EX-99.7 8 ndm_ex997.htm ADDITIONAL EXHIBITS ndm_ex997
 
 EXHIBIT 99.7
 
 
 
 
 
 
 
 
 
ANNUAL INFORMATION FORM
 
 
FOR THE YEAR ENDED DECEMBER 31, 2020
 
 
This annual information form ("AIF") is as of March 31, 2021
 
 
 
 
 
 
 
 

 
Item 1.    Table of Contents
 
Page
 
Item 1.
Table Of Contents
2
Item 2.
Preliminary Notes
3
Item 3.
Corporate Structure
11
Item 4.
General Development Of The Business
11
Item 5.
Description Of Business
16
Item 6.
Dividends
44
Item 7.
Description Of Capital Structure
44
Item 8.
Market For Securities
44
Item 9.
Escrowed Securities
45
Item 10
Directors And Officers
45
Item 11.
Promoters
53
Item 12.
Legal Proceedings
53
Item 13.
Interest Of Management And Others In Material Transactions
56
Item 14.
Transfer Agent And Registrar
56
Item 15.
Material Contracts
56
Item 16.
Interests Of Experts
56
Item 17.
Additional Information
57
Item 18.
Disclosure For Companies Not Sending Information Circulars
57
Item 19.
Audit And Risk Committee, Auditor Fees, Exemptions, Code Of Ethics
57
Appendix A - Audit And Risk Committee Charter
60
 
 
 
 
 
 
 
 
 

 
Item 2.           Preliminary Notes
 
This AIF contains "forward-looking information" within the meaning of applicable Canadian securities legislation. Wherever possible, words such as "plans", "expects", or "does not expect", "budget", "scheduled", "estimates", "forecasts", "anticipate" or "does not anticipate", "believe", "intend" and similar expressions or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, have been used to identify forward-looking information.
 
Forward-looking information in this AIF include, without limitation, statements regarding:
 
● our expectations regarding the potential for securing the necessary permits for a mine at the Pebble Project and our ability to establish that such a permitted mine can be economically developed;
 
● the success of our appeal of the record of decision (“ROD”) of the United States Army Corps of Engineers (the "USACE") denying the issuance of certain permits required for the Pebble Project ROD;
 
● our ability to successfully apply for and obtain the federal and state permits required for the Pebble Project under the Clean Water Act ("CWA"), the National Environmental Policy Act ("NEPA"), and relevant legislation;
 
● the outcome of the US government investigations involving the Company;
 
● our ability to successfully defend against purported class action lawsuits that have been commenced against us;
 
● our plan of operations, including our plans to carry out and finance exploration and development activities;
 
● our ability to raise capital for exploration and development activities and meet our working capital requirements;
 
● our expected financial performance in future periods;
 
● our expectations regarding the exploration and development potential of the Pebble Project;
 
● the outcome of the legal proceedings in which we are engaged;
 
● the uncertainties with respect to the effects of COVID-19; and
 
● factors relating to our investment decisions.
 
Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. We believe that the assumptions and expectations reflected in such forward-looking information are reasonable.
 
Key assumptions upon which the Company’s forward-looking information are based include:
 
● our appeal of the ROD of the USACE will be successful;
 
● that we will ultimately be able to demonstrate that a mine at the Pebble Project can be economically developed and operated in an environmentally sound and socially responsible manner, meeting all relevant federal, state and local regulatory requirements so that we will be ultimately able to obtain permits authorizing construction of a mine at the Pebble Project;
 
● that we will be able to secure sufficient capital necessary for continued environmental assessment and permitting activities and engineering work which must be completed prior to any potential development of the Pebble Project which would then require engineering and financing in order to advance to ultimate construction;
 
● that the COVID-19 outbreak will not materially impact or delay our ability to obtain permitting for a mine at the Pebble Project;
 
 
2020 Annual Information Form
Page | 3
 
 
 
 


● that we will ultimately be able to demonstrate that a mine at the Pebble Project will be economically feasible based on a mine plan for which permitting can be secured;
 
● that the market prices of copper, gold, molybdenum, rhenium and silver will not decline significantly or stay depressed for a lengthy period of time;
 
● that key personnel will continue their employment with us; and
 
● that we will continue to be able to secure adequate financing on acceptable terms.
 
Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions, which may have been used. Forward looking statements are also subject to risks and uncertainties facing our business, any of which could have a material impact on our outlook.
 
Some of the risks and uncertainties that could cause actual results to differ materially from those expressed in the forward-looking statements include:
 
● we may be unsuccessful in our appeal of the ROD with respect to the decision to deny the issuance of many of the permits which we require to operate a mine at the Pebble Project;
 
● an inability to ultimately obtain permitting for a mine at the Pebble Project;
 
● an inability to establish that the Pebble Project may be economically developed and mined or contain commercially viable deposits of ore based on a mine plan for which government authorities are prepared to grant permits;
 
● we may not be successful in defending shareholder securities litigation claims that have been filed against us in the US and in Canada;
 
● the uncertainty of the outcome of current or future government investigations and inquiries, including but not limited to, matters before the U.S. Department of Justice and the Securities and Exchange Commission;
 
● government efforts to curtail the COVID-19 pandemic may delay the Company in completion of its work relating to this permitting process;
 
● our ability to obtain funding for working capital and other corporate purposes associated with advancement of the Pebble Project
 
● an inability to continue to fund exploration and development activities and other operating costs;
 
● our actual operating expenses may be higher than projected;
 
● the highly cyclical nature of the mineral resource exploration business;
 
● the pre-development stage economic viability and technical uncertainties of the Pebble Project and the lack of known reserves on the Pebble Project;
 
● an inability to recover even the financial statement carrying values of the Pebble Project if we cease to continue on a going concern basis;
 
● the potential for loss of the services of key executive officers;
 
● a history of, and expectation of further, financial losses from operations impacting our ability to continue on a going concern basis;
 
● the volatility of gold, copper, molybdenum, silver and rhenium prices and the share prices of mining companies;
 
● the inherent risk involved in the exploration, development and production of minerals, and the presence of unknown geological and other physical and environmental hazards at the Pebble Project;
 
 
2020 Annual Information Form
Page | 4
 
 
 


● the potential for changes in, or the introduction of new, government regulations relating to mining, including laws and regulations relating to the protection of the environment and project legal titles;
 
● potential claims by third parties to titles or rights involving the Pebble Project;
 
● the uncertainty of the outcome of current or future litigation including but not limited to, the appeal of the ROD denying the issuance of permits required to operate a mine at the Pebble Project;
 
● the possible inability to insure our operations against all risks;
 
● the highly competitive nature of the mining business;
 
● the potential equity dilution to current shareholders due to any future equity financings or from the exercise of share purchase options and warrants to purchase the Company’s shares;
 
● that we have never paid dividends and will not do so in the foreseeable future.
 
This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements or information. Forward-looking statements or information are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements or information due to a variety of risks, uncertainties and other factors, including, without limitation, the risks and uncertainties described above. See "Risk Factors" on page 35.
 
Our forward-looking statements are based on the reasonable beliefs, expectations and opinions of management on the date of this AIF. Although we have attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There is no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should appreciate the inherent uncertainty of, and not place undue reliance on, forward-looking information. We do not undertake to update any forward-looking information, except as, and to the extent required by, applicable securities laws.
 
Incorporation of Continuous Disclosure Documents by Reference
 
In this AIF, the "Company" or "Northern Dynasty" refers to Northern Dynasty Minerals Ltd. and all its subsidiaries and affiliated partnerships together unless the context states otherwise.
 
Currency and Metric Equivalents
 
All dollar amounts are expressed in Canadian dollars unless otherwise indicated. The Company’s accounts are maintained in Canadian dollars. The daily rate of exchange on December 31, 2020, as reported by the Bank of Canada for the conversion of one Canadian dollar into one United States dollar ("U.S. dollar"), was $1.2732.
 
On March 30, 2021, the rate of exchange of the Canadian Dollar, based on the daily rate in Canada as published by the Bank of Canada, was US$1.00 = $1.2631. Exchange rates published by the Bank of Canada, available on its website www.bankofcanada.ca, are nominal quotations - not buying or selling rates - and intended for statistical or analytical purposes.
 
 
2020 Annual Information Form
Page | 5
 
 
 

 
The following tables set out the exchange rates, based on the daily rates in Canada as published by the Bank of Canada for the conversion of Canadian Dollars into U.S. dollars.
 
 
Year Ended December 31
(Canadian Dollars per U.S. Dollar)
 
2020
2019
2018
2017
Rate at end of year
$1.2732
$1.2988
$1.3642
$1.2545
Average rate for year
$1.3415
$1.3269
$1.2957
$1.2986
High for year
$1.4496
$1.3600
$1.3642
$1.3743
Low for year
$1.2718
$1.2988
$1.2288
$1.2128
 
Monthly High and Low Daily Exchange Rate (Canadian Dollar per U.S. Dollar)
Month or Period
High
Low
March 2021 (to March 30, 2021)
$1.2668
$1.2455
February 2021
$1.2828
$1.2530
January 2021
$1.2824
$1.2627
December 2020
$1.2952
$1.2718
November 2020
$1.3318
$1.2965
 
For ease of reference, the following factors for converting metric measurements into Imperial equivalents are as follows:
 
Metric Units
Multiply by
Imperial Units
hectares
2.471
= acres
metres
3.281
= feet
kilometres
0.621
= miles (5,280 feet)
grams
0.032
= ounces (troy)
tonnes
1.102
= tons (short) (2,000 pounds)
grams/tonne
0.029
= ounces (troy)/ton
 
 
2020 Annual Information Form
Page | 6
 
 
 
 

 
Glossary
 
In this AIF the following terms have the meanings set forth herein:
 
Regulatory Terms:
 
Term
Meaning
CWA
United States Clean Water Act
CWA 404 Permit Application
The permit application filed by the Pebble Partnership with the USACE pursuant to Section 404 of the CWA
EPA
United States Environmental Protection Agency
LEDPA
The "least environmentally damaging practicable alternative" under the CWA
NEPA
National Environmental Policy Act
Pebble EIS
The final environmental impact statement for the Pebble Project published by the USACE on July 24, 2020
Record of Decision
The record of decision of the USACE in respect of the Pebble Project issued by the USACE on November 25, 2020
USACE
United States Army Corps of Engineers
 
Technical Terms:
 
Term
Meaning
Alkalic
Igneous rock containing a relatively high percentage of sodium and potassium feldspar; alteration can also introduce alkali minerals.
Argillic
Hydrothermal alteration of wall rock that forms clay minerals including kaolinite, smectite, illite and other species.
CuEQ
Copper Equivalent
Comminution
Reduction of solid materials from one average particle size to a smaller average particle size by crushing, grinding, cutting, vibrating, or other means.
Deportment
Assessment of how minerals contribute to grade, as each mineral is likely to behave differently to comminution, flotation or leaching.
Diorite
Grey to dark-grey igneous intrusive rock of intermediate composition, composed principally of plagioclase feldspar along with biotite, hornblende and/or pyroxene.
Element Abbreviations
Au - Gold; Ag - Silver; Al - Aluminum; Cu - Copper; Fe - Iron; Mo - Molybdenum; Na - Sodium; O - Oxygen; Pb - Lead; Re - Rhenium; S - Sulphur; Zn - Zinc.
Geometallurgy
Practice of combining geology and/or geostatistics with metallurgy.
Graben
Down-dropped block of land bordered by faults.
Granodiorite
Medium- to coarse-grained acid igneous rock with quartz (>20%), plagioclase and alkali feldspar, commonly with minor hornblende and/or biotite.
Hypogene
Processes below the earth's surface which, in mineral deposits, result in precipitation of primary minerals like sulphides.
Hydrothermal mineral deposit
Any concentration of metallic minerals formed by the precipitation of solids from hot waters (hydrothermal solution). The solutions may be sourced from a magma or from deeply circulating water heated by magma.
Illite Pyrite
Alteration zone with significant amounts of illite – a clay mineral and pyrite – an iron sulphide mineral.
Intrusion (batholith, dyke, pluton)
Medium to coarse grained igneous bodies that crystallized at depth within the Earth's crust. Large intrusive bodies are called batholiths; smaller bodies are plutons and linear bodies are dykes.
Leached Cap
Rock that originally contained mineralization that was subsequently removed due to weathering processes.
Locked Cycle Test
A repetitive batch flotation test used in mineral processing laboratories while developing a metallurgical flowsheet.
Monzonite
Igneous intrusive rock with approximately equal amounts of plagioclase and alkali feldspar, and less than 5% quartz by volume.
National Instrument 43-101 ("NI 43-101")
The Canadian securities instrument which establishes disclosure standards for mineral projects held by Canadian publicly-traded resource companies.
K Silicate
Alteration zone with significant potassium (K) bearing silicate minerals.
Kriging
A method of estimation of a variable value (such as metal grade) at an unmeasured location from measured values, weighted by distance and orientation, at nearby locations.
Porphyry deposit
A type of mineral deposit genetically related to igneous intrusions in which ore minerals are widely distributed, generally of low grade but commonly of large tonnage.
Potassic
Hydrothermal alteration that results in the production of potassium-bearing minerals such as biotite, muscovite or sericite, and/or orthoclase.
Preliminary Economic Assessment
A study that includes an economic analysis of the potential viability of mineral resources but that does not meet the definition of either a “pre-feasibility study” or a “feasibility study”, as such terms are defined under Canadian Institute of Mining and Metallurgy ("CIM") Definitions below. It is a term defined under NI 43-101.
Pyrophyllite
Aluminosilicate hydroxide mineral that forms as a result of hydrothermal alteration or low grade metamorphism.
QSP
Quartz Sericite Pyrite; an alteration zone.
Sericite
 Alteration zone with significant sericite, a fine-grained version of the mica mineral muscovite.
Sodic Potassic
Alteration zone with significant sodium (Na) and potassium (K) bearing minerals
 
 
2020 Annual Information Form
Page | 7
 
 
 

 
 
Term
Meaning
Sodic
In this report, refers to a type of hydrothermal alteration that contains sodium-bearing minerals, most commonly albite feldspar.
Subduction
Process by which one tectonic plate moves under another tectonic plate.
Supergene
Refers to processes that occur relatively near the surface of the earth which modify or destroy original (hypogene) minerals by oxidation and chemical weathering.
Superterrane
A group of physically connected and related geological terranes (group of related rock units).
 
Canadian Mineral Property Disclosure Standards and Resource Estimates
 
The discussion of mineral deposit classifications in this AIF uses the certain technical terms presented below as they are defined in accordance with the CIM Definition Standards on mineral resources and reserves (the "CIM Definition Standards") adopted by the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM Council"), as required by NI 43-101. The following definitions are reproduced from the latest version of the CIM Standards, which were adopted by the CIM Council on May 10, 2014 (the "CIM Definitions"). Estimated mineral resources fall into two broad categories dependent on whether the economic viability of them has been established and these are namely "resources" (potential for economic viability) and "reserves" (viable economic production is feasible). Resources are sub-divided into categories depending on the confidence level of the estimate based on level of detail of sampling and geological understanding of the deposit. The categories, from lowest confidence to highest confidence, are inferred resource, indicated resource and measured resource. The Company does not claim to have any reserves at this time. The CIM definitions are as follows:
 
Term
Definition
Mineral Resource
A concentration or occurrence of solid material of economic interest in or on the Earth’s crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a mineral resource are known, estimated or interpreted from specific geological evidence and knowledge, including sampling.
Measured Mineral Resource
That part of a mineral resource for which quantity, grade or quality, densities, shape, and physical characteristics are estimated with confidence sufficient to allow the application of modifying factors to support detailed mine planning and final evaluation of the economic viability of the deposit. Geological evidence is derived from detailed and reliable exploration, sampling and testing and is sufficient to confirm geological and grade or quality continuity between points of observation. A measured mineral resource has a higher level of confidence than that applying to either an Indicated mineral resource or an inferred mineral resource. It may be converted to a proven mineral reserve or to a probable mineral reserve.
Indicated Mineral Resource
That part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with sufficient confidence to allow the application of modifying factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation. An indicated mineral resource has a lower level of confidence than that applying to a measured mineral resource and may only be converted to a probable mineral reserve.
 
 
2020 Annual Information Form
Page | 8
 
 
 

 
 
Term
Definition
Inferred Mineral Resource
That part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred mineral resource has a lower level of confidence than that applying to an indicated mineral resource and may not be converted to a mineral reserve. It is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued exploration.
Mineral Reserve
The economically mineable part of a measured and/or indicated mineral resource. It includes diluting materials and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at pre-feasibility or feasibility level as appropriate that include application of modifying factors. Such studies demonstrate that, at the time of reporting, extraction could reasonably be justified. The reference point at which mineral reserves are defined, usually the point where the ore is delivered to the processing plant, must be stated. It is important that, in all situations where the reference point is different, such as for a saleable product, a clarifying statement is included to ensure that the reader is fully informed as to what is being reported. The public disclosure of a mineral reserve must be demonstrated by a pre-feasibility study or feasibility study.
Proven Mineral Reserve
The economically mineable part of a measured mineral resource. A proven mineral reserve implies a high degree of confidence in the modifying factors.
Probable Mineral Reserve
The economically mineable part of an indicated, and in some circumstances, a measured mineral resource. The confidence in the modifying factors applying to a probable mineral reserve is lower than that applying to a proven mineral reserve.
Modifying Factors
Considerations used to convert mineral resources to mineral reserves. These include, but are not restricted to, mining, processing, metallurgical, infrastructure, economic, marketing, legal, environmental, social and governmental factors.
Feasibility Study
A comprehensive technical and economic study of the selected development option for a mineral project that includes appropriately detailed assessments of applicable modifying factors together with any other relevant operational factors and detailed financial analysis that are necessary to demonstrate, at the time of reporting, that extraction is reasonably justified (economically mineable). The results of the study may reasonably serve as the basis for a final decision by a proponent or financial institution to proceed with, or finance, the development of the project. The confidence level of the study will be higher than that of a pre-feasibility study.
Pre-feasibility Study
A comprehensive study of a range of options for the technical and economic viability of a mineral project that has advanced to a stage where a preferred mining method, in the case of underground mining, or the pit configuration, in the case of an open pit, is established and an effective method of mineral processing is determined. It includes a financial analysis based on reasonable assumptions on the modifying factors and the evaluation of any other relevant factors which are sufficient for a qualified person, acting reasonably, to determine if all or part of the mineral resource may be converted to a mineral reserve at the time of reporting. A pre-feasibility study is at a lower confidence level than a feasibility study.
 
