 

Table 16.10: Suruca block model parametres

 

Type

 

Direction

 

Offset Min (m)

 

Offset Max (m)

 

Increment (m)

 

 

 

Easting

 

0

 

2750

 

10

 

Blocks

 

Northing

 

0

 

1750

 

10

 

 

 

Elevation

 

0

 

600

 

5

 

 

16.1.2.2.10      Grade interpolation and boundary conditions

 

Grade interpolation was by ordinary kriging. Domain boundaries were treated as hard boundaries, so that samples lying in one domain were not used in the estimation of another, in order to prevent the smearing of grades from one domain to another.

 

16.1.2.2.11      Density

 

A total of 740 density determinations have been made at the Suruca Project deposit, using the volume displacement method. Eighty five measurements were made into saprolite zone and twenty seven into oxidised rocks. 628 measurements were taken from fresh rocks. The average density value, for each zone, was applied to the block model. Table 16.11 gives the density values.

 

Table 16.11: Densities applied to the Mineral Resource models

 

Rock type

 

Density (g/cm³)

Saprolite

 

1.49

Oxide

 

2.12

Fresh

 

2.88

 

16.1.2.2.12      Depletion with previously mined areas

 

It was not necessary to perform a depletion of the garimpo area on the modelling of the Suruca Project deposit because the topographic surveying was made including the mined open pit.

 

16.1.2.2.13      Model validation

 

The Suruca Project model was validated using the following techniques:

 

·                  Comparison of mean sample statistics with the mean estimated grade by ore body

 

·                  Visual inspection of block and sample composite grades in section, plan, and in three dimensions

 

123



 

·                  Drift calculation which consists of separating the model into slices and calculating the grade average, for each slice, by the composites and by the estimated blocks. Using drift calculation, it is possible to compare the kriging results with the original data.

 

16.1.2.2.13.1      Domain statistics and visual validation

 

The Suruca Project model was validated by comparing the estimated grades by ore body with the input samples. The global grade comparison between the estimated grades and the input grades are within acceptable limits for all ore bodies. The drift calculation showed a good smoothing of the original data by kriging.

 

16.1.2.2.14      Mineral Resource classification

 

There are a number of factors affecting confidence in the resource estimation, which can affect resource classification. These factors include:

 

·                  Geological continuity (including geological understanding and complexity).

 

·                  Data density and orientation.

 

·                  Grade continuity (including spatial continuity of mineralisation).

 

16.1.2.2.14.1      Geological continuity and understanding

 

Project geologists log drillhole core in detail including alteration, structural, mineralisation, and lithological properties, with a geological model representing the controls on mineralisation. A geological digital interpretation has been created which incorporated all available hydrothermal alteration information and core logging detail in three dimensional format.

 

16.1.2.2.14.2      Data density and orientation

 

Yamana has drilled the Suruca Project deposit on a pattern ranging from 100 m to 200 m along strike. Geological confidence and estimation quality are closely related to data density and this is reflected in the classification of resource confidence categories. There are two different domains, one with a 200 m x 200 m arrangement in the southern area and another domain with a 100 m x 100 m arrangement on the northern area. The first domain is considered insufficient for the required structural interpretation of the deposit, but is sufficient to infer geological and grade continuity. The second domain has an ideal arrangement for the required interpretations.

 

16.1.2.2.14.3      Spatial grade continuity

 

Spatial grade continuity, as indicated by the variogram, has been considered while assigning resource confidence classifications. Variogram characteristics strongly influence estimation quality parametres such as kriging efficiency and regression slope.

 

The nugget effect and range variance characteristics of the variograms are the most important measures of continuity. At the Suruca Project deposit, the variogram nugget effect is low with values below 20% of the population variance.

 

124



 

16.1.2.2.14.4      Resource Classification

 

All resources within the Suruca Project ore bodies (shells 1, 2, 3 and 4) have been classified, and this classification is based on the directional variogram ranges. As described in section 16.1.2.7 of this report, the directional variograms were derived from 2.5 metres run length composites, segregated as fresh rocks and soil/oxidized rocks.

 

The indicated resources were defined by the first pass grade estimation that uses the variogram ranges, and the inferred resources were defined by the second pass grade estimation that uses twice the variogram ranges. Waste bodies (shells 11, 22, 33, 44, 55 e 99) were not classified.

 

16.1.2.3             Mineral Resource reporting

 

Indicated and inferred mineral resource estimates for the Suruca Project deposit are reported in the table below.

 

Table 16.12: Mineral resources estimate

 

 

 

 

 

Indicated

 

Inferred

 

Ore

 

Cutoff

 

Au (g/t)

 

kt
(x1000)

 

koz
(x1000)

 

Au (g/t)

 

kt
(x1000)

 

koz
(x1000)

 

Oxide

 

0.2

 

0.48

 

19,247

 

298

 

0.39

 

3,755

 

47

 

Sulphide

 

0.3

 

0.50

 

132,114

 

2,127

 

0.39

 

5,423

 

68

 

Oxide and Sulphide

 

 

 

0.50

 

151,361

 

2,425

 

0.39

 

9,178

 

115

 

 

125



 

16.2              Mineral reserve estimate

 

16.2.1              Chapada

 

16.2.1.1             Block Model

 

The estimation of mineral reserves was performed by Yamana technical services and audited by Metálica, who also updated the mineral reserves estimates herein presented.

 

The main economic parametres used in the estimate of mineral reserves as of December 31, 2010 are summarized in Table 16.13 below:

 

Table 16.13: Economic Parametres for Chapada Mine Design

 

DESCRIPTION

 

UNIT

 

VALUE

 

Copper Price

 

US$/lb

 

2.50

 

Gold Price

 

US$/oz

 

900.00

 

Mining

 

US$/t

 

1.5400

 

Processing

 

US$/t

 

3.6900

 

G&A

 

US$/t

 

0.2500

 

Average Plant Copper Recov.

 

%

 

85.43

 

Average Plant Gold Recov.

 

%

 

51.07

 

Smelter Payable Copper

 

%

 

96.5

%

Smelter Payable Gold

 

%

 

97.0

%

Copper Smelter, Refin, Freight

 

US$/lb

 

0.49

 

Gold Refining

 

US$/Oz

 

5.00

 

Copper Royalty, Sales Taxes

 

% of Gross

 

2.82

 

Gold Royalty

 

% of Gross

 

1.00

 

Copper NSR Factor (1)

 

US$/t

 

41.26

 

Gold NSR Factor (2)

 

US$/t

 

27.63

 

NSR Breakeven cutoff

 

US$/t

 

5.48

 

NSR Internal cutoff

 

US$/t

 

3.94

 

NSR Stockpile

 

US$/t

 

3.53

 

 

The Table 16.14 shows the mineral reserves for the Chapada Project as of Decembery 31, 2010 based on a long range mine plan and plant production schedule developed by Yamana and Metalica. Total proven and probable mineral reserves is 368.72 million ore tons at 0.26% total copper and 0.18 g/t gold.

 

The mineral reserves are based on long term realized copper and gold prices of $2.50 per pound and $900 per ounce respectively.  The NSR value represents net revenue per ton ore net of smelting, refining, concentrate freight, gold royalties, and copper sales taxes.

 

126



 

Table 16.14: Chapada Mineral Reserve as of December 31, 2010

 

Chapada Project Mineral Reserve as of December 31, 2010

 

 

 

Ore

 

NSR

 

Copper

 

Gold

 

Copper
Contained

 

Gold
Contained
oz.

 

Reserve Class

 

Ktonnes

 

(US$/t)

 

(%)

 

(g/t)

 

lbs. (mm)

 

(000’s)

 

Proven Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore

 

140.160

 

13,84

 

0,296

 

0,209

 

915

 

943

 

Existing Mill Stockpile

 

1.214

 

16,78

 

0,356

 

0,301

 

10

 

12

 

Low Grade Stockpiles (Existing)

 

26.391

 

11,50

 

0,246

 

0,201

 

143

 

170

 

Total Proven Mineral Reserve

 

167.765

 

13,49

 

0,289

 

0,209

 

1.068

 

1.125

 

Probable Mineral Reserve

 

 

 

 

 

 

 

 

 

 

 

 

 

Open Pit Ore

 

200.951

 

10,35

 

0,244

 

0,148

 

1.081

 

957

 

Total Probable Mineral Reserve

 

200.951

 

10,35

 

0,244

 

0,148

 

1.081

 

957

 

Total Proven and Probable Mineral Reserve

 

368.716

 

11,78

 

0,264

 

0,176

 

2.149

 

2.082

 

 


Notes:

(1)- Total Pit Material 473,599 Ktonnes, Strip Ratio 0.39 to 1;

(2)- Mineral Reserve estimated at $900/oz gold price and $2.50/lb copper price;

(3) - 3.53 $/t NSR cutoff for Open Pit

 

16.2.1.2             Mine Production Schedule

 

16.2.1.2.1             Economic Parametres for Mine Design

 

The basis of the mineral reserve presented is a mine design and mine and plant production schedule developed by Yamana during January of 2011.  The final pit design is based on copper price of US$ 2.50 per pound and a gold price of US$ 900 per ounce.  These prices were established by Yamana guidelines.

 

Table 16.15 shows the economic parametres used for pit design.  The mining, processing, and G&A unit costs were provided by Chapada.

 

The smelting, refining, and freight cost is estimated at $0.490 per pound copper. This estimate is based on a concentrate grade of 28% (27% payable), a TCRC of US$ 93.87 per tonne concentrate and a freight cost of US$ 198.12 per tonne concentrate.

 

For mine design the costs were calculated on a block-by-block basis and incorporated into the model. An NSR value was also calculated for each block in the model to simplify economic calculations since the copper and gold recoveries are dependent on head grade.  As discussed above, the NSR value is the value per tonne ore net of smelting, refining, concentrate freight, royalties and sales taxes. An example of this calculation for a block with a copper grade of 0.292% and a gold grade of 0.266 g/t is shown in the following sections.

 

127



 

Table 16.15 Economic Parametres for Chapada Mine Design

 

DESCRIPTION

 

UNIT

 

VALUE

 

Copper Price

 

US$/lb

 

2.50

 

Gold Price

 

US$/oz

 

900.00

 

Mining

 

US$/t

 

1.5400

 

Processing

 

US$/t

 

3.6900

 

G&A

 

US$/t

 

0.2500

 

Average Plant Copper Recov.

 

%

 

85.43

 

Average Plant Gold Recov.

 

%

 

51.07

 

Smelter Payable Copper

 

%

 

96.5

 

Smelter Payable Gold

 

%

 

97.0

 

Copper  Smelter, Refin, Freight

 

US$/lb

 

0.49

 

Gold Refining

 

US$/Oz

 

5.00

 

Copper Royalty, Sales Taxes

 

% of Gross

 

2.82

 

Gold Royalty

 

% of Gross

 

1.00

 

Copper NSR Factor (1)

 

US$/t

 

41.26

 

Gold NSR Factor (2)

 

US$/t

 

27.63

 

NSR Breakeven cutoff

 

US$/t

 

5.48

 

NSR Internal cutoff

 

US$/t

 

3.94

 

NSR Stockpile

 

US$/t

 

3.53

 

Copper NSR

 

 

 

10.29

 

Gold NSR

 

 

 

3.75

 

NSR Total

 

 

 

14.05

 

 


Note (1): NSR Cu = $41.26 x recovered copper grade

 

 

 

 

 

Note (2): NSR Au = $27.63 x recovered gold grade

 

 

 

 

 

 

16.2.1.2.2             Plant Recoveries

 

The copper/gold recoveries were based on the simulator supplied by Yamana´s MMIC Mineral Processing department. The Figure 16.6 illustrates the simulator supplied.

 

128



 

Figure 16.6: Mineral Processing Recovery Simulator

 

 

16.2.1.2.3             NSR Calculation for Mine Design

 

An NSR value was calculated for each model block.  The value is per ore tonne and reflects gross revenue less smelting, refining, freight, and royalty costs, as well as sales taxes.

 

·                  NSR copper = (2.50 – 0.490 – 0.0705)(Cu)(cu recovery)(0.965)(22.046)

 

= $41.26 x recovered copper grade

 

The $0.0705 term is for royalties and sales taxes at 2.82% of gross value.

 

·                  NSR gold = (900 – 5.00 – 9.00)(Gold)(au recovery)(0.97)/31.103

 

= $27.63 x recovered gold grade.

 

The $ 9.00 term reflects the gold royalty of 1% of gross revenue.

 

These factors are shown at the bottom of Table 16.15.

 

For a block, the total NSR is:

 

·                  NSR = $41.26 x recovered cu grade + $27.63 x recovered gold grade

 

Since the NSR value incorporates all the direct costs except mining, processing, and G&A, the breakeven and internal NSR cutoff grades are as follows:

 

129



 

·                  Breakeven NSR Cutoff = Mining + Processing + G&A = $1.54 + $3.69 + $0.25 = 5.48 US$/t

 

·                  Internal NSR Cutoff = Processing + G&A= $3.69 + $0.25 =3.94 US$/t

 

·                  Internal cutoff applies to blocks that must be mined, i.e. mining is a sunk cost.

 

For the 2004 feasibility study, a low grade stockpile cutoff grade was established based on the formula:

 

·                  Stockpile NSR cutoff = 0.70 x (process + G&A) + 0.5 x mining cost

 

This is based on the assumption that at the end of the mine life, when processing stockpile material is the only activity, process and G&A costs would be reduced to 70% of normal costs.  50% of the mining cost is an estimate of the mining rehandle cost. Applying this same equation results in a current low grade stockpile cutoff grade of $3.53 per tonne.

 

16.2.1.2.4             Pit Optimization

 

The main purpose of mining planning, from a financial perspective, is to design an ultimate pit that maximizes profit. This objective considers maximizing the mineral resources, environmental issues, safety, and slope stability.

 

The Lerchs & Grossman (LG”) algorithm can be used to find the optimum pit shells. Shell selection is based on the total benefit associated with it. At a resource that is typified by a 3D block model, each block can have its economical value assessed by a benefit function that takes into account the rock type (ore or waste), production costs, price of the concentrate and mass recoveries. Therefore, the pit shell benefit can be calculated as the sum of the individual benefit of each block that is inside the shell. Pit slopes crucially affect the final shape of the shells.

 

For a given amount of metal content, only one pit has the maximum total benefit. Therefore, it is possible to find a pit family that represents the envelope of the optimum solutions for all possible metal contents. The LG algorithm is used to find the pit that has the maximum total benefit but not the maximum metal content inside it. That pit is usually called ultimate pit (or final pit) and process used to find it is usually called pit optimization.

 

The variables that mainly affect the process are:

 

·                  Price of the ore

 

·                  Operating cost

 

·                  Stripping ratio

 

·                  Mass recovery

 

The study was carried using the Software MineSight Economic Planner® that uses an implementation of the LG algorithm to develop optimum pit shells (Mintec/USA).

 

130



 

Pit optimization was carried using the measured + indicated resources available for the deposits that have NSR (“net of smelting, refining, and freight” and represents revenue value in $US per tonne less the charges for smelting, refining, concentrate freight, royalties and sales taxes) above US$ 3.53/t (stockpile NSR cutoff). The inferred resources were considered as waste during the pit optimization.

 

The benefit function was implemented into MineSight using Multiruns (resource available in MineSight that is possible to integrate the data during the calculation using the existing sub-routines). The following figure shows the Multirun and the validation of the benefit function directly in the excel (using Visual Basic Macro).

 

Figure 16.7: Multirun and Benefit Function Validation

 

GRAPHIC

 

 

 

 

 

 

 

 

 

 

 

Rec.Cu (%)

 

Rec Au (%)

 

NSR (US$/t)

 

I

 

J

 

K

 

Cu (%)

 

Au (ppm)

 

MS

 

EXCEL

 

DIF(%)

 

MS

 

EXCEL

 

DIF (%)

 

MS

 

EXCEL

 

DIF(%)

 

319.00

 

60.00

 

7.00

 

0.157

 

0.060

 

82.39

 

82.39

 

0.0

%

0.00

 

0.00

 

0.0

%

4.67

 

4.67

 

0.0

%

320.00

 

60.00

 

7.00

 

0.158

 

0.060

 

82.42

 

82.42

 

0.0

%

0.00

 

0.00

 

0.0

%

4.70

 

4.70

 

0.0

%

321.00

 

60.00

 

7.00

 

0.256

 

0.075

 

85.41

 

85.41

 

0.0

%

0.00

 

0.00

 

0.0

%

7.89

 

7.89

 

0.0

%

319.00

 

61.00

 

7.00

 

0.158

 

0.074

 

82.42

 

82.42

 

0.0

%

0.00

 

0.00

 

0.0

%

4.70

 

4.70

 

0.0

%

320.00

 

61.00

 

7.00

 

0.158

 

0.060

 

82.42

 

82.42

 

0.0

%

0.00

 

0.00

 

0.0

%

4.70

 

4.70

 

0.0

%

321.00

 

61.00

 

7.00

 

0.159

 

0.075

 

82.45

 

82.45

 

0.0

%

0.00

 

0.00

 

0.0

%

4.73

 

4.73

 

-0.1

%

319.00

 

62.00

 

7.00

 

0.162

 

0.074

 

82.54

 

82.54

 

0.0

%

0.00

 

0.00

 

0.0

%

4.83

 

4.82

 

0.0

%

320.00

 

62.00

 

7.00

 

0.164

 

0.074

 

82.60

 

82.60

 

0.0

%

0.00

 

0.00

 

0.0

%

4.89

 

4.89

 

0.0

%

321.00

 

62.00

 

7.00

 

0.161

 

0.074

 

82.51

 

82.51

 

0.0

%

0.00

 

0.00

 

0.0

%

4.80

 

4.79

 

0.0

%

322.00

 

62.00

 

7.00

 

0.161

 

0.073

 

82.51

 

82.51

 

0.0

%

0.00

 

0.00

 

0.0

%

4.80

 

4.79

 

0.0

%

219.00

 

63.00

 

7.00

 

0.246

 

0.091

 

85.07

 

85.07

 

0.0

%

19.62

 

19.62

 

0.0

%

8.01

 

8.01

 

0.0

%

220.00

 

63.00

 

7.00

 

0.194

 

0.133

 

83.32

 

83.32

 

0.0

%

26.12

 

26.12

 

0.0

%

6.71

 

6.71

 

0.0

%

221.00

 

63.00

 

7.00

 

0.189

 

0.130

 

83.18

 

83.18

 

0.0

%

25.11

 

25.11

 

0.0

%

6.50

 

6.50

 

0.0

%

222.00

 

63.00

 

7.00

 

0.161

 

0.122

 

82.36

 

82.36

 

0.0

%

21.19

 

21.19

 

0.0

%

5.44

 

5.44

 

0.0

%

319.00

 

63.00

 

7.00

 

0.163

 

0.073

 

82.57

 

82.57

 

0.0

%

0.00

 

0.00

 

0.0

%

4.86

 

4.86

 

0.0

%

320.00

 

63.00

 

7.00

 

0.165

 

0.074

 

82.63

 

82.63

 

0.0

%

0.00

 

0.00

 

0.0

%

4.92

 

4.92

 

0.0

%

321.00

 

63.00

 

7.00

 

0.167

 

0.074

 

82.69

 

82.69

 

0.0

%

0.00

 

0.00

 

0.0

%

4.98

 

4.98

 

0.0

%

322.00

 

63.00

 

7.00

 

0.164

 

0.076

 

82.60

 

82.60

 

0.0

%

0.00

 

0.00

 

0.0

%

4.89

 

4.89

 

0.0

%

218.00

 

64.00

 

7.00

 

0.215

 

0.079

 

84.15

 

84.15

 

0.0

%

0.00

 

0.00

 

0.0

%

6.53

 

6.53

 

0.1

%

219.00

 

64.00

 

7.00

 

0.184

 

0.118

 

83.08

 

83.08

 

0.0

%

22.07

 

22.07

 

0.0

%

6.18

 

6.18

 

0.0

%

220.00

 

64.00

 

7.00

 

0.190

 

0.123

 

83.24

 

83.24

 

0.0

%

23.68

 

23.68

 

0.0

%

6.45

 

6.44

 

0.0

%

 

16.2.1.2.5             Pit Design

 

The Chapada Project’s mine recommended slope angles as follows:

 

131



 

·                  26º: for soil slopes (soils and saprolite). This material generally represents the top 10 to 30 metres of the entire mine area.

 

·                  45º: for weathered rock slopes.  This was interpreted as the southeast wall of the pit.

 

·                  56º: for unweathered rock slopes on the southwest wall.

 

·                  53º: for unweathered rock slopes on the central wall of the pit (contact in between southwest/northwest wall).

 

·                  50º: for unweathered rock slopes on the northeast of the pit.

 

Figure 16.8: Geotechnical Sectors of the Pit

 

 

The pit was operationalized in such a way as to include consideration of access roadways, individual slopes and berms.

 

132



 

Figure 16.9: Pit Design — Geometric Parametres

 

 

The road/access has 30 metres wide and a grade equal to 10%. During the mining operation the road/access must have 8% to not force the mining equipment during the hauling.  The bench high below the elevation 150 has 10 metres to recovery the ore, minimizing the dilution.

 

Figure 16.10: Base topography Dec. 31, 2010 without stocks and waste dumps

 

 

Figure below shows the final pit design.

 

133



 

Figure 16.11: Final Pit Design

 

 

134



 

Figure 16.12: Chapada Mine 3D view of general arrangement including the dump areas for waste dump and stockpiles

 

 

135



 

16.2.1.2.6             Mine Production Schedule

 

The tonnage and grade distribution from the mining phases was used to develop a mining production schedule. The topography as of the end of 2010 was incorporated into the phase tonnages for the calculation of the updated schedule.

 

Table 16.16 shows the Chapada Project mine production schedule:

 

·                  During the life of mine (19 years) an amount of 368.72 Mt of ore reserves are sent to plant, including the processing of the materials of stocks.

 

·                  The average grades sent to plant are 0.264% CuT and 0.176 Au g/t.

 

·                  The mine requires a maximal removal of 60 Mtpy, totalizing during the life of mine 657.8 Mt of rock removed, representing an overall stripping ratio of 0.78. Re-handling of 194.0 Mt of low grade stocks is included.

 

Table 16.16 shows the mine movement material. From 2011 to 2029, 132.5 Mt will be sent to the waste dump and 156 Mt will be sent to stocks. A total of 194.0 Mt will be reclaimed from stock.

