Cheyenne Prairie

Construction of Cheyenne Prairie, a 132 MW natural gas-fired electric generating facility, by us and Cheyenne Light is expected to cost approximately $222.0 million, exclusive of financing costs. Construction is expected to be completed by September 30, 2014. As of March 31, 2013, committed contracts for equipment purchases and for construction were 28% and 13% complete, respectively.

Oil Creek Fire

On June 29, 2012, a forest and grassland fire occurred in the western Black Hills. We subsequently received written damage claims from the State of Wyoming and one landowner seeking recovery for alleged injury to timber, grass, fencing, fire suppression and rehabilitation costs of approximately $8.0 million. On April 16, 2013, thirty-four private landowners filed suit in United States District Court for the District of Wyoming, asserting similar claims, based upon allegations of negligence, common law nuisance and trespass. The suit seeks recovery of both actual and exemplary damages in an unspecified amount. Our investigation into the cause and origin of the fire is pending. We expect to deny and will vigorously defend all claims arising out of the lawsuit, pending the completion of our investigation. Given the uncertainty of litigation, however, a loss related to the fire and the litigation is reasonably possible. We cannot reasonably estimate the amount of a potential loss because our investigation is ongoing. Further claims may be presented by other parties. Although we cannot predict the outcome of our investigation or the viability of alleged claims, based on information currently available, management believes that any such claims, if determined adversely to us, will not have a material adverse effect on our financial condition or results of operation.