 
2020 Annual Information Form
Page | 9
 
 
 

 
 
Cautionary Notes to United States Investors Concerning Canadian Mineral Property Disclosure Standards
 
As a Canadian issuer, Northern Dynasty is required to comply with reporting standards in Canada that require that we make disclosure regarding our mineral properties, including any estimates of mineral reserves and resources, in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. In accordance with NI 43-101, the Company uses the terms mineral reserves and resources as they are defined in accordance with the CIM Definition Standards on mineral reserves and resources adopted by the Canadian Institute of Mining, Metallurgy and Petroleum.
 
 
The United States Securities and Exchange Commission (the "SEC") has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the US Exchange Act (the "SEC Modernization Rules") with compliance required for the first fiscal year on or after January 1, 2021. The SEC Modernization Rules have replaced the historical property disclosure requirements for mining registrants that were included in SEC Industry Guide 7 ("Guide 7").
 
 
The SEC Modernization Rules include the adoption of definitions of the following terms, which are substantially similar to the corresponding terms under the CIM Definition Standards that are presented above under "Canadian Mineral Property Disclosure Standards and Resource Estimates":
 
●        mineral resource;
 
●        indicated mineral resource;
 
●        inferred mineral resource;
 
●        mineral reserve;
 
●        proven mineral reserve;
 
●        probable mineral reserve;
 
●        modifying factors;
 
●        feasibility study; and
 
●        preliminary feasibility study (or "pre-feasibility study").
 
As a result of the adoption of the SEC Modernization Rules, the SEC will now recognize estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources". In addition, the SEC has amended its definitions of "proven mineral reserves" and "probable mineral reserves" to be substantially similar to the corresponding CIM Definitions.
 
Northern Dynasty is not required to provide disclosure on our mineral properties, including the Pebble Project, under the SEC Modernization Rules as we are presently a "foreign issuer" under the US Exchange Act and entitled to file continuous disclosure reports with the SEC under the Multi-Jurisdictional Disclosure System ("MJDS") between Canada and the United States. Accordingly, we anticipate that we will be entitled to continue to provide disclosure on our mineral properties, including the Pebble Project, in accordance with NI 43-101 disclosure standards and CIM Definition Standards. However, if we either cease to be a "foreign issuer" or cease to be entitled to file reports under the MJDS, then we will be required to provide disclosure on our mineral properties under the SEC Modernization Rules. Accordingly, United States investors are cautioned that the disclosure that we provide on our mineral properties, including the Pebble Project, in the AIF and under our continuous disclosure obligations under the US Exchange Act may be different from the disclosure that we would otherwise be required to provide as a US domestic issuer or a non-MJDS foreign issuer under the SEC Modernization Rules.
 
 
2020 Annual Information Form
Page | 10
 
 
 

 
 
United States investors are cautioned that while the above terms are substantially similar to CIM Definitions, there are differences in the definitions under the SEC Modernization Rules and the CIM Definition Standards. Accordingly, there is no assurance any mineral resources that we may report as "measured mineral resources", "indicated mineral resources" and "inferred mineral resources" under NI 43-101 would be the same had we prepared the resource estimates under the standards adopted under the SEC Modernization Rules.
 
Investors are cautioned not to assume that any "measured mineral resources", "indicated mineral resources", or "inferred mineral resources" that we report in this AIF are or will be economically or legally mineable.
 
Further, "inferred resources" have a great amount of uncertainty as to whether they can be mined legally or economically. In accordance with Canadian securities laws, estimates of "inferred mineral resources" cannot form the basis of feasibility or other economic studies, except in limited circumstances where permitted under NI 43-101.
 
For the above reasons, information contained in this AIF and the documents incorporated by reference herein containing descriptions of our mineral deposits may not be comparable to similar information made public by United States companies subject to the reporting and disclosure requirements under the United States federal securities laws and the rules and regulations thereunder.
 
Item 3. Corporate Structure
 
Northern Dynasty is a mineral exploration company incorporated on May 11, 1983 pursuant to the Company Act of the Province of British Columbia (predecessor statute to the British Columbia Corporations Act in force since 2004), under the name "Dynasty Resources Inc." On November 30, 1983, the Company changed its name to "Northern Dynasty Explorations Ltd." and subsequently, on October 11, 1997, changed its name to Northern Dynasty Minerals Ltd. Northern Dynasty became a reporting company in the Province of British Columbia on April 10, 1984 and was listed on the Vancouver Stock Exchange (now absorbed by the TSX Venture Exchange and herein generally "TSX-V") from 1984-1987, listed on the Toronto Stock Exchange ("TSX") from 1987-1993, and delisted from trading but continued to comply with its continuous disclosure obligations from 1993 to 1994, and thereafter listed on TSX-V from 1994 to October 30, 2007, when it again began trading on the TSX. In November 2004, the common shares of Northern Dynasty were also listed on the American Stock Exchange ("AMEX"). AMEX was purchased by the New York Stock Exchange ("NYSE") and the Company now trades on the NYSE American Exchange ("NYSE American").
 
The head office of Northern Dynasty is located at 1040 West Georgia Street, 15th floor, Vancouver, British Columbia, Canada V6E 4H1, telephone (604) 684-6365, facsimile (604) 684-8092. The Company’s legal registered office is in care of its Canadian attorneys, McMillan LLP, Barristers & Solicitors, at Suite 1500, 1055 West Georgia Street, Vancouver, British Columbia, Canada V6E 4N7, telephone (604) 689-9111, facsimile (604) 685-7084.
 
The Company’s Alaska mineral resource exploration business is operated through a wholly-owned Alaskan registered limited partnership, the Pebble Limited Partnership (the "Pebble Partnership" or "PLP"), in which the Company owns a 100% interest through an Alaskan general partnership, the Northern Dynasty Partnership, which is a partnership formed by two of its subsidiaries. An indirectly wholly-owned subsidiary of the Company, Pebble Mines Corp. is the general partner of the Pebble Partnership and responsible for its day-to-day operations. The business address of the Northern Dynasty Partnership is Suite 505, 3201 C Street, Anchorage, Alaska, USA, 99503.
 
In this AIF, a reference to the "Company" or "Northern Dynasty" includes a reference to PLP and the Company’s wholly-owned subsidiaries and other consolidated interests and entities, unless the context clearly indicates otherwise. Certain terms used herein are defined in the text and others are included in the glossary of this AIF.
 
Item 4. General Development of the Business
 
Company Development
 
 
Northern Dynasty is a mineral exploration company focused on the exploration and advancement towards feasibility, permitting and ultimately development of the Pebble Project, a copper-gold-molybdenum-silver-rhenium mineral project located in southwest Alaska (the "Pebble Project" or the "Project"). The Pebble Project is comprised of mineral claims that are held by subsidiaries of the Pebble Partnership, which is a 100% wholly-owned subsidiary of Northern Dynasty.
 
 
2020 Annual Information Form
Page | 11
 
 
 

 
 
Northern Dynasty acquired a 100% interest the Pebble Project from an Alaskan subsidiary of Teck Resources Limited ("Teck") in a series of transactions from October 2001 through to June 2006. Teck has retained certain royalties in the Pebble Project, as described in detail below under Item 5 – Description of Business.
 
The Pebble Partnership was converted into a limited partnership in July 2007 in connection with a joint venture for the Pebble Project entered into between the Company and an affiliate of Anglo American plc ("Anglo American"). From July 2007 to December 2013, approximately US$573 million was provided to the Pebble Partnership by the affiliate of Anglo American, largely spent on exploration programs, resource estimates, environmental data collection and technical studies, with a significant portion spent on engineering of various possible mine development models and related infrastructure, power and transportation systems. The technical and engineering studies that were completed relating to mine-site and infrastructure development are not considered to be current or necessarily representative of management’s current understanding of the most likely development scenario for the Project. Accordingly, the Company is uncertain whether it can realize significant value from this prior work. Environmental baseline studies and data, as well as geological information from exploration, remain important information available to the Company from this period in continuing its advancement of the Project. Anglo American withdrew from the Pebble Partnership effective December 10, 2013.
 
In December 2017, Northern Dynasty and First Quantum Minerals Ltd. ("First Quantum" or collectively, the "parties") entered into a framework agreement, which contemplated that the parties would execute an option agreement whereby First Quantum could earn a 50% interest in the Pebble Partnership. First Quantum also made a non-refundable early option payment of US$37.5 million to be applied solely for the purpose of progressing permitting of the Pebble Project. On May 25, 2018, the Company announced that the parties had been unable to reach agreement on the option and partnership transaction contemplated in the December 2017 framework agreement, and it was terminated in accordance with its terms.
 
Northern Dynasty holds a 100% interest in the Pebble Partnership and the Pebble Project. Northern Dynasty continues its efforts to secure a partner for the project.
 
To December 31, 2020, approximately $979 million (US$883 million) in expenditures have been incurred on the Pebble Project. In addition, Northern Dynasty has spent approximately $106 million in acquisition costs on the Pebble Project.
 
Northern Dynasty does not have any operating revenue, although currently and historically it has had non-material annual interest revenue as a consequence of investing its surplus funds, and has received consideration for the sale of a net proceeds interest royalty held on a non-core property that was carried at nominal value.
 
Three Year History
 
In February 2014, the US Environmental Protection Agency ("EPA") announced a pre-emptive regulatory action under Section 404(c) the CWA to consider restriction or a prohibition of mining activities associated with the Pebble deposit. From 2014-2017, Northern Dynasty and the Pebble Partnership focused on a multi-dimensional strategy, including legal and other initiatives to ward off this action. These efforts were successful, resulting in the legal agreement with the EPA announced on May 12, 2017, enabling Pebble to enter normal course permitting under the NEPA. On December 22, 2017, the Pebble Partnership filed its 404 wetlands permit application (the “CWA 404 Permit Application”) under the CWA with the USACE, which was “receipted” as complete by USACE on January 5, 2018 and initiated the federal Environmental Impact Statement ("EIS") permitting process for the Pebble Project under NEPA. The permit application included a project description (the "Project Description") that was based on a smaller mine concept developed for the Pebble Project in the latter part of 2017 (see further details in B. Technical Summary - Introduction). The Project Description in the permit application envisages the project developed as an open pit mine and processing facility with supporting infrastructure.
 
The Pebble Project has completed the US NEPA Environmental Impact Statement ("Pebble EIS") process with the final Pebble EIS being published by the USACE on July 24, 2021. The Pebble EIS process required a comprehensive "alternatives assessment" be undertaken to consider a broad range of development alternatives, such that the final project design and operating parameters for the Pebble Project and associated infrastructure may vary significantly from that being advanced. As a result, the Company will continue to consider various development options and no final project design has been selected at this time.
 
 
2020 Annual Information Form
Page | 12
 
 
 

 
 
On March 26, 2020, in accordance with the order of the Governor of Alaska, the Pebble Partnership, along with all other nonessential offices in Alaska, closed its offices for the health and safety of its personnel. Notwithstanding the closure, the Company has maintained its staff and employees to help ensure that the project schedule announced by the USACE for the final EIS remained on track. Technical review meetings were completed before the implementation of the Governor’s order in response to COVID-19.
 
On April 17, 2020, a US federal district court judge in Alaska ruled in favour of the EPA by granting a motion to dismiss a case brought by a collection of litigants opposed to the Pebble Mine that challenged the EPA’s July 2019 decision to formally withdraw its prior regulatory action under Section 404(c) of the CWA. The ruling was based on a determination that the litigants had failed to state a claim upon which relief can be granted. This dismissal has been appealed to the Ninth Circuit Court of Appeals.
 
On May 22, 2020, the USACE announced a development alternative for the Pebble Project as the ‘least environmentally damaging practicable alternative’ or LEDPA for the transportation corridor for the proposed Pebble mine. The LEDPA transportation corridor includes an all land-based transportation route to connect the proposed mine site to a port site on Cook Inlet via an approximate 85-mile road north of Lake Iliamna, thereby avoiding the need for ferry transport across the lake. The transportation corridor, which is referred to as the ‘northern transportation corridor’ and otherwise known and evaluated in the Pebble EIS as ‘Alternative 3’, has been extensively studied by the Pebble Partnership, and the Company believes that this transportation corridor presents several compelling benefits over the alternative lake ferry transportation corridor options. The EPA, in a letter to the USACE dated May 28, 2020, confirmed its view that the northern corridor transportation route was the least environmentally damaging practicable alternative under the EPA’s guidelines.
 
The USACE published the final EIS for the Pebble Project on July 24, 2020. Led by the USACE, the Pebble EIS also involved eight federal cooperating agencies (including the US EPA and US Fish & Wildlife Service), three state cooperating agencies (including the Alaska Department of Natural Resources and the Alaska Department of Environmental Conservation), the Lake & Peninsula Borough and federally recognized tribes.
 
The final Pebble EIS was viewed by the Company as positive in that it found impacts to fish and wildlife would not be expected to affect harvest levels, there would be no measurable change to the commercial fishing industry including prices and there would be a number of positive socioeconomic impacts on local communities.
 
 
2020 Annual Information Form
Page | 13
 
 
 

 
The CWA 404 Permit Application was submitted in December 2017, and the permitting process over the next three years involved the Pebble Partnership being actively engaged with the USACE on the evaluation of the Pebble Project. There were numerous meetings between representatives of the USACE and the Pebble Partnership regarding, among other things, compensatory mitigation for the Pebble Project. The Pebble Partnership submitted several draft compensatory mitigation plans to the USACE, each refined to address comments from the USACE and that the Pebble Partnership believed were consistent with mitigation proposed and approved for other major development projects in Alaska. In late June 2020, USACE verbally identified the “significant degradation” of certain aquatic resources, with the requirement of new compensatory mitigation. The Pebble Partnership understood from these discussions that the new compensatory mitigation plan for the Pebble Project would include in-kind, in-watershed mitigation and continued its work to meet these new USACE requirements.
 
The USACE formally advised the Pebble Partnership by letter dated August 20, 2020 that it had made preliminary factual determinations under Section 404(b)(1) of the CWA that the Pebble Project as proposed would result in significant degradation to aquatic resources. In connection with this preliminary finding of significant degradation, the USACE formally informed the Pebble Partnership that in-kind compensatory mitigation within the Koktuli River watershed would be required to compensate for all direct and indirect impacts caused by discharges into aquatic resources at the mine site. The USACE requested the submission of a new compensatory mitigation plan to address this finding within 90 days of its letter.
 
Based on these requirements, the Pebble Partnership continued with its efforts to develop the new compensatory mitigation plan (the "CMP") to align with the requirements outlined by the USACE as conveyed to the Pebble Partnership. This plan envisioned creation of an 112,445-acre Koktuli Conservation Area on land belonging to the State of Alaska in the Koktuli River watershed downstream of the Project. During the period in which this CMP was developed, the Pebble Partnership continued to confer with the USACE regarding its proposed approach to mitigation. An initial draft of the CMP was submitted to the USACE for an interim review by the USACE in September 2020. The Pebble Partnership then revised the CMP based on the input from the USACE. The objective of the preservation of the Koktuli Conservation Area was to allow the long-term protection of a large and contiguous ecosystem that contains valuable aquatic and upland habitats. If adopted, the Koktuli Conservation Area would preserve 31,026 acres of aquatic resources (wetlands) within the aquatic resource of national importance-designated Koktuli River watershed. The protected resources were designed to address the physical, chemical, and biological functions highlighted by the EPA and US Fish & Wildlife Service. Preservation of the Koktuli Conservation Area was proposed with the objective of minimizing the threat to, and preventing the decline of, aquatic resources in the Koktuli River watershed from potential future actions, and sustaining the fish and wildlife species that depend on these aquatic resources, while protecting the subsistence lifestyle of the residents of Bristol Bay and commercial and recreational sport fisheries. The revised plan was submitted to the USACE on November 4, 2020.
 
On November 25, 2020, the USACE issued the ROD. The ROD rejected the compensatory mitigation plan as “noncompliant” and determined the project would cause “significant degradation” and was contrary to the public interest. Based on this finding, the USACE rejected Pebble Partnership’s permit application under the Clean Water Act.
 
The Pebble Partnership submitted its request for appeal of the ROD (the "RFA") to the USACE Pacific Division on January 19, 2021. The RFA reflects the Pebble Partnership’s position that the USACE's Record of Decision and permitting decision – including its “significant degradation” finding, its ‘public interest review' findings, and its perfunctory rejection of the Pebble Partnership's CMP – are contrary to law, unprecedented in Alaska, and fundamentally unsupported by the administrative record, including the Pebble EIS. The specific reasons for appeal asserted by the Pebble Partnership in the RFA include (i) the finding of “significant degradation” by the USACE is contrary to law and unsupported by the record, (ii) the USACE’s rejection of the compensatory mitigation plan is contrary to the USACE regulations and guidance, including the failure to provide the Pebble Partnership with an opportunity to correct the alleged deficiencies, and (iii) the determination by the USACE that the Pebble Project is not in the public interest is contrary to law and unsupported by the public record.
 