 

136



 

Table 16.16 : Chapada Mine production Schedule

 

Yamana Gold

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Name of Asset

 

Chapada

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Status

 

Operating

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

 

December 31, 2010

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PRODUCTION

 

Unit

 

Total

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Ore Feed Chapada

 

kt

 

368.716

 

21.555

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.500

 

14.000

 

14.000

 

14.000

 

14.000

 

14.400

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.261

 

Copper Grade

 

%

 

0,264

%

0,431

%

0,371

%

0,308

%

0,298

%

0,290

%

0,305

%

0,330

%

0,316

%

0,321

%

0,360

%

0,257

%

0,202

%

0,190

%

0,189

%

0,185

%

0,180

%

0,185

%

0,174

%

0,180

%

Copper Recovery

 

%

 

85,3

%

86,8

%

87,1

%

86,1

%

86,0

%

85,9

%

86,4

%

86,9

%

86,6

%

87,6

%

84,1

%

84,1

%

84,3

%

84,4

%

84,2

%

83,9

%

84,0

%

84,0

%

84,0

%

84,0

%

Copper Contained

 

Mlb

 

2.149

 

205

 

180

 

150

 

144

 

141

 

148

 

127

 

98

 

99

 

111

 

79

 

64

 

92

 

92

 

90

 

87

 

90

 

85

 

68

 

Copper Production

 

Mlb

 

1.840

 

178

 

157

 

129

 

124

 

121

 

128

 

111

 

84

 

87

 

93

 

67

 

54

 

78

 

77

 

75

 

73

 

75

 

71

 

58

 

Gold Grade

 

g/t

 

0,176

 

0,330

 

0,304

 

0,243

 

0,228

 

0,210

 

0,199

 

0,220

 

0,199

 

0,200

 

0,240

 

0,169

 

0,129

 

0,100

 

0,098

 

0,098

 

0,097

 

0,106

 

0,091

 

0,093

 

Gold Recovery

 

%

 

62,2

%

60,7

%

60,8

%

58,8

%

64,8

%

63,0

%

62,1

%

63,7

%

61,8

%

76,0

%

64,9

%

61,9

%

61,6

%

61,3

%

60,6

%

61,1

%

61,1

%

61,1

%

61,1

%

61,1

%

Gold Contained

 

koz

 

2.082

 

229

 

215

 

172

 

161

 

149

 

140

 

124

 

90

 

90

 

108

 

76

 

60

 

71

 

69

 

69

 

69

 

75

 

64

 

52

 

Gold Production

 

koz

 

1.299

 

139

 

131

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

Waste + Stock Low Grade

 

kt

 

289.113

 

38.838

 

32.000

 

32.000

 

32.000

 

32.000

 

32.000

 

16.500

 

20.000

 

20.000

 

20.000

 

13.775

 

 

 

 

 

 

 

 

 

Waste

 

kt

 

132.488

 

18.448

 

24.441

 

19.026

 

13.853

 

18.308

 

17.810

 

6.327

 

9.007

 

4.711

 

5

 

552

 

 

 

 

 

 

 

 

 

Low Grade Ore + Oxide

 

kt

 

156.625

 

20.390

 

7.559

 

12.974

 

18.147

 

13.692

 

14.190

 

10.173

 

10.993

 

15.289

 

19.995

 

13.223

 

 

 

 

 

 

 

 

 

Low Grade Reclaiming

 

kt

 

194.001

 

 

 

 

 

6.757

 

11.000

 

9.400

 

10.500

 

6.000

 

6.000

 

4.000

 

21.000

 

21.000

 

21.000

 

21.000

 

21.300

 

21.300

 

13.744

 

 

 

 

Strip Ratio (REM)

 

 

 

0,78

 

1,80

 

1,45

 

1,45

 

1,45

 

1,45

 

1,45

 

0,94

 

1,43

 

1,43

 

1,43

 

0,98

 

 

 

 

 

 

 

 

 

Haulage profile (DMT)

 

m

 

1.607

 

2.033

 

1.706

 

1.614

 

1.457

 

1.501

 

1.537

 

1.944

 

1.919

 

1.750

 

1.715

 

1.491

 

1.146

 

1.489

 

1.390

 

1.370

 

1.329

 

1.350

 

1.350

 

1.350

 

Total mine move

 

kt

 

657.829

 

60.393

 

54.000

 

54.000

 

54.000

 

54.000

 

54.000

 

34.000

 

34.000

 

34.000

 

34.000

 

27.775

 

14.400

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.261

 

 

137



 

16.2.2              Suruca

 

The resources at the Suruca Project property will be mined by open-pit. AMEC has developed an ultimate pit design and a pre-feasibility level production plan with separated sulphide and oxide gold bearing ore types. AMEC has included only indicated mineral resources in this assessment.

 

The block model used for mine planning was provided by Yamana. Block dimensions, origin and rotation are shown:

 

Size of blocks:

 

·                  X: 5 m

·                  Y: 5 m

·                  Z: 5 m

 

Block origin:

 

·                  X: 682,200 E

·                  Y: 8,428,200 N

·                  Z: -100

·                  Rotation: 40°

 

Blocks not classified as mineral resources were considered as waste.

 

16.2.2.1             Mineral Reserves Statement

 

Mineral reserves for the Suruca Project are classified in accordance with the 2005 CIM definition standards for mineral resources and mineral reserves, and are reported to a gold price of US$900/oz. Mineral reserves are summarized in Table 16.17.

 

Table 16.17: Suruca Project Probable Mineral Reserve, Effective Date December 2010.

 

 

 

 

 

Probable Reserves

 

Contained Metal (oz)

 

Suruca Project

 

Cutoff

 

Tonnes
(tx1000)

 

Au (g/t)

 

Au (oz x 1,000)

 

Oxide

 

0.2

 

16,331

 

0.510

 

268

 

Sulphide

 

0.3

 

44,124

 

0.553

 

784

 

Total

 

 

 

60,455

 

0.541

 

1,052

 

 


Notes:

(5)   All mineral reserves are in the probable category.

(6)   Reserves are estimated using a US$ 900/oz gold price and economic function that includes operating costs, metallurgical recoveries and selling costs has been applied.

(7)   Rounding as required by reporting guidelines may result in apparent differences between tonnes, grade and contained metal content.

(8)   Tonnage and grade measurements are in metric units. Gold ounces are reported as troy ounces.

 

138



 

The block model used in this pre feasibility study includes only indicated and inferred resources. The optimization was completed using only indicated resources. Inferred material blocks were classed similar to waste material.

 

Yamana, through the geologist, Mr. Franco Bazzon, states that it owns the mineral rights covering the area called Suruca which is adequate for exploration purposes. Prior to beginning the feasibility study, Yamana must also obtain the exploitation rights.

 

16.2.2.2             Ultimate Pit design Criteria

 

Micromine software was used to generate an optimized pit shell using the LG algorithm. Using the defined limits of the optimized open pit shell a series of phases and the ultimate pit design were completed. Table 16.18 shows the parametres which were used in Micromine to generate the ultimate pit. This pit was validated by Yamana and AMEC.

 

Table 16.18: Ultimate Pit Input Parametres

 

Parameter

 

unit

 

value

Metal price Au

 

US$/oz

 

900

Mining Cost

 

US$/t mined

 

1.80

Processing cost - leaching

 

US$/t ore

 

3.00

Processing cost - flotation

 

US$/t ore

 

5.01

Sales and G&A costs

 

US$/oz

 

12.44

Recovery with leaching process

 

%

 

80.0

Recovery with flotation/CIL process

 

%

 

80.0

Marginal Cut-off grade (OxideOre)

 

g/t Au

 

0.20

Marginal Cut-off grade (SulphideOre)

 

g/t Au

 

0.30

Ore recovery in the pit

 

%

 

97.0

Ore dilution in the pit

 

%

 

3.0

Pit slope - oxide

 

degrees

 

30

Pit slope - sulphide

 

degrees

 

35

 

16.2.2.3             Geotechnical & Slope Angle Selection

 

AMEC — MINPROC contracted VOGBR Consulting to develop the geotechnical and slope selection study.

 

The result of this study shows two slope zones defined for different rock types. The first zone (“saprolitos” and oxide material), indicates that from the top of the pit to the 350 bench the pit design can have a maximum bench face angle of 45°. This material requires the addition of a 7 meter wide berm with each 10 metres in depth (double bench).

 

139



 

In the second zone (sulphide material) from bench 350 to the bottom of the pit, the maximum bench face angle is 70°, with a berm of 12 metres every 30 metres in depth (6 benches). Accordingly, pit slopes are 30° and 53° respectively for both zones.

 

16.2.2.4             Lerch Grossman Optimization Results

 

Table 16.19 shows the results of the LG pit optimization. The sulphides are the dominant economic driver of the pit.  Furthermore, Figure 16.13 and Figure 16.14 show the final pit of oxide and sulphide respectively.

 

Table 16.19: Ultimate Pit Results

 

Parameter

 

Resource
(kt)

 

Gold Grade
g/t Au

Indicated

 

 

 

 

Saprolito

 

10,940

 

0.516

Oxide

 

6,266

 

0.496

Sulphide

 

48,216

 

0.554

Total Indicated

 

65,421

 

0.542

Waste Rock

 

77,185

 

 

Total Rock

 

142,605

 

 

Stripping Ratio

 

1.18

 

 

 

Figure 16.13: Ultimate Pit Limit Oxide

 

 

140



 

Figure 16.14: Ultimate Pit Limit Sulphide

 

 

17               OTHER RELEVANT DATA AND INFORMATION

 

17.1              Suruca Hydrogeological study

 

Mineração Maracá is currently conducting a pre-feasibility study for a gold mine project situated approximately 270 km northwest from Brasilia, in the Goias State, Brazil. In order to plan the future dewatering requirements of this operation, Yamana hired Schlumberger Water Services (Schlumberger”) to carry out a hydrogeological study in the project area.

 

This report deals specifically with the first stage of the work, including the following tasks: data compilation and review, a survey of springs and other hydrological points of interest and the design of a hydrological monitoring network. During the field survey it was detected that the majority of the streams were dry, a situation that was also verified in the main surface water body crossing the area, Rio dos Bois. Therefore, additional investigation will be required to assess the water levels in these surface water channels.

 

The field survey resulted in 10 springs being identified, within which 5 had low flows (<0.1L/s) and 5 were only seeps with no associated flow. The survey also identified 22 points related to natural lakes, artificial lakes and dams; 2 water points where the spring was not identified; 4 flow monitoring points; 6 control points in dry channels; and 1 effluent discharge point from Mineração Lavrinhas.

 

Where flowing springs were identified, their flow (< 0.1 L/s) was associated with sandy-clayey sediments. In terms of the water’s physical-chemical parametres, these were measured as follows: average temperature around 27.7°C, oxi-redox potential (Eh) in the order of 227mV, neutral pH and electrical conductivity was measured in the order of 123 mS/cm (with anomalies occurring up to 1180 mS/cm). The anomalous electrical conductivity values detected in two of

 

141



 

the springs (NSC-04 and NSC-10) may be related to a natural acid drainage from the local geology or even from sewer contamination of groundwater.

 

In addition to the survey of natural springs, 18 groundwater level measurements were obtained from exploration boreholes, private supply wells and a few shallow hand auger holes drilled into the dry bed of the Rio dos Bois river. This allowed for a preliminary potentiometric map to be prepared, which showed that the groundwater flow essentially follows the topography, with 2 main groundwater flow directions: one to the northwest, towards the Formiga River and another to the south, towards the Rio dos Bois channel.

 

The groundwater flow in the Suruca Project area occurs through a system composed of a shallow unconsolidated material (porous medium flow) and the fractured rock mass (fracture flow). Results from hydraulic tests conducted in these units at the Mineração Maracá area indicated hydraulic conductivity values varying between 10-8 m/s and 10-6 m/s. Overall the aquifers’ production potential is considered to be low.

 

Groundwater recharge to this aquifer system is considered to occur by direct precipitation that infiltrates the superficial sediment layer that occurs in the area. The discharge occurs as base flow to the rivers mentioned above.

 

The next stages of this study will involve the installation of monitoring wells, groundwater sampling and chemical analyses, followed by the development of a groundwater flow model to simulate the future requirements for mine dewatering and their potential impacts.

 

17.2              Tailings Dam

 

The report prepared by Geoconsultoria presents the conceptual study for the Suruca Project tailings disposal system, to be installed close to the Chapada Project, at Alto Horizonte, GO.The Suruca Project will include the gold ore mining and its transportation and concentration in the Chapada plant. Accordingly, it is more desirable that the tailings facility in operation for the Chapada Project be used to contain the tailings from the Suruca Project. Drawings are in Appendix A.

 

The Chapada Project has been in operation for about 4 years. It comprises an open pit mine and abeneficiation plant for copper and gold. The concentrate is exported and the tailings are deposited behind a dam raised with the UF of the cycloned tailings, using the centerline method of construction.

 

The present dam crest is at elevation 360 m, designed for a final crest elevation of 382 m (Dam Projetos dwg. No. BPI-E-BP-DE-301-0, April/2010). The total mass of solids already deposited in the dam reservoir is around 70 Mt, with the plant operational regime of 63.000 t/day, 7.892 hrs/year or 328 days/year.

 

The total ore reserve to be mined has been calculated as 368 Mt, from 2011 on, for a period of 17 years. The Suruca Project will add its tailings to the Chapada Project’s tailings, considering a total reserve to be mined of 60 Mt.

 

For the Chapada Project a 95% mass recovery for the tailings is considered and for the Suruca Project the recovery will be 97%. The total mass of tailings to be stored will amount to 407.8Mt. Considering the value of dry density as 1,4 t/m³ for the tailings in the reservoir, results the total volume to be occupied of 291.3 Mm³. To this volume another volume of 50 Mm³ will be added

 

142



 

as the volume already disposed in the present tailings dam, so resulting in the total volumeof 341.3 Mm³.

 

About 150 t/hr of the Suruca Project tailings, representing the flotation cleaner stage, shows around 2 to 5% of sulphides in its composition. As this mass will represent only 6% of the total mass of tailings, in this study the potential for acid generation is not considered, due to the expected dilution.

 

17.3              Present Dam situation and Raising Needs

 

The present dam, according to the design developed by DAM Projetos de Engenharia Ltda., will be raised until elevation 382 m (DAM dwg. BPI-E-BP-DE 301-0, April/2010), shown in Geoconsultoria dwg. No. YM16-DE-001.

 

For the retention of the total volume of tailings as calculated above (341.3 Mm³), the dam will have to be raised above the initial design. For this reason, the reservoir filling has been simulated until elevation 388 m. In this condition the total capacity of the reservoir will be 349.5 Mm³, sufficient for the operation of both projects as shown in Geoconsultoria dwg. YM16-DE-002.

 

For this simulation the following premises have been considered, and they are different fromthose defined in the DAM Projetos concept:

 

a) the tailings will be discharged by pipeline from the south, east and north borders of thereservoir, in such a way that the supernatant water pool will be displaced to the west side;

 

b) from an elevation of 388 metres and above, the pipeline will be moved towards the center of the reservoir,to form a horizontal platform until a certain position. From this point on the tailings beach will show the normal slope of 0.7% above water and 3% below water;

 

c) the final water level will be at el. 378 m;

 

d) the crest elevation, along the entire perimeter of the dam, will be variable, being more elevated (388 m) at the south, east and north sides and less in the west side;

 

e) as the pool will be displaced to the west area of the reservoir, the water reclaim pumping station will also be moved to this region as well the spillway system;

 

f) for easy of operation and to guarantee an adequate tailings and pool handling during the dam raising operation, the spillway will be changed to a gallery and penstock system,and operated with stop logs. At the closure stage the spillway will turn again to the openchannel system;

 

g) the operation of the reservoir will favor the closure plan, because one of the alternatives that can be considered in the future is to eliminate the pool area and transform the entire reservoir in a tailings dump;

 

h) the almost horizontal surface that will result from the operation of the pipelines and spigotting, as planned, shall be revegetated to avoid dust generation.

 

In this filling simulation, shown in dwg. No. YM16-DE-002, the tailings volume amounts to 329.1 Mm³ and the water volume to 20.4 Mm³, representing the total volume of 349.5 Mm³. The total

 

143



 

volume of tailings will be 341.3 Mm³ to accommodate the required volume there will be a need to move a little the pipeline towards the west side, replacing the water volume for the tailings volume, without changing the total mass balance.

 

In this simulation, no distinction is made for the behavior of the two tailings, from the Chapada Project and from the Suruca Project.

 

17.4              General Layout of Chapada Project Mine and Suruca Project

 

The Chapada Project property is located in northern part of Goias State, approximately 320 kilometres north of the state capital Goiania and 270 kilometres northwest of the national capital of Brasilia.  The Suruca Project is located 6 kms northeast of the Chapada Project mine.

 

Yamana is mining the copper-gold ores of Chapada Project by conventional open pit methods, with 2007 being the first year of commercial production. Processing occurs in a conventional copper sulphide flotation plant designed to process about 22 million tonnes per year of ore.  The plant produces a copper-gold concentrate that is shipped to smelting and refining facilities.

 

The Suruca Project’s ore deposit includes two distinct basic ore types: Suruca oxide ore and Suruca sulphide ore. The production plan that was completed by AMEC was based on a two stage plan. The first step is to send only oxidized material to the heap leach pad located adjacent to the Suruca Project pit, and the second stage is to send sulphide material to the Chapada Project’s concentrator plant. The plan indicates that all of the oxidized material will be exhausted by 2017. Subsequently, the sulphide ore will be sent to a primary crusher and then to the concentrator located in the Chapada Project mine.

 

Figure 17.1 shows the general layout of the Chapada Project’s mine infrastructure and Suruca Project.

 

144



 

Figure 17.1: General Layout Chapada Project Mine & Suruca Project

 

 

145



 

18               INTERPRETATION AND CONCLUSIONS

 

Mineral reserve and Mine

 

The resources used by AMEC to develop this study for the Suruca Project have been verified in the Section 16 of this report and conform to the current CIM standards and definitions for estimating resources as required pursuant to NI 43-101.

 

These resources will be mined by open-pit. AMEC has included only indicated mineral resources in this assessment.

 

Geotechnical slope angle selection and the waste dump design were completed by VOGBR Consulting.

 

Mineral reserves for the Suruca Project are classified in accordance with the 2005 CIM definition standards for mineral resources and mineral reserves, and are reported to a gold price of US$900/oz.

 

The production plan that was completed by AMEC was based on two stages. The first step is to send only oxidized material to the heap leach pad located adjacent to the Suruca Project pit, and the second stage is to send sulphide material to the Chapada Project concentrator plant. This production plan must start in 2013 and is scheduled to finish in 2022. The maximum material movement is 18.4 Mt between 2015 and 2020.

 

The project’s economic model has been developed and completed by Yamana using the Suruca Project’s production schedule developed by AMEC, and integrating the costs from the operating Chapada Project’s mine.

 

Tailings Dam

 

The present dam shows sufficient capacity to store the tailings from the Suruca Project, just with crest elevation of 4 m, above the final elevation defined in the original design.

 

Metallurgy

 

A metallurgical test work and design review was also conducted and the following is a summary of the review;

 

The test work for both the Suruca oxides and sulphides is limited at this point in time. Greater detail and precision is evident in the oxide test work compared to the sulphide test work program. The selection of samples for the next section of metallurgical test work is critical. A drilling campaign needs to be developed which covers the ore body from the perspectives of grade and lithology. A geometallurgical selection of samples for the next metallurgical test work campaign is highly recommended to ensure that both the physical and recovery characteristics of the Suruca Project ore body are covered adequately for a definitive feasibility study level design study.

 

Neither the current sample selection process details nor the representative nature of both the oxide and sulphide samples are known. Therefore, the results from the test work conducted to date have been used as a basis for physical characterisation and metal recovery. Whether

 

146



 

these samples represent the ore body has yet to be ascertained and needs to be confirmed by independent geometallurgical experts.

 

19               RECOMMENDATIONS

 

Mine — Suruca Project

 

It is recommended that the waste dump be relocated closer to the pit exit so as to decrease the transport distances and potentially the mining cost.

 

It is recommended that a mining cost of US$ 1.62/t be used in the feasibility study as this is the cost calculated for the current production schedule.

 

Yamana must have the exploitation rights before starting the feasibility study.

 

It is recommended that the exploration drilling campaign be completed so as to improve the geological estimate. Completion of the campaign may also convert some inferred resources into indicated as well as and indicated to measured resources.

 

Metallurgy

 

The following testworks are recommended:

 

Oxides

 

·                  Further heap leach test work focussing on optimization of:

 

·                  Cement agglomeration;

·                  Crush size (sizing) versus gold recovery;

·                  Optimal application rates;

·                  Optimal application volumes.

 

This test work should be conducted on a variety of samples (variability) from the Suruca Project’s oxide deposit. It is known that there is also a small transition zone between the Suruca oxide and sulphide ores. It is important that the metallurgical response of this ore is known, particularly from the perspective of heap leach recovery characteristics. It is important that the development of a methodology, which will determine whether the ore is characterised as either oxide or sulphide ore. Characterization is important because the treatment route for the oxide and sulphide ores is completely different.

 

Sulphides

 

·                  For the Suruca ores further flotation test work including the following:

 

·                  Open circuit test work which focuses on the optimization of grind size, reagent additions/types and residence time requirements. This includes conducting variability tests on different samples across the sulphide deposit;

·                  Once the open circuit tests have been defined, a series of bench scale closed circuit testing will need to be conducted which represents the intended flow-

 

147



 

sheet. The closed circuit test work will confirm reagent requirements, residence time requirements and confirm the circuit mass and water balances;  and

·                  Larger bench scale test work or pilot scale test work needs to be completed in order to produce sufficient quantities of concentrates for other test work including but not limited to leach test work optimisation, regrind mill physical test work, detoxification, and settling/flocculant selection.

 

·                  Study the use of oxygen injection versus air injection in the concentrate leach and adsorption circuit. PSA oxygen plants are now available and can be cost effective in comparison to air blowers. However, as the gold concentrate for leaching is predominantly pyrite and therefore a non reactive sulphide, it is believed that the use of air will be cost effective in this instance;

 

·                  For the existing Chapada Project’s plant, which will be used to treat a combination of Suruca and Maraca ore, it is suggested that modeling of various grinding circuit options be considered. The models will determine circuit options which could be implemented to reduce overall project costs. At this point in time, a pyrite comminution and flotation circuit has been considered. However, it is believed that other options exist, which are more cost effective from the perspective of energy and capital costs;

 

·                  Further gravity recovery testwork needs to be completed on a variety of Suruca samples to confirm both “batch” free gold recovery using standard gravity recoverable gold (GRG”) test work and also sulphide recovery test work to determine whether continuous gravity recovery devices can replace some sections of flotation within the current projected flow-sheet. The test work should also produce sufficient quantities of concentrate in order to complete intensive cyanide leach tests on both the batch and the sulphide concentrates;

 

·                  As mentioned above, INCO detoxification testing needs to be conducted on the residues from the cyanide leaching of pyrite flotation concentrates. This will confirm chemical (SMBS and Air), mixing and residence time requirements. Assumptions have been made in relation to chemical, mixing and residence time requirements for this level of study;

 

·                  As mentioned above, settling and flocculant selection tests need to be conducted on the pyrite concentrates produced from the locked cycle tests. Flocculant screening tests and flocculant addition tests need to be conducted. The possibility of using rake-less thickeners rather than conventional high rate thickeners needs to be investigated;

 

·                  Original test work has indicated that the ore does not have preg-robbing tendencies. This needs to be confirmed with variability testing;

 

·                  Viscosity and settling testing needs to be conducted on the pyrite flotation concentrates produced to confirm the agitator and tank dimension requirements for the concentrate leach tanks;

 

·                  In order to conduct the modeling above a greater amount of physical characterisation test work needs to be conducted in variable sulphide samples;

 

·                  Drop weight index (DWi) and SAG mill competency (SMC) sample testing

·                  Ultimate compressive strength (UCS)

·                  Bond ball mill work index (BWi) testing

·                  Bond rod mill work index (RWi) testing

·                  Impact crushing work index (CWi)

 

148



 

·                  Operating power index (OWi)

·                  Abrasion indices (Ai)

 

Maraca Ore

 

The copper recovery characteristics of the Maraca ore treated in the Chapada Project plant seem to be well understood. The current losses of gold from the Maraca ore are also well understood. It is apparent that these losses are associated with pyrite and to a lesser extent silica.

 

Test work on future Maraca ores treated with the Suruca ore need to undergo the same test work indicated above. A greater understanding of the gold and size distributions within the existing circuits needs to be understand along with the impact that grind size has on gold recovery and overall power requirements with respect to the various Maraca ore types.

 

Work has been conducted by UIMIN consultants in June 2010 focussing on the improvement of gold and copper recoveries from the existing Maraca ores. The recommendations from the work conducted and confirmed by the author include the following:

 

·                  Improve plant sampling in a number of plant locations:

 

·                  Samples from within the comminution circuit including primary cyclone feed,overflow and underflow, secondary cyclone feed, overflow and underflow;

·                  Head grade sample (before and after flotation)

·                  Rougher-scavenger flotation tailings

·                  Rougher and scavenger flotation concentrates

·                  Cleaner-scavenger flotation tailings

·                  Final flotation tailings

 

·                  Conducting campaigns on individual types of ores from the Maraca deposit. Normally, ores are blended in the Chapada Project plant. It is recommended that the ores are treated separately for a period of one week to determine individual ore characteristics. During this period detailed plant sampling in both the comminution and flotation circuits needs to be conducted. Modeling of the various ore types within the circuit will assist in the determination of design requirements for the Maraca plant when Suruca ore is introduced;

 

·                  Profile monitoring of the flotation circuit rougher-scavenger cells to determine:

 

·                  Whether there is a gold loss or not at the last scavenger cell

·                  Residence time for the rougher scavengers

·                  Whether increased numbers of rougher scavenger cells are required

 

·                  Sampling of rougher-scavenger tails collected over different periods when treating distinct ore types from the Maraca orebody and include the following analysis:

 

·                  Fractional analysis of the rough-scavenger tails

·                  Cycloning of the RST to produce U/F of 20 to 40% by weight and fractional analysis of both U/Fand O/F

·                  Grinding the U/F samples collected and carry out standard flotation tests

·                  Determine the grinding index for both ball and Verti-mills

 

·                  Sampling of cleaner scavenger tailings (CST) over different time periods with distinct samples. Collect samples and conduct cyanidation tests.