In a letter dated February 24, the USACE confirmed the Pebble Partnership’s RFA is “complete and meets the criteria for appeal.” The USACE has appointed a Review Officer to oversee the administrative appeal process. The appeal process will now move to consideration by the USACE of the merits of the appeal. The appeal will be reviewed by the USACE based on the administrative record and any clarifying information provided, and the Pebble Partnership will be provided with a written decision on the merits of the appeal at the conclusion of the process. The appeal is governed by the policies and procedures of the USACE administrative appeal regulations. While federal guidelines suggest the appeal should conclude within 90 days, the USACE has indicated the complexity of issues and volume of materials associated with Pebble’s case means the review will likely take additional time. There is no assurance that the Company’s appeal of the ROD will be successful or that the required permits for the Pebble Project will ultimately be issued. The permits are required in order that the Pebble Project can be developed as proposed by the Company. If the Pebble Partnership’s administrative appeal of the ROD is successful, then we anticipate that the permitting decision would be remanded back to the USACE’s Alaska District in order that the permitting process would then continue based on the administrative record and the findings and determinations made by the USACE Pacific Division in its appeal decision. There is no assurance that a successful appeal will ultimately result in the issuance of a positive ROD by the USACE Alaska District. If the Pebble Partnership’s administrative appeal is not successful, the Company may seek judicial review of the ROD in the appropriate US District Court.  There is no assurance that any judicial review would be successful in overturning an unsuccessful appellate decision.
 
On January 22, 2021, the State of Alaska, acting in its role as owner of the Pebble lands and subsurface mineral estate, announced that it had also filed a request for appeal. That appeal was rejected on the basis that the State did not have standing to pursue an administrative appeal with the USACE.
 
 
2020 Annual Information Form
Page | 14
 
 
 

 
 
Much of the work by the Company through the Pebble Partnership in 2020, and since 2017 has focused on facilitating and providing support to the federal EIS permitting process. The Company also continued to actively engage and consult with project stakeholders to share information and gather feedback on the Pebble Project, its potential effects and proposed mitigation. In 2018, 2019 and 2020, right-of-way agreements were secured with Alaska Native village corporations and other landowners whose lands cover portions of several proposed transportation and infrastructure routes for the Pebble Project. Opportunities for additional community benefits from development of the project have also been explored, including the Pebble Performance Dividend revenue sharing program for full-time adult residents of Bristol Bay communities, and a Memorandum of Understanding with Alaska Peninsula Corporation announced in July 2020.
 
Corporate activities have been directed toward raising capital to support the EIS process and discussions directed toward securing a partner with which to advance the overall development of the project. Northern Dynasty has completed the following financings and/or raised funds within the past three years in order to fund its business operations:
 
● In December 2017, the Company received a non-refundable early option payment of US$37.5 million as a result of a framework agreement with First Quantum, which was terminated in May 2018.
 
● In December 2018, the Company completed a private placement of 10,150,322 special warrants (the "Special Warrants") at a price of $0.83 (US$0.62) per Special Warrant for aggregate gross proceeds of approximately $8.4 million (US$6.3 million). The Special Warrants converted into common shares on a one-for-one basis without payment of any additional consideration on February 19, 2019.
 
● In 2019 and 2020, the Company completed four two-part financings.
 
● in March 2019, the Company completed:
 
o a bought deal offering of 17,968,750 common shares at US$0.64 per common share for gross proceeds of US$11.5 million ($15.3 million), which included the exercise of an over-allotment option of 2,343,750 common shares for additional gross proceeds of US$1.5 million. The offering was completed pursuant to an underwriting agreement, among the Company and Cantor Fitzgerald Canada Corporation, as lead underwriter and sole bookrunner, and a syndicate of underwriters including BMO Nesbitt Burns Inc., H.C. Wainwright & Co., LLC. and TD Securities Inc. (collectively, the "Underwriters"); and
 
o a private placement of 3,769,476 common shares at $0.86 (US$0.64) per common share for gross proceeds of approximately $3.2 million (US$2.4 million).
 
● in June 2019, the Company completed:
 
o a bought deal offering of 12,200,000 common shares at US$0.41 per common share for gross proceeds of approximately US$5.0 million ($6.6 million). The offering was made through the Underwriters described above. The Underwriters received 244,000 non-transferable common share warrants, each warrant exercisable into one common share of the Company at an exercise price of US$0.41 per common share until June 24, 2020, which were all exercised; and
 
o a private placement of 3,660,000 common shares of the Company at US$0.41 per common share for gross proceeds of approximately US$1.5 million ($2.0 million).
 
● in August 2019, the Company completed:
 
o a bought deal offering of 15,333,334 common shares of the Company at the price of US$0.75 per Offered Share for aggregate gross proceeds of approximately US$11.5 million ($15.3 million); and
 
o a non-brokered private placement to investors outside of the United States of 2,866,665 common shares of the Company at the Issue Price for gross proceeds to the Company of US$2.15 million ($2.8 million).
 
 
2020 Annual Information Form
Page | 15
 
 
 

 
 
● in December 2019 and January 2020, the Company completed:
 
o an underwritten public offering of 41,975,000 common shares at a price of US$0.37 per common share for gross proceeds of approximately US$15.5 million ($20.6 million, completed in December 2019); and
 
o a non-brokered private placement of 13,688,823 common shares of the Company at a price of US$0.37 per common share for gross proceeds of approximately US$5.1 million ($6.7 million, completed in January 2020).
 
● in May 2020, the Company completed:
 
o an underwritten public offering of 14,375,000 common shares at a price of $0.70 per common share for gross proceeds of approximately $10.1 million; and
 
o a non-brokered private placement of 10,357,143 common shares of the Company at a price of $0.70 per common share for gross proceeds of approximately $7.3 million.
 
● in July and August 2020, the Company completed:
 
o an underwritten public offering of 24,150,000 common shares at a price of US$1.46 per common share for gross proceeds of approximately US$35.3 million ($47.6 million, completed in August 2020); and
 
o a non-brokered private placement of 5,807,534 common shares of the Company at a price of US$1.46 per common share for gross proceeds of approximately US$8.6 million ($11.7 million, completed in two tranches in July and August 2020).
 
Item 5. Description of Business
 
A.        The Pebble Project
 
The Company’s business is the exploration and advancement towards feasibility, permitting and ultimately development of the Pebble Project.
 
The Pebble Project Is Subject To State and Federal Laws
 
The Pebble Partnership and its subsidiaries are required to comply with all Alaska statutes in connection with the Pebble Project. These statutes govern titles, operations, environmental, development, operating and generally all aspects of exploration, development and operation of a mine in Alaska.
 
Alaska Statute 38.05.185, among others, establishes the rights to mining claims and mineral leases on lands owned by the State of Alaska and open to mineral entry. This group of statutes also cover annual labor and rental requirements, and royalties.
 
Operations on claims or leases on state owned land must be permitted under a plan of operations as set out in Title 11 of the Alaska Administrative Code, Chapter 86, Section 800. This regulation generally provides that the State Division of Mining can be the lead agency in coordinating the comments of all agencies, which must consent to the issuance of a plan of operations, and sets the requirements for the approval of a plan of operations.
 
Environmental conditions are controlled by Alaska Statute 46.08 (which prohibits release of oil and hazardous substances), Alaska Statute 46.03.060 (which sets water quality standards), and Alaska Statute 46.14 (which sets air quality standards).
 
Once a decision is made to enter permitting, the Pebble Project will be required to satisfy permitting requirements at three levels: federal, state and local (borough). The process takes approximately 3-4 years to complete and involves 11 regulatory agencies, 60+ categories of permits and significant ongoing opportunities for public involvement. The Alaska Department of Natural Resources Large Mine Permitting Team is responsible for coordinating permitting activities for large mine projects.
 
 
2020 Annual Information Form
Page | 16
 
 
 

 
 
To satisfy permitting requirements under NEPA and other regulatory statutes, a project must provide a comprehensive project design and operating plan for mine-site and infrastructure facilities; documentation of development alternatives investigated; mitigation and compensation strategies, and identification of residual effects; and environmental monitoring, reclamation and closure plans. The first step is to provide the required information (including a Project Description and Environmental Baseline Document) for an EIS under NEPA, prepared by a third-party contractor under the direction of a lead federal agency. The EIS determines whether sufficient evaluation of the project's environmental effects and development alternatives has been undertaken. It also provides the basis for federal, state and local government agencies to make individual permitting decisions.
 
Under the CWA, Section 404(c), the Administrator of the EPA is given the right to disallow the specification (including the withdrawal of specification) of any defined area as a disposal site if he or she determines that the release of material at the disposal site will have an unacceptable adverse effect on municipal water supplies, local wildlife, spawning and breeding areas of fisheries, shellfish beds, and/or recreational areas. Such decisions made by the Administrator require notice and opportunity for public hearings, and consultation with the Secretary of the Army. The Administrator shall set forth in writing and make public his or her findings and reasons for making any determination under this subsection.
 
B.        Technical Summary
 
The following disclosure is mainly summarized from the "2021 Technical Report on the Pebble Project, Southwest Alaska, USA" by J. David Gaunt, P.Geo., James Lang, P.Geo., Eric Titley, P.Geo., Hassan Ghaffari, P.Eng., and Stephen Hodgson, P.Eng., effective date February 24, 2021 ("2021 Technical Report"), and updated by Company staff. J. David Gaunt, P.Geo., James Lang, P.Geo., Eric Titley, P.Geo., Hassan Ghaffari, P.Eng., and Stephen Hodgson, P.Eng., are the qualified persons for the 2018 Technical Report and have reviewed and approved the content derived from that report. All qualified persons, other than Hassan Ghaffari, P.Eng., are not independent of Northern Dynasty.
 
Introduction
 
The Pebble deposit was originally discovered in 1989 and was acquired by Northern Dynasty in 2001. Since that time, Northern Dynasty and subsequently the Pebble Partnership have conducted significant mineral exploration, environmental baseline data collection, and engineering work on the Pebble Project to advance it towards development.
 
Since the acquisition by Northern Dynasty, work at Pebble has led to an overall expansion of the Pebble deposit, as well as the discovery of several other mineralized occurrences along an extensive northeast-trending mineralized system underlying the property. Over 1 million feet of drilling has been completed on the property, a large proportion of which has been focused on the Pebble deposit.
 
Comprehensive deposit delineation, environmental, socioeconomic and engineering studies of the Pebble deposit began in 2004 and continued through 2013.
 
Northern Dynasty completed a Preliminary Assessment (now known as a Preliminary Economic Assessment or PEA) on the Pebble Project in February 2011 (“2011 PEA”). After considering stakeholder feedback, Northern Dynasty initiated a broad review of the Pebble Project that took place in 2016 and 2017 to consider , among other things, a smaller project footprint and improved environmental and safety enhancements, and incorporated these and other improvements into a new proposed development concept for the Pebble Project.
 
The Pebble Partnership submitted an application for a CWA 404 permit in December 2017 for the Pebble Project on the basis of a substantially smaller mine facility footprint and with other material revisions than what was envisaged in the 2011 PEA. As a result, the economic analysis included in the 2011 PEA is considered by Northern Dynasty to be out of date such that it can no longer be relied upon. In light of the foregoing, the Pebble Project is no longer an advanced property for the purposes of NI 43-101, as the potential economic viability of the Pebble Project is not currently supported by a preliminary economic assessment, pre-feasibility study or feasibility study.
 
 
2020 Annual Information Form
Page | 17
 
 
 

 
 
The permit application under Section 404 of the CWA and Section 10 of the Rivers and Harbors Act (RHA) was submitted to the USACE by the Pebble Partnership on December 22, 2017. On January 8, 2018, USACE accepted the permitting documentation and confirmed that an EIS level of analysis was required to comply with its NEPA review of the Pebble Project. The EIS process progressed through the scoping phase in 2018. The USACE delivered the draft EIS in the first quarter of 2019 and completed a public comment period from March to July 2019. In the latter part of 2019 and early 2020, the USACE and its consultants advanced toward a final EIS. The preliminary final EIS was circulated to co-operating agencies for review in February 2020. As part of the EIS preparation process, the USACE and its consultants had undertaken a comprehensive alternatives assessment to consider a broad range of development alternatives and announced the conclusions of the draft LEDPA in May 2020. The USACE published the final Pebble EIS on July 24, 2020.  
 
The Pebble Partnership developed the CMP (further described in the Company’s Three Year History above) to align with the requirements outlined by the USACE. The CMP was submitted on November 4, 2021.
 
On November 25, 2020, the USACE issued a ROD rejecting the Pebble Partnership’s permit application. The Pebble Partnership submitted a RFA of the ROD on January 19, 2021. In a letter dated February 24, 2021, the USACE confirmed the Pebble Partnership’s RFA is “complete and meets the criteria for appeal.”
 
Several estimates of the mineral resources in the Pebble Deposit have been done since Northern Dynasty acquired the project in 2001, indicating that the deposit contains significant amounts of copper, gold, molybdenum and silver. In September 2020, Northern Dynasty published a Technical Report on the Pebble Project documenting recent studies of the occurrence of rhenium and an estimate of the rhenium mineral resources in the Pebble deposit. Although previous work also determined significant amounts of palladium are present, at least in parts of the deposit, insufficient analyses have been completed to date to undertake an estimate of the palladium resource. The report also summarized the proposed plan for the project as documented in the June 2020 Project Description and final Pebble EIS.
 
The purpose of the 2021 Technical Report that will be filed with this AIF is to update the current status of the EIS process for the Pebble Project, given the decisions of the USACE. No changes were made to the resource estimate from the September 2020 Technical Report. Information on closure was also added to the Project Description and Permitting section of the 2021 Technical Report.
 
Property Description and Location
 
The Pebble Project is located in southwest Alaska, approximately 200 miles southwest of Anchorage, 17 miles northwest of the village of Iliamna, and approximately 60 miles west of Cook Inlet.
 
 
2020 Annual Information Form
Page | 18
 
 
 

 
 
Figure 1                        Property Location – Pebble Project
 
 
Source: 2018 Technical Report
 
Northern Dynasty holds, indirectly through wholly-owned subsidiaries of the wholly-owned Pebble Partnership, Pebble East Claims Corporation and Pebble West Claims Corporation, a 100% interest in a contiguous block of 2,402 mineral claims covering approximately 417 square miles (which includes the Pebble Deposit) (Figure 2).
 
State mineral claims in Alaska are kept in good standing by performing annual assessment work or in lieu of assessment work by paying $100 per year per 40 acre (0.06 square mile) mineral claim, and by paying annual escalating state rentals. All of the assessment work payment obligations come due annually on or before September 1. Credit for excess work can be banked for a maximum of four years, and can be applied as necessary to continue to hold the claims in good standing. The Project claims have a variable amount of work credit available that can be applied in this way1. State rentals for 2021 are approximately US$1,375,910 and are payable no later than 90 days after the assessment work is due (approximately December 1).
 
The Pebble Partnership currently does not own surface rights associated with the mineral claims that comprise the Pebble property. All lands are held by the State of Alaska, and surface rights may be acquired from the state government once areas required for mine development have been determined and permits awarded. Permits necessary for exploration drilling and other field programs associated with pre-development assessment of the Pebble Project are applied for each year.  Environmental liabilities associated with the Pebble Project include removal of structures, closing monitoring wells, and removal of piezometers. The State of Alaska holds a $2 million bond associated with removal and reclamation of these liabilities.
__________________
1 Annual assessment work obligations for the claims that are part of the current property of US$667,700 are due in 2021.
 
 
2020 Annual Information Form
Page | 19
 
 
 

 
 
Figure 2                   Mineral Claims – Pebble Project
 
 

Source: 2021 Technical Report
 
Northern Dynasty acquired the Pebble property by way of a two-part (Resource Lands and Exploration Lands) purchase option from an Alaskan subsidiary of Teck Cominco Limited (now Teck), which still retains a 4% pre-payback advance net profits royalty interest (after debt service) and 5% after-payback net profits royalty interest in any mine production from the Exploration Lands portion of the Pebble property, as shown on the figure above.
 
In June 2020, the Pebble Partnership established the Pebble Performance Dividend LLP to distribute a 3% Net Profits Royalty Interest in the Pebble Project to adult residents of Bristol Bay villages that have subscribed as participants. The Pebble Performance Dividend will distribute a guaranteed minimum annual payment of US$3 million each year the Pebble mine operates beginning at the outset of project construction.
 
Accessibility, climate, local resources, infrastructure and physiography
 
The Pebble property is located in southwest Alaska. The map shows a proposed infrastructure corridor for the project, as further described as the LEDPA in the Final EIS and the 2021 Technical Report.
 
 
2020 Annual Information Form
Page | 20
 
 
 

 
 
 
Source: 2021 Technical Report
 
Access to the property is typically via air travel from the city of Anchorage, which is situated at the northeastern end of Cook Inlet and is connected to the national road network via Interstate Highway 1 through Canada to the USA. Anchorage is serviced daily by several regularly scheduled flights to major airport hubs in the USA. From Anchorage, there are regular flights to Iliamna through Iliamna Air Taxi. Charter flights may also be arranged from Anchorage. From Iliamna, access to the Pebble property is by helicopter.
 
There are paved roads that connect the villages of Iliamna and Newhalen to the airport and to each other, and a partly paved, partly gravel road that extends to a proposed Newhalen River crossing near Nondalton. The property is currently not connected to any of these local communities by road; a road is planned as part of the project design.
 
There is no access road connecting the communities nearest to the Pebble Project with the coast on Cook Inlet. From the coast, at Williamsport on Iniskin Bay, there is an 18.6-mile state-maintained road that terminates at the east end of Iliamna Lake, where watercraft and transport barges may be used to access Iliamna. The route from Williamsport, over land to Pile Bay on Iliamna Lake, is currently used to transport bulk fuel, equipment and supplies to communities around the lake during the summer months.
 