 

149



 

·                  Geometallurgical selection of samples representing both locations and ore-types for ore to be treated jointly with the Suruca ore. These tests would include standard flotation tests including sequential chalcopyrite and pyrite flotation tests and grind tests for work indexes.

 

In summary, all of the information on the current and future Maraca ores should be used to predict the performance of the ore when treated jointly in the existing and modified Maraca plant. This information will be useful when conducting a financial analysis of the options being considered.

 

150



 

20               DATE AND SIGNATURE PAGE

 

This report titled “Chapada Mine and Suruca project technical report”, dated as of March 7th 2011, was prepared and signed by the following authors:

 

(Signed) Sergio Brandão

 

Sergio Brandão

 

 

 

(Signed) Homero Delboni

 

Homero Delboni

 

 

 

(Signed) Greg Walker

 

Greg Walker

 

 

 

(Signed) Emerson Ricardo Ré

 

Emerson Ricardo Ré

 

 

 

(Signed) Raúl Contreras

 

Raúl Contreras

 

 

 

(Signed) Renato Petter

 

Renato Petter

 

 

151



 

21               ADDITIONAL REQUIREMENTS FOR TECHNICAL REPORTS ON DEVELOPMENT PROPERTIES AND PRODUCTION PROPERTIES

 

21.1              Mining Operations

 

21.1.1              Chapada

 

Mining at the Chapada Project is by conventional open pit methods. Benches are 10 metres high, doubling to 20 m towards the limit of the pit, except in upper benches where the benches are 10 m high in soil.

 

The operating phases have been designed to support the mine production from initial topography of January 2011 up to the final pit geometry. To allow the operations of 150 tonne trucks, haulage ramps with a width of 30 metres are required with a maximum gradient of 10%.

 

The interamp angle by zone is shown in Figure 21.1 and ranges from 45º up to 56º for more competent rock zone.

 

Figure 21.1: Inter-Ramp Angles by Zone

 

 

An in-pit primary crusher will be built in bench at an elevation of 300 m in July, 2012. This will allow for a more flexible operation of ore blending to plant and will reduce the truck fleet requirements.

 

152



 

Figure 21.2: In pit crusher 3D view, July 2012

 

 

Figure 21.3: In pit crusher 3D view layout operation, July 2012

 

 

The plant has been in operation since 2008 in accordance with a feasibility study conducted in 2004. The mine plan developed by Metalica is based on supplying ore to a conventional copper sulphide flotation plant over four years at an increasing rate of 22 million tonnes per year. To achieve this ore production it is necessary that the Chapada Project mine remove 53 Mt in 2010 (ore and waste rock), 60 Mt in 2011, 54 Mt in 2011, 54 Mt in 2012, and continue this rate. After completion the mine plan schedule, Yamana estimated the metallurgical recoveries year to year for copper and gold.

 

153



 

21.1.1.1             Mine Equipment

 

The plant has been in operation since 2008 in accordance with a feasibility study conducted in 2004. The mine plan developed by Metalica is based on supplying ore to a conventional copper sulphide flotation plant over four years at an increasing rate of 22 million tonnes per year. To achieve this ore production it is necessary that Chapada Project mine remove 53 Mt in 2010 (ore and waste rock), 60 Mt in 2011, 54 Mt in 2011, 54 Mt in 2012, and continue this rate. After completion of the mine plan schedule, Yamana estimated the metallurgical recoveries year to year for copper and gold.

 

Table 21.1 Chapada Current Mining Equipment Contractor Fleet

 

DESCRIPTION

 

Number

HAULAGE

 

 

Caterpillar 785D

 

9

LOAUDING

 

 

Excavator (RH-120 O&K)

 

2

Loader (Caterpillar 993K)

 

1

DRILLING

 

 

Drilling Roc L8 - 6 3/4''

 

4

SERVICES

 

 

Bulldozer (Caterpillar D9T)

 

1

Bulldozer (Caterpillar D8T)

 

1

Wheeldozer (Caterpillar 824H)

 

1

Wheel loader (Caterpillar 980H)

 

1

Motor grade (Caterpillar 16M)

 

1

Motor grade (Caterpillar 140H)

 

1

Excavator (Liebherr R964B)

 

2

Hammer machine (Liebherr R944)

 

1

Backhoe Loader (Caterpillar 416B)

 

1

 

The mine is operated by Yamana (24Mtpy 2011, 29Mtpy 2012, 34 Mtpy 2013-2020) and Contractors (difference of total move) equipment. From 2017 on, the operation is totally operated with own equipment. The haulage distances were calculated to the different points of discharge (waste dump, crusher and stock areas) with a total average of 1.6 kilometres. Figure 21.4 shows the annual haulage distances and annual mine movement. Figure 21.4 shows the annual haulage distances and annual mine movement.

 

154



 

Figure 21.4: Mine Haulage Distances

 

 

The estimate took into account the characteristics of equipment according as dictated by the mining plan: drilling machines of 7”, hydraulic backhoe (O&K RH 120) of 17 m(3) and trucks 150 tons (CAT 785C). Table 21.2 summarizes the mine fleet requirements by year during the mine life.

 

Table 21.2 Mine Major Equipment Fleet Requirement

 

DESCRIPTION

 

unit

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Total material move

 

kt

 

60,393

 

54,000

 

54,000

 

54,000

 

54,000

 

54,000

 

34,000

 

34,000

 

34,000

 

34,000

 

27,775

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Chapada Own Fleet

 

kt

 

24,000

 

29,000

 

34,000

 

34,000

 

34,000

 

34,000

 

34,000

 

34,000

 

34,000

 

34,000

 

27,775

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Haulage distances (DMT)

 

m

 

2,127

 

1,809

 

1,538

 

1,348

 

1,298

 

1,319

 

1,919

 

1,908

 

1,640

 

1,612

 

1,475

 

1,146

 

1,489

 

1,390

 

1,370

 

1,329

 

1,350

 

1,350

 

1,350

 

Chapada Contractors Fleet

 

kt

 

36,393

 

25,000

 

20,000

 

20,000

 

20,000

 

20,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Haulage distances (DMT)

 

m

 

1,971

 

1,586

 

1,742

 

1,643

 

1,847

 

1,908

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DESCRIPTION

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HAULAGE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Caterpillar 785D

 

unit

 

9

 

13

 

13

 

13

 

13

 

13

 

13

 

13

 

13

 

13

 

11

 

8

 

8

 

8

 

8

 

7

 

7

 

7

 

6

 

LOAUDING

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Excavator (RH-120 O&K)

 

unit

 

2

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

Loader (Caterpillar 993K)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

DRILLING

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Drilling Roc L8 - 6 3/4''

 

unit

 

4

 

4

 

4

 

4

 

4

 

4

 

4

 

4

 

4

 

3

 

2

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

SERVICES

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Bulldozer (Caterpillar D9T)

 

unit

 

1

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

3

 

Bulldozer (Caterpillar D8T)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

Wheeldozer (Caterpillar 824H)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

Wheel loader (Caterpillar 980H)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

Motor grade (Caterpillar 16M)

 

unit

 

1

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

Motor grade (Caterpillar 140H)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

Excavator (Liebherr R964B)

 

unit

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

2

 

Hammer machine (Liebherr R944)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

Backhoe Loader (Caterpillar 416B)

 

unit

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

1

 

 

For the determination of the mining equipment, the following parametres were considered: 60 minutes per day for shift change, 130 minutes per day for meals and for blasting and others delays 30 minutes per day. The productivity for drilling machine in ore is 96 t/m and in waste is 112 t/m. The effective drilling velocity is 29 m/hr. For the shovel RH 120 (17 m3) the productivity was defined in approximated 2,000 t/h. For the trucks CAT 785 C (150 metric ton) the final productivity in according with de haulage distances was approximated 8,500 t/unit-day.

 

155



 

21.1.2              Suruca

 

21.1.2.1             Production Planning

 

To complete the production plan, five operational phases were designed from the pit optimization which was performed with the LG algorithm. The first three phases are aimed at achieving early extraction of oxide material, and the bottom benches of these phases extract the sulphide contents. Phases four and five are exclusively designed to complete the sulphide material mining in order to meet the required plant delivery schedule for the Chapada Project mine.

 

The design parametres of the operating phases are shown:

 

·                  Saprolitos and Oxide materials (top of the pit to the 350 bench):

 

·                  Maximum height of bench: 10 m (double bench)

·                  Ramp width: 25 m

·                  Ramp gradient: ±10%

·                  Bench face angle: 45°

·                  Berm width: 7 m each 10 metres in depth (double bench)

·                  Inter-ramp angle: 30°

 

·                  Sulphide material (bench 350 to the bottom of the pit):

 

·                  Maximum height of bench: 30 m (6 benches)

·                  Ramp width: 25 m

·                  Ramp gradient: ±10%.

·                  Bench face angle: 70°

·                  Berm width: 12 m each 30 metres in depth (6 benches)

·                  Inter-ramp angle: 53°

 

Figure 21.5 shows the location of the operating phases. Also, Figure 21.6 through Figure 21.10 shows each of individually designed phases. Figure 21.11 and

 

Figure 21.12 show the operating final pit with the mathematical pit. It shows that there are not many differences with the final boundaries of the two cases which were developed.

 

156



 

Figure 21.5: Pit Phase Design

 

 

Figure 21.6: Phase 1

 

 

157



 

Figure 21.7: Phase 2

 

 

Figure 21.8: Phase 3

 

 

158



 

Figure 21.9: Phase 4

 

 

Figure 21.10: Phase 5

 

 

159



 

Figure 21.11: Operating Final Pit vs Ultimate Pit Optimization

 

 

Figure 21.12: Operating Final Pit vs Ultimate Pit Optimization (Section)

 

 

These five phases are summarized in Table 21.3.

 

Table 21.3: Planned Suruca Project Phases

 

 

 

To Process Oxide Plant

 

To Porcess Sulphide Plant

 

To Porcess Total Plant

 

Waste

 

Total

 

 

 

 

 

Tonnes

 

Au

 

Tonnes

 

Au

 

Tonnes

 

Au

 

Tonnes

 

Tonnes

 

Strip

 

 

 

(x 1,000)

 

(g/t)

 

(x 1,000)

 

(g/t)

 

(x 1,000)

 

(g/t)

 

(x 1,000)

 

(x 1,000)

 

Ratio

 

Phase 1

 

4,721

 

0.602

 

2,079

 

0.584

 

6,800

 

0.596

 

7,417

 

14,217

 

1.09

 

Phase 2

 

8,498

 

0.492

 

2,309

 

0.497

 

10,807

 

0.493

 

10,030

 

20837

 

0.93

 

Phase 3

 

2,769

 

0.412

 

1,912

 

0.444

 

4,681

 

0.425

 

5,052

 

9733

 

1.08

 

Phase 4

 

193

 

0.458

 

10,648

 

0.578

 

10,841

 

0.576

 

15,884

 

26725

 

1.47

 

Phase 5

 

150

 

0.566

 

27,176

 

0.553

 

27,326

 

0.553

 

43,847

 

71173

 

1.60

 

Total

 

16,331

 

0.510

 

44,124

 

0.553

 

60,455

 

0.541

 

82,230

 

142,685

 

1.36

 

 

160



 

The production plan that was completed by AMEC was based on a two stage plan in accordance with the requirements of Yamana. The first step is to send only oxidized material to the heap leach pad located adjacent to the Suruca Project’s pit, and the second stage is to send sulphide material to the Chapada Project concentrator plant.

 

The plan indicates that all of the oxidized material will be completed by 2017. Subsequently, the sulphide ore will be sent to a crusher and then to the concentrator located near the Chapada Project mine only 7 km away, helping to enhance the production of this mine.  This strategy was decided by Yamana in accordance with the results of different production scenarios developed in this study.

 

For the mine plan to meet the production scenario outlined in the previous paragraph, it was necessary to develop a stockpile that would contain the sulphide ore until shipment in 2017.

 

The mine production schedule was prepared using periods of one year, beginning in 2013. At this stage of project development, there is no need to increase the time resolution to shorter periods, however, tighter time periods could help to optimize the mine plan and decrease the sulphide stockpile necessity, by completing more selective mining.

 

The mine schedule requires a total of 3 Mt of oxide material to be send to stockpile year 2013 and 4 Mt from year 2014 forward. Furthermore, to increase the production of Chapada Project’s mine it was necessary to send sulphide to the plant from year 2017, generating a ramp up of 4.5 Mt this year and 8 Mt from 2018 forward.

 

Figure 21.13 and Table 21.4shows the scheduled mine plan production.

 

Figure 21.13: Line Production Schedule

 

 

161



 

Table 21.4: Mine Production Schedule

 

 

 

 

 

Mineral to Plant

 

Mineral to Stock

 

 

 

 

 

 

 

 

 

 

 

Oxide

 

Sulphide From Mine

 

Sulphide From
Stock

 

Total Sulphide

 

Total to Plant

 

Sulphide

 

Waste

 

Total

 

Year

 

Day

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au (gr/t)

 

kt

 

Au(gr/t)

 

kt

 

Au(gr/t)

 

kt

 

kt

 

ktpd

 

2013

 

365

 

3,000

 

0.580

 

 

 

 

 

 

 

 

 

 

 

 

 

3,000

 

0.580

 

 

 

 

 

3,579

 

6,579

 

18

 

2014

 

365

 

4,000

 

0.531

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.531

 

1,154

 

0.596

 

5,281

 

10,435

 

29

 

2015

 

365

 

4,000

 

0.477

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.477

 

1,041

 

0.563

 

9,559

 

14,600

 

40

 

2016

 

365

 

4,000

 

0.535

 

 

 

 

 

 

 

 

 

 

 

 

 

4,000

 

0.535

 

3,146

 

0.491

 

11,104

 

18,250

 

50

 

2017

 

365

 

1,331

 

0.321

 

2,830

 

0,470

 

1,670

 

0.528

 

4,500

 

0,491

 

5,831

 

0.452

 

 

 

 

 

12,596

 

18,427

 

50

 

2018

 

365

 

 

 

 

 

6,405

 

0,510

 

1,595

 

0.528

 

8,000

 

0,514

 

8,000

 

0,514

 

 

 

 

 

10,250

 

18,250

 

50

 

2019

 

365

 

 

 

 

 

6,727

 

0.537

 

1,273

 

0.528

 

8,000

 

0.535

 

8,000

 

0.535

 

 

 

 

 

10,250

 

18,250

 

50

 

2020

 

365

 

 

 

 

 

7,583

 

0.530

 

417

 

0.528

 

8,000

 

0.530

 

8,000

 

0.530

 

 

 

 

 

10,250

 

18,250

 

50

 

2021

 

365

 

 

 

 

 

7,614

 

0.568

 

386

 

0.528

 

8,000

 

0.566

 

8,000

 

0.566

 

 

 

 

 

6,097

 

14,097

 

39

 

2022

 

365

 

 

 

 

 

7,624

 

0.658

 

 

 

 

 

7,624

 

0.658

 

7,624

 

0.658

 

 

 

 

 

3,264

 

10,888

 

30

 

Total

 

3,650

 

16,331

 

0.510

 

38,783

 

0.556

 

5,341

 

0.528

 

44,124

 

0.553

 

60,455

 

0.541

 

5,341

 

0.528

 

82,230

 

148,026

 

41

 

 

162



 

21.1.2.2             Waste Dumps

 

The waste dump location and stability study was completed by VOGBR Consulting.

 

Ideally, the waste dump could be redesigned closer to the final pit limit to decrease the haulage distances and consequently reduce the mining cost associated with this item.

 

Figure 21.14 shows the location of the actual waste dump design.

 

Figure 21.14: Waste Dump Location

 

 

21.2                                                Recoverability

 

Recoveries are based on a copper tail grade of 0.04% copper, a gold tail grade of 0.12 g/t and a 28% copper concentrate grade.  For example, for a copper grade of 0.332% the copper recovery and concentration ratio from the standard two product formulas are:

 

·                  Copper Recovery = 100% x 28 x (0.332 — 0.040) / (0.332 x (28 — 0.040)) = 88.1%

 

·                  Concentration Ratio = (28 — 0.040) / (0.332 — 0.040) = 95.8

 

Assuming the same concentration ratio for gold, the gold concentrate grade for a gold grade, for example of 0.239 g/t is:

 

·                  Gold Concentrate Grade = 95.8 x (0.239 — 0.120) + 0.120 = 11.5 g/t

 

163



 

·                  Gold Recovery = 100% x 11.5 x (0.239 — 0.120) / ( 0.239 x (11.5 — 0.120) = 50.3%

 

It can be shown algebraically that the equation for recovered gold simplifies to:

 

·                  Recovered Gold Grade = gold — tail + tail/concentration ratio

 

·                  Recovered Gold = 0.239 — 0.120 + 0.120/95.8 = 0.120 g/t

 

·                  And 0.120 / 0.239 = 50.3% recovery.

 

This also shows that the gold recovery is not sensitive to the concentration ratio and concentrate grade assumptions.

 

21.3              Production Scheduling Integrated

 

The planned Chapada Project and Suruca Project gold and copper production for the life of mines is summarized in Table 21.5 below. The summary includes all three phases of the project and is based on the pre-feasibility production levels.

 

164



 

Table 21.5: Processing Plant Production Plan — Chapada/Suruca

 

Yamana Gold

Name of Asset

 

Chapada and Suruca

 

Status

 

Operating and Project

 

Date

 

December 31, 2010

 

PRODUCTION

 

Unit

 

Total

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Ore Feed Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Copper Grade

 

%

 

0.264

%

0.431

%

0.371

%

0.308

%

0.298

%

0.290

%

0.305

%

0.330

%

0.316

%

0.321

%

0.360

%

0.257

%

0.202

%

0.190

%

0.189

%

0.185

%

0.180

%

0.185

%

0.174

%

0.180

%

Copper Recovery

 

%

 

85.3

%

86.8

%

87.1

%

86.1

%

86.0

%

85.9

%

86.4

%

86.9

%

86.6

%

87.6

%

84.1

%

84.1

%

84.3

%

84.4

%

84.2

%

83.9

%

84.0

%

84.0

%

84.0

%

84.0

%

Copper Contained

 

Mlb

 

2,149

 

205

 

180

 

150

 

144

 

141

 

148

 

127

 

98

 

99

 

111

 

79

 

64

 

92

 

92

 

90

 

87

 

90

 

85

 

68

 

Copper Production

 

Mlb

 

1,840

 

178

 

157

 

129

 

124

 

121

 

128

 

111

 

84

 

87

 

93

 

67

 

54

 

78

 

77

 

75

 

73

 

75

 

71

 

58

 

Gold Grade

 

g/t

 

0.176

 

0.330

 

0.304

 

0.243

 

0.228

 

0.210

 

0.199

 

0.220

 

0.199

 

0.200

 

0.240

 

0.169

 

0.129

 

0.100

 

0.098

 

0.098

 

0.097

 

0.106

 

0.091

 

0.093

 

Gold Recovery

 

%

 

62.2

%

60.7

%

60.8

%

58.8

%

64.8

%

63.0

%

62.1

%

63.7

%

61.8

%

76.0

%

64.9

%

61.9

%

61.6

%

61.3

%

60.6

%

61.1

%

61.1

%

61.1

%

61.1

%

61.1

%

Gold Contained

 

koz

 

2,082

 

229

 

215

 

172

 

161

 

149

 

140

 

124

 

90

 

90

 

108

 

76

 

60

 

71

 

69

 

69

 

69

 

75

 

64

 

52

 

Gold Production

 

koz

 

1,299

 

139

 

131

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

Ore Feed Suruca Oxides

 

kt

 

16,331

 

 

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.511

 

 

 

 

 

0.580

 

0.531

 

0.477

 

0.535

 

0.321

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

85.0

%

 

 

 

 

85.0

%

85.0

%

85.0

%

85.0

%

85.0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

228

 

 

 

 

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore Feed Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.553

 

 

 

 

 

 

 

 

 

 

 

 

 

0.491

 

0.514

 

0.535

 

0.530

 

0.566

 

0.658

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

626

 

 

 

 

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

 

 

 

 

 

 

 

Total Ore Feed

 

kt

 

429,171

 

21,555

 

22,000

 

25,000

 

26,000

 

26,000

 

26,000

 

23,331

 

22,000

 

22,000

 

22,000

 

22,000

 

22,024

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Suruca Oxides

 

kt

 

16,331

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

2,152

 

139

 

131

 

149

 

162

 

146

 

146

 

147

 

161

 

178

 

179

 

163

 

166

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

 

165



 

21.4                Contracts

 

The following contracts are within industry norms.

 

The Chapada Project mine has a long term sales contracts with Hidalco Industries Limited - Birla Copper Group of India covering a total volume of 70,000 dmt in 2007, 130,000 dmt during 2008 and 100,000 dmt from 2009 up to 2018; Atlantic Copper-Freeport MacMoRan Copper & Gold Inc - American Group covering a total volume of 30,000 dmt in 2007, 50,000 dmt in 2008 and 50,000 dmt each per year from 2009 to 2011; Paranapanema S/A — Brazilian Group covering a total of 16.000 dmt in 2007, 24,000 dmt each per year during 2008 and 2009, 35,000 dmt in 2010 and 44.800 dmt in 2011. Yamana also has contracts with two trading companies: Trafigura AG, 40,000 dmt in 2007, 30,000 dmt in 2008 and 30,000 dmt each per year from 2009 to 2010 and 40,000 dmt each per year from 2011 to 2012; Louis Dreyfus Commodities Metals Suisse S/A covering a total of 30,000 dmt each during the period 2007 - 2008 and 40,000 dmt each per year from 2009 to 2012.

 

21.5                Environmental Considerations

 

21.5.1     Chapada

 

A substantial amount of environmental study, analysis and regulatory review was made for the Chapada Project.  In November, 1996, Geomina Consultants, from Goiânia, State of Goiás, Brazil, developed an environmental impact study. This report was used for public comment and as support for application for permits. Yamana obtained the three environmental permits required for mine operations in Brazil: 1) the first environmental license was issued in December 1999; 2) the construction license was issued in April 2001 and was renewed twice in April 2003 and April 2006; and 3) the operation license was published in November 2006, and it was valid until April 2008. The operation of the Maraca Mine started up in November 2006.

 

On December 2007, Maracá mine submitted to the State of Goiás Environmental Agency all necessary documents to obtain the operational environmental license renewal. The license renewal was issued in September 2009 and is valid until March 2011.

 

The Chapada Project mine is with all licenses (operation, deforest, water use permit, etc) needed to operate.

 

The environmental impact study was carried out by Geomina Consultants, the results of which are summarized as follows:

 

Environmental and socioeconomic characterization of the mine influence area was done by using existing available data, and by obtaining site-specific information. No ethnic minorities or tribal groups were identified in the mine area of influence.

 

A non-intervening archaeological inspection, developed in May 2004, led to the identification and registration of eight and nine archaeological sites and occurrences, respectively. The archaeological rescue identified 19 sites and eight occurrences effectively. The pieces rescued are entrusted at Porangatu Museum.

 

During 2009 a new archeological rescue effort was done at the new sites that will be flooded to increase the tailings dam.

 

166



 

The site vegetation survey identified 118 species of six types of vegetation, reinforcing the tropical (savannah) characteristics of the natural vegetative. Four protected species were found. Deforestation licenses were approved. Forest reservations were created according to the legislations, and the land use in these areas is restricted.

 

Fauna studies identified a total of 121 species, six of them being protected.

 

An environmental characterization test program was conducted on the unprocessed rock and mill products during 1997 by using Environmental Protection Agency (EPA”) standards protocols. The results have suggested low acid rock drainage potential. Aluminum, iron and manganese were found in drill holes within concentrations detected in the local groundwater. The potential implication of selenium presence in some cases should be reviewed during operation.

 

Surface water background concentrations of some of the parametres are higher than the maximum value permitted by the National Environmental Council (“CONAMA”) Rule 357/2006.  Effluent physicochemical treatment facilities include a specific pond for tailing dam overflow and/or contaminated excess pit water. The monitoring program is permanent to evaluate the quality of the water whitin the mine site and vicinities.

 

Storm water runoff and hazardous liquids handling are adequately addressed using best management practices.

 

The sewage treatment plant is operating in order to attend all mine sanitary requirements. Industrial, sanitary and solid waste is disposed of at the Chapada Project’s facilities in a temporary deposit, then taken to recyclers and to the Alto Horizonte landfill.

 

The closure and reclamation plan is being revised in order to improve environmental and human life protection, reducing long-term monitoring, maintenance, and potential liabilities. An amount of US$ 54 million is estimated for closure and abandonment costs

 

21.5.2     Suruca

 

MINERAL Engenharia e Meio Ambiente is developing the environmental studies for Suruca Project. This project involves mining of sulphide and oxide gold ore in an open pit mine Suruca. The Suruca Project is located at the city of Alto Horizonte in the State of Goias and the oxide ore will be leached in pile close to the open pit and will be transported to the processing plant on site. The sulphide ore will be transported by road or conveyor belt to Maraca plant.

 

According to the surveys carried out on the Suruca’s Project, it was verified that levels of total particles in suspension were in conformity with the primary standard adopted by CONAMA Resolution 03/90.

 

The water courses in the Suruca Project area were characterized as being small, with a great majority of intermittent courses. In order to assess the quality of surface waters at the areas of interest, the parametres identified above the allowed limit may be linked to the lithotypes that occur in the region or the occurrence of rains that could have remobilized the sediments or carried solids.

 

167



 

The groundwater at the Suruca Project’s region occurs in a mixed aquifer system and the anomalous concentrations observed can be attributed to a background effect, since the rocks of the region are naturally rich in metallic sulphides, the form in which the explored mineral occurs.

 

The noise levels in the surrounding areas of the Suruca Project were measured. Results were above the limits as expected according to the established limits by NBR10151, due to the presence of a variety of animals in the region.

 

The vegetation in the Suruca Project area is savannah woodland, savannah “stricto sensu”, secondary formations, gallery forest and anthropic field. Some fauna species observed are sensitive to the anthropic disturbance and can be considered as conservation priority.

 

Alto Horizonte has a reasonable infrastructure regarding the aspects of health, education and basic sanitation. The infraestruture is comprised of a Health Basic Unit, two educational institutions and a sewer system that is currently being implemented.

 

The conflict over land was part of the history at the North of Goias, which had the expansion of the mineral exploitation as its main front. Currently there are no records of conflicts of this kind, and the city does not have any rural settlement or settlement projects.

 

The region has a significant archeological heritage, and given the magnitude of the impact of the project, it is recommended the accomplishment of the Archaeological Prospection and Rescue Program, complying with the Brazilian legislation and regulation.

 

No indigenous communities were identified at the project as well as real state property or immaterial heritage tumbled by the National Historic and Artistic Heritage Institute (IPHAN).

 

A Quilombola community was identified at the city of Uruaçu, which is classified as direct influence area of the Suruca Project. There is no record of any process in progress for requesting the land possession at the National Institute for Colonization and Agrarian Reform (INCRA).

 

All impacts observed for the Suruca Project may have mitigation measures that will minimize possible adverse effects, through the monitoring programs already implanted by Yamana.

 

21.5.2.1    Acid Rock Drainage

 

The main objectives of the prediction of the acid rock drainage program are: rock characterization, identification of all materials with potential acidity and potential sources of contaminants in the water of drainages, and also evaluation of control measures with the development of project management of water, waste and tailings.

 

The Suruca Project is developing the acid rock drainage studies where representative samples of ore and waste were collected and sent for analysis in an independent laboratory for testing of acid- base accounting (MABA”), net acid generation (NAG”), waste characterization and analysis of gross weight.

 

168



 

21.6     Financial Analysis

 

21.6.1     Suruca Financial Analysis

 

21.6.1.1    Objective

 

The main objective of this analysis is to evaluate the Suruca Project development and implementation.

 

The project Project is to achieve average annual gold sales of:

 

·      46 koz/year of oxide ore gold from 2013 to 2017, generating a total of 228 koz;

 

·      104 koz/year of sulphide ore gold from 2017 to 2022, generating a total of 626 koz;

 

·      14 koz/year of gold generated from the increased recovery of gold at the Chapada Project mine where the sulphide ore will be processed. The carbon in leach system (CIL) used in the sulphide ore processing will be implemented at the beginning of the project, increasing the recovery of gold from 2013 to 2029 generating, 230 koz an additional during that period;

 

·      Total project gold sales during the project life, based on existing reserves will be 1,084 koz.

 

Project construction will take place in 2011 and 2012 and the production phase of the project will start at the beginning of 2013.

 

The Chapada Project’s gold recovery rate increase will happen in two stages:

 

1.     The first stage is associated with the carbon in leach (CIL) plant implementation at the beginning of the project (Phase 1), adding 10% to the average recovery rate and;

 

2.     The second stage occurs on completion of the Suruca Project sulphide plant in 2016 (Phase 2), adding an additional 10% to the recovery rate.

 

The cash flow analysis was completed by Yamana based upon data generated in the pre-feasibility study.

 

Base Case

 

The main assumptions related to the base case are:

 

·      Gold price equal to US$ 1,300/oz in 2013 and US$ 1,100/oz in subsequent years

 

·      Rate of exchange equal to R$ 1.80/US$

 

·      Sale tax (CEFEM): 1% of annual sales value

 

·      Investment made with 100% equity capital

 

·      Third party mine operation

 

·      Processing plant operated by company

 

·      Discount rate of 5% in real terms per year

 

·      Interest on equity equal to 10% per year (annual “Selic” rate of the Brazil Central Bank)

 

169



 

·      Use of the following incentives: special regime for acquisition of capital assets by exporting cmpanies (RECAP) and drawback incentive for international supplies acquisition.

 

·      Depreciation: according the present Brazilian legislation

 

·      Income tax of 25% plus social contribution of 9%, generating a total income tax of 34%

 

·      Residual value is comprised of assets sells, tax credit recover of 70% for state taxes (federal tax credits recovered, during the life project), and working capital recovery.

 

The base case economic analysis data (financial statement and cash flow) is presented in section 21.6.1.9.

 

Gold Production Basis

 

The total project mineral reserves are estimated to be 60.4 Mt /at an average grade of 0.541 g/t, 1,052 koz, with an average recovery rate of 82% recovered gold, equalling 854 koz.

 

The Suruca oxide reserves are estimated to be 16.3 Mt / 0.510 g/t, 268 koz, with an average recovery rate of 85% recovered gold equalling 228 koz.

 

The Suruca sulphide reserves are estimated to be 44.1 Mt / 0.553 g/t, 784 koz, with an average recovery rate of 79,8% recovered gold, equalling 626 koz.

 

The implementation of the sulphide plant phase 1 in Maracá will increase gold recovery at Chapada Project plant, generating an additional of 230 koz.

 

The project will increase gold production by 1,084 koz, 854 koz from Suruca ore and 230 koz from Chapada Project ore.

 

170



 

Table 21.6: Suruca Project Gold Production

 

Yamana Gold

Name of Asset

 

Chapada and Suruca

Status

 

Operating and Project

Date

 

December 31, 2010

 

PRODUCTION

 

Unit

 

Total

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Ore Feed Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Copper Grade

 

%

 

0.264

%

0.431

%

0.371

%

0.308

%

0.298

%

0.290

%

0.305

%

0.330

%

0.316

%

0.321

%

0.360

%

0.257

%

0.202

%

0.190

%

0.189

%

0.185

%

0.180

%

0.185

%

0.174

%

0.180

%

Copper Recovery

 

%

 

85.3

%

86.8

%

87.1

%

86.1

%

86.0

%

85.9

%

86.4

%

86.9

%

86.6

%

87.6

%

84.1

%

84.1

%

84.3

%

84.4

%

84.2

%

83.9

%

84.0

%

84.0

%

84.0

%

84.0

%

Copper Contained

 

Mlb

 

2,149

 

205

 

180

 

150

 

144

 

141

 

148

 

127

 

98

 

99

 

111

 

79

 

64

 

92

 

92

 

90

 

87

 

90

 

85

 

68

 

Copper Production

 

Mlb

 

1,840

 

178

 

157

 

129

 

124

 

121

 

128

 

111

 

84

 

87

 

93

 

67

 

54

 

78

 

77

 

75

 

73

 

75

 

71

 

58

 

Gold Grade

 

g/t

 

0.176

 

0.330

 

0.304

 

0.243

 

0.228

 

0.210

 

0.199

 

0.220

 

0.199

 

0.200

 

0.240

 

0.169

 

0.129

 

0.100

 

0.098

 

0.098

 

0.097

 

0.106

 

0.091

 

0.093

 

Gold Recovery

 

%

 

62.2

%

60.7

%

60.8

%

58.8

%

64.8

%

63.0

%

62.1

%

63.7

%

61.8

%

76.0

%

64.9

%

61.9

%

61.6

%

61.3

%

60.6

%

61.1

%

61.1

%

61.1

%

61.1

%

61.1

%

Gold Contained

 

koz

 

2,082

 

229

 

215

 

172

 

161

 

149

 

140

 

124

 

90

 

90

 

108

 

76

 

60

 

71

 

69

 

69

 

69

 

75

 

64

 

52

 

Gold Production

 

koz

 

1,299

 

139

 

131

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

Ore Feed Suruca Oxides

 

kt

 

16,331

 

 

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.511

 

 

 

 

 

0.580

 

0.531

 

0.477

 

0.535

 

0.321

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

85.0

%

 

 

 

 

85.0

%

85.0

%

85.0

%

85.0

%

85.0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

228

 

 

 

 

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore Feed Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Grade

 

g/t

 

0.553

 

 

 

 

 

 

 

 

 

 

 

 

 

0.491

 

0.514

 

0.535

 

0.530

 

0.566

 

0.658

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Recovery

 

%

 

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

79.8

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

626

 

 

 

 

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

 

 

 

 

 

 

 

Total Ore Feed

 

kt

 

429,171

 

21,555

 

22,000

 

25,000

 

26,000

 

26,000

 

26,000

 

23,331

 

22,000

 

22,000

 

22,000

 

22,000

 

22,024

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Chapada

 

kt

 

368,716

 

21,555

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,500

 

14,000

 

14,000

 

14,000

 

14,000

 

14,400

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

22,000

 

17,261

 

Suruca Oxides

 

kt

 

16,331

 

 

 

3,000

 

4,000

 

4,000

 

4,000

 

1,331

 

 

 

 

 

 

 

 

 

 

 

 

 

Suruca Sulphides

 

kt

 

44,124

 

 

 

 

 

 

 

 

 

 

 

 

 

4,500

 

8,000

 

8,000

 

8,000

 

8,000

 

7,624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Gold Production

 

koz

 

2,152

 

139

 

131

 

149

 

162

 

146

 

146

 

147

 

161

 

178

 

179

 

163

 

166

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

 

Table 21.7: Additional Gold recovered

 

Id

 

Description

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

MMIC original gold recovery

 

%

 

55,8

%

54,8

%

53,0

%

52,1

%

53,7

%

51,8

%

56,0

%

44,9

%

41,9

%

41,6

%

41,3

%

40,6

%

43,8

%

41,1

%

41,1

%

41,1

%

41,1

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

MMIC original gold recovered

 

koz

 

96

 

88

 

79

 

73

 

66

 

46

 

50

 

48

 

32

 

25

 

29

 

28

 

30

 

28

 

31

 

26

 

21

 

799

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

MMIC after sulphite gold recovery

 

%

 

58,8

%

64,8

%

63,0

%

62,1

%

63,7

%

61,8

%

76,0

%

64,9

%

61,9

%

61,6

%

61,3

%

60,6

%

61,1

%

61,1

%

61,1

%

61,1

%

61,1

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

MMIC after sulphite gold recovered

 

koz

 

101

 

104

 

94

 

87

 

79

 

55

 

68

 

70

 

47

 

37

 

43

 

42

 

42

 

42

 

46

 

39

 

32

 

1.029

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

MMIC gold variance

 

koz

 

5

 

16

 

15

 

14

 

12

 

9

 

18

 

22

 

15

 

12

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

230

 

 

171



 

21.6.1.2             Economic Results

 

In the base scenario, assuming a discount rate of 5%, the project net present value (NPV) will be US$ 117.2 million and the after-tax internal rate of return (IRR) will be 15.0% per year.

 

As mentioned above, the financial statements and cash flow of the base case are presented in the item 21.6.1.9

 

The main financial parametres for the base case are shown in the Table 21.8.

 

Table 21.8: Suruca Project Financial Parametres

 

Project Indicators

 

 

 

Ratio

 

Unit

 

Value

 

Observation

 

After-Tax NPV & IRR

 

 

 

 

 

 

 

NPV (discount rate 5% p.y.)

 

US$

 

117.180.852

 

 

 

IRR

 

%

 

15,0

%

 

 

Other Indicators

 

 

 

 

 

 

 

Total Capex (excluding working capital)

 

US$

 

224.697.921

 

Capex including all taxes but excluding working capital and sustaining

 

Suruca Oxide

 

US$

 

59.652.346

 

Capex Suruca Oxide excluding working capital and sustaining

 

Suruca Sulphide Phase 1

 

US$

 

39.410.525

 

Capex Suruca Sulphide Phase 1 excluding working capital and sustaining

 

Suruca Sulphide Phase 2

 

US$

 

125.635.050

 

Capex Suruca Sulphide Phase 2 excluding working capital and sustaining

 

Total Capex (including working capital)

 

US$

 

230.518.343

 

Capex including all taxes and working capital but excluding sustaining

 

Sustaining Capital

 

US$

 

86.541.744

 

Sustaining including all taxes but not including Mine Closure treated as an expense

 

Total Capital Cost (excluding working capital)

 

US$

 

311.239.665

 

Total capital cost (excluding working capital) = Capex excluding working capital + Sustaining.

 

Total Capital Cost (including working capital)

 

US$

 

317.060.087

 

Total capital cost (including working capital) = Capex inclunding work capital + Sustaining.

 

Capex/oz (excluding working)

 

US$/oz

 

212,70

 

Capex/oz including all taxes and excluding working capital and sustaining

 

Sustaining/oz

 

US$/oz

 

79,85

 

Sustaining/oz including all taxes.

 

Total Capital Cost/oz

 

US$/oz

 

292,56

 

Total capital cost/oz = Capex/oz + Sustaining/oz.

 

Underground Mine Cash Cost/oz

 

US$/oz

 

0,00

 

Underground Mine Cash Cost/oz

 

Open Pit Mine Cash Cost/oz

 

US$/oz

 

177,74

 

Open Pit Mine Cash Cost/oz

 

Plant Cash cost/oz

 

US$/oz

 

183,75

 

Plant Cash Cost/oz

 

Other Cash Cost/oz

 

US$/oz

 

139,72

 

Other Cash Cost/oz

 

Total Cash Cost/oz

 

US$/oz

 

501,20

 

Total Cash Cost/oz = (Underground+ Open Pit) Cash Cost/oz + Plant Cash Cost/ + Other Cash Cost/oz

 

Underground Mine Cash Cost/t ore mined

 

US$/t

 

0,00

 

Underground Mine Cash Cost/t ore mined

 

Open Pit Mine Cash Cost/t ore mined

 

US$/t

 

3,19

 

Open Pit Mine Cash Cost/t ore mined

 

Plant Cash Cost/t ore processed

 

US$/t

 

3,29

 

Plant Cash Cost/t ore processed

 

Other Cash Cost/t ore processed

 

US$/t

 

2,50

 

Other Cash Cost/t ore processed

 

Total Cash Cost/t

 

US$/t

 

8,98

 

Total Cash Cost/t = (Underground + Open Pit) Cash Cost/tmined + Plant Cash Cost/tprocessed
+OtherCash Cost/tprocessed

 

Life of mine

 

years

 

17

 

 

 

 

172



 

The discount rate sensitivity analysis is present in the Table 21.9.

 

Table 21.9: Suruca Project Sensitivity NPV x Discount Rate

 

Sensitivity Analysis - NPV x Discount Rate to the Firm

 

Discount Rate

 

NPV

 

15,00

%

184.120

 

12,50

%

18.143.413

 

10,00

%

41.961.762

 

7,50

%

73.882.126

 

5,00

%

117.180.852

 

0,00

%

259.946.288

 

 

In order to estimate the relative strength of the project, first level sensitivity analysis was developed for the following items: gold price, capital cost and operating costs.

 

In this analysis, when one factor varies, the other factors remain constant.

 

Table 21.10 and Table 21.11 present the sensitivity analysis for the 5% NPV of the project and the IRR respectively, and Figure 21.15 and Figure 21.16 show the results graphically. For example, a 10% price change impacts the projects NPV and after-tax IRR by approximately US$ 61.0 million (US$ 117.2 million — US$ 56.2 million) and 5.2% (15.0% - 9.8%) respectively.

 

Table 21.10: Suruca Project NPV Sensitivity Analysis (discount rate 5% p.y.)

 

Net present value of the cash flow to the firm

 

 

 

 

 

Opex and

 

 

 

 

 

 

 

other

 

Capex and

 

 

 

Sale prices

 

expenses

 

sustaining

 

-30%

 

-77.862.067

 

205.247.285

 

168.795.289

 

-20%

 

-6.581.141

 

176.113.333

 

151.791.735

 

-10%

 

56.227.793

 

146.824.413

 

134.740.287

 

0%

 

117.180.852

 

117.180.852

 

117.180.852

 

10%

 

176.209.718

 

86.777.139

 

98.921.112

 

20%

 

234.333.135

 

56.226.025

 

80.756.360

 

30%

 

291.461.892

 

25.208.987

 

62.292.397

 

 

173



 

Figure 21.15: Suruca Project NPV Sensitivity Analysis

 

 

Table 21.11: Suruca Project IRR Sensitivity Analysis

 

IRR TO THE FIRM

 

 

 

 

 

Opex and

 

 

 

 

 

 

 

other

 

Capex and

 

 

 

Sale prices

 

expenses

 

sustaining

 

-30%

 

-1,2

%

22,1

%

25,0

%

-20%

 

4,4

%

19,9

%

21,0

%

-10%

 

9,8

%

17,5

%

17,7

%

0%

 

15,0

%

15,0

%

15,0

%

10%

 

19,9

%

12,5

%

12,7

%

20%

 

24,6

%

9,8

%

10,8

%

30%

 

29,1

%

7,1

%

9,2

%

 

Figure 21.16: Suruca Project IRR Sensitivity Analysis

 

 

According to this analysis, the project is more sensitive to price, followed by OPEX variation, and then by CAPEX/Sustaining.

 

174



 

The worst case scenario occurs if the price drops 30% (average near US$ 777/oz) and when the IRR falls to — 1.2% per year.

 

An increase of 30% in Opex and Capex reduces the IRR to 7.1% per year and 9.2% per year, respectively.

 

A second level of sensitivity analysis is present in Table 21.12 and Table 21.13, where cross sensitivity is shown for Opex, Capex, exchange rate and price.

 

In this analysis, simultaneous variations occur.

 

Table 21.12: Suruca Project Cross NPV Sensitivity Analysis (discount rate 5% p.y.)

 

US$

NET PRESENT VALUE OF THE CASH FLOW TO THE FIRM

 

Opex and other expenses sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

24.707.272

 

-7.210.938

 

-41.381.012

 

-77.862.067

 

-115.629.444

 

-153.844.459

 

-192.490.535

 

 

 

-20%

 

86.615.194

 

56.210.822

 

25.190.274

 

-6.581.141

 

-41.087.536

 

-77.660.999

 

-115.371.518

 

Sale prices

 

-10%

 

146.631.338

 

117.014.634

 

86.680.695

 

56.227.793

 

25.312.569

 

-5.951.050

 

-40.803.150

 

sensitivity

 

0%

 

205.247.285

 

176.113.333

 

146.824.413

 

117.180.852

 

86.777.139

 

56.226.025

 

25.208.987

 

factor

 

10%

 

262.327.392

 

233.986.247

 

205.430.820

 

176.209.718

 

146.997.408

 

117.222.761

 

86.872.118

 

 

 

20%

 

319.375.556

 

291.072.166

 

262.724.069

 

234.333.135

 

205.518.082

 

176.306.103

 

147.056.069

 

 

 

30%

 

375.593.033

 

347.810.589

 

319.816.940

 

291.461.892

 

263.076.125

 

234.675.116

 

205.614.466

 

 

Capex and sustaining sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

-12.624.271

 

-33.935.136

 

-55.689.762

 

-77.862.067

 

-100.205.691

 

-122.587.502

 

-145.043.542

 

 

 

-20%

 

50.128.717

 

31.567.545

 

12.913.976

 

-6.581.141

 

-27.174.348

 

-48.539.326

 

-69.995.322

 

Sale prices

 

-10%

 

110.287.132

 

92.739.005

 

74.599.967

 

56.227.793

 

37.678.891

 

18.499.381

 

-1.119.243

 

sensitivity

 

0%

 

168.795.289

 

151.791.735

 

134.740.287

 

117.180.852

 

98.921.112

 

80.756.360

 

62.292.397

 

factor

 

10%

 

225.745.712

 

209.697.081

 

193.268.599

 

176.209.718

 

159.065.276

 

141.496.213

 

123.334.618

 

 

 

20%

 

281.930.424

 

266.536.860

 

250.582.483

 

234.333.135

 

217.687.506

 

200.626.091

 

183.353.516

 

 

 

30%

 

337.502.687

 

322.721.571

 

307.327.630

 

291.461.892

 

275.217.516

 

258.968.382

 

242.103.567

 

 

Exchange rate sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

-341.695.227

 

-230.579.215

 

-145.143.047

 

-77.862.067

 

-24.958.286

 

15.271.536

 

47.211.906

 

 

 

-20%

 

-262.910.179

 

-153.202.036

 

-69.433.179

 

-6.581.141

 

39.613.445

 

76.784.857

 

107.705.346

 

Sale prices

 

-10%

 

-185.408.825

 

-77.595.999

 

262.591

 

56.227.793

 

100.690.290

 

136.580.413

 

166.360.974

 

sensitivity

 

0%

 

-109.449.506

 

-7.280.010

 

62.846.809

 

117.180.852

 

159.913.773

 

194.788.637

 

223.524.628

 

factor

 

10%

 

-36.946.614

 

55.725.776

 

123.799.990

 

176.209.718

 

217.958.486

 

251.916.703

 

280.070.950

 

 

 

20%

 

28.719.673

 

116.828.966

 

183.122.445

 

234.333.135

 

275.084.851

 

308.317.905

 

335.874.685

 

 

 

30%

 

90.545.065

 

177.023.893

 

241.647.518

 

291.461.892

 

331.498.966

 

364.085.460

 

390.865.796

 

 

175



 

Table 21.13: Suruca Project Cross IRR Sensitivity Analysis

 

US$

IRR TO THE FIRM

 

Opex and other expenses sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

7,1

%

4,4

%

1,6

%

-1,2

%

-3,7

%

-5,9

%

-7,7

%

 

 

-20%

 

12,4

%

9,8

%

7,2

%

4,4

%

1,6

%

-1,1

%

-3,6

%

Sale prices

 

-10%

 

17,4

%

15,0

%

12,4

%

9,8

%

7,2

%

4,5

%

1,7

%

sensitivity

 

0%

 

22,1

%

19,9

%

17,5

%

15,0

%

12,5

%

9,8

%

7,1

%

factor

 

10%

 

26,6

%

24,5

%

22,3

%

19,9

%

17,6

%

15,1

%

12,5

%

 

 

20%

 

30,9

%

28,9

%

26,8

%

24,6

%

22,4

%

20,0

%

17,6

%

 

 

30%

 

35,0

%

33,1

%

31,1

%

29,1

%

27,0

%

24,8

%

22,5

%

 

Capex and sustaining sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

3,5

%

1,6

%

0,0

%

-1,2

%

-2,3

%

-3,1

%

-3,9

%

 

 

-20%

 

11,0

%

8,3

%

6,2

%

4,4

%

2,9

%

1,6

%

0,5

%

Sale prices

 

-10%

 

18,3

%

14,8

%

12,1

%

9,8

%

7,9

%

6,3

%

4,9

%

sensitivity

 

0%

 

25,0

%

21,0

%

17,7

%

15,0

%

12,7

%

10,8

%

9,2

%

factor

 

10%

 

31,3

%

26,7

%

23,0

%

19,9

%

17,4

%

15,1

%

13,2

%

 

 

20%

 

37,2

%

32,1

%

28,0

%

24,6

%

21,7

%

19,3

%

17,1

%

 

 

30%

 

42,8

%

37,3

%

32,8

%

29,1

%

25,9

%

23,2

%

20,8

%

 

With this analysis, the project is more sensitive to the combination price x exchange rate.

 

21.6.1.3             Assumptions

 

The follow items present the assumptions of the Suruca Project.

 

Gold Production and Revenue

 

Total project gold producted and sold is 1,084 koz.

 

Oxide ore average gold recovery is 85% and sulphide ore average gold recovery is 80%.