A small run-of-river hydroelectric installation on the nearby Tazimina River provides power for the three communities (Iliamna, Newhalen and Nondalton) in the summer months. Supplemental power generation using diesel generators is required during winter months.
 
Iliamna and surrounding communities have a combined population of just over 400 people. As such, there is limited local commercial infrastructure except that which services seasonal sports fishing and hunting.
 
The property is situated at approximately 1,000 ft above mean sea level in an area described as subarctic tundra. It is characterized by gently rolling hills and an absence of permafrost. The climate is sufficiently moderate to allow a well-planned mineral exploration program to be conducted year-round at Pebble.
 
 
2020 Annual Information Form
Page | 21
 
 
 

 
 
Geological Setting and Mineralization
 
Pebble is a porphyry-style copper-gold-molybdenum-silver-rhenium deposit that comprises the Pebble East and Pebble West zones of approximate equal size, with slightly lower-grade mineralization in the center of the deposit where the two zones merge. The Pebble deposit is located at the intersection of crustal-scale structures that are oriented both parallel and obliquely to a magmatic arc which was active in the mid-Cretaceous and which developed in response to the northward subduction of the Pacific Plate beneath the Wrangellia Superterrane.
 
The oldest rock within the Pebble district is the Jurassic-Cretaceous age Kahlitna flysch, composed of turbiditic clastic sedimentary rocks, interbedded basalt flows and associated gabbro intrusions. During the mid-Cretaceous (99 to 96 Ma), the Kahlitna assemblage was intruded first by approximately coeval granodiorite and diorite sills and slightly later by alkalic monzonite intrusions. At approximately 90 Ma, hornblende diorite porphyry plutons of the Kaskanak batholith were emplaced. Copper-gold-molybdenum-silver-rhenium mineralization is related to smaller granodiorite plutons and dykes that are similar in composition to, and emplaced near and above the margins of, the Kaskanak batholith.
 
The Pebble East and Pebble West zones are coeval hydrothermal centers within a single magmatic-hydrothermal system. The movement of mineralizing fluids was constrained by a broadly vertical fracture system acting in conjunction with a hornfels aquitard that induced extensive lateral fluid migration. The large size of the deposit, as well as variations in metal grade and ratios, may be the result of multiple stages of metal introduction and redistribution.
 
Mineralization in the Pebble West zone extends from surface to approximately 3,000 ft depth and is centered on four small granodiorite plutons. Mineralization is hosted by flysch, diorite and granodiorite sills, and alkalic intrusions and breccias. The Pebble East zone is of higher grade and extends to a depth of at least 5,810 ft; mineralization on the eastern side of the zone was later dropped 1,970 to 2,950 ft by normal faults which bound the northeast-trending East Graben. East zone mineralization is hosted by a granodiorite plutons and dykes, and by adjacent granodiorite sills and flysch. The East and West zone granodiorite plutons merge with depth
 
Mineralization at Pebble is predominantly hypogene, although the Pebble West zone contains a thin zone of variably developed supergene mineralization overlain by a thin leached cap. Disseminated and vein-hosted copper-gold-molybdenum-silver-rhenium mineralization, dominated by chalcopyrite and locally accompanied by bornite, is associated with early potassic alteration in the shallow part of the Pebble East zone and with early sodic-potassic alteration in the Pebble West zone and deeper portions of the Pebble East zone. Rhenium occurs in molybdenite and high rhenium concentrations are present in molybdenite concentrates. Elevated palladium concentrations occur in many parts of the deposit but are highest in rocks affected by advanced argillic alteration. High-grade copper-gold mineralization is associated with younger advanced argillic alteration that overprinted potassic and sodic-potassic alteration and was controlled by a syn-hydrothermal, brittle-ductile fault zone located near the eastern margin of the Pebble East zone. Late quartz veins introduced additional molybdenum into several parts of the deposit.
 
Exploration
 
Historical
 
Cominco Alaska, a division of Cominco Ltd. (now Teck), began reconnaissance exploration in the Pebble region in the mid-1980s and in 1984 discovered the Sharp Mountain gold prospect near the southern margin of the current property. Gold was discovered in quartz veins of probable Tertiary age near the peak of Sharp Mountain. Grab samples of veins in talus ranged from 0.045 oz/ton Au to 9.32 oz/ton Au and 3.0 oz/ton Ag. In 1987, examination and sampling of several prominent limonitic and hematitic alteration zones yielded anomalous gold concentrations from the Sill prospect and the Pebble discovery outcrop.
 
Geophysical surveys were conducted on the property between 1988 and 1997. An induced polarization ("IP") survey in 1989 at Pebble displayed response characteristics of a large porphyry-copper system. The surveys were dipole-dipole IP surveys, which defined a chargeability anomaly about 31.1 square miles in extent within Cretaceous age rocks that surround the eastern to southern margins of the Kaskanak batholith. All known zones of mineralization of Cretaceous age on the Pebble property occur within the broad IP anomaly.
 
 
2020 Annual Information Form
Page | 22
 
 
 

 
 
In 1991, baseline environmental and engineering studies were initiated and weather stations were established. A preliminary evaluation was undertaken by Teck in 1991, and updated in 1992. Historical estimates of the mineral resources for the Pebble deposit were completed by Teck, most recently in 2000.
 
Northern Dynasty and Pebble Partnership
 
Between 2001 and 2006, the entire Pebble property was mapped for rock type, structure and alteration at a scale of 1:10,000, providing an important geological framework for interpretation of other exploration data. A geological map of the Pebble deposit was also constructed but, due to a paucity of outcrop, was based solely on drill hole information. The content and interpretation of district and deposit scale geological maps have not changed materially from those presented in 2009 and 2010.
 
A number of geophysical surveys, including IP, magnetic and other survey types were completed by Northern Dynasty and the Pebble Partnership between 2001 and 2010 to test the Pebble deposit and other occurrences on the Pebble property. Between 2001 and 2003, Northern Dynasty collected 1,026 soil samples, outlining high-contrast, coincident anomalies in gold, copper, molybdenum and other metals in an area that measures at least 5.6 miles north-south by up to 2.5 miles east-west, with strong but smaller anomalies in several outlying zones. All soil geochemical anomalies lie within the 31.1 square mile IP chargeability anomaly. Limited surficial geochemical surveys were completed in 2010 and 2011.
 
Drilling
 
Extensive drilling totalling 1,048,509.8 ft has been completed in 1,389 holes on the Pebble Project. These drill programs took place during 21 of the 31 years from 1988 to 2019. Teck completed several drilling programs between 1988 and 1997.
 
Northern Dynasty with its partners completed drilling for exploration, deposit delineation, engineering and environmental purposes between 2002 and 2019. Highlights from exploration and deposit delineation drilling include:
 
● prior to 2001, Teck completed a total of 164 drill holes, 39 of which were completed in the Sill Zone and 125 of which were collared within or near the Pebble deposit;
 
● in 2002, drill testing of IP chargeability and multi-element geochemical anomalies outside of the Pebble deposit but within the larger and broader IP chargeability anomaly discovered the 38 Zone porphyry copper-gold-molybdenum deposit, the 52 Zone porphyry copper occurrence, the 37 Zone gold-copper skarn deposit, the 25 Zone gold deposit, and several small occurrences in which gold values exceeded 3.0 g/t;
 
● in 2003, drilling took place within and adjacent to the Pebble West zone and outside the Pebble deposit to test for extensions and new mineralization at four other zones, including the 38 Zone porphyry copper-gold-molybdenum deposit and the 37 Zone gold-copper skarn deposit;
 
● in 2004, 147 exploration holes were drilled in the Pebble deposit resulting in the identification of the Pebble East zone and discovery of the 308 Zone porphyry copper-gold-molybdenum deposit;
 
● in 2005 and 2006, drilling at Pebble East confirms its large size and higher grades of copper, gold and molybdenum;
 
● in 2007, 34 holes extend Pebble East to the northeast, northwest, south and southeast;
 
● in 2008, 31 delineation and infill holes were drilled at Pebble East. Full Metal Minerals (USA) Inc. ("FMMUSA") drilled seven exploration holes on land that is now controlled by the Pebble Partnership;
 
● in 2009 and 2010, delineation holes were drilled at the margins of Pebble West and exploration holes were drilled elsewhere on the property;
 
● in 2011 and 2012, holes drilled in the Pebble West zone indicate potential for resource expansion laterally and to depth, and exploration targets were tested on the Kaskanak claims to the northwest and south of Pebble, and on the KAS claims further south;
 
 
2020 Annual Information Form
Page | 23
 
 
 

 
 
● in 2013 and 2018, geotechnical holes were drilled to test tailings and water storage facilities in areas remote from the Pebble deposit; and
 
● in 2019, a series of percussion holes were drilled adjacent to the Pebble deposit to enable hydrological testing.
 
No drilling took place in 2014, 2015, 2016 or 2017.
 
The spatial distribution and type of holes drilled at Pebble are illustrated below.
 
Figure 3                   Location of Drill Holes – Pebble Project
 
 
Source: 2021 Technical Report
 
Most of the footage on the Pebble Project was drilled using diamond core drills; the Pebble resource estimate was calculated exclusively from these holes. Many of the cored holes were advanced through overburden using a tricone bit with no core recovery. These overburden lengths are included in the core drilling total.
 
Since early 2004, all Pebble drill core has been geotechnically logged. Nearly 70,000 measurements were made for a variety of geotechnical parameters on 736,000 ft of core drilling. Recovery is generally very good and averages 98.6% overall; two-thirds of all measured intervals have 100% core recovery. Additionally, all Pebble drill core from the 2002 through 2018 drill programs was photographed in a digital format.
 
All drill hole collars have been surveyed using a differential global positioning system. A digital terrain model for the site was generated by photogrammetric methods in 2004. All post-Teck drill holes have been surveyed downhole, typically using a downhole survey (single shot magnetic gravimetric) tool. A total of 1,029 holes were drilled vertically (-90°) and 190 were inclined from -42° to -85° at various azimuths.
 
A summary of drilling by various categories (operator, type, year and area) to the end of the 2019 program are compiled in the table below. As shown in Figure 3 and Table 1 (East, West, Main), a large proportion of the drilling has been directed toward the Pebble deposit.
 
 
2020 Annual Information Form
Page | 24
 
 
 

 
 
Table 1                   Summary of Drill Holes – Pebble Project
 
 
No. of Holes
Feet
Metres
By Operator
Teck 1
164
75,741.0
23,086
Northern Dynasty
578
495,069.5
150,897
Pebble Partnership 2
640
472,249.3
143,942
FMMUSA
7
5,450.0
1,661
Total
1,389
1,048,509.8
319,586
By Type
Core 1,5
1,160
1,027,671.9
313,234
Percussion 6
229
20,838.0
6,351
Total
1,389
1,048,509.8
319,586
By Year
1988 1
26
7,601.5
2,317
1989 1
27
7,422.0
2,262
1990
25
10,021.0
3,054
1991
48
28,129.0
8,574
1992
14
6,609.0
2,014
1993
4
1,263.0
385
1997
20
14,695.5
4,479
2002
68
37,236.8
11,350
2003
67
71,226.6
21,710
2004
267
165,567.7
50,465
2005
114
81,978.5
24,987
2006 3
48
72,826.9
22,198
2007 4
92
167,666.9
51,105
2008 5
241
184,726.4
56,305
2009
33
34,947.5
10,652
2010
66
57,582.0
17,551
2011
85
50,767.7
15,474
2012
81
35,760.2
10,900
2013
29
6,190.0
1,887
2018
28
4,374.2
1,333
2019
6
1,917.4
584
Total
1,389
1,048,509.8
319,586
By Area
East
149
450,047.3
137,174
West
447
349,128.7
106,414
Main 7
83
9,629.8
2,935
NW
215
49,951.1
15,225
North
84
30,927.0
9,427
NE
15
1,495.0
456
South
117
48,387.8
14,749
25 Zone
8
4,047.0
1,234
37 Zone
7
4,252.0
1,296
38 Zone
20
14,221.5
4,335
52 Zone
5
2,534.0
772
308 Zone
1
879.0
268
Eastern
5
621.5
189
Southern
147
64,374.4
19,621
SW
39
6,658.8
2,030
Sill
39
10,445.5
3,184
Cook Inlet
8
909.5
277
Total
1,389
1,048,509.8
319,586
 
 
2020 Annual Information Form
Page | 25
 
 
 

 
 
Notes to table:
1. Includes holes drilled on the Sill prospect.
2. Holes started by Northern Dynasty and finished by the Pebble Partnership are included as the Pebble Partnership.
3. Drill holes counted in the year in which they were completed.
4. Wedged holes are counted as a single hole including full length of all wedges drilled.
5. Includes FMMUSA drill holes; data acquired in 2010.
6. Percussion holes were drilled for engineering and environmental purposes. Shallow (<15 ft) auger holes not included.
7. Comprises holes drilled entirely in Tertiary cover rocks within the Pebble West and Pebble East areas.
 
Some numbers may not sum exactly due to rounding.
 
Sampling, Analysis and Security of Samples
 
The Pebble deposit has been explored by extensive core drilling, with 80,859 samples having been taken from drill core for assay analysis. Nearly all potentially mineralized Cretaceous core drilled and recovered has been sampled by halving in 10 ft lengths. Similarly, all core recovered from the Late Cretaceous to Early Tertiary cover sequence has also been sampled, typically on 20 ft sample lengths, with some shorter sample intervals in areas of geologic interest. Unconsolidated overburden material, where it exists, is generally not recovered by core drilling and therefore not usually sampled.
 
Rock chips from the 223 rotary percussion holes were generally not sampled for assay analysis, as the holes were drilled for monitoring wells and environmental purposes. Only 35 samples were taken from the drill chips of 26 rotary percussion holes outside the Pebble deposit area, which were drilled for condemnation purposes.
 
Analytical work in 2002 and from 2004 to 2018 was completed by ALS Minerals Laboratories of North Vancouver, an ISO/IEC 17025:2005 certified laboratory. Analytical work for the 2003 drilling program was completed by SGS Canada Inc. of Toronto, ON, an ISO 9002 registered, ISO 17025 accredited laboratory.
 
Northern Dynasty maintained an effective Quality Control/Quality Assurance ("QA/QC") program consistent with industry best practices, which was continued from 2007 to 2018 under the Pebble Partnership. This program is in addition to the QA/QC procedures used internally by the analytical laboratories. The QA/QC program has also been subject to independent review by Analytical Laboratory Consultants Ltd. and Nicholson Analytical Consulting through 2012. The analytical consultants provide ongoing monitoring, including facility inspection and timely reporting of the performance of standards, blanks and duplicates in the sampling and analytical program. The results of this program indicate that analytical results are of a high quality, suitable for use in detailed modelling and resource evaluation studies. The QA/QC sample types used in the program are described in the table below.
 
 
2020 Annual Information Form
Page | 26
 
 
 

 
 
Table 2                   Summary of Quality Control/Quality Assurance Sampling – Pebble Project
 
QC Code
Sample Type
Description
% of Total
MS
Regular Mainstream
Regular samples submitted for preparation and analysis at the primary laboratory.
89%
ST
Standard (Certified Reference Material)
Mineralized material in pulverized form with a known concentration and distribution of element(s) of interest.
Randomly inserted using pre-numbered sample tags.
4.5%or9 in 200
DP
Duplicate or Replicate
An additional split taken from the remaining pulp reject, coarse reject, ¼ core or ½ core remainder.
Random selection using pre-numbered sample tags.
4.5%or9 in 200
SD
Standard Duplicate
Standard reference sample submitted with duplicates and replicates to the check laboratory.
<1%
BL
Blank
Sample containing negligible or background amounts of elements of interest, to test for contamination.
2%
1 in 50
 
Pebble core was boxed at the rig and transported daily by helicopter to a secure logging facility in Iliamna. Half cores remaining after sampling were replaced in the original core boxes and stored at Iliamna, AK in a secure compound. Crushed reject samples from the 2006 through 2018 analytical programs are stored in locked containers at Delta Junction, AK. Drill core assay pulps from the 1989 through 2018 programs are stored at a secure warehouse in Surrey, BC.
 
Mineral Resources
 
The current resource estimate is based on approximately 59,000 assays obtained from 699 drill holes. The resource was estimated by ordinary kriging and is presented in the table below titled “Table 3 – Mineral Resources – Pebble Deposit.” The tabulation is based on copper equivalency that incorporates the contribution of copper, gold and molybdenum. Although the estimate includes silver and rhenium, neither were used as part of the copper equivalency (CuEQ) calculation in order to facilitate comparison with previous estimates, which did not consider the economic contribution of either of these metals. The highlighted 0.3% CuEq cut off is considered appropriate for deposits of this type in the Americas.
 
 
2020 Annual Information Form
Page | 27
 
 
 

 
 
 
Cautionary Note to Investors Concerning Estimates of Measured, Indicated and Inferred Resources
 
This section uses the terms "measured resources", "indicated resources" and “inferred resources”. United States investors are cautioned that while these terms are “substantially similar” to CIM Definitions, there are differences in the definitions under the SEC Modernization Rules and the CIM Definition Standards. Accordingly, there is no assurance any mineral resources that we may report as measured mineral resources, indicated mineral resources and inferred mineral resources under NI 43-101 would be the same had we prepared the resource estimates under the standards adopted under the SEC Modernization Rules. Investors are cautioned not to assume that all or any part of the mineral deposits in these categories will ever be converted into reserves. In addition, "inferred resources" have a great amount of uncertainty as to their economic and legal feasibility. Under Canadian rules, estimates of inferred resources may not form the basis of feasibility or pre-feasibility studies, or economic studies except for a Preliminary Economic Assessment as defined under NI 43-101. Investors are cautioned not to assume that all or any part of an inferred resource is economically or legally mineable.
 
 
 
Table 3                   Mineral Resources – Pebble Deposit

Measured, Indicated and Inferred Categories
 
Cutoff
CuEq %
CuEq%
Metric
Tonnes
Cu
(%)
Au
(g/t)
Mo
(ppm)
Ag
(g/t)
Re
(ppm)
Cu
Blb
Au
Moz
Mo
Blb
Ag
Moz
Re
Kkg
Measured
0.3
0.65
 527,000,000
0.33
0.35
178
1.7
0.32
3.83
5.93
0.21
28.1
167
0.4
0.66
 508,000,000
0.34
0.36
180
1.7
0.32
3.81
5.88
0.20
27.4
163
0.6
0.77
 279,000,000
0.40
0.42
203
1.8
0.36
2.46
3.77
0.12
16.5
100
1.0
1.16
 28,000,000
0.62
0.62
302
2.3
0.52
0.38
0.56
0.02
2.0
14
Indicated
0.3
0.77
 5,929,000,000
0.41
0.34
246
1.7
0.41
53.58
64.81
3.21
316.4
2,443
0.4
0.82
 5,185,000,000
0.45
0.35
261
1.8
0.44
51.42
58.35
2.98
291.7
2,271
0.6
0.99
 3,455,000,000
0.55
0.41
299
2.0
0.51
41.88
45.54
2.27
221.1
1,748
1.0
1.29
 1,412,000,000
0.77
0.51
343
2.4
0.60
23.96
23.15
1.07
109.9
853
Measured + Indicated
0.3
0.76
 6,456,000,000
0.40
0.34
240
1.7
0.41
56.92
70.57
3.42
344.6
2,615
0.4
0.81
 5,693,000,000
0.44
0.35
253
1.8
0.43
55.21
64.06
3.18
320.3
2,431
0.6
0.97
 3,734,000,000
0.54
0.41
291
2.0
0.50
44.44
49.22
2.40
237.7
1,848
1.0
1.29
 1,440,000,000
0.76
0.51
342
2.4
0.60
24.12
23.61
1.08
112.0
867
Inferred
0.3
0.55
 4,454,000,000
0.25
0.25
226
1.2
0.36
24.54
35.80
2.22
170.4
1,603
0.4
0.68
 2,646,000,000
0.33
0.30
269
1.4
0.44
19.24
25.52
1.57
119.1
1,154
0.6
0.89
 1,314,000,000
0.48
0.37
292
1.8
0.51
13.90
15.63
0.85
75.6
673
1.0
1.20
 361,000,000
0.68
0.45
377
2.3
0.69
5.41
5.22
0.30
26.3
251
 
The tabulated mineral resources are subject to the notes below:
 
David Gaunt, P.Geo., a qualified person who is not independent of Northern Dynasty is responsible for the estimate. The effective date of the estimate is August 20, 2020.
 
Copper equivalent calculations use metal prices of US$1.85/lb for copper, US$902/oz for gold and US$12.50/lb for molybdenum, and recoveries of 85% for copper 69.6% for gold, and 77.8% for molybdenum in the Pebble West zone and 89.3% for copper, 76.8% for gold, and 83.7% for molybdenum in the Pebble East zone.
 
Contained metal calculations are based on 100% recoveries.
 
A 0.30% CuEQ cut-off is considered to be comparable to that used for porphyry deposit open pit mining operations in the Americas.
 
The mineral resource estimate is constrained by a conceptual pit shell that was developed using a Lerchs-Grossman algorithm and is based in the following parameters: 42 degree pit slope; metal prices and recoveries of US$1,540.00/oz and 61% Au, US$3.63/lb and 91% Cu, US$20.00/oz and 67% Ag and US$12.36/lb and 81% Mo, respectively; a mining cost of US$1.01/ton with a US$0.03/ton/bench increment and other costs (including processing, G&A and transport) of US$6.74/ton.
 
All mineral resource estimates, cut-offs and metallurgical recoveries are subject to change as a consequence of more detailed analyses that would be required in pre-feasibility and feasibility studies.

 
2020 Annual Information Form
Page | 28
 
 
 

 
 
These mineral resource estimates may ultimately be affected by a broad range of economic/financial, environmental, permitting, legal, title, socio-economic, marketing and political factors commensurate with the specific characteristics of the Pebble deposit (including its scale, location, orientation and poly-metallic nature) as well as its setting (from a natural, social, jurisdictional and political perspective).
 
The mineral resource estimates contained herein have not been adjusted for any risk that the required environmental permits may not be obtained for the Pebble Project. The risk associated with the ability of the Pebble Project to obtain required environmental permits is a risk to the reasonable prospects for eventual economic extraction of the mineralization and their definition as a mineral resource.
 
Mineral Processing and Metallurgical Testing
 
Metallurgical testwork for the Pebble Project was initiated by Northern Dynasty in 2003, and continued under the direction of Northern Dynasty until 2008.  From 2008 to 2013, metallurgical testwork progressed under the direction of the Pebble Partnership.
 
Geometallurgical studies were initiated by the Pebble Partnership in 2008 and continued through 2012. The principal objective of this work was to quantify significant differences in metal deportment that may result in variations in metal recoveries during mineral processing. The results of the geometallurgical studies indicate that the deposit comprises several geometallurgical (or material type) domains. These domains are defined by distinct, internally consistent copper and gold deportment characteristics that correspond spatially with changes in silicate and sulphide alteration mineralogy.
 
Metallurgical testwork and associated analytical procedures were performed by recognized testing facilities with extensive experience with this analysis, with this type of deposit, and with the Pebble Project. The samples selected for the comminution, copper/gold/molybdenum bulk flotation, and copper molybdenum separation testing were representative of the various types and styles of mineralization at the Pebble deposit.
 
A conventional flotation process is proposed to produce copper concentrate and molybdenum concentrate. The flotation test results on variability samples derived from the 103 locked cycle flotation and the subsequent copper-molybdenum separation flotation tests indicate that marketable copper and molybdenum concentrates can be produced. The copper concentrate will also contain gold and silver contents that meet or exceed payable levels in representative smelter contracts; the molybdenum concentrate will contain significant rhenium (Re), with a reported grade range from 791 to 832 g/t Re observed in the locked cycle test (LCT) results of the copper-molybdenum separation.
 
A preliminary hydrometallurgical test program was performed on rougher and cleaner molybdenum concentrates to investigate the production of the marketable products of molybdenum trioxide (MoO3) and ammonium perrhenate (NH4ReO4). The test program included pressure oxidation leach, a series of metal extractions/purifications from the pregnant leach solution, and a calcination process. The tested methods were found technically feasible. Satisfactory dissolution rates of molybdenum and rhenium were obtained from the rougher molybdenum concentrate samples, while additional alkaline leach is required on the pressure oxidation leach residues for the cleaner molybdenum concentrate samples.
 
In this technical report, the metal recovery projections of copper, gold, silver and molybdenum stay the same as those published in the 2018 and 2020 technical reports. A rhenium recovery estimate at a high level has been completed and included. Table 4 provides projected metals recoveries via flotation concentration for metals and a gravity circuit for gold. The recovery estimate bases are summarized as follows:
 
The initial metal recovery projections of copper, gold, silver and molybdenum were published in 2014 based on a combined flotation and cyanide leach method. A total of 111 locked cycle tests on the 103 samples representing eight geometallurgical domains across the east and west of Pebble deposit were reviewed to establish the copper, gold and molybdenum distributions to the bulk copper-molybdenum concentrate. Ten of the 111 locked cycle flotation tests with silver assay results were utilized to estimate the silver recovery to the bulk flotation concentrate.
 
 
2020 Annual Information Form
Page | 29
 
 

 
 
The 2018 metal recoveries were updated to reflect the changes of the proposed processing methods, including the exclusion of the cyanide leach process and the implementation of a finer primary grind particle size. The flotation tests on composite samples indicate a general increase of metal recoveries with a decreasing primary grind size.
 
The 2020 metal recovery projections were further updated to include the rhenium recovery to the molybdenum concentrate. The estimated rhenium recovery was 70.8%, based on the 10 LCT results of the rhenium recovery to the bulk concentrate, a one LCT stage recovery result in the subsequent separation of copper and molybdenum, as well as a recovery adjustment due to the reduction of primary grind size.
 
Table 4  Projected Metallurgical Recoveries
 
 
Flotation Recovery %
 
Cu Con, 26% Cu
Mo Con, 50% Mo
Domain
Cu
Au
Ag
Mo
Re
Supergene:
 
 
 
 
 
Sodic Potassic
78.7
63.6
67.5
53.9
70.8
Illite Pyrite
72.1
46.5
67.8
66.3
70.8
Hypogene:
 
 
 
 
 
Illite Pyrite
89.8
45.6
66.6
76.1
70.8
Sodic Potassic
90.1
63.2
67.0
80.1
70.8
Potassic
93.7
63.6
66.5
85.4
70.8
Quartz Pyrophyllite
94.7
65.2
64.4
80.4
70.8
Sericite
89.6
40.6
66.5
75.9
70.8
Quartz Sericite Pyrite
89.8
32.9
66.9
86.1
70.8
 
Rhenium Recovery Estimate
 
Copper-molybdenum porphyry deposits are the world’s primary source of rhenium (SME, 2018). The metallurgical test work from 2011 to 2013 on Pebble deposit indicates that significant rhenium can be recovered to the bulk Cu-Mo flotation concentrate and further concentrated into the final molybdenum flotation concentrate. The overall rhenium recovery is determined by the rhenium recovery to the bulk copper-molybdenum concentrate and the separation efficiency of the rhenium into the molybdenum concentrate in the subsequent copper-molybdenum separation stage. The estimated rhenium recovery is about 70.8% on average for all the domains based on the following considerations:
 
The available rhenium distributions to the bulk copper/molybdenum concentrates are based on the 10 of the 111 LCT tests on variability samples. The average recovery was calculated as 73.4% representing five of the eight geometallurgical domains.
 
The application of a similar separation efficiency of molybdenum as of 92.7% in the copper-molybdenum separation to estimate the rhenium stage recovery, considering the significant linear relationship between the molybdenum and rhenium bulk and circuit recovery test data.
 
The adjustment of the overall rhenium recovery by applying a similar factor for an average recovery increase of 0.5% per 10 µm reduction of primary grind size.
 
Environmental and Socioeconomic
 
The Pebble deposit is located on state land specifically designated for mineral exploration and development. The project area has been the subject of two comprehensive land-use planning exercises conducted by the Alaska Department of Natural Resources (the "ADNR"), the first in the 1980s and the second completed in 2005. The ADNR identified five land parcels (including Pebble) within the Bristol Bay planning area as having "significant mineral potential," and where the planning intent is to accommodate mineral exploration and development. These parcels total 2.7% of the total planning area (ADNR, 2005).
 
Environmental standards and permitting requirements in Alaska are stable, objective, rigorous and science-driven. These features are an asset to projects like Pebble that are being designed to meet U.S. and international best practice standards of design and performance.
 
 
2020 Annual Information Form
Page | 30
 
 
 

 
 
Environmental Baseline Studies
 
Northern Dynasty and its partners carried out extensive field study programs from 2004 onward to characterize the existing physical, chemical, biological, and social environments in the Bristol Bay and Cook Inlet areas where the Pebble Project might occur. The Pebble Partnership compiled the data for the 2004-2008 study period into a multi-volume Environmental Baseline Document ("EBD"). These studies have been designed to:
 
● fully characterize the existing biophysical and socioeconomic environment;
 
● support environmental analyses required for effective input into Project design;
 
● provide a strong foundation for internal environmental and social impact assessment to support corporate decision-making;
 
● provide the information required for stakeholder consultation and mine permitting in Alaska; and,
 
● provide a baseline for long-term monitoring of potential changes associated with mine development.
 
The baseline study program includes:
 
 surface water
 wildlife
 groundwater
 air quality
 surface and groundwater quality
 cultural resources
 geochemistry
 subsistence
 snow surveys
 land use
 fish and aquatic resources
 recreation
 noise
 socioeconomics
 wetlands
 visual aesthetics
 trace elements
 climate and meteorology
 fish habitat – stream flow modeling
 Iliamna Lake
 Cook Inlet marine studies
 
  
The final Pebble EIS published by the USACE on July 24, 2020 was the culmination of a 2 ½-year long, intensive review process under the NEPA. Further details on the CMP and Record of Decision on the Pebble EIS, as well as the Pebble Partnership’s appear of the Record of Decision are provided in the Introduction.
 
In addition to federal permits, the Pebble Partnership would also have to secure a number of permits issued by the State of Alaska, a process expected to take 2 – 3 years.
 
 
2020 Annual Information Form
Page | 31
 
 
 

 
 
Community Consultation and Stakeholder Relations
 
Pebble Project technical programs are supported by stakeholder engagement activities in Alaska. The objective of stakeholder outreach programs undertaken by the Pebble Partnership are to:
 
● advise residents of nearby communities and other regional interests about Pebble work programs and other activities being undertaken in the field;
 
● provide information about the proposed development plan for the Pebble Project, including potential environmental, social and operational effects, proposed mitigation and environmental safeguards;
 
● allow the Pebble Partnership to better understand and address stakeholder priorities and concerns with respect to development of the Pebble Project;
 
● encourage stakeholder and public participation in the USACE-led EIS permitting process for Pebble; and
 
● facilitate economic and other opportunities associated with advancement and development of the Pebble Project for local residents, communities and companies.
 
In addition to meeting with stakeholder groups and individuals, and providing project briefings in communities throughout Bristol Bay and the State of Alaska, the Pebble Partnership’s outreach and engagement program includes:
 
● workforce and business development initiatives intended to enhance economic opportunities for regional residents and Alaska Native corporations;
 
● initiatives to develop partnerships with Alaska Native corporations, commercial fishing interests and other in-region groups and individuals;
 
● outreach to elected officials and political staff at the national, state and local levels; and
 
● outreach to third-party organizations and special interest groups with an interest in the Pebble Project, including business organizations, community groups, outdoor recreation interests, Alaska Native entities, commercial and sport fishery interests, and conservation organizations, among others.
 
Through these various stakeholder initiatives, the Company seeks to advance a science-based project design that is responsive to stakeholder priorities and concerns, provides meaningful benefits and opportunities to local residents, businesses and Alaska Native corporations, and energizes the economy of Southwest Alaska.
 
Agreements and Other Initiatives with Alaska Native Village Corporations
 
The Pebble Partnership carries out an active program of engagement and consultation with stakeholders in the area of the Pebble Project in parallel with its technical work, and includes discussions to secure stakeholder agreements to support the project’s development. Right-of-way agreements established to date are described below. These agreements cover land access routes for infrastructure alternatives proposed in the EIS documents.
 
Right-of-Way Agreements
 
The Pebble Partnership has finalized Right-of-Way ("ROW") agreements with Alaska Native village corporations and other landowners with land holdings along proposed transportation and infrastructure routes for the Pebble Project. Discussions with other landowners continued in 2020. The ROW Agreements secure access to portions of several proposed transportation and infrastructure routes to the Pebble Project site for construction and operation of the proposed mine, and represent a significant milestone in the developing relationship between Pebble and the Alaska Native people of the region. The Pebble Partnership believes it will secure the right to use defined portions of each of the Native village corporations’ lands for the construction and operation of transportation infrastructure associated with the Pebble Project in future.
 
 
2020 Annual Information Form
Page | 32
 
 
 

 
 
Agreements include the following provisions:
 
 
The Pebble Partnership will make annual toll payments to the Alaska Native village corporations land upon whose lands Pebble-related transportation infrastructure is built and operated, and pay other fees prior to and during project construction and operation;
 
 
Village corporations have been granted ‘Preferred Contractor’ status at Pebble, which provides a preferential opportunity to bid on Pebble-related contracts located on their lands; and
 
 
The Pebble Partnership has agreed to negotiate a profit sharing agreement with Alaska Native village corporations that will ensure the corporations and their shareholders benefit directly from the profits generated by mining activity in the region.
 
Additionally, transportation and other infrastructure for a mine at Pebble is expected to benefit the Alaska Native village corporations, their shareholders and villages through access to lower cost power, equipment and supplies, as well as enhanced economic activity in the region. Spur roads connecting to local villages will allow local residents to access jobs at the Pebble mine site, port site and ferry landing sites.
 
 
The USACE’s identification of the Northern Transportation Route as the draft LEDPA for the Pebble Project requires that the Pebble Partnership secure additional right-of-way agreements with Alaska Native village corporations and other private landowners with land holdings along the northern route. The Pebble Partnership was in the process of securing these additional right-of-way agreements but suspended those efforts, pending appeal of the November 25, 2020 ROD.
 
Bristol Bay Revenue Sharing Program
 
On June 16, 2020, Northern Dynasty announced that the Pebble Partnership has established the Pebble Performance Dividend LLP to provide for a local revenue sharing program with the objective of ensuring that full-time residents of communities in southwest Alaska will benefit directly from the future operation of the proposed Pebble Project. The intention is for the Pebble Performance Dividend LLP to distribute cash generated from a 3% net profits royalty interest in the Pebble Project to adult residents of Bristol Bay villages that have subscribed as participants, with a guaranteed minimum aggregate annual payment of US$3 million each year the Pebble mine operates beginning at the outset of project construction and with future payments following capital payback expected to increase beyond this initial amount.
 
Logistics MOU with Alaska Peninsula Corporation
 
The Company announced on July 6, 2020 that the Pebble Partnership entered into a memorandum of understanding (the "MOU") with APC which envisages that APC will lead the development of a consortium of Alaska Native village corporations to provide logistics services to the project. It is contemplated that the final agreement may include access road maintenance, truck transport, port operations and other logistical services should the development of the mine proceed. The MOU is consistent with the Company’s strategy of ensuring the development of the Pebble Project will benefit local Alaska communities and people. The MOU is not a binding final contract which will require further negotiation of definitive contracts. There is no assurance that these contracts will be concluded.
 