 

Average annual gold sales are the following:

 

·                  46 koz/year of oxide ore gold from 2013 to 2017, generating a total of 228 koz;

 

·                  104 koz/year of sulphide ore gold from 2017 to 2022, generating a total of 626 koz;

 

·                  14 koz/year of gold generated from the increasedrecovery of gold at the Chapada Project mine where the sulphide ore will be processed. The carbon in leach system (CIL) used in the sulphide ore processing will be implemented at the beginning of the project (Sulphide Phase 1) increasing the recovery of gold from 2013 to 2029, generating an additional 230 koz during that period (See Table 21.5);

 

·                  Gold price equal to US$ 1,300/oz in 2013 and US$ 1,100/oz from 2014 to 2029.

 

A sales tax (CEFEM) of 1% was considered in the net income calculation.

 

Capital Cost

 

Process plant and infrastructure capital costs were mainly supplied by AMEC Minproc, whom specified the equipment, and prepared the general arrangements of the processing and infrastructure elements of the project.

 

176



 

It was considered an accuracy of +25%/ - 15% for the Suruca Project oxide ore. For Maracá Phase I and II, it was considered an accuracy of ±35%.

 

The investment to implement the oxide ore processing and the sulphide Phase 1 in 2011 and 2012 are summarized and segregated in Table 21.14, Table 21.15 and Table 21.16.

 

The capital cost to implement the complete sulphide process (sulphide Phase 2) is shown in the Table 21.17. This investment will occur in 2016.

 

Future sustaining capital is defined as follows (gross values):

 

ID

 

Description

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Sulphide Phase 2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

SHEC

 

608

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

608

 

3.

 

Inter Lift (Leaching Pile)

 

1.280

 

 

 

 

 

1.280

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.560

 

4.

 

Waste moved for Mine Development

 

3.410

 

5.381

 

12.397

 

14.931

 

11.769

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

47.887

 

5.

 

TCLD

 

 

 

 

 

 

 

17.068

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

17.068

 

6.

 

Closure costs

 

 

 

 

 

 

 

 

 

 

 

3.070

 

3.070

 

3.070

 

 

 

 

 

3.070

 

3.070

 

3.070

 

 

 

 

 

18.420

 

 

 

Total

 

5.297

 

5.381

 

12.397

 

33.278

 

11.769

 

3.070

 

3.070

 

3.070

 

 

 

 

 

3.070

 

3.070

 

3.070

 

 

 

 

 

86.542

 

 

 

177



 

Table 21.14: Suruca Project Capital Cost Summary: Oxide + Sulphide Phase 1 in MMIC

 

 

 

 

 

Capital Cost

 

Description

 

US$

 

% Total

 

 

 

Mechanical and Plateworks

 

21,011,156

 

19.9

%

Equipment

 

Electrical and Instrumentation

 

3,151,698

 

3.0

%

 

 

Sub-Total

 

24,162,854

 

22.8

%

 

 

Electrical

 

1,608,339

 

1.5

%

 

 

Piping

 

2,028,898

 

1.9

%

Material

 

Steel Structure

 

2,901,748

 

2.7

%

 

 

Spare Parts

 

428,250

 

0.4

%

 

 

Other Materials

 

402,085

 

0.4

%

 

 

Sub-Total

 

7,369,320

 

7.0

%

Civil Construction

 

Indutrial Building & Civil Works

 

6,948,384

 

6.6

%

 

Power Line

 

1,500,103

 

1.4

%

 

Drainage, Paving, Urbanization & Slope Protection

 

3,465,243

 

3.3

%

 

Sub-Total

 

11,913,729

 

11.3

%

Electromechanical Installation

 

Sub-Total

 

9,369,548

 

8.9

%

Mine

 

Mine development

 

7,588,825

 

7.2

%

 

Sub-Total

 

7,588,825

 

7.2

%

 

 

Engineering

 

3,040,454

 

2.9

%

 

 

Management

 

5,466,070

 

5.2

%

Indirect Costs

 

Insurance

 

805,777

 

0.8

%

 

 

Commissioning

 

427,353

 

0.4

%

 

 

Sub-Total

 

9,739,655

 

9.2

%

 

 

First Fill

 

806,429

 

0.8

%

Pre-Operation

 

Pre-Operation

 

2,289,598

 

2.2

%

 

 

Sub-Total

 

3,096,028

 

2.9

%

Freight

 

 

 

2,238,117

 

2.1

%

Land Acquisition

 

 

 

5,200,000

 

4.9

%

Safety, Health, Environment and Community

 

 

 

3,246,953

 

3.1

%

Contingency

 

 

 

16,053,860

 

15.2

%

SUB-TOTAL

 

 

 

99,978,889

 

94.5

%

Working Capital

 

 

 

5,820,422

 

5.5

%

TOTAL

 

 

 

105,799,311

 

100.0

%

 

178



 

Table 21.15: Suruca Project Capital Cost: Oxide (without working capital)

 

 

 

Capital Cost

 

Description

 

US$

 

% Total

 

 

 

Mechanical and Plateworks

 

10,049,985

 

16.8

%

Equipment

 

Electrical and Instrumentation

 

1,249,222

 

2.1

%

 

 

Sub-Total

 

11,299,208

 

18.8

%

Material

 

Electrical

 

750,790

 

1.3

%

 

Piping

 

1,019,772

 

1.7

%

 

Steel Structure

 

883,496

 

1.5

%

 

Spare Parts

 

333,126

 

0.6

%

 

Other Materials

 

187,698

 

0.3

%

 

Sub-Total

 

3,174,882

 

5.3

%

Civil Construction

 

Industrial Building & Civil Works

 

4,581,992

 

7.6

%

 

Power Line

 

1,500,103

 

2.5

%

 

Drainage, Paving, Urbanization & Slope Protection

 

2,229,789

 

3.7

%

 

Sub-Total

 

8,311,884

 

13.9

%

Electromechanical Installation

 

Sub-Total

 

4,005,727

 

6.7

%

Mine

 

Mine development

 

7,588,825

 

12.7

%

 

Sub-Total

 

7,588,825

 

12.7

%

Indirect Costs

 

Engineering

 

1,824,300

 

3.0

%

 

Management

 

3,193,066

 

5.3

%

 

Insurance

 

412,946

 

0.7

%

 

Commissioning

 

236,859

 

0.4

%

 

Sub-Total

 

5,667,171

 

9.4

%

Pre-Operation

 

First Fill

 

643,760

 

1.1

%

 

Pre-Operation

 

1,184,296

 

2.0

%

 

Sub-Total

 

1,828,056

 

3.0

%

Freight

 

 

 

1,012,646

 

1.7

%

Land Acquisition

 

 

 

5,200,000

 

8.7

%

Safety, Health, Environment and Community

 

 

 

3,246,953

 

5.4

%

Contingency

 

 

 

8,654,835

 

14.4

%

TOTAL

 

 

 

59,990,188

 

100.0

%

 

179



 

Table 21.16: Suruca Project Capital Cost: Sulphide Phase 1 (without working capital)

 

 

 

Capital Cost

 

Description

 

US$

 

% Total

 

 

 

Mechanical and Plateworks

 

10,961,171

 

27.4

%

Equipment

 

Electrical and Instrumentation

 

1,902,475

 

4.8

%

 

 

Sub-Total

 

12,863,646

 

32.2

%

 

 

Electrical

 

857,549

 

2.1

%

 

 

Piping

 

1,009,126

 

2.5

%

Material

 

Steel Structure

 

2,018,251

 

5.0

%

 

 

Spare Parts

 

95,124

 

0.2

%

 

 

Other Materials

 

214,387

 

0.5

%

 

 

Sub-Total

 

4,194,438

 

10.5

%

 

 

Indutrial Building & Civil Works

 

2,366,392

 

5.9

%

Civil Construction

 

Power Line

 

 

0.0

%

 

 

Drainage, Paving, Urbanization & Slope Protection

 

1,235,454

 

3.1

%

 

 

Sub-Total

 

3,601,846

 

9.0

%

Electromechanical Installation

 

Sub-Total

 

5,363,822

 

13.4

%

Mine

 

Mine development

 

 

0.0

%

 

Sub-Total

 

 

0.0

%

 

 

Engineering

 

1,216,155

 

3.0

%

Indirect Costs

 

Management

 

2,273,004

 

5.7

%

 

Insurance

 

392,831

 

1.0

%

 

Commissioning

 

190,494

 

0.5

%

 

Sub-Total

 

4,072,483

 

10.2

%

 

 

First Fill

 

162,669

 

0.4

%

Pre-Operation

 

Pre-Operation

 

1,105,302

 

2.8

%

 

 

Sub-Total

 

1,267,971

 

3.2

%

Freight

 

1,225,471

 

3.1

%

Land Acquisition

 

 

0.0

%

Safety, Health, Environment and Community

 

 

0.0

%

Contingency

 

7,399,025

 

18.5

%

TOTAL

 

39,988,701

 

100.0

%

 

180



 

Table 21.17 — Suruca Project Capital Cost: Sulphide Phase 2 (without working capital)

 

 

 

Capital Cost

 

Description

 

US$

 

% Total

 

 

 

Mechanical and Plateworks

 

44.448.153

 

35,4

%

Equipment

 

Electrical and Instrumentation

 

3.250.047

 

2,6

%

 

 

Sub-Total

 

47.698.201

 

38,0

%

 

 

Electrical/Instrum./Communication

 

4.181.535

 

3,3

%

 

 

Piping

 

1.914.740

 

1,5

%

Material

 

Steel Structure

 

3.829.481

 

3,0

%

 

 

Spare Parts

 

406.256

 

0,3

%

 

 

Other Materials

 

812.512

 

0,6

%

 

 

Sub-Total

 

11.144.523

 

8,9

%

 

 

Indutrial Building & Civil Works

 

6.724.894

 

5,4

%

Civil Construction

 

Power Line

 

 

 

0,0

%

 

 

Drainage, Paving, Urbanization & Slope Protection

 

1.417.692

 

1,1

%

 

 

Sub-Total

 

8.142.586

 

6,5

%

Electromechanical Installation

 

Sub-Total

 

18.964.201

 

15,1

%

Mine

 

Mine development

 

 

 

0,0

%

 

Sub-Total

 

 

0,0

%

 

 

Engineering

 

3.952.035

 

3,1

%

 

 

Management

 

5.451.330

 

4,3

%

Indirect Costs

 

Insurance

 

456.521

 

0,4

%

 

 

Commissioning

 

642.234

 

0,5

%

 

 

Sub-Total

 

10.502.121

 

8,4

%

 

 

First Fill

 

549.462

 

0,4

%

Pre-Operation

 

Pre-Operation

 

745.286

 

0,6

%

 

 

Sub-Total

 

1.294.748

 

1,0

%

Freight

 

4.578.090

 

3,6

%

Land Acquisition

 

 

 

0,0

%

Safety, Health, Environment and Community

 

 

 

0,0

%

Contingency

 

23.310.580

 

18,6

%

TOTAL

 

125.635.049

 

100,0

%

 

181



 

21.6.1.4             Operating Cost

 

Operating costs for the Suruca Project were estimated based upon the information presented in this technical report using project specific staffing, salary, wage and benefit requirements; unit consumption of materials, supplies, power, water; and delivered supply costs, where possible.

 

It was considered an accuracy of +25%/ - 15% for the Suruca oxide ore. For Maracá Phase I and II, it was considered an accuracy of ±35%.

 

All costs are presented in United States dollars. An exchange rate of 1.8 R$/US$ was used when costs were supplied in the local Brazilian currency.

 

The mine costs were calculated using the U&M contracts (loading and hauling), Orica (rock blasting) and master (rock drilling), based on November 2010 and current performed in the Chapada Project mine.

 

For the cost calculation was used the average distance of transport by type of ore and waste and ore type ANX for drilling and rock blasting.

 

A specific treatment was made on the taxation side, considering the analysis of federal and state taxes.

 

The Suruca Project cash cost details are presented from Table 21.18 to Table 21.34 and the mine operation will be developed by third party companies.

 

182



 

Table 21.18: Suruca Project Total Cash Cost Summary (a)

 

Projeto Suruca: Total Cash Cost (a)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Mine (b)

 

US$k

 

6.660

 

8.880

 

8.880

 

8.880

 

19.904

 

32.215

 

32.012

 

31.473

 

24.642

 

19.076

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

192.622

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Plant (c)

 

US$k

 

10.057

 

13.409

 

13.409

 

13.409

 

19.185

 

26.174

 

26.174

 

26.174

 

26.174

 

24.974

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

199.138

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Other Cash Cost (d) (e)

 

US$k

 

3.933

 

10.063

 

9.915

 

10.074

 

9.549

 

9.897

 

9.961

 

9.946

 

10.057

 

10.245

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

151.418

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total (f)

 

US$k

 

20.650

 

32.352

 

32.204

 

32.363

 

48.638

 

68.285

 

68.147

 

67.592

 

60.873

 

54.295

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

543.178

 

(a)

 

Production Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Ore Processed

 

k t/year

 

3.000

 

4.000

 

4.000

 

4.000

 

5.831

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

60.455

 

 

 

Oxide Ore Processed

 

k t/year

 

3.000

 

4.000

 

4.000

 

4.000

 

1.331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16.331

 

 

 

Sulphite Ore Processed

 

k t/year

 

 

 

 

 

 

 

 

 

4.500

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

44.124

 

 

 

Gold Production

 

k oz/year

 

53

 

74

 

67

 

73

 

81

 

114

 

128

 

130

 

131

 

141

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

1.084

 

 

 

Oxide Gold Production

 

k oz/year

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

228

 

 

 

Suphide Gold Production

 

k oz/year

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

626

 

 

 

MMIC Recovery Gold Increase

 

k oz/year

 

5

 

16

 

15

 

14

 

12

 

9

 

18

 

22

 

15

 

12

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

230

 

(b)

 

Mine Unitary Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

2,22

 

2,22

 

2,22

 

2,22

 

3,41

 

4,03

 

4,00

 

3,93

 

3,08

 

2,50

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3,19

 

 

 

US$/oz

 

US$/oz

 

126,34

 

119,75

 

132,52

 

122,44

 

246,60

 

281,46

 

250,46

 

241,38

 

187,56

 

135,63

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

177,74

 

(c)

 

Plant Unitary Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

3,35

 

3,35

 

3,35

 

3,35

 

3,29

 

3,27

 

3,27

 

3,27

 

3,27

 

3,28

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3,29

 

 

 

US$/oz

 

US$/oz

 

190,78

 

180,83

 

200,12

 

184,89

 

237,69

 

228,68

 

204,78

 

200,74

 

199,21

 

177,56

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

183,75

 

(d)

 

Other Cash Cost Unitary

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

1,31

 

2,52

 

2,48

 

2,52

 

1,64

 

1,24

 

1,25

 

1,24

 

1,26

 

1,34

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2,50

 

 

 

US$/oz

 

US$/oz

 

74,61

 

135,70

 

147,97

 

138,90

 

118,31

 

86,47

 

77,94

 

76,28

 

76,54

 

72,84

 

583,48

 

594,67

 

690,14

 

601,53

 

548,85

 

641,19

 

799,66

 

139,72

 

(e)

 

G&A, laboratory and other costs and MMIC Grade Increase.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(f)

 

Total Cash Cost Unitary

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

6,88

 

8,09

 

8,05

 

8,09

 

8,34

 

8,54

 

8,52

 

8,45

 

7,61

 

7,12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8,98

 

 

 

US$/oz

 

US$/oz

 

391,72

 

436,28

 

480,61

 

446,23

 

602,60

 

596,61

 

533,18

 

518,39

 

463,31

 

386,03

 

583,48

 

594,67

 

690,14

 

601,53

 

548,85

 

641,19

 

799,66

 

501,20

 

 

183



 

Table 21.19: Suruca Project Mine Cost Details

 

Projeto Suruca: Mine Annual Cash Cost

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Mine movement

 

k t

 

4.500

 

6.000

 

6.000

 

6.000

 

11.251

 

18.250

 

18.250

 

18.250

 

14.097

 

10.888

 

113.486

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Oxide Ore

 

k t

 

3.000

 

4.000

 

4.000

 

4.000

 

1.331

 

 

 

 

 

 

 

 

 

 

 

16.331

 

1.2

 

Suphide Ore

 

k t

 

 

 

 

 

 

 

 

 

4.500

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

44.124

 

1.3

 

Waste

 

k t

 

1.500

 

2.000

 

2.000

 

2.000

 

5.420

 

10.250

 

10.250

 

10.250

 

6.097

 

3.264

 

53.031

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Unitary cost (a) (b)

 

US$/tmoved

 

1,48

 

1,48

 

1,48

 

1,48

 

1,77

 

1,77

 

1,75

 

1,72

 

1,75

 

1,75

 

1,70

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Oxide Ore

 

US$/tmoved

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

1,40

 

2.2

 

Suphide Ore

 

US$/tmoved

 

 

 

 

 

 

 

 

 

2,03

 

1,93

 

1,90

 

1,83

 

1,83

 

1,80

 

1,88

 

2.3

 

Waste

 

US$/tmoved

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

1,64

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Total Cost

 

US$ k

 

6.660

 

8.880

 

8.880

 

8.880

 

19.904

 

32.215

 

32.012

 

31.473

 

24.642

 

19.076

 

192.622

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Oxide Ore

 

 

 

4.200

 

5.600

 

5.600

 

5.600

 

1.863

 

 

 

 

 

 

 

 

 

 

 

22.863

 

2.2

 

Suphide Ore

 

 

 

 

 

 

 

 

 

 

 

9.152

 

15.405

 

15.202

 

14.663

 

14.643

 

13.723

 

82.788

 

2.3

 

Waste

 

 

 

2.460

 

3.280

 

3.280

 

3.280

 

8.889

 

16.810

 

16.810

 

16.810

 

9.999

 

5.353

 

86.971

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(a)

 

Unitary cost/ore mined

 

US$/tore mined

 

2,22

 

2,22

 

2,22

 

2,22

 

3,41

 

4,03

 

4,00

 

3,93

 

3,08

 

2,50

 

3,19

 

 

 

Oxide Ore Mined

 

k t

 

3.000

 

4.000

 

4.000

 

4.000

 

1.331

 

 

 

 

 

 

 

 

 

 

 

16.331

 

 

 

Suphide Ore Mined

 

k t

 

 

 

 

 

 

 

 

 

4.500

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

44.124

 

 

 

Total Ore Mined

 

k t

 

3.000

 

4.000

 

4.000

 

4.000

 

5.831

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

60.455

 

(b)

 

Unitary cost/once

 

US$/toz

 

126,34

 

119,75

 

132,52

 

122,44

 

246,60

 

281,46

 

250,46

 

241,38

 

187,56

 

135,63

 

177,74

 

 

 

Oxide Gold Production

 

k oz

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

228

 

 

 

Suphide Gold Production

 

k oz

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

626

 

 

 

MMIC Recovery Gold Increase (*)

 

k oz

 

5

 

16

 

15

 

14

 

12

 

9

 

18

 

22

 

15

 

12

 

230

 

 

 

Total Gold Production

 

k oz

 

53

 

74

 

67

 

73

 

81

 

114

 

128

 

130

 

131

 

141

 

1.084

 

 


 

 

(*) Total until 2029

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

184



 

Table 21.20: Suruca Project Plant and Other Cash Cost Summary (a)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Plant Cost (b)

 

US$k

 

10.057

 

13.409

 

13.409

 

13.409

 

19.185

 

26.174

 

26.174

 

26.174

 

26.174

 

24.974

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

199.138

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Labor

 

US$k

 

1.401

 

1.868

 

1.868

 

1.868

 

992

 

658

 

658

 

658

 

658

 

658

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11.288

 

1.2

 

Supplies, Power and Maintenance

 

US$k

 

8.656

 

11.541

 

11.541

 

11.541

 

18.193

 

25.515

 

25.515

 

25.515

 

25.515

 

24.316

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

187.850

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Other Cash Costs (c) (d)

 

US$k

 

3.933

 

10.063

 

9.915

 

10.074

 

9.549

 

9.897

 

9.961

 

9.946

 

10.057

 

10.245

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

151.418

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Labor

 

US$k

 

589

 

1.426

 

1.426

 

1.426

 

1.222

 

1.129

 

1.129

 

1.129

 

1.129

 

1.129

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

19.216

 

2.2

 

Other

 

US$k

 

3.344

 

8.636

 

8.489

 

8.647

 

8.327

 

8.768

 

8.832

 

8.817

 

8.928

 

9.116

 

7.185

 

7.185

 

7.185

 

7.185

 

7.185

 

7.185

 

7.185

 

132.202

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total (e)

 

US$k

 

13.990

 

23.472

 

23.324

 

23.483

 

28.734

 

36.070

 

36.135

 

36.120

 

36.230

 

35.219

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

350.556

 

(a)

 

Production Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total Ore Processed

 

k t/year

 

3.000

 

4.000

 

4.000

 

4.000

 

5.831

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

60.455

 

 

 

Oxide Ore Processed

 

k t/year

 

3.000

 

4.000

 

4.000

 

4.000

 

1.331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16.331

 

 

 

Sulphite Ore Processed

 

k t/year

 

 

 

 

 

 

 

 

 

4.500

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

44.124

 

 

 

Gold Production

 

k oz/year

 

53

 

74

 

67

 

73

 

81

 

114

 

128

 

130

 

131

 

141

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

1.084

 

 

 

Oxide Gold Production

 

k oz/year

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

228

 

 

 

Suphide Gold Production

 

k oz/year

 

 

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

626

 

 

 

MMIC Recovery Gold Increase

 

k oz/year

 

5

 

16

 

15

 

14

 

12

 

9

 

18

 

22

 

15

 

12

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

230

 

(b)

 

Plant Unitary Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

3,35

 

3,35

 

3,35

 

3,35

 

3,29

 

3,27

 

3,27

 

3,27

 

3,27

 

3,28

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3,29

 

 

 

US$/oz

 

US$/oz

 

190,78

 

180,83

 

200,12

 

184,89

 

237,69

 

228,68

 

204,78

 

200,74

 

199,21

 

177,56

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

183,75

 

(c)

 

Other Cash Cost Unitary

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

1,31

 

2,52

 

2,48

 

2,52

 

1,64

 

1,24

 

1,25

 

1,24

 

1,26

 

1,34

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2,50

 

 

 

US$/oz

 

US$/oz

 

74,61

 

135,70

 

147,97

 

138,90

 

118,31

 

86,47

 

77,94

 

76,28

 

76,54

 

72,84

 

583,48

 

594,67

 

690,14

 

601,53

 

548,85

 

641,19

 

799,66

 

139,72

 

(d)

 

G&A, laboratory and other costs and MMIC Grade Increase.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(e)

 

Total Cash Cost Unitary

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

US$/tore

 

US$/tore

 

4,66

 

5,87

 

5,83

 

5,87

 

4,93

 

4,51

 

4,52

 

4,51

 

4,53

 

4,62

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5,80

 

 

 

US$/oz

 

US$/oz

 

265,38

 

316,53

 

348,09

 

323,79

 

356,00

 

315,15

 

282,72

 

277,02

 

275,76

 

250,40

 

583,48

 

594,67

 

690,14

 

601,53

 

548,85

 

641,19

 

799,66

 

323,47

 

 

185



 

Table 21.21: Suruca Project Oxide Plant Cash Cost Summary (a)

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Plant Cost

 

US$k

 

10.057

 

13.409

 

13.409

 

13.409

 

4.462

 

 

 

 

 

 

 

 

 

 

 

54.747

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Labor

 

US$k

 

1.401

 

1.868

 

1.868

 

1.868

 

622

 

 

 

 

 

 

 

 

 

 

 

7.627

 

1.2

 

Supplies, Power and Maintenance

 

US$k

 

8.656

 

11.541

 

11.541

 

11.541

 

3.840

 

 

 

 

 

 

 

 

 

 

 

47.120

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Other Cash Costs (b)

 

US$k

 

1.457

 

1.809

 

1.661

 

1.819

 

411

 

 

 

 

 

 

 

 

 

 

 

7.157

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Labor

 

US$k

 

268

 

357

 

357

 

357

 

119

 

 

 

 

 

 

 

 

 

 

 

1.459

 

2.2

 

Other

 

US$k

 

1.189

 

1.451

 

1.304

 

1.462

 

292

 

 

 

 

 

 

 

 

 

 

 

5.697

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

US$k

 

11.514

 

15.218

 

15.070

 

15.229

 

4.873

 

 

 

 

 

 

 

 

 

 

 

61.903

 

 

 

Total (US$/tprocessed)

 

 

 

3,84

 

3,80

 

3,77

 

3,81

 

3,66

 

 

 

 

 

 

 

 

 

 

 

3,79

 

 

 

Total (US$/oz)

 

 

 

242,14

 

262,17

 

289,02

 

260,40

 

417,33

 

 

 

 

 

 

 

 

 

 

 

271,63

 

 


(a)

 

Production Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

. Ore Processed

 

k t/year

 

3.000

 

4.000

 

4.000

 

4.000

 

1.331

 

 

 

 

 

 

 

 

 

 

 

16.331

 

 

 

. Gold Production

 

k oz/year

 

48

 

58

 

52

 

58

 

12

 

 

 

 

 

 

 

 

 

 

 

228

 

(b)

 

G&A, laboratory and other costs.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

186



 

Table 21.22: Suruca Project Oxide Plant 2014 Labour Cost Details (a)

 

 

 

 

 

Number

 

Unitary Annual

 

Total

 

 

 

 

 

of

 

Cost (a)

 

Annual

 

Id

 

Description

 

Employees

 

(US$/employee)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Metallurgical/Process Engineer

 

1

 

92.000

 

92

 

1.2

 

Metallurgical/Process Supervisor

 

1

 

130.333

 

130

 

1.3

 

Shift Supervisor

 

4

 

76.667

 

307

 

1.4

 

Maintenance Supervisor

 

1

 

76.667

 

77

 

1.5

 

Assistant Maintenance Supervisor

 

1

 

46.000

 

46

 

1.6

 

Mechanical Supervisor

 

1

 

122.667

 

123

 

1.7

 

Electrical Supervisor

 

1

 

122.667

 

123

 

1.8

 

Operator

 

16

 

28.643

 

458

 

1.9

 

Auxiliary Technicians

 

4

 

15.855

 

63

 

1.10

 

Planner (Mechanical and Electrical)

 

1

 

53.667

 

54

 

1.11

 

Shift Mechanics

 

4

 

38.333

 

153

 

1.12

 

Shift Electrician

 

4

 

38.333

 

153

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency (b)

 

 

 

 

 

89

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

39

 

48

 

1.868

 

 

 

(Total (US$/tprocessed)

 

 

 

 

 

0,47

 

 

 

Total (US$/oz)

 

 

 

 

 

32,18

 

 


(a)

Including tax and social benefits

 

 

 

(b)

Contingencies:

5,0

%

 

 

Table 21.23: Suruca Project Oxide Plant 2014 Supplies, Power and Maintenance Details

 

 

 

 

 

 

 

Consumption

 

 

 

Annual

 

 

 

 

 

Unitary

 

Specific
Average

 

Standard
Annual

 

Annual

 

Unitary
Net

 

Standard
Net

 

 

 

 

 

Dimension

 

Consumption

 

Production

 

Consumption

 

Price

 

Cost

 

Id

 

Description

 

(dim.)