Project Description
 
On December 22, 2017, the Pebble Partnership submitted its CWA 404 permit application in which it is envisaged that the Pebble copper-gold-molybdenum-silver-rhenium porphyry deposit would be developed as an open pit mine, with associated on and off-site infrastructure. In subsequent years, additional engineering work was completed to support the environmental assessment process, as well as recommendations from USACE in the final Pebble EIS, has resulted in some modifications to the plan and the Project Description has been updated accordingly.
 
Proposed project infrastructure includes:
 
●  a 270 megawatt power plant located at the mine site;
 
 
2020 Annual Information Form
Page | 33
 
 
 

 
 
●  a 164 mile natural gas pipeline connecting existing supply on the Kenai Peninsula to the power plant at the mine site;
 
●  an 82-mile transportation corridor from the mine site to a port site located north of Diamond Point in Iliamna Bay on Cook Inlet consisting of:
 
o  a private two-lane unpaved road that connects to the existing Iliamna/Newhalen road system;
 
o  the onland portion of the natural gas pipeline buried adjacent to the road; and
 
o  a concentrate pipeline to transport copper-gold concentrate from the mine site to the port with a return water pipeline to the mine site, both buried adjacent to the road; and
 
●  a port facility incorporating:
 
o  concentrate dewatering, storage and handling;
 
o  fuel and supply storage;
 
o  local power supply; and
 
o  barge docks for supplies and to facilitate bulk lightering of concentrate between the Diamond Point Port and an offshore lightering location in Iniskin Bay for loading onto bulk carriers.
 
The Pebble Partnership’s permit application envisages the Pebble Project being developed as an open pit mine with associated on and off-site infrastructure described in this section. Construction will last for approximately four years, followed by a commissioning period and 20 years of mineral processing.
 
Item
Value
General Operation
Construction
Total project operations
Daily schedule
Annual schedule
 
4 years
20 years
24 hours
365 days
Mine Operation
Preproduction mined tonnage
Average annual mining rate
Operations mined tonnage
Mine life strip ratio
Open pit dimensions
 
33 million tons
70 million tons
1,440 million tons
0.12:1 (waste: mineralized material)
6,800 ft x 5,600 ft, 1,950 ft deep
Process Operation
Daily process rate
Annual process volume
Copper-gold concentrate
Molybdenum concentrate
 
180,000 tons
66 million tons
613,000 tons per year (average)
15,000 tons per year (average)
Pyritic Tailings Storage Facility
Approximate capacity (tailings)
Approximate capacity (PAG waste)
South embankment (height)
North embankment (height)
East embankment
 
155 million tons
93 million tons
215 feet
335 feet
225 feet
Bulk Tailings Storage Facility
Approximate capacity
Main embankment (height)
South embankment (height)
 
1,140 million tons
545 feet
300 feet
Main Water Management Pond
Approximate capacity
 
2,450 million cubic feet (56,000 ac-ft)
Embankment height
190 feet
Concentrate Pipeline
Diameter
 
6.25 inches
a Design criteria as presented are approximate and have been averaged and rounded as appropriate for ease of reference.
 
 
2020 Annual Information Form
Page | 34
 
 
 

 
 
The Pebble Mine will be a conventional drill, blast, truck, and shovel operation with an average mining rate of approximately 70 million tons per year and an overall stripping ratio of 0.12 ton of waste per ton of mineralized material.

The open pit will be developed in stages, with each stage expanding the area and deepening the previous stage. The final dimensions of the open pit will be approximately 6,800 feet long and 5,600 feet wide, with depths to 1,950 feet.
 
The development proposed in Pebble’s Project Description is substantially smaller than previous iterations, and presents significant new environmental safeguards, including:
 
●  a development footprint less than half the size previously envisaged;
 
●  the consolidation of most major site infrastructure in a single drainage (the North Fork Koktuli), and the absence of any primary mine operations in the Upper Talarik drainage;
 
●  a more conservative Tailings Storage Facility ("TSF") design, including enhanced buttresses, flatter slope angles and an improved factor of safety;
 
●  separation of potentially acid generating ("PAG") tailings from non-PAG bulk tailings for storage in a fully-lined TSF;
 
●  a comprehensive tailings and water management plan including a flow through design for the bulk tailings embankment;
 
●  no permanent waste rock piles; and
 
●  no secondary gold recovery plant.
 
The project proposed in the Project Description uses a portion of the currently estimated Pebble mineral resources. This does not preclude development of additional resources in other phases of the project in the future, but such development would require additional evaluation and would be subject to separate permitting processes.
 
C.        Plans For 2021
 
In 2021, the Company plans include: continuing with the appeal of the ROD by the USACE; undertaking additional engineering, environmental, permitting and evaluation work on the Pebble Project as required; maintaining an active corporate presence in Alaska and Washington DC in order to advance relationships with political and regulatory offices of government, Alaska Native partners and broader stakeholder groups;(contingent on the appeal of the ROD and issuance of a permit from the Alaska District), initiating Alaska state permitting activities; and, seeking potential partner(s) with sufficient financial resources to further advance the Pebble Project. Additional details for the Company’s plan of operations for 2021 is provided in the Company’s Management Discussion and Analysis for the year ended December 31, 2020.
 
 
2020 Annual Information Form
Page | 35
 
 

 
 
D.        Organizational Structure
 
Structure as at December 31, 2020:
 
 
 
2020 Annual Information Form
Page | 36
 
 
 

 
 
E.        Property, Plant and Equipment
 
The Company’s principal property is the Pebble Project, as discussed in A and B, above.
 
The Company has approximately $197 in plant and equipment (excluding right-of-use assets) primarily at the Pebble Project site located in Iliamna.
 
The Company, through the Pebble Partnership, has leased premises in Anchorage and at the Pebble Project site and as result the Company has lease commitments which have been disclosed in the accompanying audited financial statements.
 
F.        Risk Factors
 
The securities of Northern Dynasty are highly speculative and subject to a number of risks. A prospective investor or other person reviewing Northern Dynasty for a prospective investor should not consider an investment in Northern Dynasty unless the investor is capable of sustaining an economic loss of their entire investment. The risks associated with Northern Dynasty’s business include:
 
Northern Dynasty May be Unsuccessful in Appealing the Record of Decision and may Ultimately not be able to Obtain the Required Environmental Permits for the Pebble Project.
 
The USACE’s ROD issued on November 25, 2020, has denied Northern Dynasty’s environmental permit for development of the Pebble Project under the Clean Water Act. This environmental permit is required for Northern Dynasty to proceed with the development of the Pebble Project. While the Pebble Partnership is appealing this Record of Decision, there is no assurance that Northern Dynasty’s appeal of the Record of Decision will be successful. Even if the appeal is successful, there is no assurance that a positive Record of Decision will ultimately be obtained by the Pebble Partnership or that the required environmental permit will be obtained. Northern Dynasty’s inability to successfully appeal the Record of Decision will mean that Northern Dynasty cannot proceed with development of the Pebble Project as presently envisioned. There is no assurance that Northern Dynasty will be able to redesign the Pebble Project in a manner that addresses the "significant degradation" conclusion reached by the USACE or ultimately develop any compensatory mitigation plan that the USACE accepts as appropriately addressing the "significant degradation" determination or that will change the USACE’s position that environmental permitting of the Pebble Project under the CWA is against the public interest. Northern Dynasty’s inability to address these issues may mean that the Company is ultimately not able to secure the environmental permits that are required to develop the Pebble Project. Accordingly, there is no assurance that investors will be able to recover their investment in the Company.
 
Inability to Ultimately Achieve Mine Permitting and Build a Mine at the Pebble Project
 
The Company may ultimately be unable to secure the necessary permits under United States Federal and Alaskan State laws to build and operate a mine at the Pebble Project. There is no assurance that the EPA will not seek to undertake future regulatory action to impede or restrict the Pebble Project. In addition, there are prominent and well-organized opponents of the Pebble Project and the Company may be unable, even if it present solid scientific and technical evidence of risk mitigation, to overcome such opposition and convince governmental authorities that a mine should be permitted at the Pebble Project. The Company faces not only the permitting and regulatory issues typical of companies seeking to build a mine, but additional public and regulatory scrutiny due to its location and potential size. Accordingly, there is no assurance that the Company will obtain the required permits. Although, the Company received a denial of its CWA 404 permit application from the USACE, the Company has submitted an appeal of the ROD, and should the appeal be successful, the Company will still be required to secure the full range of permits and authorizations from multiple federal and state regulatory agencies, which will take several years. After all permits necessary to begin construction are in hand, a number of years would be required to finance and build a mine and commence operations. During these periods, the Company would likely have no income and so would require additional financing to continue its operations. Unless and until the Company builds a mine at the Pebble Project it will be unable to achieve revenues from operations and may not be able to sell or otherwise recover its investment in the Pebble Project, which would have a material adverse effect on the Company and an investment in the Company’s common shares.
 
 
2020 Annual Information Form
Page | 37
 
 
 

 
 
If Northern Dynasty is Unable to Defend the "Class Action" Lawsuits against it, there is No Assurance that Northern Dynasty will not be Subject to Judgements for Damages against it
 
 
Northern Dynasty is the subject of several "class action" lawsuits against it that assert liability against Northern Dynasty on behalf of a purported class of shareholders under securities laws, both in Canada and the United States. While Northern Dynasty intends to vigorously defend these claims, there is no assurance that Northern Dynasty will be successful in defending all claims made against it. Should Northern Dynasty not be successful in defending these claims, it may be subject to judgements against it and be required to pay substantial amounts in damages to the plaintiffs under these judgements. These damages could result in a material and adverse impairment to Northern Dynasty’s financial condition and capital resources, and may further impair its ability to pursue the development of the Pebble Project.
 
 
In addition, Northern Dynasty is required under the terms of the indemnification agreements that it has entered into with underwriters in connection with Northern Dynasty’s public financings to indemnify the underwriters for any losses that they incur. As certain of Northern Dynasty’s underwriters have been named as defendants in certain of these class action lawsuits, Northern Dynasty may be required to indemnify and pay monies to the underwriters for any losses that they suffer and expenses that they incur. In addition, Northern Dynasty may be required to indemnify certain of its officers and directors for any losses that they suffer or expenses that they incur.
 
There is no assurance that Northern Dynasty’s existing insurance policies will respond and be sufficient to cover any amounts that it may be required to pay to the plaintiffs in these class action lawsuits, or the underwriters under our indemnification obligations. We may also be required to indemnify certain of our officers and directors who have been named as party to these lawsuits. These damages could result in a material and adverse impairment to our financial condition and capital resources, and may further impair our ability to raise additional financing and pursue the development of the Pebble Project.
 
 
Grand Jury Investigations and Related Matters
 
The Company is cooperating with a grand jury investigation involving the United States Attorney’s Office for the District of Alaska, and an SEC inquiry, as described below under Legal. The Company is not able to provide investors with guidance as to the outcome of the grand jury investigation or SEC inquiry, or whether either of them will result in any charges or other claims against the Company, the Pebble Partnership or their associated individuals. The Company does anticipate, however, that it will incur substantial expenses in connection with cooperating with the grand jury and SEC matters, including legal fees and expenses related to the collection, review, and production of documents, among other things. Any adverse civil or criminal proceedings could have a material adverse impact on Northern Dynasty’s prospects and ability to advance development of the Pebble Mine project.
 
In addition, Northern Dynasty and the Pebble Partnership may face ongoing and further inquiries, demands or allegations concerning future plans for the Pebble Project from the US Congress’ House Committee on Transportation and Infrastructure. Again, any adverse civil or criminal proceedings relating to the Committee’s investigation could have a material adverse impact on Northern Dynasty’s prospects and ability to advance development of the Pebble Project. In addition, these inquiries or any possible resulting civil or criminal proceedings could erode any existing political support for the Pebble Project which may reduce the likelihood of the Pebble Project obtaining the required environmental permitting.
 
The Record of Decision has had and will continue to have an Ongoing Adverse Impact on Northern Dynasty’s Ability to Finance the Pebble Project.
 
Northern Dynasty believes that the USACE’s ROD has had a material adverse impact on its ability to finance its operations and will continue to adversely impact its financing options for so long as the ROD remains outstanding. As Northern Dynasty does not have any revenues, and does not anticipate revenues in the foreseeable future, Northern Dynasty will require additional financing to continue its operations. If Northern Dynasty is unsuccessful in its appeal of the ROD, Northern Dynasty’s financing options may be substantially limited and it may not be able to generate the necessary financing to enable continued operations without a substantial reduction or restructuring of the Pebble Project.
 
 
2020 Annual Information Form
Page | 38
 
 
 

 
 
Risk associated with the Novel Coronavirus ("COVID-19”)
 
The current outbreak of COVID-19, and any future emergence and spread of similar pathogens, could have a material adverse effect on global and local economic and business conditions which may adversely impact Northern Dynasty’s business and results of operations and the operations of contractors and service providers. The extent to which COVID-19 impacts our operations will depend on future developments, which are highly uncertain and cannot be predicted with confidence, including the duration of the outbreak, new information that may emerge concerning its severity and the actions taken to contain the virus or treat its impact, among others. The adverse effects on the economy, the stock market and Northern Dynasty’s share price could adversely impact its ability to raise capital, with the result that our ability to pursue development of the Pebble Project could be adversely impacted, both through delays and through increased costs. Any of these developments, and others, could have a material adverse effect on the Company’s business and results of operations and could delay its plans for development of the Pebble Project.
 
Risk of Secure Title or Property Interest
 
There can be no certainty that title to any property interest acquired by the Company or any of its subsidiaries is without defects. Although the Company has taken reasonable precautions to ensure that legal title to its properties is properly documented, there can be no assurance that its property interests may not be challenged or impugned. Such property interests may be subject to prior unregistered agreements or transfers or other land claims, and title may be affected by undetected defects and adverse laws and regulations.
 
The Pebble Partnership’s mineral concessions at Pebble are located on State of Alaska lands specifically designated for mineral exploration and development. Alaska is a stable jurisdiction with a well-developed regulatory and legal framework for resource development and public lands management, a strong commitment to the rule of law and lengthy track record for encouraging investment in the development of its land and natural resources.
 
The Pebble Project is Subject to Political and Environmental Regulatory Opposition
 
The Pebble Project faces concerted opposition from certain individuals and organizations who are motivated to preclude any possible mining in the Bristol Bay Watershed (the "BBW"). The BBW is an important wildlife and salmon habitat area. Accordingly, one of the greatest risks to the Pebble Project is seen to be political/permitting risk, which may ultimately preclude construction of a mine at the Pebble Project. Opposition may include legal challenges to exploration and development permits, which may delay or halt development. Other tactics may also be employed by opposition groups to delay or frustrate development at Pebble, included political and public advocacy, electoral strategies, media and public outreach campaigns and protest activity.
 
The Pebble Partnership’s Mineral Property Interests Do Not Contain Any Mineral Reserves or Any Known Body of Economic Mineralization.
 
Although there are known bodies of mineralization on the Pebble Project, and the Pebble Partnership has completed core drilling programs within, and adjacent to, the known deposits to determine measured and indicated resources, there are currently no known reserves or body of commercially viable ore. Accordingly, the Pebble Project must be considered an exploration prospect only. Extensive additional work is required before Northern Dynasty or the Pebble Partnership can ascertain if any mineralization may be economic and hence constitute "ore".
 
The current mine plan that is included in the Project Description for the development of the Pebble Project is not supported by any preliminary economic assessment or any preliminary or final feasibility study. Accordingly, even if permitting is achieved, there is a substantial risk the Company we will not be able to proceed with the development of the Pebble Project and shareholders may not be able to recover their investment in the Company
 
 
2020 Annual Information Form
Page | 39
 
 
 

 
 
Mineral Resources Disclosed by Northern Dynasty or the Pebble Partnership for the Pebble Project are Estimates Only.
 
Northern Dynasty has included mineral resource estimates that have been made in accordance with NI 43-101. These resource estimates are classified as "measured resources", "indicated resources" and "inferred resources". Northern Dynasty advises United States investors that although, with the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources", there is no assurance any mineral resources that Northern Dynasty may report as "measured mineral resources", "indicated mineral resources" and "inferred mineral resources" under NI 43-101 would be the same had Northern Dynasty prepared the resource estimates under the standards adopted under the SEC Modernization Rules. Further, "inferred resources" have a great amount of uncertainty as to their economic and legal feasibility. Under Canadian securities law, estimates of inferred mineral resources may not form the basis of feasibility or prefeasibility studies, or any economic study except a Preliminary Economic Assessment as prescribed under NI 43-101.
 
All amounts of mineral resources are estimates only, and Northern Dynasty cannot be certain that any specified level of recovery of metals from the mineralized material will in fact be realized or that the Pebble Project or any other identified mineral deposit will ever qualify as a commercially mineable (or viable) ore body that can be economically exploited. Mineralized material which is not mineral reserves does not have demonstrated economic viability. In addition, the quantity of mineral reserves and mineral resources may vary depending on, among other things, metal prices and actual results of mining. There can be no assurance that any future economic or technical assessments undertaken by the Company with respect to the Pebble Project will demonstrate positive economics or feasibility.
 
The mineral resource estimates contained herein have not been adjusted for any risk that the required environmental permits may not be obtained for the Pebble Project. The risk associated with the ability of the Pebble Project to obtain required environmental permits is a risk to the reasonable prospects for eventual economic extraction of the mineralization and their definition as a mineral resource.
 
There is no assurance that Northern Dynasty will be able to partner the Pebble Project.
 
One of Northern Dynasty’s business objectives is to enter into a joint venture or other partnership arrangement with a third-party partner to fund the advancement of the development of the Pebble Project. There is no assurance that the Company will be able to enter into an arrangement with a partner for the development of the Pebble Project. To the extent that the Company does not enter into any agreement to partner the Pebble Project, it will continue to be required to fund all exploration and other related expenses for advancement of the Pebble Project.
 
Negative Operating Cash Flow
 
The Company currently has a negative operating cash flow and anticipates that it will continue to do so for the foreseeable future. Accordingly, the Company will require substantial additional capital in order to fund its future exploration and development activities. The Company does not have any arrangements in place for this additional funding and there is no assurance that such funding will be achieved when required. Any failure to obtain additional financing or failure to achieve profitability and positive operating cash flows will have a material adverse effect on its financial condition and results of operations.
 
Northern Dynasty Has No History Of Earnings and No Foreseeable Earnings, and May Never Achieve Profitability or Pay Dividends.
 
Northern Dynasty has only had losses since inception and there can be no assurance that Northern Dynasty will ever be profitable. Northern Dynasty has paid no dividends on its shares since incorporation. Northern Dynasty presently has no ability to generate earnings from its mineral properties as its mineral properties are in the pre-development stage.
 
 
2020 Annual Information Form
Page | 40
 
 
 

 
 
Northern Dynasty’s Consolidated Financial Statements Have Been Prepared Assuming Northern Dynasty Will Continue on a Going Concern Basis.
 
Northern Dynasty’ has prepared its Financial Statements on the basis that Northern Dynasty will continue as a going concern. At December 31, 2020, the Company had working capital of approximately $36.5 million. The Group has prioritized the allocation of its financial resources to meet key corporate and Pebble Project expenditure requirements in the near term, including the funding of the appeal of the ROD and associated costs of US government investigations and SEC securities litigation. Additional financing will be required to progress any material expenditures at the Pebble Project and for working capital. Northern Dynasty’s continuing operations and the underlying value and recoverability of the amounts shown for mineral property interest are entirely dependent upon the existence of economically recoverable mineral reserves at the Pebble Project, the ability of the Company to finance its operating costs, the completion of the exploration and development of the Pebble Project, the Pebble Partnership obtaining the necessary permits to mine, and on future profitable production at the Pebble Project. Furthermore, failure to continue as a going concern would require that Northern Dynasty's assets and liabilities be restated on a liquidation basis, which would likely differ significantly from their going concern assumption carrying values.
 
As the Pebble Project is Northern Dynasty’s Only Mineral Property Interest, the Failure to establish that the Pebble Project Possesses Commercially Viable and Legally Mineable Deposits of Ore May Cause a Significant Decline in the Trading Price of Northern Dynasty’s Common Shares and Reduce Its Ability to Obtain New Financing.
 
The Pebble Project, through the Pebble Partnership, is Northern Dynasty’s only mineral project. Northern Dynasty’s principal business objective is to carry out further exploration and related activities to establish whether the Pebble Project possesses commercially viable deposits of ore. If Northern Dynasty is not successful in its plan of operations, Northern Dynasty may have to seek a new mineral property to explore or acquire an interest in a new mineral property or project. Northern Dynasty anticipates that such an outcome would adversely impact the price of Northern Dynasty’s common shares. Furthermore, Northern Dynasty anticipates that its ability to raise additional financing to fund exploration of a new property or the acquisition of a new property or project would be impaired as a result of the failure to establish commercial viability of the Pebble Project.
 
If Prices for Copper, Gold, Molybdenum, Silver and Rhenium Decline, Northern Dynasty May Not Be Able to Raise the Additional Financing Required to Fund Expenditures for the Pebble Project.
 
The ability of Northern Dynasty to raise financing to fund the Pebble Project, will be significantly affected by changes in the market price of the metals for which it explores. The prices of copper, gold, molybdenum, silver and rhenium are volatile, and are affected by numerous factors beyond Northern Dynasty’s control. The level of interest rates, the rate of inflation, the world supplies of and demands for copper, gold, molybdenum, silver and rhenium and the stability of exchange rates can all cause fluctuations in these prices. Such external economic factors are influenced by changes in international investment patterns and monetary systems and political developments. The prices of copper, gold, molybdenum and silver have fluctuated in recent years, and future significant price declines could cause investors to be unprepared to finance exploration of copper, gold, molybdenum, silver and rhenium, with the result that Northern Dynasty may not have sufficient financing with which to fund its activities related to the advancement of the Pebble Project.
 
Mining is Inherently Dangerous and subject to Conditions or Events beyond the Company’s control, which could have a Material Adverse Effect on the Company’s Business.
 
Hazards such as fire, explosion, floods, structural collapses, industrial accidents, unusual or unexpected geological conditions, ground control problems, power outages, inclement weather, seismic activity, cave-ins and mechanical equipment failure are inherent risks in the Company’s exploration, development and mining operations. These and other hazards may cause injuries or death to employees, contractors or other persons at the Company’s mineral properties, severe damage to and destruction of the Company’s property, plant and equipment and mineral properties, and contamination of, or damage to, the environment, and may result in the suspension of the Company’s exploration and development activities and any future production activities. Safety measures implemented by the Company may not be successful in preventing or mitigating future accidents.
 
 
2020 Annual Information Form
Page | 41
 
 

 
 
Northern Dynasty Competes with Larger, Better Capitalized Competitors in the Mining Industry.
 
The mining industry is competitive in all of its phases, including financing, technical resources, personnel and property acquisition. It requires significant capital, technical resources, personnel and operational experience to effectively compete in the mining industry. Because of the high costs associated with exploration, the expertise required to analyze a project’s potential and the capital required to develop a mine, larger companies with significant resources may have a competitive advantage over Northern Dynasty. Northern Dynasty faces strong competition from other mining companies, some with greater financial resources, operational experience and technical capabilities than Northern Dynasty possesses. As a result of this competition, Northern Dynasty may be unable to maintain or acquire financing, personnel, technical resources or attractive mining properties on terms Northern Dynasty considers acceptable or at all.
 
Compliance with Environmental Requirements will take Considerable Resources and Changes to these Requirements Could Significantly Increase the Costs of Developing the Pebble Project and Could Delay these Activities.
 
The Pebble Partnership and Northern Dynasty must comply with stringent environmental legislation in carrying out work on the Pebble Project. Environmental legislation is evolving in a manner that will require stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects and a heightened degree of responsibility for companies and their officers, directors and employees. Changes in environmental legislation could increase the cost to the Pebble Partnership of carrying out its exploration and, if warranted, development of the Pebble Project. Further, compliance with new or additional environmental legislation may result in delays to the exploration and, if warranted, development activities.
 
Changes in Government Regulations or the Application Thereof and the Presence of Unknown Environmental Hazards on Northern Dynasty’s Mineral Properties May Result in Significant Unanticipated Compliance and Reclamation Costs.
 
Government regulations relating to mineral rights tenure, permission to disturb areas and the right to operate can adversely affect Northern Dynasty. Northern Dynasty and the Pebble Partnership may not be able to obtain all necessary licenses and permits that may be required to carry out exploration at the Pebble Project. Obtaining the necessary governmental permits is a complex, time-consuming and costly process. The duration and success of efforts to obtain permits are contingent upon many variables not within the Company’s control. Obtaining environmental permits may increase costs and cause delays depending on the nature of the activity to be permitted and the interpretation of applicable requirements implemented by the permitting authority. There can be no assurance that all necessary approvals and permits will be obtained and, if obtained, that the costs involved will not exceed those that the Company previously estimated. It is possible that the costs and delays associated with the compliance with such standards and regulations could become such that the Company would not proceed with the development or operation of a mine at the Pebble Project.
 
Litigation
 
The Company is, and may in future be subject to legal proceedings, including with regard to actions in Item 12 Legal in the pursuit of its Pebble Project. Given the uncertain nature of these actions, the Company cannot reasonably predict the outcome thereof. If the Company is unable to resolve these matters favorably, it will likely have a material adverse effect on the Company.
 
Northern Dynasty is Subject to Many Risks that Are Not Insurable and, as a Result, Northern Dynasty Will Not Be Able to Recover Losses Through Insurance Should Certain Events Occur.
 
Hazards such as unusual or unexpected geological formations and other conditions are involved in mineral exploration and development. Northern Dynasty may become subject to liability for pollution, cave-ins or hazards against which it cannot insure. The payment of such liabilities could increase Northern Dynasty’s operating expenses which could, in turn, have a material adverse effect on Northern Dynasty’s financial position and its results of operations. Although Northern Dynasty and the Pebble Partnership maintain liability insurance in an amount which they consider adequate, the nature of these risks is such that the liabilities might exceed policy limits, the liabilities and hazards might not be insurable against, or Northern Dynasty and the Pebble Partnership might elect not to insure themselves against such liabilities due to high premium costs or other reasons, in which event Northern Dynasty could incur significant liabilities and costs that could materially increase Northern Dynasty’s operating expenses.
 
 
2020 Annual Information Form
Page | 42
 
 
 

 
 
If Northern Dynasty Loses the Services of Key Personnel that It Engages to Undertake Its Activities, then Northern Dynasty’s Plan of Operations May Be Delayed or Be More Expensive to Undertake than Anticipated.
 
Northern Dynasty’s success depends to a significant extent on the performance and continued service of certain contractors, including Hunter Dickinson Services Inc. ("HDSI"). The Company has access to the full resources of HDSI, an experienced exploration and development firm with in-house geologists, engineers and environmental specialists, to assist in its technical review of the Pebble Project. There can be no assurance that the services of all necessary key personnel will be available when required or, if obtained, that the costs involved will not exceed those previously estimated. It is possible that the costs and delays associated with the loss of services of key personnel could become such that the Company would not proceed with the development or operation of a mine at the Pebble Project.
 
The Market Price of Northern Dynasty’s Common Shares is Subject to High Volatility and Could Cause Investor Loss and Expose Northern Dynasty to the Risk of Litigation.
 
The market price of a publicly traded stock, especially a resource issuer like Northern Dynasty, is affected by many variables in addition to those directly related to exploration successes or failures. Such factors include the general condition of markets for resource stocks, the strength of the economy generally, the availability and attractiveness of alternative investments, and the breadth of the public markets for the stock. The effect of these and other factors on the market price of the Company’s common shares suggests Northern Dynasty’s shares will continue to be volatile. Therefore, investors could suffer significant losses if Northern Dynasty’s shares are depressed or illiquid when an investor needs to sell Northern Dynasty shares.
 
The Volatility of Northern Dynasty’s Common Shares Can Expose Northern Dynasty to the Risk of Litigation.
 
Northern Dynasty’s common shares are listed on the TSX and NYSE American. Securities of mining companies have experienced substantial volatility in the past, often based on factors unrelated to the financial performance or prospects of the companies involved (see previous risk). These factors include macroeconomic developments in North America and globally, currency fluctuations and market perceptions of the attractiveness of particular industries. The price of Northern Dynasty’s common shares is also likely to be significantly affected by short-term changes in copper, gold, molybdenum, silver and rhenium prices or in Northern Dynasty’s financial condition or results of operations as reflected in quarterly earnings reports.
 
As a result of any of these factors, the market price of Northern Dynasty’s common shares at any given point in time may not accurately reflect their long-term value. Securities class action litigation often has been brought against companies following periods of volatility in the market price of their securities. Northern Dynasty is, and may in the future be the target of similar litigation. Securities litigation could result in substantial costs and damages and divert management’s attention and resources.
 
Northern Dynasty Will Require Additional Funding to Meet the Development Objectives of the Pebble Project.
 
Northern Dynasty will need to raise additional financing (through share issuances, debt or asset level partnering) to achieve permitting and development of the Pebble Project. In addition, a positive production decision at the Pebble Project would require significant capital for project engineering and construction. Accordingly, the continuing permitting and development of the Pebble Project will depend upon Northern Dynasty’s ability to obtain financing through debt financing, equity financing, the joint venturing of the project, or other means. There can be no assurance that Northern Dynasty will be successful in obtaining the required financing, or that it will be able to raise the funds on terms that do not result in high levels of dilution to shareholders. If we are unable to raise the necessary capital resources, we may at some point have to reduce or curtail our operations, which would have a material adverse effect on our ability to pursue the permitting and development of the Pebble Project.
 
 
2020 Annual Information Form
Page | 43
 
 
 

 
 
Item 6. Dividends
 
The Company has not paid any dividends on any of its shares since incorporation and does not presently have any intention of paying dividends.
 
Item 7. Description of Capital Structure
 
Northern Dynasty’s share capital consists of no par value common shares only, with an unlimited number being authorized, of which 509,046.631 common shares were issued and outstanding as fully paid and non-assessable as of December 31, 2020. The audited consolidated annual financial statements describe share issuances effected by Northern Dynasty and the weighted average issue price for shares since January 1, 2019.
 
There have been no changes in the classification of common shares (reclassifications, consolidations, reverse splits or the like) within the previous five years. All common shares of Northern Dynasty rank pari passu (i.e. equally) for voting and the payment of any dividends and distributions in the event of a windup.
 
There are no constraints imposed on the ownership of securities of Northern Dynasty.
 
Northern Dynasty’s securities have not received any ratings from any rating organization.
 
Northern Dynasty has entered into registration rights agreements with certain United States shareholders as part of past financing activities. See the Company’s US public filings at www.sec.gov.
 
Item 8. Market for Securities
 
Trading Markets
 
Northern Dynasty's common shares have been listed in Canada on the TSX since October 2007, under the symbol NDM and have traded in the US on NYSE American (formerly NYSE MKT), since November 2004, under the symbol NAK.
 
The following tables set forth, for the periods indicated, the share price history on the TSX and on the NYSE American. Share trading information is available through free internet search services (see below).
 
 
TSX Trading under the symbol NDM
NYSE American Trading under the symbol NAK
Fiscal Year Ended December 31,
High
($)
Low
($)
Average daily
trading
volume
High
(US$)
Low
(US$)
Average daily
trading
volume
2020
3.28
0.39
1,455,055
2.49
0.31
10,183,409
2019
1.47
0.50
290,638
1.12
0.38
1,722,131
2018
2.32
0.55
309,266
1.86
0.43
1,416,234
2017
4.54
1.43
1,700,010
3.45
1.06
5,399,128
2016
3.12
0.28
775,654
2.50
0.20
1,295,079
2015
0.83
0.37
55,058
0.72
0.28
103,728
 
 
TSX Trading under the symbol NDM
NYSE American Trading under the symbol NAK
Fiscal Quarter
High
($)
Low
($)
Average daily
trading
volume
High
(US$)
Low
(US$)
Average daily
trading
volume
Q4 2020
1.67
0.39
1,357,256
1.26
0.31
14,736,695
Q3 2020
3.28
0.77
2,817,989
2.49
0.58
18,375,268
Q2 2020
2.07
0.54
1,135,533
1.53
0.38
4,574,946
Q1 2020
0.93
0.50
509,441
0.71
0.35
2,726,052
Q4 2019
0.86
0.50
235,984
0.66
0.38
1,552,302
Q3 2019
1.25
0.60
453,635
0.95
0.46
2,577,083
Q2 2019
0.88
0.56
173,634
0.66
0.41
1,363,837
Q1 2019
1.47
0.79
299,438
1.12
0.57
1,373,354
 
 
2020 Annual Information Form
Page | 44
 
 
 

 
 
 
TSX Trading under the symbol NDM
NYSE American Trading under the symbol NAK
Last twelve months
High
($)
Low
($)
Average daily
trading
volume
High
(US$)
Low
(US$)
Average daily
trading
volume
February 2021
1.45
0.75
2,911,542
1.15
0.58
75,302,616
January 2021
0.92
0.41
2,223,762
0.73
0.32
46,093,465
December 2020
0.51
0.39
1,082,900
0.40
0.31
14,591,291
November 2020
1.26
0.43
2,193,607
0.97
0.35
22,173,357
October 2020
1.67
1.10
795,260
1.26
0.82
8,121,498
September 2020
1.59
1.19
1,571,781
1.22
0.90
12,616,812
August 2020
2.30
0.77
3,757,958
1.76
0.58
24,750,656
July 2020
3.28
1.87
3,153,034
2.49
1.35
17,786,373
June 2020
2.07
1.49
1,401,302
1.53
1.11
4,841,329
May 2020
2.07
0.78
1,537,762
1.50
0.56
6,241,274
April 2020
0.88
0.54
474,033
0.63
0.38
2,708,898
March 2020
0.83
0.50
436,701
0.62
0.35
2,872,717
 
Source for share price information:
 
● For TSX, refer to www.tmxmoney.com, enter NDM.TO; and.
● For NYSE American, use either https://www.nyse.com/listings_directory/stock or https://ca.finance.yahoo.com/ and enter NAK.
 
Item 9. Escrowed Securities
 
Following the Company’s acquisition of Mission Gold Ltd. on December 24, 2015 there are currently 753,728 common shares in the capital of the Company held in escrow pursuant to TSX-V value escrow agreements and supplemental escrow agreements dated February 13, 2013 among Delta Gold Corporation, a predecessor company to Mission Gold Ltd. (the "issuer"), Olympia Trust Company and the holder of the escrowed shares.
 
In addition to the applicable TSX-V time-based release conditions, the supplemental escrow agreements provide, among other things, that the escrowed shares shall not be released from escrow until the issuer has obtained requisite permits authorizing exploration and development activities at the issuer’s Imperial Project which would allow the issuer to complete the drilling component of the Phase 1 recommended work program as set out in the issuer’s filing statement dated December 28, 2012.
 
Except as outlined above, there are no shares of Northern Dynasty held in escrow.

Item 10. Directors and Officers
 
The names and municipalities of residence of the directors and officers of the Company, their principal occupations during the past five years, and the period of time they have served as directors or officers of Northern Dynasty are presented in the table below. Except where indicated, each director and senior officer of Northern Dynasty has held the same or similar principal occupation with the organization indicated or a predecessor thereof for the last five years. Where shown, the reference to "CEO" refers to "Chief Executive Officer" and "CFO" to "Chief Financial Officer".
 