 

(dim./k tprocessed)

 

(k tprocessed)

 

(dim.)

 

(US$/dim.)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Power

 

MWh

 

4,891781

 

4.000

 

19.567

 

58,87

 

1.152

 

2.

 

Liners for MMD Sizers

 

t

 

0,000496

 

4.000

 

2

 

5.253,36

 

10

 

3.

 

High Early Cement (Portland Type 2 cement)

 

t

 

15,000000

 

4.000

 

60.000

 

130,12

 

7.807

 

4.

 

Sodium Cyanide

 

t

 

0,100000

 

4.000

 

400

 

1.874,19

 

750

 

5.

 

Sodium Hydroxide

 

t

 

0,000780

 

4.000

 

3

 

472,80

 

1

 

6.

 

Hydrochloric Acid

 

t

 

0,046250

 

4.000

 

185

 

231,15

 

43

 

7.

 

Activated Carbon

 

t

 

0,015000

 

4.000

 

60

 

3.309,61

 

199

 

8.

 

Maintenance

 

 

 

 

 

 

 

 

 

 

 

1.070

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingências (a)

 

 

 

 

 

 

 

 

 

 

 

509

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

 

 

 

 

 

 

 

 

 

 

11.541

 

 

 

(Total (US$/tprocessed)

 

 

 

 

 

 

 

 

 

 

 

2,89

 

 

 

Total (US$/oz)

 

 

 

 

 

 

 

 

 

 

 

198,83

 

 


(a)

Contingencies:

5

%

 

 

187



 

Table 21.24: Suruca Project Oxide Plant Other Cash Cost 2014 Summary

 

 

 

 

 

Annual

 

Id

 

Description

 

Cost (US$)

 

 

 

 

 

 

 

1.

 

Labor

 

357

 

 

 

 

 

 

 

2.

 

Other Expenses (a)

 

580

 

 

 

 

 

 

 

4.

 

Refining and Transport (b)

 

871

 

 

 

 

 

 

 

 

 

Total

 

1.809

 

 

 

Total (US$/tprocessed)

 

0,45

 

 

 

Total (US$/oz)

 

31,16

 

 


(a)

 

Other Expenses:

 

10,00

 

US$/oz

 

(b)

 

Refining and Transport:

 

15,00

 

US$/oz

 

 

Table 21.25: Suruca Project Oxide Plant Other Cash Cost 2014 Labor Details (a)

 

 

 

 

 

Number

 

Unitary Annual

 

Total

 

 

 

 

 

of

 

Cost (a)

 

Annual

 

Id

 

Description

 

Employees

 

(US$/employee)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Plant Manager

 

1

 

184.000

 

184

 

1.2

 

Clerk

 

1

 

22.433

 

22

 

1.3

 

Laboratory Supervisor

 

1

 

76.667

 

77

 

1.4

 

Laboratory Technicians

 

2

 

28.643

 

57

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency (b)

 

 

 

 

 

17

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

5

 

71.481

 

357

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

 

 

 

 

Total (US$/oz)

 

 

 

 

 

 

 

 


(a)

 

Including tax and social benefits

 

 

 

 

(b)

 

Contingencies:

 

5,0

%

 

 

188



 

Table 21.26: Suruca Project MMIC Recovery Increase (CIL/Phase 1) Other Cash Cost Summary (US$) (a)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Labor

 

US$k

 

321

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

1.069

 

17.422

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Supplies and Power

 

US$k

 

1.406

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

4.688

 

71.721

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Maintenace and Other costs

 

US$k

 

749

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

2.498

 

38.214

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

 

 

2.476

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

8.254

 

127.357

 

 

 

(Total (US$/tprocessed)

 

 

 

0,11

 

0,38

 

0,38

 

0,38

 

0,47

 

0,59

 

0,59

 

0,59

 

0,59

 

0,57

 

0,38

 

0,38

 

0,38

 

0,38

 

0,38

 

0,38

 

0,48

 

0,39

 

 

 

Total (US$/oz)

 

 

 

479,42

 

512,42

 

555,28

 

587,77

 

668,35

 

921,50

 

458,45

 

382,04

 

542,54

 

691,03

 

583,48

 

594,67

 

690,14

 

601,53

 

548,85

 

641,19

 

799,66

 

553,25

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


  (a)

 

Production Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· MMIC Ore Processed (k t/year):

 

22.000

 

22.000

 

22.000

 

22.000

 

17.500

 

14.000

 

14.000

 

14.000

 

14.000

 

14.400

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

22.000

 

17.261

 

325.161

 

 

 

· Incremental Gold Production (k oz/year):

 

5

 

16

 

15

 

14

 

12

 

9

 

18

 

22

 

15

 

12

 

14

 

14

 

12

 

14

 

15

 

13

 

10

 

230

 

 

189



 

Table 21.27: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Labour Cost Details (a)

 

 

 

 

 

Number

 

Unitary Annual

 

Total

 

 

 

 

 

of

 

Cost (a)

 

Annual

 

Id

 

Description

 

Employees

 

(US$/employee)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Plant Clerk

 

1

 

22.433

 

22

 

1.2

 

Metallurgical/Process Engineer

 

2

 

46.000

 

92

 

1.6

 

Plant Laboratory Technicians

 

2

 

57.285

 

115

 

1.8

 

Assistant Maintenance Supervisor

 

1

 

46.000

 

46

 

1.10

 

Electrical Supervisor

 

1

 

122.667

 

123

 

1.11

 

Operator

 

8

 

35.803

 

286

 

1.12

 

Auxiliary Technicians (not including security)

 

6

 

21.140

 

127

 

1.13

 

Planner (Mechanical and Electrical)

 

1

 

53.667

 

54

 

1.14

 

Shift Mechanics (note 1)

 

2

 

38.333

 

77

 

1.15

 

Shift Electrician

 

2

 

38.333

 

77

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency (b)

 

 

 

 

 

51

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

26

 

41

 

1.069

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

0,05

 

 

 

Total (US$/oz)

 

 

 

 

 

66,35

 

 


(a)

 

Including tax and social benefits

 

 

 

 

 

 

 

 

 

 

(b)

 

Contingencies:

 

5,0

%

 

 

 

 

 

 

 

 

Table 21.28: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Consumables/Supplies and Power Data Details

 

 

 

 

 

 

 

Consumption

 

 

 

Annual

 

Id

 

Description

 

Unitary
Dimension
(dim.)

 

Specific
Average
Consumption
(dim./k t
processed)

 

Standard
Annual
Production
(k t
processed)

 

Annual
Consumption
(dim.)

 

Unitary
Net
Price
(US$/dim.)

 

Standard
Net
Cost
(US$ k)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Power

 

MWh

 

0,757203

 

22.000

 

16.658

 

58,87

 

981

 

2.

 

Lime

 

t

 

0,009520

 

22.000

 

209

 

132,38

 

28

 

3.

 

Sodium Cyanide

 

t

 

0,019000

 

22.000

 

418

 

1.874,19

 

783

 

4.

 

Sodium Hydroxide

 

t

 

0,055000

 

22.000

 

1.210

 

472,80

 

572

 

5.

 

Flocculant

 

t

 

0,000590

 

22.000

 

13

 

2.931,37

 

38

 

6.

 

Sodium Metabisulphide

 

t

 

0,034000

 

22.000

 

748

 

1.267,11

 

948

 

7.

 

Hydrochloric Acid

 

t

 

0,010000

 

22.000

 

220

 

231,15

 

51

 

8.

 

Frother - MIBC

 

t

 

 

 

22.000

 

 

 

 

 

 

 

9.

 

Frother - D25

 

t

 

 

 

22.000

 

 

 

 

 

 

 

10.

 

Xanthate - PAX

 

t

 

 

 

22.000

 

 

 

 

 

 

 

11.

 

Activated Carbon

 

t

 

0,000900

 

22.000

 

20

 

3.307,72

 

65

 

12.

 

LPG Gas

 

t

 

10,000000

 

22.000

 

220.000

 

1,42

 

312

 

13.

 

Other

 

 

 

 

 

 

 

 

 

 

 

686

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingências (a)

 

 

 

 

 

 

 

 

 

 

 

223

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

 

 

 

 

 

4.688

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

 

0,21

 

 

 

Total (US$/oz)

 

 

 

 

 

 

291,01

 

 


(a)

 

Contingencies:

 

5

%

 

 

 

 

 

 

 

 

 

 

 

190



 

Table 21.29: Suruca Project MMIC Recovery Increase (CIL/Phase 1) 2014 Maintenance and Other Costs

 

Id

 

Description

 

Annual
Cost (US$)

 

 

 

 

 

1.

 

Maintenance

 

1.574

 

 

 

 

 

2.

 

Other

 

924

 

 

 

 

 

Total

 

2.498

Total (US$/tprocessed)

 

0,11

Total (US$/oz)

 

155,05

 

Table 21.30: Suruca Project Sulphide/Phase 2 Plant Cash Cost Summary (a)

 

 

 

Description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Id

 

Descrimination

 

Dimension

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Plant Cost

 

US$ k

 

 

 

 

 

 

 

 

 

14.723

 

26.174

 

26.174

 

26.174

 

26.174

 

24.974

 

144.392

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Labor

 

US$ k

 

 

 

 

 

 

 

 

 

370

 

658

 

658

 

658

 

658

 

658

 

3.661

 

1.2

 

Supplies, Power and Maintenance

 

US$ k

 

 

 

 

 

 

 

 

 

14.352

 

25.515

 

25.515

 

25.515

 

25.515

 

24.316

 

140.730

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Other Cash Costs (b)

 

US$ k

 

 

 

 

 

 

 

 

 

884

 

1.643

 

1.707

 

1.692

 

1.803

 

1.991

 

9.719

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Labor

 

US$ k

 

 

 

 

 

 

 

 

 

34

 

60

 

60

 

60

 

60

 

60

 

335

 

2.2

 

Other

 

US$ k

 

 

 

 

 

 

 

 

 

850

 

1.582

 

1.647

 

1.632

 

1.743

 

1.931

 

9.385

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

US$ k

 

 

 

 

 

 

 

 

 

15.607

 

27.816

 

27.881

 

27.866

 

27.976

 

26.965

 

154.111

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

 

 

 

 

3,47

 

3,48

 

3,49

 

3,48

 

3,50

 

3,54

 

3,49

 

 

 

Total (US$/oz)

 

 

 

 

 

 

 

 

 

 

 

275,31

 

263,66

 

253,90

 

256,16

 

240,82

 

209,51

 

246,32

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(a)

 

Production Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Ore Processed (k t/year):

 

 

 

 

 

 

 

 

 

 

 

4.500

 

8.000

 

8.000

 

8.000

 

8.000

 

7.624

 

44.124

 

 

 

Gold Production (k oz/year):

 

 

 

 

 

 

 

57

 

105

 

110

 

109

 

116

 

129

 

626

 

(b)

 

G&A, laboratory and other costs.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 21.31: Suruca Project Sulphide/Phase 2 Plant 2017 Labour Cost Details (a)

 

 

 

 

 

Number

 

Unitary Annual

 

Total

 

 

 

 

 

of

 

Cost (a)

 

Annual

 

Id

 

Description

 

Employees

 

(US$/employee)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Metallurgical/Process Engineer

 

 

 

 

 

 

 

1.2

 

Assistant Maintenance Supervisor

 

 

 

 

 

 

 

1.3

 

Electrical Supervisor

 

 

 

 

 

 

 

1.4

 

Operator

 

10

 

28.643

 

286

 

1.5

 

Auxiliary Technicians

 

6

 

15.855

 

95

 

1.6

 

Planner (Mechanical and Electrical)

 

 

 

 

 

 

 

1.7

 

Shift Mechanics (note 1)

 

2

 

38.333

 

77

 

1.8

 

Shift Electrician

 

2

 

38.333

 

77

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency (b)

 

 

 

 

 

27

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

20

 

28

 

562

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

0,07

 

 

 

Total (US$/oz)

 

 

 

 

 

5,11

 

 


(a)

 

Including tax and social benefits

 

 

 

 

 

 

 

 

 

 

 

(b)

 

Contingencies:

 

5,0

%

 

 

 

 

 

 

 

 

 

191



 

Table 21.32: Suruca Project Sulphide/Phase 2 Plant 2017 Consumables/Supplies, Power and Maintenance Data Details

 

 

 

 

 

 

 

Consumption

 

 

 

Annual

 

 

 

 

 

 

 

Specific

 

Standard

 

 

 

Unitary

 

Standard

 

 

 

 

 

Unitary

 

Average

 

Annual

 

Annual

 

Net

 

Net

 

 

 

 

 

Dimension

 

Consumption

 

Production

 

Consumption

 

Price

 

Cost

 

Id

 

Description

 

(dim.)

 

(dim./k tprocessed)

 

(k tprocessed)

 

(dim.)

 

(US$/dim.)

 

(US$ k)

 

1.

 

Power

 

MWh

 

28,906016

 

8.000

 

231.248

 

58,82

 

13.603

 

2.

 

Ball Mill Liners

 

t

 

0,046892

 

8.000

 

375

 

4.313,01

 

1.618

 

3.

 

Ball Mill Balls

 

t

 

0,570526

 

8.000

 

4.564

 

761,74

 

3.477

 

4.

 

Jaw Crusher Liners

 

t

 

0,001484

 

8.000

 

12

 

4.313,01

 

51

 

5.

 

Lime

 

t

 

 

 

8.000

 

 

 

 

 

 

 

6.

 

Sodium Cyanide

 

t

 

 

 

8.000

 

 

 

 

 

 

 

7.

 

Sodium Hydroxide

 

t

 

 

 

8.000

 

 

 

 

 

 

 

8.

 

Flocculant

 

t

 

 

 

8.000

 

 

 

 

 

 

 

9.

 

Sodium Metabisulphide

 

t

 

 

 

8.000

 

 

 

 

 

 

 

10.

 

Hydrochloric Acid

 

t

 

 

 

8.000

 

 

 

 

 

 

 

11.

 

Frother - MIBC

 

t

 

0,011083

 

8.000

 

89

 

2.345,10

 

208

 

12.

 

Frother - D25

 

t

 

0,008058

 

8.000

 

64

 

2.931,37

 

189

 

13.

 

Xanthate - PAX

 

t

 

0,016500

 

8.000

 

132

 

1.607,53

 

212

 

14.

 

Activated Carbon

 

t

 

 

 

8.000

 

 

 

 

 

 

 

15.

 

LPG Gas

 

t

 

 

 

8.000

 

 

 

 

 

 

 

16.

 

MMIC Plant Cost (b)

 

 

 

 

 

 

 

 

 

 

 

 

 

17.

 

Maintenance

 

 

 

 

 

 

 

 

 

 

 

5.190

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingências (a)

 

 

 

 

 

 

 

 

 

 

 

968

 

 

 

 

 

 

 

 

Total

25.515

 

Total (US$/tprocessed)

3,19

 

Total (US$/oz)

232,36

 

 


(a)

 

Contingencies:

 

4

%

 

 

Table 21.33: Suruca Project Sulphide/Phase 2 2017 Other Cash Cost

 

 

 

 

 

Annual

 

Id

 

Description

 

Cost (US$)

 

 

 

 

 

 

 

1.

 

Labor

 

 

 

 

 

 

 

 

 

2.

 

Other Expenses (a)

 

 

 

 

 

 

 

 

 

4.

 

Refining and Transport (b)

 

1.647

 

 

 

 

 

 

 

Total

 

1.647

 

Total (US$/tprocessed)

 

0,21

 

Total (US$/oz)

 

15,00

 

 


(a)

 

Other Expenses:

 

US$/tprocessed

 

 

 

 

 

Plant Administration

 

 

 

 

 

 

 

Other Cash Costs

 

 

 

 

 

 

 

Business Unit G&A

 

 

 

 

 

 

 

Total

 

 

 

 

 

(b)

 

Refining and Transport:

 

15,00

 

US$/oz

 

 

192



 

Table 21.34: Suruca Project Sulphide/Phase 2 Other Cash 2017 Labour Details (a)

 

 

 

 

 

Number

 

Unitary Annual

 

Total

 

 

 

 

 

of

 

Cost (a)

 

Annual

 

Id

 

Description

 

Employees

 

(US$/employee)

 

(US$ k)

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Clerk

 

 

 

 

 

 

 

1.2

 

Laboratory Technicians

 

2

 

28.643

 

57

 

 

 

 

 

 

 

 

 

 

 

 

 

Contingency (b)

 

 

 

 

 

3

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

2

 

30.075

 

60

 

 

 

Total (US$/tprocessed)

 

 

 

 

 

 

 

 

 

Total (US$/oz)

 

 

 

 

 

 

 

 


(a)

Including tax and social benefits

 

 

 

(b)

Contingencies:

5,0

%

 

 

21.6.1.5             Royalties

 

There are no landowner royalties because the properties will be purchased prior to the start of operations.

 

21.6.1.6             Residual Value

 

At the end of the Suruca Project, there will likely be salvage values for the mobile equipment, plant equipments, shop, lands and other. The salvage value is based in the original cost of the equipment.

 

A total of US$ 16.967 million is estimated as a net residual value for plant, properties and equipments.

 

At the end of the project, 70% of existing state tax credit with value equal to US$ 38.384 million and a return of the working capital with value equal to US$ 284.000 will be recovered.

 

21.6.1.7             Taxes

 

There are various taxes that are calculated for each item. The tax rates vary considerably for each tax and depend on numerous factors including equipment or material source and type. As an example, a list of taxes for investments and a range of rates are presented below:

 

·                  PIS: 0.65% on civil works, 1.65% on all equipment, materials and labor;

 

·                  COFINS: 3% on civil works, 7.6% on all equipment, materials and install labor;

 

·                  ICMS: 0% on civil works, 17% on all equipment and materials;

 

·                  IPI: 0% on civil works, 0% to 10% on all equipment and materials;

 

·                  ISS: 2% on installation only;

 

·                  II: 14% on imported equipment.

 

·                  Two fiscal incentives were considered in the project:

 

·                  Special regime for acquisition of capital assets by exporting companies (RECAP) that reduces the PIS and COFINS to zero in the investments.

 

193



 

·                  Drawback incentive for international supplies acquisition that reduce to zero IPI, ICMS, PIS and COFINS in the international purchase.

 

21.6.1.8             Working Capital

 

The basic assumptions for the working capital forecast were the following:

 

·                  Accounts receivables: 1 day of gross sales

 

·                  Inventories: 30 days of gross sales

 

·                  Accounts payables: 30 days of cost of goods sold

 

·                  Income tax payable: 30 days of income taxes

 

·                  Initial working capital: 100% of the uses of the first operational year

 

Table 21.35 presents the working capital data.

 

194



 

Table 21.35: Working Capital

 

ID

 

Description

 

2013

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Uses

 

5.820

 

5.820

 

6.928

 

6.260

 

6.776

 

7.541

 

10.693

 

11.941

 

12.181

 

12.275

 

13.140

 

1.322

 

1.297

 

1.117

 

1.282

 

1.405

 

1.203

 

964

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Accounts receivable

 

 

 

188

 

223

 

202

 

219

 

243

 

345

 

385

 

393

 

396

 

424

 

43

 

42

 

36

 

41

 

45

 

39

 

31

 

0

 

1.2

 

Inventories

 

 

 

5.633

 

6.704

 

6.058

 

6.557

 

7.297

 

10.348

 

11.556

 

11.789

 

11.879

 

12.716

 

1.279

 

1.255

 

1.081

 

1.241

 

1.360

 

1.164

 

933

 

0

 

1.3

 

Other current

 

 

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Sources

 

 

 

2.648

 

3.305

 

3.077

 

3.020

 

3.998

 

6.025

 

6.351

 

6.258

 

6.138

 

6.211

 

678

 

678

 

678

 

808

 

775

 

714

 

681

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1

 

Accounts payable

 

 

 

1.697

 

2.659

 

2.647

 

2.660

 

3.998

 

5.612

 

5.601

 

5.556

 

5.003

 

4.463

 

678

 

678

 

678

 

678

 

678

 

678

 

678

 

0

 

2.2

 

Other current

 

 

 

951

 

646

 

430

 

360

 

0

 

413

 

750

 

703

 

1.135

 

1.749

 

0

 

0

 

0

 

130

 

97

 

35

 

2

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Working Capital (Sources - Uses)

 

-5.820

 

-3.172

 

-3.623

 

-3.183

 

-3.755

 

-3.543

 

-4.668

 

-5.590

 

-5.923

 

-6.136

 

-6.929

 

-643

 

-618

 

-439

 

-474

 

-630

 

-489

 

-284

 

0

 

Working Capital Variantion

 

 

 

2.648

 

-451

 

440

 

-572

 

212

 

-1.125

 

-922

 

-333

 

-213

 

-793

 

6.286

 

25

 

179

 

-35

 

-156

 

141

 

205

 

284

 

 

195



 

21.6.1.9             Financial Statement, Cash Flow and Payback

 

Table 21.36 and Table 21.37 present the projected financial statement and cash flow for the Suruca Project.

 

As is possible to see in the cash flow spreadsheet the project operational payback is equal 8.04 years (discount rate equal to 5% per year).

 

196



 

Table 21.36: Suruca Project Financial Statement

 

ID

 

Description

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Gross Income

 

 

 

 

 

68.531

 

81.568

 

73.707

 

79.778

 

88.785

 

125.901

 

140.595

 

143.427

 

144.524

 

154.717

 

15.561

 

15.268

 

13.156

 

15.094

 

16.543

 

14.160

 

11.354

 

 

 

1.202.670

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Gold

 

 

 

 

 

68.531

 

81.568

 

73.707

 

79.778

 

88.785

 

125.901

 

140.595

 

143.427

 

144.524

 

154.717

 

15.561

 

15.268

 

13.156

 

15.094

 

16.543

 

14.160

 

11.354

 

 

 

1.202.670

 

1.2

 

Other

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Sales Tax

 

 

 

 

 

-685

 

-816

 

-737

 

-798

 

-888

 

-1.259

 

-1.406

 

-1.434

 

-1.445

 

-1.547

 

-156

 

-153

 

-132

 

-151

 

-165

 

-142

 

-114

 

 

 

-12.027

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Net Income

 

 

 

 

 

67.845

 

80.753

 

72.970

 

78.980

 

87.897

 

124.642

 

139.189

 

141.993

 

143.079

 

153.170

 

15.405

 

15.116

 

13.025

 

14.943

 

16.377

 

14.019

 

11.241

 

 

 

1.190.644

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

Cash Cost

 

 

 

 

 

-20.650

 

-32.352

 

-32.204

 

-32.363

 

-48.638

 

-68.285

 

-68.147

 

-67.592

 

-60.873

 

-54.295

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

 

 

-543.178

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1

 

Open Pit Cash Cost

 

 

 

 

 

-6.660

 

-8.880

 

-8.880

 

-8.880

 

-19.904

 

-32.215

 

-32.012

 

-31.473

 

-24.642

 

-19.076

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-192.622

 

4.2

 

Underground Cash Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.3

 

Plant Cash Cost

 

 

 

 

 

-10.057

 

-13.409

 

-13.409

 

-13.409

 

-19.185

 

-26.174

 

-26.174

 

-26.174

 

-26.174

 

-24.974

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-199.138

 

4.4

 

Other Cash Cost (a)

 

 

 

 

 

-3.933

 

-10.063

 

-9.915

 

-10.074

 

-9.549

 

-9.897

 

-9.961

 

-9.946

 

-10.057

 

-10.245

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

-8.254

 

 

 

-151.418

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

Gross Profit (contribution margin)

 

 

 

 

 

47.195

 

48.401

 

40.766

 

46.617

 

39.259

 

56.357

 

71.042

 

74.400

 

82.206

 

98.874

 

7.151

 

6.861

 

4.770

 

6.689

 

8.123

 

5.765

 

2.987

 

 

 

647.465

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.

 

Expenses (b)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-3.070

 

-3.070

 

-3.070

 

 

 

 

 

-3.070

 

-3.070

 

-3.070

 

 

 

 

 

 

 

 

 

 

 

-18.420

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

 

EBITDA

 

 

 

 

 

47.195

 

48.401

 

40.766

 

46.617

 

39.259

 

53.287

 

67.972

 

71.330

 

82.206

 

98.874

 

4.081

 

3.791

 

1.700

 

6.689

 

8.123

 

5.765

 

2.987

 

 

 

629.045

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8.

 

Depreciation & Amortization

 

 

 

 

 

-13.130

 

-14.167

 

-15.243

 

-21.617

 

-34.878

 

-29.950

 

-28.913

 

-27.837

 

-25.358

 

-22.138

 

-14.746

 

-14.746

 

-10.851

 

 

 

 

 

 

 

 

 

 

 

-273.575

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9.

 

EBIT

 

 

 

 

 

34.066

 

34.234

 

25.523

 

25.000

 

4.381

 

23.337

 

39.058

 

43.493

 

56.848

 

76.736

 

-10.665

 

-10.955

 

-9.151

 

6.689

 

8.123

 

5.765

 

2.987

 

 

 

355.471

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10.

 

Financial Results

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11.

 

Operational Results

 

 

 

 

 

34.066

 

34.234

 

25.523

 

25.000

 

4.381

 

23.337

 

39.058

 

43.493

 

56.848

 

76.736

 

-10.665

 

-10.955

 

-9.151

 

6.689

 

8.123

 

5.765

 

2.987

 

 

 

355.471

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12.

 

Interest on Equity

 

 

 

 

 

 

 

-11.085

 

-10.096

 

-12.067

 

-11.918

 

-2.190

 

-11.002

 

-18.301

 

-16.185

 

-14.121

 

-12.292

 

 

 

 

 

 

 

-3.134

 

-3.904

 

-2.824

 

-1.488

 

-130.609

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

13.

 

Income Before Tax

 

 

 

 

 

34.066

 

23.150

 

15.427

 

12.933

 

-7.537

 

21.147

 

28.056

 

25.192

 

40.663

 

62.615

 

-22.957

 

-10.955

 

-9.151

 

6.689

 

4.989

 

1.860

 

163

 

-1.488

 

224.862

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14.

 

Income Tax

 

 

 

 

 

-11.569

 

-7.858

 

-5.232

 

-4.384

 

 

 

-5.020

 

-9.120

 

-8.552

 

-13.812

 

-21.276

 

 

 

 

 

 

 

-1.579

 

-1.174

 

-429

 

-27

 

 

 

-90.031

 

 

 

Tax Rate (%)

 

 

 

 

 

34,0

%

33,9

%

33,9

%

33,9

%

 

 

23,7

%

32,5

%

33,9

%

34,0

%

34,0

%

 

 

 

 

 

 

23,6

%

23,5

%

23,1

%

16,8

%

 

 

40,0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15.

 

Net Profit

 

 

 

 

 

22.497

 

15.292

 

10.195

 

8.549

 

-7.537

 

16.127

 

18.936

 

16.640

 

26.851

 

41.339

 

-22.957

 

-10.955

 

-9.151

 

5.110

 

3.815

 

1.431

 

135

 

-1.488

 

134.830

 

 

 

 % of Net Income

 

 

 

 

 

33,2

%

18,9

%

14,0

%

10,8

%

-8,6

%

12,9

%

13,6

%

11,7

%

18,8

%

27,0

%

-149,0

%

-72,5

%

-70,3

%

34,2

%

23.3

%

10,2

%

1,2

%

 

 

11,3

%

 


(a)

 

Laboratory, SHEC Depto., Adm. Depto, product transport, final refinning insurance and other.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(b)

 

Sales expenses, reclamation and closure and other.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

197



 

Table 21.37: Suruca Project Cash Flow

 

ID

 

Description

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

Total

 

Verif.1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Net Profit

 

 

 

 

 

22.497

 

15.292

 

10.195

 

8.549

 

-7.537

 

16.127

 

18.936

 

16.640

 

26.851

 

41.339

 

-22.957

 

-10.955

 

-9.151

 

5.110

 

3.815

 

1.431

 

135

 

-1.488

 

134.830

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Interest on Equity

 

 

 

 

 

 

 

11.085

 

10.096

 

12.067

 

11.918

 

2.190

 

11.002

 

18.301

 

16.185

 

14.121

 

12.292

 

 

 

 

 

 

 

3.134

 

3.904

 

2.824

 

1.488

 

130.609

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Depreciation & Amortization

 

 

 

 

 

13.130

 

14.167

 

15.243

 

21.617

 

34.878

 

29.950

 

28.913

 

27.837

 

25.358

 

22.138

 

14.746

 

14.746

 

10.851

 

 

 

 

 

 

 

 

 

 

 

273.575

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

Investments

 

-28.813

 

-67.229

 

-11.005

 

-5.381

 

-47.449

 

-113.759

 

-11.769

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-285.404

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1

 

Capex

 

-28.813

 

-67.229

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-96.042

 

 

 

4.2

 

Sustaining

 

 

 

 

 

-5.185

 

-5.381

 

-47.449

 

-113.759

 

-11.769

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-183.542

 

 

 

4.3

 

Initial Working Capital

 

 

 

 

 

-5.820

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-5.820

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

Working Capital Variations

 

 

 

 

 

2.648

 

-451

 

440

 

-572

 

212

 

-1.125

 

-922

 

-333

 

-213

 

-793

 

6.286

 

25

 

179

 

-35

 

-156

 

141

 

205

 

284

 

5.820

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.

 

Tax balance

 

-1.181

 

-2.756

 

-498

 

-722

 

-3.390

 

-8.254

 

-5.453

 

-5.491

 

-6.832

 

-6.860

 

-6.860

 

-6.538

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

38.384

 

-16.450

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.1

 

Capex/Long Term Tax Balance

 

-1.181

 

-2.756

 

137

 

125

 

-2.543

 

-7.407

 

 

 

56

 

28

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9.478

 

-4.062

 

 

 

6.2

 

Opex/Short Term Tax Balance

 

 

 

 

 

-635

 

-847

 

-847

 

-847

 

-5.453

 

-5.547

 

-6.860

 

-6.860

 

-6.860

 

-6.538

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

28.906

 

-12.388

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

 

Project Residual Value

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16.967

 

16.967

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash Flow (c)

 

-29.994

 

-69.985

 

26.772

 

33.990

 

-14.865

 

-80.352

 

22.250

 

41.652

 

51.098

 

55.585

 

61.321

 

70.268

 

10.367

 

3.816

 

1.880

 

5.076

 

6.793

 

5.476

 

3.164

 

55.635

 

259.946

 

 

 

 


(a)

 

IRR:

 

15,0%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(b)

 

Net Present Value:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Interest Rate (% p.y)

 

US$ 000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15,0 %

 

184

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12,5 %

 

18.143

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10,0 %

 

41.962

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7,5 %

 

73.882

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5,0 %

 

117.181

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

zero

 

259.946

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(c)

 

Payback Calculation:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Discount Rate:

 

5,0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Years count starting zero

 

 

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

19

 

 

 

 

 

 

 

· Years count based on operation

 

-1

 

 

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

 

 

 

 

 

 

· Discounted Cash Flow (zero base)

 

-29.994

 

-66.653

 

24.283

 

29.362

 

-12.229

 

-62.958

 

16.603

 

29.601

 

34.585

 

35.831

 

37.646

 

41.084

 

5.773

 

2.024

 

949

 

2.441

 

3.112

 

2.389

 

1.315

 

22.017

 

 

 

 

 

 

 

· Accumulated Discounted C.F.

 

-29.994

 

-96.646

 

-72.363

 

-43.002

 

-55.231

 

-118.189

 

-101.586

 

-71.985

 

-37.400

 

-1.569

 

36.076

 

77.161

 

82.933

 

84.957

 

85.907

 

88.348

 

91.460

 

93.849

 

95.164

 

117.181

 

 

 

 

 

 

 

· Payback based on operation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8,04

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

198



 

21.6.2              Chapada and Suruca Financial Analysis

 

21.6.2.1             Economic Results

 

In the base scenario, assuming a discount rate of 5%, the project Net Present Value will be US$ 572 million.

 

The main financial parametres for the base case are shown in the Table 21.38.

 

Table 21.38: Chapada and Suruca Project Financial Parametres

 

Project Indicators

 

 

Ratio

 

Unit

 

Value

 

Observation

After-Tax NPV

 

 

 

 

 

 

NPV (discount rate 5% p.y.)

 

US$

 

572.016.051

 

 

Other Indicators

 

 

 

 

 

 

Total Capex (excluding working capital)

 

US$

 

224.697.921

 

Capex including all taxes but excluding working capital and sustaining

Suruca Oxide

 

US$

 

59.652.346

 

Capex Suruca Oxide excluding working capital and sustaining

Suruca Sulphide Phase 1

 

US$

 

39.410.525

 

Capex Suruca Sulphide Phase 1 excluding working capital and sustaining

Suruca Sulphide Phase 2

 

US$

 

125.635.050

 

Capex Suruca Sulphide Phase 2 excluding working capital and sustaining

Total Capex (including working capital)

 

US$

 

224.697.921

 

Capex including all taxes and working capital but excluding sustaining

Sustaining Capital

 

US$

 

86.541.744

 

Sustaining including all taxes but not including Mine Closure treated as an expense

Total Capital Cost (excluding working capital)

 

US$

 

311.239.665

 

Total capital cost (excluding working capital) = Capex excluding working capital + Sustaining.

Total Capital Cost (including working capital)

 

US$

 

311.239.665

 

Total capital cost (including working capital) = Capex inclunding work capital + Sustaining.

Capex/oz (excluding working)

 

US$/oz

 

107,65

 

Capex/oz including all taxes and excluding working capital and sustaining

Sustaining/oz

 

US$/oz

 

41,46

 

Sustaining/oz including all taxes.

Total Capital Cost/oz

 

US$/oz

 

149,11

 

Total capital cost/oz = Capex/oz + Sustaining/oz.

Underground Mine Cash Cost/oz

 

US$/oz

 

0,00

 

Underground Mine Cash Cost/oz

Open Pit Mine Cash Cost/oz

 

US$/oz

 

561,61

 

Open Pit Mine Cash Cost/oz

Plant Cash cost/oz

 

US$/oz

 

956,87

 

Plant Cash Cost/oz

Other Cash Cost/oz

 

US$/oz

 

221,08

 

Other Cash Cost/oz

Total Cash Cost/oz

 

US$/oz

 

1.739,56

 

Total Cash Cost/oz = (Underground + Open Pit) Cash Cost/oz + Plant Cash Cost/oz + Other Cash Cost/oz

Underground Mine Cash Cost/t ore mined

 

US$/t

 

0,00

 

Underground Mine Cash Cost/t  ore mined

Open Pit Mine Cash Cost/t ore mined

 

US$/t

 

2,88

 

Open Pit Mine Cash Cost/t  ore mined

Plant Cash Cost/t ore processed

 

US$/t

 

4,90

 

Plant Cash Cost/t ore processed

Other Cash Cost/t ore processed

 

US$/t

 

1,13

 

Other Cash Cost/t ore processed

Total Cash Cost/t

 

US$/t

 

8,91

 

Total Cash Cost/t = (Underground + Open Pit) Cash Cost/tmined+ Plant Cash Cost/tprocessed+Other Cash Cost/tprocessed

Life of mine

 

years

 

19

 

 

 

The discount rate sensitivity analysis is present in the Table 21.39.

 

199



 

Table 21.39: Chapada and Suruca Project Sensitivity NPV x Discount Rate

 

Sensitivity Analysis - NPV x Discount Rate to the Firm

 

Discount Rate

 

NPV

 

15,00

%

383.852.470

 

12,50

%

418.794.820

 

10,00

%

460.458.990

 

7,50

%

510.699.126

 

5,00

%

572.016.051

 

0,00

%

742.844.860

 

 

In order to estimate the relative strength of the project, first level sensitivity analysis was developed for the following items: gold price, capital cost and operating costs.

 

In this analysis, when one factor varies, the other factors remain constant.

 

Table 21.40 presents the sensitivity analysis for the 5% NPV of the project and Figure 21.17 shows the results graphically. For example, a 10% price change impacts the projects NPV by approximately US$ 327.4 million (US$ 572.0 million – US$ 244.6 million).

 

Table 21.40: Chapada and Suruca Project NPV  Sensitivity Analysis (discount rate 5% per year)

 

Net Present value of the cash flow to the firm

 

 

 

Sale prices

 

Opex and other
expenses

 

Capex and
sustaining

 

-30%

 

-486.028.367

 

1.184.503.952

 

667.395.763

 

-20%

 

-112.370.302

 

988.483.389

 

636.088.533

 

-10%

 

244.625.721

 

788.442.198

 

605.018.862

 

0%

 

572.016.051

 

572.016.051

 

572.016.051

 

10%

 

854.399.333

 

320.564.722

 

538.403.113

 

20%

 

1.121.462.522

 

49.094.506

 

503.777.132

 

30%

 

1.385.366.702

 

-230.128.951

 

466.913.992

 

 

200



 

Figure 21.17: Chapada and Suruca Project NPV Sensitivity Analysis

 

 

According to this analysis, the project is more sensitive to price, followed by Opex variation, and then by Capex/ Sustaining.

 

The worst case scenario occurs when the price drops 30% (average near US$ 777/oz) and when the NPV falls to US$ - 486 million.

 

An increase of 30% in Opex and Capex reduces the NPV to US$ - 230 million and US$ 467 million, respectively.

 

A second level of sensitivity analysis is present in Table 21.41 where cross sensitivity is shown for Opex, Capex, exchange rate and price.

 

In this analysis, simultaneous variations occur.

 

201



 

Table 21.41: Chapada Project and Suruca Project Cross NPV Sensitivity Analysis (discount rate 5% p.y.)

 

US$

NET PRESENT VALUE OF THE CASH FLOW TO THE FIRM

 

Opex and other expenses sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

358.556.611

 

86.292.350

 

-196.256.484

 

-486.028.367

 

-776.598.921

 

-1.068.672.267

 

-1.368.338.305

 

 

 

-20%

 

655.626.084

 

431.526.918

 

166.043.532

 

-112.370.302

 

-399.399.338

 

-689.524.065

 

-980.167.018

 

Sale prices

 

-10%

 

922.194.995

 

722.126.877

 

502.621.092

 

244.625.721

 

-31.461.977

 

-312.841.679

 

-602.782.456

 

sensitivity

 

0%

 

1.184.503.952

 

988.483.389

 

788.442.198

 

572.016.051

 

320.564.722

 

49.094.506

 

-230.128.951

 

factor

 

10%

 

1.445.486.565

 

1.251.192.115

 

1.054.712.437

 

854.399.333

 

640.667.231

 

394.995.625

 

127.613.775

 

 

 

20%

 

1.706.372.488

 

1.512.911.166

 

1.318.273.593

 

1.121.462.522

 

920.863.627

 

707.285.937

 

467.273.503

 

 

 

30%

 

1.967.208.607

 

1.773.877.847

 

1.580.266.579

 

1.385.366.702

 

1.188.165.262

 

987.384.096

 

773.877.923

 

 

Capex and sustaining sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

-358.110.170

 

-400.740.606

 

-443.380.643

 

-486.028.367

 

-528.683.218

 

-571.341.793

 

-614.339.415

 

 

 

-20%

 

11.299.957

 

-29.914.808

 

-71.139.173

 

-112.370.302

 

-153.606.375

 

-195.218.909

 

-237.858.813

 

Sale prices

 

-10%

 

360.388.992

 

322.572.762

 

283.779.843

 

244.625.721

 

204.365.944

 

163.595.146

 

123.107.633

 

sensitivity

 

0%

 

667.395.763

 

636.088.533

 

605.018.862

 

572.016.051

 

538.403.113

 

503.777.132

 

466.913.992

 

factor

 

10%

 

938.707.558

 

909.885.568

 

882.058.121

 

854.399.333

 

826.121.155

 

797.619.374

 

769.565.565

 

 

 

20%

 

1.204.027.936

 

1.175.759.633

 

1.148.528.191

 

1.121.462.522

 

1.094.470.050

 

1.067.901.267

 

1.041.797.250

 

 

 

30%

 

1.466.973.063

 

1.439.071.182

 

1.412.211.706

 

1.385.366.702

 

1.358.636.458

 

1.332.241.874

 

1.306.301.170

 

 

Exchange rate sensitivity factor

 

 

 

 

 

-30%

 

-20%

 

-10%

 

0%

 

10%

 

20%

 

30%

 

 

 

-30%

 

-1.946.198.943

 

-1.327.157.620

 

-857.207.733

 

-486.028.367

 

-183.494.426

 

62.295.380

 

265.000.236

 

 

 

-20%

 

-1.545.128.376

 

-942.653.501

 

-479.365.897

 

-112.370.302

 

178.167.159

 

408.759.865

 

581.131.374

 

Sale prices

 

-10%

 

-1.161.076.294

 

-565.191.086

 

-108.648.778

 

244.625.721

 

511.599.456

 

701.813.320

 

850.521.125

 

sensitivity

 

0%

 

-783.141.495

 

-194.115.984

 

247.568.890

 

572.016.051

 

795.217.979

 

968.647.380

 

1.113.634.397

 

factor

 

10%

 

-407.183.450

 

163.107.118

 

577.068.420

 

854.399.333

 

1.061.504.725

 

1.231.510.462

 

1.374.474.583

 

 

 

20%

 

-46.320 716

 

503.678.451

 

866.633.607

 

1.121.462.522

 

1.325.101.782

 

1.493.032.682

 

1.634.994.953

 

 

 

30%

 

305.262.318

 

812.069.837

 

1.136.150.664

 

1.385.366.702

 

1.587 042 896

 

1.754.071.249

 

1.895.310.196

 

 

21.6.2.2 Financial Statement, Cash Flow and Payback

 

Table 21.42 and Table 21.43 presents the projected financial statement and cash flow for the Chapada Project and Suruca Project.

 

202



 

Table 21.42: Chapada Project and Suruca Project Financial Statement

 

ID

 

Description

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Gross Income

 

742.180

 

672.8I4

 

607.140

 

530.815

 

444.912

 

462.344

 

425.832

 

378.860

 

400.474

 

425.233

 

342.866

 

314.413

 

238.490

 

235.498

 

231.381

 

226.137

 

235.405

 

217.697

 

176.005

 

 

 

 

 

 

 

7.308.495

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1

 

Gold

 

161.588

 

161.482

 

186.312

 

172.906

 

155.147

 

155.397

 

157.377

 

173.861

 

192.254

 

192.918

 

177.013

 

180.042

 

45.275

 

43.925

 

44.252

 

43.801

 

48.005

 

41.091

 

32.948

 

 

 

 

 

 

 

2.366.194

 

1.2

 

Other

 

580.592

 

511.332

 

420.228

 

357.908

 

289.765

 

306.947

 

268.454

 

204.999

 

208.221

 

232.315

 

165.853

 

134.371

 

193.216

 

191.573

 

187.129

 

182.336

 

187.401

 

176.606

 

143.057

 

 

 

 

 

 

 

4.942.301

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Sales Tax

 

-36.299

 

-32.926

 

-32.936

 

-28.810

 

-29.364

 

-34.280

 

-33.657

 

-32.863

 

-33.233

 

-33.653

 

-32.236

 

-31.727

 

-30.403

 

-30.351

 

-30.281

 

-30.191

 

-30.349

 

-30.046

 

-29.315

 

 

 

 

 

 

 

-602.919

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Net Income

 

705.880

 

639.888

 

574.204

 

502.004

 

416.549

 

428.064

 

392.175

 

345.997

 

367.241

 

391.580

 

310.629

 

282.685

 

208.087

 

205.147

 

201.101

 

195.946

 

205.057

 

187.651

 

146.690

 

 

 

 

 

 

 

6.705.575

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

Cash Cost

 

-217.445

 

-216.952

 

-221.353

 

-240.280

 

-233.206

 

-229.513

 

-221 294

 

-229.628

 

-235.988

 

-232.756

 

-205.495

 

-175.398

 

-144.021

 

-142.553

 

-141.840

 

-143.240

 

-142.553

 

-142.553

 

-115.045

 

 

 

 

 

 

 

-3.631.114

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1

 

Open Pit Cash Cost

 

-89.783

 

-91.168

 

-84.474

 

-88.795

 

-86.974

 

-87.373

 

-77.723

 

-86.819

 

-88.635

 

-85.648

 

-65.156

 

-38.498

 

-30.516

 

-29.732

 

-29.114

 

-29.115

 

-29.732

 

-29.732

 

-23.327

 

 

 

 

 

 

 

-1.172.293

 

4.2

 

Underground Cash Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.3

 

Plant Cash Cost

 

-82.135

 

-84.431

 

-94.155

 

-111.291

 

-111.665

 

-111.078

 

-117.162

 

-123.809

 

-124.715

 

-123.991

 

-123.627

 

-123.040

 

-97.906

 

-97.728

 

-97.546

 

-97.732

 

-97.728

 

-97.728

 

-79.876

 

 

 

 

 

 

 

-1.997.345

 

4.4

 

Other Cash Cost (a)

 

-45.547

 

-41.354

 

-42.724

 

-40.193

 

-34.566

 

-31.063

 

-26.409

 

-19.000

 

-22.639

 

-23.117

 

-16.712

 

-13.859

 

-15.599

 

-15.093

 

-15.181

 

-16.393

 

-15.093

 

-15.093

 

-11.842

 

 

 

 

 

 

 

-461.476

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

Gross Profit (contribution margin)

 

488.435

 

422.935

 

352.851

 

261.725

 

182.343

 

198.551

 

170.881

 

116.369

 

131.253

 

158.824

 

105.134

 

107.287

 

64.066

 

62.594

 

59.260

 

52.706

 

62.503

 

45.098

 

31.645

 

 

 

 

 

 

 

3.074.461

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.

 

Expenses (b)

 

-78.484

 

-71.820

 

-64.732

 

-78.279

 

-77.256

 

-70.157

 

-62.845

 

-57.569

 

-57.487

 

-57.576

 

-54.494

 

-54.506

 

-57.617

 

-57.413

 

-57.547

 

-54.458

 

-54.343

 

-54.343

 

42.637

 

-11.452

 

-11.452

 

-11.452

 

-1.197.919

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

 

EBITDA

 

409.950

 

351.115

 

288.119

 

183.446

 

105.087

 

128.394

 

108.037

 

58.800

 

73.767

 

101.248

 

50.640

 

52.782

 

6.449

 

5.180

 

1.713

 

-1.752

 

8.160

 

-9.245

 

-10.992

 

-11.452

 

-11.452

 

-11.452

 

1.876.542

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8.

 

Depreciation & Amortization

 

-24.288

 

-30.881

 

-41.095

 

-53.331

 

-57.295

 

-66.482

 

-76.156

 

-75.103

 

-69.088

 

-69.695

 

41.910

 

-37.367

 

-29.195

 

-25.937

 

-23.430

 

-18.309

 

-7.336

 

-6.636

 

4.207

 

-2.310

 

 

 

 

 

-760.049

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

9.

 

EBIT

 

385.662

 

320.234

 

247.024

 

130.115

 

47.792

 

61.912

 

31.880

 

-16.303

 

4.679

 

31.553

 

8.730

 

15.415

 

-22.746

 

-20.757

 

-21.717

 

-20.061

 

824

 

-15.881

 

-15.198

 

-13.762

 

-11.452

 

-11.452

 

1.116.493

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10.

 

Financial Results

 

-289.247

 

-240.176

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-529.422

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11.

 

Operational Results

 

96.416

 

80.058

 

247.024

 

130.115

 

47.792

 

61.912

 

31.880

 

-16.303

 

4.679

 

31.553

 

8.730

 

15.415

 

-22.746

 

-20.757

 

-21.717

 

-20.061

 

824

 

-15.881

 

-15.198

 

-13.762

 

-11.452

 

-11.452

 

587.071

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12.

 

Interest on Equity

 

 

 

-3.652

 

-12.110

 

-20.940

 

-10.205

 

-10.411

 

-16.660

 

-12.927

 

 

 

-1.565

 

-608

 

-856

 

-302

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-90.237

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

13.

 

Income Before Tax

 

96.416

 

76.406

 

234.914

 

109.175

 

37.587

 

51.501

 

15.220

 

-29.230

 

4.679

 

29.988

 

8.122

 

14.559

 

-23.048

 

-20.757

 

-21.717

 

-20.061

 

824

 

-15.881

 

-15.198

 

-13.762

 

-11.452

 

-11.452

 

496.833

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14.

 

Income Tax

 

-32.768

 

-25.965

 

-79.857

 

-37.106

 

-12.766

 

-17.497

 

-5.162

 

 

 

-1.100

 

-7.124

 

-1.920

 

-3.452

 

 

 

 

 

 

 

 

 

-183

 

 

 

 

 

-61.321

 

 

 

 

 

-286.221

 

 

 

Tax Rate (%)

 

34,0

%

34,0

%

34,0

%

34,0

%

34,0

%

34,0

%

33,9

%

 

 

23,5

%

23,8

%

23,6

%

23,7

%

 

 

 

 

 

 

 

 

22,2

%

 

 

 

 

-445,6

%

 

 

 

 

57,6

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15.

 

Net Profit

 

63.648

 

50.441

 

155.057

 

72.069

 

24.821

 

34.004

 

10.059

 

-29.230

 

3.579

 

22.864

 

6.203

 

11.107

 

-23.048

 

-20.757

 

-21.717

 

-20.061

 

641

 

-15.881

 

-15.198

 

-75.083

 

-11.452

 

-11.452

 

210.613

 

 

 

% of Net Income

 

9,0

%

7,9

%

27,0

%

14,4

%

6,0

%

7,9

%

2,6

%

-8,4

%

1,0

%

5,8

%

2,0

%

3,9

%

-11,1

%

10,1

%

-10,8

%

-10,2

%

0,3

%

-8,5

%

-10,4

%

 

 

 

 

 

 

3,1

%

 


(a)   Laboratory, SHEC Depto., Adm. Depto, product transport, final refinning insurance and other.

(b)   Sales expenses, reclamation and closure snd other.

 

203



 

Table 21.43: Chapada Project and Suruca Project Cash Flow

 

ID

 

Description

 

2011

 

2012

 

2013

 

2014

 

2015

 

2016

 

2017

 

2018

 

2019

 

2020

 

2021

 

2022

 

2023

 

2024

 

2025

 

2026

 

2027

 

2028

 

2029

 

2030

 

2031

 

2032

 

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

 

Net Profit

 

63.648

 

50.441

 

155.057

 

72.069

 

24.821

 

34.004

 

10.059

 

-29 230

 

3.579

 

22.864

 

6.203

 

11.107

 

-23.048

 

-20.757

 

-21.717

 

-20.061

 

641

 

-15.881

 

-15.198

 

-75.083

 

-11.452

 

-11.452

 

210.613

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

 

Interest on Equity

 

 

 

3.652

 

12.110

 

20.940

 

10.205

 

10.411

 

16.660

 

12.927

 

 

 

1.565

 

608

 

856

 

302

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

90.237

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

 

Depreciation & Amortization

 

24.288

 

30.881

 

41.095

 

53.331

 

57.295

 

66.482

 

76.156

 

75.103

 

69.088

 

69.695

 

41.910

 

37.367

 

29.195

 

25.937

 

23.430

 

18.309

 

7.336

 

6.636

 

4.207

 

2.310

 

 

 

 

 

760.049

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

 

Investments

 

-35.985

 

-80.572

 

-85.308

 

-22.059

 

-68.306

 

-130.513

 

-23.799

 

-15.364

 

-30.230

 

-8.551

 

-8.294

 

-2.899

 

-10.279

 

-1.216

 

-1.326

 

-1.417

 

-1.326

 

-1.326

 

-548

 

 

 

 

 

 

 

-529.318

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1

 

Capex

 

 

 

-28.819

 

-67.245

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-96.065

 

4.2

 

Sustaining

 

-35.985

 

-51.752

 

-18.063

 

-22.059

 

-68.306

 

-130.513

 

-23.799

 

-15.364

 

-30.230

 

-8.551

 

-8.294

 

-2.899

 

-10.279

 

-1.216

 

-1.326

 

-1.417

 

-1.326

 

-1.326

 

-548

 

 

 

 

 

 

 

-433.253

 

4.3

 

Initial Working Capital

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.

 

Working Capital Variations

 

-3.310

 

18.384

 

22.965

 

19.731

 

20.662

 

-4.842

 

7.976

 

13.472

 

-5.047

 

-6.687

 

18.778

 

4.211

 

16.649

 

639

 

1.040

 

1.609

 

-2.609

 

4.837

 

8.031

 

39.077

 

-5.040

 

 

 

170.525

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.

 

Tax balance

 

-1.155

 

-6.299

 

-4.848

 

-3.930

 

-5.582

 

-7.316

 

-3.244

 

-5.910

 

-6.644

 

-5.492

 

-5.076

 

-3.639

 

2.544

 

2.683

 

2.698

 

2.685

 

2.706

 

2.706

 

5.331

 

26.448

 

 

 

 

 

-11.334

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.1

 

Capex/Long Term Tax Balance

 

-538

 

-4.005

 

-2.993

 

-127

 

-3.013

 

-7.368

 

-560

 

-642

 

-1.325

 

-317

 

-264

 

-125

 

-140

 

-59

 

-25

 

-37

 

-36

 

-36

 

-36

 

15.153

 

 

 

 

 

-6.494

 

6.2

 

Opex/Short Term Tax Balance

 

-617

 

-2.294

 

-1.855

 

-3.803

 

-2.569

 

52

 

-2.683

 

-5.268

 

-5.319

 

-5.175

 

-4.812

 

-3.514

 

2.684

 

2.742

 

2.722

 

2.722

 

2.742

 

2.742

 

5.367

 

11.295

 

 

 

 

 

-4.841

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

 

Project Residual Value

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

52.073

 

 

 

 

 

52.073

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cash Flow (c)

 

47.485

 

16.488

 

141.070

 

140.082

 

39.095

 

-31.774

 

83.809

 

50.998

 

30.745

 

73.395

 

54.128

 

47.002

 

15.363

 

7.286

 

4.124

 

1.126

 

6.748

 

-3.029

 

1.822

 

44.824

 

-16.492

 

-11.452

 

742.845

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net Present Value:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Interest Rate (% p.y)

 

US$ 000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15,0

%

 

 

383.852

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12,5

%

 

 

418.795

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10,0

%

 

 

460.459

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7,5

%

 

 

510.699

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5,0

%

 

 

572.016

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Zero

 

 

 

742.845

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Payback Calculation:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Discount Rate:

 

5,0

%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

· Years count starting zero

 

 

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

19

 

20

 

21

 

 

 

 

 

· Years count based on operation

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

10

 

11

 

12

 

13

 

14

 

15

 

16

 

17

 

18

 

19

 

20

 

21

 

22

 

 

 

 

 

· Discounted Cash Flow (zero base)

 

47.485

 

15.703

 

127.955

 

121.008

 

32.163

 

24.896

 

62.539

 

36.243

 

20.809

 

47.311

 

33.230

 

27.481

 

8.555

 

3.864

 

2.083

 

542

 

3.092

 

-1.322

 

757

 

17.739

 

-6.216

 

-4.111

 

 

 

 

 

· Accumulated Discounted C.F.

 

47.485

 

63.189

 

191.144

 

312.151

 

344.315

 

319.419

 

381.958

 

418.202

 

439.011

 

486.322

 

519.552

 

547.033

 

555.588

 

559.452

 

561.535

 

562.077

 

565.168

 

563.847

 

564.604

 

582.342

 

576.127

 

572.016

 

 

 

 

Description

 

Factors

 

Units

 

Gold Price

 

1.100

 

US$/oz

 

Copper Price

 

2.50

 

US$lb

 

Operating Costs

 

8.91

 

US$/t

 

Mining Costs (ore + Waste)

 

2.88

 

US$/t

 

Process Plant Costs

 

4.90

 

US$/t

 

Other Cash Costs

 

1.13

 

US$/t

 

Capital Costs

 

111,91

 

US$/oz

 

Mine Operational Capex

 

4,27

 

US$/oz

 

Plant Capex

 

107,65

 

US$/oz

 

Sustaining Operational

 

41,46

 

US$/oz

 

Reclamation & Closure

 

25,28

 

US$/oz

 

 

204



 

22               CERTIFICATES OF QUALIFIED PERSONS

 

205



 

Sergio Brandão Silva, PGeo.

Yamana Gold Inc.

Telephone: +55 2163 8466

Fax: +55 2163 8324

E-mail: sbrandao@yamana.com

 

CERTIFICATE of QUALIFIED PERSON

 

I, Sergio Brandão Silva, do hereby certify that:

 

1.              I hold the position of Exploration Director with Yamana Gold Inc and I am responsible for directing all exploration works in Brazil, which include Chapada Mine/Near Mine and Suruca property. My current office address is Rua Funchal, 411, 4º Andar, São Paulo, SP, Brazil, CEP04551-060.

 

2.              I have degree in Bachelor of Science in Honours Geology, 1997, University of São Paulo State (UNESP).

 

3.              I am practising member of Association of Professional Geoscientists of Ontario (#1760), member of Canadian Institute of Mining, Metallurgy and Petroleum (#144740), member of Society of Economic Geologists (#731580) and registered geologist of Conselho Regional de Engenharia, Arquitetura e Agronomia (CREASP# 5061047124).

 

4.              I have been practising as a professional exploration geologist since 1998.

 

5.              By reason of my education, experience and professional registration I fulfill the requirements of a qualified person as set out in National Instrument 43101 (“43101”)

 

6.              I have visited the Chapada Mine and Suruca Property site in person in a number of occasions as Exploration Director. My most recent visit was for two days in November, 2010.

 

7.              I have been responsible for the preparation of the sections 3.PROPERTY DESCRIPTION AND LOCATION, 4. ACCESSIBILITY, CLIMATE, LOCAL RESOURCE, INFRASTRUCTURE AND PHYSIOGRAPHY, 5.HISTORY, 6.GEOLOGICAL SETTINGS, 7.DEPOSIT TYPES, 8. MINERALIZATION, 9. EXPLORATION, 10.DRILLING, 11.SAMPLING METHODS AND APPROACH, 12. SAMPLE PREPARATION, ANALYSES AND SECURITY AND 13. DATA VERIFICATION (“Geology and Exploration Sections”) of the report titled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated March 7th, 2011.

 

8.              As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the Technical Report not misleading.

 

9.              By virtue of my employment with Yamana Gold Inc since March 2004, I am not independent of the issuer. I also beneficially own securities in Yamana Gold Inc.

 

10.       I have read NI 43-101 and Form 43-101 F1, and this Technical Report has been prepared in compliance with that instrument and form.

 

11.       I consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them for regulatory purposes, including electronic publication in the public company files on their websites accessible by the public, of the Technical Report.

 

Dated this 7th day of March, 2011.

 

 

(Signed)

 

Sergio Brandão Silva, PGeo.

 

206



 

Gregory W. Walker, P.G.

Yamana Gold Inc.

Telephone: (775) 850-3700 ext. 3726

Fax: (775) 850-3756

E-mail: greg.walker@yamana.com

 

CERTIFICATE of QUALIFIED PERSON

 

I, Gregory W. Walker, do hereby certify that:

 

1.                                     I hold the position of Senior Manager Resource Estimation with Meridian Gold Company, a wholly owned subsidiary of Yamana Gold Inc and I am responsible for overseeing all exploration resource modeling for the Company, which includes the Suruca property. My current office address is 4635 Longley Lane Unit 110, Suite 4A, Reno Nevada, USA, 89502.

 

2.                                     I graduated with a Bachelor of Science degree in Geological Engineering, 1983, Montana College of Mineral Science and Technology.

 

3.                                     I am a licensed Professional Geologist in good standing in the State of Utah (#5326374-2250). I am also an SME Registered Member (#3361570) in good standing.

 

4.             I have been practicing as a professional mining geologist since 1983.

 

5.                                     By reason of my education, experience and professional registration, I fulfill the requirements of a qualified person as set out in the National Instrument 43-101.

 

6.             I have not visited the Suruca Project site in person.

 

7.                                     I have supervised the preparation of the Mineral Resources (section 16.1.2) of section 16. Mineral Resource and Mineral Reserve Estimates of the report titled “Chapada Mine and Suruca Project Goias State, Brazil, Technical Report” pursuant to National Instrument 43-101 of the Canadian Securities Administrators, dated March 7, 2011.

 

8.                                     As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the Technical Report not misleading.

 

9.                                     By virtue of my employment with Meridian Gold Company since August 1997, a wholly owned subsidiary of Yamana Gold Inc since October 2007, I am not independent of the issuer.

 

10.                              I have read National Instrument 43-101 and Form 43-101 F1, and the Technical Report has been prepared in compliance with that instrument and form.

 

11.                              I consent to the filing of the Technical Report with any stock exchange and other regulatory authority and any publication by them for regulatory purposes, including electronic publication in the public company files on their websites accessible by the public, of the Technical Report.

 

Dated this 7th day of March, 2011.

 

 

(Signed & Sealed)

 

Gregory W. Walker, P.G.

 

207



 

Emerson Ricardo Re, MAusIMM.

Yamana Gold Inc.

Telephone: +55 2163 8359

Fax: +55 2163  8324

E-mail: emerson.re@yamana.com

 

CERTIFICATE of QUALIFIED PERSON

 

I, Emerson Ricardo Re, do hereby certify that:

 

1.                                     I hold the position of Resource and Reserves Corporative Manager with Yamana Gold Inc and I am responsible for manager the resources and reserves works in Brazil and Argentina, which include Chapada Mine. My current office address is Rua Funchal, 411, 4º Andar, São Paulo, SP, Brazil, CEP04551-060.

 

2.                                     I have degree in Bachelor of Science in Honours Geology, 1999, University of São Paulo State (UNESP) and Master of Science in Mining Engineering, 2002, Polytechnic School University of Sao Paulo (Poll - USP)

 

3.             I am practising member of the Australasian Institute of Mining and Metallurgy (#305892)

 

4.                                     I have been practising as a professional geologist since 2000 and resource and reserve geologist since 2002.

 

5.                                     By reason of my education, experience and professional registration I fulfill the requirements of a qualified person as set out in National Instrument 43101 (“43101”)

 

6.                                     I have visited the Chapada Mine and Suruca Property site in person in a number of occasions as resource and reserve manager. My most recent visit was in January 25 - 28, 2011.

 

7.                                     I have been responsible for the preparation of the sections 16.1.1 MINERAL RESOURCE ESTIMATE of the report titled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report pursuant to National Instrument 43-101 of the Canadian Securities Administrators”, dated March, 7th, 2011.

 

8.                                     As of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all scientific and technical information required to be disclosed to make the Technical Report not misleading.

 

9.                                     By virtue of my employment with Yamana Gold Inc since September 2010, I am not independent of the issuer. I also beneficially own securities in Yamana Gold Inc.

 

10.                              I have read NI 43-101 and Form 43-101F1, and this Technical Report has been prepared in compliance with that instrument and form.

 

11.                              I consent to the filing of this Technical Report with any stock exchange and other regulatory authority and any publication by them for regulatory purposes, including electronic publication in the public company files on their websites accessible by the public, of the Technical Report.

 

Dated this 7th day of March, 2011.

 

 

(Signed)

 

Emerson Ricardo Re, MAusIMM

 

208



 

Certificate of Homero Delboni, Jr

 

As a qualified person responsible for preparing or supervising the preparation of the technical report entitled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report Pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated as of March 7, 2011, I hereby certify as follows:

 

(a)         My name is Homero Delboni Junior of business address at Rua Cel. Raul Humaitá Vila Nova, 44/61, São Paulo, Brasil, and I am a Professional Engineer and Director of HDA Serviços S/S Ltda.

 

(b)         This certificate relates to the technical report entitled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report Pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated March 7, 2011.

 

(c)          I am qualified as a Professional Engineer. I have practiced my profession continuously since graduation in 1983. I am a member in good standing of CANADIAN INSTITUTE OF MINING METALLURGY AND PETROLEUM n° 144235, and AusIMM n° 112813 AUSTRALIAN INSTITUTE OF MINING AND METALLURGY. I am a “qualified person” for the purposes of National Instrument 43-101.

 

(d)         I have personally visited the Chapada property several times during 2005-2008 for assessing the plant operation. I have conducted two comprehensive surveys at the Chapada property, the most recent for 10 days during December 2009. These included crushing/grinding/flotation circuit surveys, supervised the sample treatment, tested the various ore types for comminution, modelled and simulated its operation.

 

(e)          I am independent of Yamana Gold Inc. within the meaning of National Instrument 43-101.

 

(f)           My prior involvement with the Chapada property includes: (a) designing the grinding circuit for the Chapada industrial plant, as described in the report “Grinding Circuit Design for Chapada Deposit”, reference: HDA/YM 01.02.04, prepared for Yamana Desenvolvimento Mineral S.A., issued in April, 2004, (b) optimization of the blasting/crushing/grinding circuits, as described in the report (in Portuguese) “Mine-to-Mill na MMIC”, reference RPT HDA/MMIC 02/07 — Rev.2, prepared for Mineração Maracá Industria e Comércio Ltda. / Yamana Gold Inc., issued in August 2007, and Suruca property includes: (a) Comminution parameters characterization for Suruca target — Rev 1 issued in July, 2010.

 

(g)          I am responsible for the preparation of section 15 of the technical report.

 

(h)         I have read National Instrument 43-101 and the technical report has been prepared in compliance with National Instrument 43-101.

 

(i)             As of the date of this certificate, to the best of my knowledge, information and belief, the technical report contains all scientific and technical information that is required to be disclosed to make the technical report not misleading.

 

Signed as of March 7th, 2011

 

 

(Signed)

 

Homero Delboni, Jr

 

Senior Consultant of HDA Serviços S/S Ltda

 

209



 

As auditor in this report, on mineral reserves of Yamana Gold Inc. in the state of Goias, Brazil, I Raúl Contreras G. do certify that:

 

1.                                     I am a senior engineer with Metálica Consultores de Mineracao Brasil Ltda, Belo Horizonte — MG, Brasil, of Metálica Consultores S.A. of 78 Evaristo Lillo street, Las Condes, Santiago, Chile, phone number (56) (02) 290-6969.

 

2.                                     This certificate applies to the Technical Report titled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report Pursuant to National Instrument 43-101 of the Canadian Securities Administrators”, dated March 7th, 2011.

 

3.                                     I hold the following academic qualifications:

 

·      Mining Engineering, University of La Serena - Chile,1978

 

·      Civil Mining Engineering, University of Santiago - Chile,1983

 

· Master’s Degree in Business Management and Administration, University of Chile, 2002

 

4.                                     I am a Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM # 211642), a professional association as defined by NI 43-101.

 

5.                                     I have worked in the minerals industry as an engineer continuously since 1983, a period of 27 years. I have also worked as Professor part time at the University of Santiago of Chile (1986-1987 and 2009) where I taught classes in open pit mine planning and evaluation of mineral deposits. I was employed as an engineer and manager of BHPBilliton, Cerro Colorado Mine, Chile from 1992 to 2006

 

6.                                     I am familiar with NI 43-101 and, by reason of education, experience and professional registration, I fulfill the requirements of a Qualified Person as defined in N143-101.

 

7.                                     I have read NI 43-101 and this Technical Report has been prepared in compliance with the instrument.

 

8.                                     I am responsible for section 16.2 of the Technical Report. I visited the Chapada property during February 1-2, 2011 to review conditions at the site.

 

9.                                     I am independent of the issuers for which this report is required.

 

10.                              That, as of the date of this certificate, to the best of my knowledge, information and belief, the Technical Report contains all the scientific and technical information that is required to be disclosed to make this Technical Report not misleading.

 

11.                             I consent to the filing of this report with any Canadian stock exchange or securities regulatory authority, and any publication,by them of the report.

 

Dated this 7th day of March, 2011

 

(Signed)

 

Raúl Contreras G., MAusIMM

 

210



 

Renato Aurélio Petter

Telephone: +55 11 21638357

E-mail: rpetter@yamana.com

 

Certificate of Qualified Person

 

As a qualified person responsible for preparing or supervising the preparation of the technical report entitled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated as of March 7th, 2011, I hereby certify as follows:

 

(a)           My name is Renato Petter of business address at Funchal 411, São Paulo, Brasil, and I am a Professional Engineer and the Director of Technical Services at Yamana Gold Inc.

 

(b)           This certificate relates to the technical report entitled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated as of March 7th, 2011.

 

(c)           I am qualified as a Professional Engineer. I have practiced my profession continuously since graduation. I am a member in good standing of CANADIAN INSTITUTE OF MINING METALLURGY AND PETROLEUM nº 141768, and MAusIMM nº 209012 AUSTRALIAN INSTITUTE OF MINING AND METALLURGY. I am a “qualified person” for the purposes of National Instrument 43-101.

 

(d)           My most recent personal inspection of the Chapada and Suruca property was in August 2010, and the duration of my visited was for four days.

 

(e)           I am responsible for the sections of the study: 1: Executive Summary, 2: Introduction, 14: Adjacent Properties, 17: Other relevant data and Information, 18: Interpretations and Conclusions, 19: Recommendations, 21.1: Mining Operations, 21.2: Recoverability, 21.3: Production Scheduling Integrated, 21.4: Contracts, 21.5: Environmental, 21.6: Financial Analysis of the report titled “Chapada Mine and Suruca Project, Goias State, Brazil, Technical Report pursuant to National Instrument 43-101 of the Canadian Securities Administrators” dated March 7th, 2011.

 

(f)            I am not independent of Yamana Gold Inc. within the meaning of National Instrument 43-101.

 

(g)           My prior involvement with the Chapada and Suruca property includes periodical technical revisions.

 

(h)           By virtue of my employment with Yamana Gold Inc since January 2006, I am not independent of the issuer. I also beneficially own securities in Yamana Gold Inc.

 

(i)            I have read National Instrument 43-101 and the technical report has been prepared in compliance with National Instrument 43-101.

 

(j)            As of the date of this certificate, to the best of my knowledge, information and belief, the technical report contains all scientific and technical information that is required to been disclosed to make the technical report not misleading.

 

Signed as of March 7th, 2011.

 

(Signed)

 

Renato Petter, P.Eng.

 

Director, Technical Services

 

211



 

APPENDIX A

 

GRAPHIC

 

212



 

GRAPHIC

 

213