Name
Position
Director or Officer Since
Desmond M. Balakrishnan
Vancouver, BC, Canada
Director
December 2015
Steven A. Decker 4
Sherman Oaks, CA, United States
Director
March 2016
Robert A. Dickinson
Lions Bay, BC, Canada
Chairman of the Board and Director
June 1994
Gordon B. Keep 2, 3
Vancouver, BC, Canada
Director
October 2015
 
 
2020 Annual Information Form
Page | 45
 
 
 

 
 
Name
Position
Director or Officer Since
Wayne Kirk
Orcas, WA, United States
Director
March 2021
David C. Laing 3, 4, 5
Vancouver, BC, Canada
Director
May 2016
Christian Milau 2, 4, 5
Vancouver, BC, Canada
Director
May 2016
Kenneth W. Pickering 2, 3, 5
Chemainus, BC, Canada
Director
August 2013
Mark Peters North
Vancouver, BC, Canada
CFO
April 2019
Ronald W. Thiessen
West Vancouver, BC, Canada
President, CEO and Director
November 1995
Trevor Thomas
Vancouver, BC, Canada
Secretary
February 2008
Bruce Jenkins
Vancouver, BC, Canada
Executive Vice President, Environment and Sustainability
June 2004
Stephen Hodgson
Vancouver, BC, Canada
Vice President Engineering
March 2005
Sean Magee
North Vancouver, BC, Canada
Vice President Public Affairs
October 2006
Adam Chodos
North Vancouver, BC, Canada
Executive Vice President, Corporate Development
August 2020
Mike Westerlund
North Vancouver, BC, Canada
Vice President, Investor Relations
September 2020
 
(1) To the best of the Company's knowledge, none of such persons has any family relationship with any other and none were elected as a director or appointed as an officer as a result of an arrangement or understanding with a major shareholder, customer, supplier, or any other party.
 
(2) Member of the Audit and Risk Committee. Mr. Milau serves as Chair.
 
(3) Member of the Compensation Committee. Mr. Pickering serves as Chair.
 
(4) Member of the Nominating and Governance Committee. Mr. Laing serves as Chair.
 
(5) Member of the Sustainability Committee. Mr. Pickering serves as Chair.
 
As at March 30, 2021, the directors and officers of Northern Dynasty, and their respective affiliates, directly and indirectly, own or control as a group an aggregate of 11,340,482 common shares (2.2%), or 29,727,459 common shares (5.4%) on a diluted basis.
 
Biographical information
 
The following is the biographical information on each of the persons listed above:
 
Desmond M. Balakrishnan BA., LLB. – Director
 
Mr. Balakrishnan is a lawyer practicing in the areas of Corporate Finance and Securities, Mergers and Acquisitions, Lending, Private Equity and Gaming and Entertainment for McMillan LLP, where he has been a partner since 2004.  McMillan serves as the Company’s Canadian attorneys. He has been lead counsel on over $3 billion in financing transactions and in mergers and acquisitions aggregating in excess of $6 billion.  He also serves as a director and/or officer of several resource, finance and gaming firms.  He holds CLA and BA from Simon Fraser University and a Bachelor of Laws (with Distinction) from the University of Alberta. 
 
 
2020 Annual Information Form
Page | 46
 
 
 

 
 
Mr. Balakrishnan is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
December 2015
Present
Aroway Energy Inc.
TSX-V
Director
July 2010
June 2017
Big Sky Petroleum Corporation
TSX-V
Director
November 2011
November 2020
Contagious Gaming Inc.
TSX-V
Director
August 2014
Present
GrowMax Resources Corp.
TSX-V
Director
May 2020
Present
Isracann Biosciences Inc.
CSE
Director
July 2019
June 2020
Karam Minerals Inc.
CSE
Director
November 2018
Present
Ynvisible Interactive Inc. (formerly Network Exploration Ltd.)
TSX-V
Secretary
May 2008
Present
Liberty One Lithium Corp. (formerly Petro Basin Energy Corp.)
TSX-V (NEX)
Director
February 2012
May 2017
Netcoins Holdings Inc.
CSE
Director
August 2018
Present
Red Rock Capital Corp.
TSX-V (NEX)
Director
February 2012
July 2017
Solution Financial Inc.
TSX-V (NEX)
Director
December 2010
Present
Strategem Capital Corp.
TSE-V
Director
October 2020
Present
 
Steven A. Decker, CFA – Director
 
Mr. Decker is a Chartered Financial Analyst® charter-holder with more than 20 years of investment experience as an Analyst and Portfolio Manager. He holds an MBA in Finance from the Marshall School of Business at the University of Southern California where he received the Marcia Israel Award for Entrepreneurship and was a manager of the California Equity Fund.
 
Mr. Decker is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
March 2016
Present
 
Robert A. Dickinson, B.Sc., M.Sc. – Chairman of the Board and Director
 
Mr. Dickinson is an economic geologist who has been actively involved in mineral exploration and mine development for over 45 years. He was inducted into the Canadian Mining Hall of Fame in 2012. He is Chairman of HDI and HDSI as well as a director and member of the management team of a number of the public companies associated with Hunter Dickinson Inc. He is also President and Director of United Mineral Services Ltd., a private resources company. He also serves as a Director of the Britannia Mine Museum and a Trustee of the BC Mineral Resources Education Program.
 
 
2020 Annual Information Form
Page | 47
 
 
 

 
 
Mr. Dickinson is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
June 1994
Present
Chairman
April 2004
Present
Amarc Resources Ltd.
TSX-V, OTCBB
Director
April 1993
Present
Chairman
April 2004
Present
Heatherdale Resources Ltd.
TSX-V
Director
November 2009
September 2020
Northcliff Resources Ltd.
TSX
Director
June 2011
Present
Quartz Mountain Resources Ltd.
TSX-V
Director
December 2011
February 2019
Chairman
December 2011
February 2019
President & CEO
November 2017
February 2019
Taseko Mines Limited
TSX, NYSE American
Director
January 1991
Present
 
Gordon B. Keep, B.Sc., MBA, P.Geo. – Director
 
Mr. Keep is a Professional Geologist with extensive business experience in investment banking and creating public natural resource companies. Mr. Keep is CEO of Fiore Management & Advisory Corp., a private financial advisory firm. He also serves as an officer and/or director for several natural resource companies. He holds a B.Sc. in Geological Science from Queen's University and an MBA from the University of British Columbia.
 
Mr. Keep is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
October 2015
Present
Tekmodo Industries Inc. (previously CarbonOne Technologies Inc.)
TSX-V
Director
July 2015
January 2017
Catalyst Copper Corp.
TSX-V
Director
April 2008
May 2016
Eastern Platinum Limited
TSX, JSE
Director
November 2003
July 2016
Encanto Potash Corp.
TSX-V
Director
December 2008
December 2017
Chairman
October 2009
December 2017
Gold X Mining Corp. (previously Sandspring Resources Ltd.)
TSX-V
Director
March 2017
March 2020
Klondike Gold Corp.
TSX-V
Director
December 2013
Present
NG Energy International Corp. (previously Cruzsur Energy Ltd.)
TSX-V
Director
July 2017
Present
Oceanic Iron Ore Corp.
TSX-V
Director
September 2010
Present
Petromanas Energy Inc.
TSX-V
Director
August 2010
May 2016
Renaissance Oil Corp.
TSX-V
Director
September 2014
Present
Rusoro Mining Ltd.
TSX-V
Director
November 2006
Present
Vanadian Energy Ltd. (previously Uracan Resources Ltd.)
TSX-V
Director
November 2003
Present
 
Wayne Kirk, LL.B – Director
 
Mr. Kirk has over 35 years of experience as a corporate attorney, including nine years’ experience as Vice President, General Counsel and Corporate Secretary of Homestake Mining Company, and over 16 years of experience as a director of publicly held companies. Mr. Kirk holds a B.A. in Economics (Distinction) from the University of California (Berkeley) and an LL.B (magna cum laude) degree from Harvard University, and has been a member of the California Bar since 1969. Mr. Kirk was a director of the Company from July 2004 to February 2016.
 
Mr. Kirk is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
March 2021
Present
Gabriel Resources Ltd.
TSXV
Director
June 2008
September 2020
Nickel Creek Platinum Corp.
TSX
Director
March 2016
Present
 
 
2020 Annual Information Form
Page | 48
 
 
 

 
 
David Laing, BSc Mining Engineering – Director
 
Mr. Laing is a Mining Engineer with 40 years’ experience in mining operations, projects, engineering studies, mining finance, investor relations, mergers and acquisitions, corporate development, and company building. Mr. Laing was Chief Operating Officer ("COO") of Equinox Gold Corp. Previously he was COO and director of Trek Mining Inc., Luna Gold Corp. and COO of True Gold Mining Inc. Prior to joining True Gold Mining Inc., Mr. Laing was COO and led the origination and execution of stream financing transactions of Quintana Resources Capital ULC, a base metals streaming company. He was also one of the original executives of Endeavour Mining Corporation as the group grew from one mine in Burkina Faso to a 500,000 ounce gold producer in West Africa. Mr. Laing was an integral part of the acquisition and integration of three junior gold producers and led the feasibility of a fourth project, in Burkina Faso. Prior to these recent roles, Mr. Laing held senior positions in mining investment banking at Standard Bank in New York, technical consulting at MRDI in California, the Refugio project at Bema Gold Corp. and various roles at Billiton and Royal Dutch Shell's mining business.
 
Mr. Laing is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
May 2016
Present
Amarillo Gold Corporation
TSX-V
Director
October 2020
Present
Aton Resources Inc.
TSX-V
Director
May 2016
Present
Blackrock Gold Corp.
TSX-V
Director
April 2020
Present
Equinox Gold Corp.2
TSX, NYSE American
COO
December 2017
November 2018
Fortuna Silver Mines Inc.
TSX, NYSE
Director
September 2016
Present
KBL Mining Limited
ASX
Director
March 2015
January 2016
Luna Gold Corp.2
TSX
COO and Director
August 2016
March 2017
Gold X Mining Corp. (previously Sandspring Resources Ltd.)
TSX-V
Director
August 2015
March 2020
Trek Mining Inc.2
TSX-V
COO and Director
March 2017
December 2017
True Gold Mining Inc. 1
TSX-V
COO
July 2015
April 2016
 
Note:
 
1. The Company was acquired by Endeavour in April 2016 and its shares were delisted.
 
2. Equinox Gold Corp. is the result of the merger in December 2017 of Trek Mining Inc., NewCastle Gold Ltd. and Anfield Gold Corp. Trek Mining Inc. was the result of the merger of Luna Gold Corp. and TSX-V listed JDL Gold Corp. in March 2017.
 
Christian Milau, CPA, CA, CPA (Illinois) – Director
 
Mr. Milau is is a Chartered Professional Accountant (Chartered Accountant). Mr Milau is CEO and Director of Equinox Gold Corp. Prior to this he was President and CEO of Trek Mining Inc., Luna Gold Corp. and True Gold Mining Inc. Mr. Milau has finance and capital markets experience as well as operational, government and stakeholder relations experience in North and South America and West Africa. Prior to these recent roles, Mr. Milau was CFO at Endeavour Mining Corporation and was Treasurer at New Gold Inc.
 
Mr. Milau is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
May 2016
Present
Equinox Gold Corp.2
TSX, NYSE American
CEO and Director
December 2017
Present
Luna Gold Corp. 2
TSX
CEO and Director
August 2016
March 2017
Plateau Energy Metals Inc.
TSX-V
Director
June 2016
Present
Trek Mining Inc.2
TSX-V
CEO and Director
March 2017
December 2017
True Gold Mining Inc. 1
TSX-V
President, CEO and Director
March 2015
April 2016
 
 
2020 Annual Information Form
Page | 49
 
 
 

 
 
Note:
 
1. The Company was acquired by Endeavour in April 2016 and its shares were delisted.
 
2. Equinox Gold Corp. is the result of the merger in December 2017 of Trek Mining Inc., NewCastle Gold Ltd. and Anfield Gold Corp. Trek Mining Inc. was the result of the merger of Luna Gold Corp. and TSX-V listed JDL Gold Corp. in March 2017.
 
Kenneth W. Pickering., PEng. – Director
 
Mr. Pickering is a Professional Engineer and mining executive with 40 years of experience in a variety of capacities in the natural resources industry. He has led the development, construction and operation of world-class mining projects in Canada, Chile, Australia, Peru and the United States, focusing on operations, executive responsibilities and country accountabilities.
 
Mr. Pickering is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
August 2013
Present
Enaex Chile
IPSA
Director
May 2011
May 2018
Endeavour Silver Corp.
TSX, NYSE
Director
August 2012
Present
Taseko Mines Limited
TSX, NYSE American
Director
July 2018
Present
Teck Resources
TSX, NYSE
Director
March 2015
Present
THEMAC Resources Group Limited
TSX-V
Director
March 2011
December 2016
 
Ronald W. Thiessen, FCPA, FCA – Director, President and Chief Executive Officer
 
Mr. Thiessen is a Chartered Professional Accountant (CPA, CA) with professional experience in finance, taxation, mergers, acquisitions and re-organizations. Since 1986, Mr. Thiessen has been involved in the acquisition and financing of mining and mineral exploration companies. Mr. Thiessen is a director of HDI and HDSI (and HDI), a company providing management and administrative services to several publicly-traded companies and focuses on directing corporate development and financing activities.
 
Mr. Thiessen is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Director
November 1995
Present
President and CEO
November 2001
Present
Amarc Resources Ltd.
TSX-V, OTCBB
Director
September 1995
February 2019
CEO
September 2000
February 2019
Quartz Mountain Resources Ltd.
TSX-V
President, CEO and Director
December 2011
December 2017
Taseko Mines Limited
TSX, NYSE American
Director
October 1993
Present
Chairman
May 2006
Present
 
Mark Peters, CPA, CA – Chief Financial Officer
 
Mr. Peters is a Chartered Professional Accountant (CPA, CA) who has more than 18 years of experience in the areas of financial reporting and taxation, working primarily with Canadian and US public corporations. He is an experienced CFO, having served as CFO for HDSI since 2016 and for a TSX Venture-listed company from 2012 until 2020. Prior to that, Mr. Peters led the tax department for the HDI group of companies. Before joining HDI in 2007, Mr. Peters worked for PricewaterhouseCoopers LLP in the both the audit and tax groups.
 
 
2020 Annual Information Form
Page | 50
 
 
 

 
 
Mr. Peters is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
CFO
April 2019
Present
Heatherdale Resources Ltd.
TSX-V
CFO
March 2012
August 2020
Canada Rare Earth Corp.
TSX-V
Director
March 2017
Present
 
Trevor Thomas, LLB – Secretary
 
Trevor Thomas has practiced in the areas of corporate commercial, corporate finance, securities and mining law since 1995, both in private practice environment as well as in house positions and is currently general counsel for HDI. Prior to joining HDI, he served as in-house legal counsel with Placer Dome Inc.
 
Mr. Thomas is, or was within the past five years, an officer and/or director of the following public companies:
 
Company
Name of Market
Positions Held
From
To
Northern Dynasty Minerals Ltd.
TSX, NYSE American
Secretary
February 2008
Present
Amarc Resources Ltd.
TSX-V, OTCBB
Secretary
February 2008
Present
Heatherdale Resources Ltd.
TSX-V
Secretary
June 2013
August 2020
Mineral Mountain Resources Ltd.
TSX-V
Director
September 2016
Present
Northcliff Resources Ltd.
TSX
Secretary
June 2011
Present
Quadro Resources Ltd.
TSX-V
Secretary
June 2017
Present
Quartz Mountain Resources Ltd.
TSX-V
Secretary
June 2013
Present
Rathdowney Resources Ltd.
TSX-V
Secretary
March 2011
Present
RE Royalties Ltd.
TSX-V
Secretary
November 2018
Present
Taseko Mines Limited
TSX, NYSE American
Secretary
July 2008
Present
 
Bruce Jenkins – Executive Vice President, Environment and Sustainability
 
Mr. Jenkins is an environmental and government relations executive with more than 40 years of experience in project and corporate management. He supports the Pebble Partnership and helps guide environmental studies, mitigation planning and permitting activities. Mr. Jenkins is also Executive Vice President of Environment and Sustainability for HDI.
 
Stephen Hodgson – Vice President, Engineering
 
Mr. Hodgson is a professional engineer with over 40 years of experience in consulting, project management, feasibility-level design and implementation, and mine operations at some of the largest mineral development projects in the world. He brings a unique perspective to the Pebble team with his experience at northern and Arctic mines. He has led the Northern Dynasty engineering team since 2005. He was also Senior Vice President of Engineering and Project Director, Engineering, for the Pebble Limited Partnership until February 28, 2021.
 
Sean Magee – Vice President, Public Affairs
 
Mr. Magee is a former journalist, speech writer and public affairs consultant with more than 30 years of communications experience. His experience and expertise spans the fields of government and stakeholder relations, community and First Nations/Native engagement, media relations, crisis and issues management. He has played a central role at Pebble for more than a decade. He has had a working relationship with HDI for more than 25 years and is HDI's Executive Vice President of Strategic Communications and Public Affairs.
 
Adam Chodos – Executive Vice President, Corporate Development
 
Mr. Chodos is a senior executive with over 19 years of experience in Corporate Development and Investment Banking advisory. Mr. Chodos was most recently a Director of Corporate Development for Teck Resources and, prior to that, was a Group Executive with Newmont’s Corporate Development team. Before joining Newmont, Mr. Chodos spent nine years as an Investment Banker with J.P. Morgan Securities Inc., in New York, specializing in the Natural Resources sector. He had a significant role in over US$28 billion of mergers, acquisitions, divestitures and capital markets transactions. Mr. Chodos has a Bachelor of Commerce degree from McGill University. He is also Executive Vice President, Corporate Development for HDSI.
 
 
2020 Annual Information Form
Page | 51
 
 
 

 
 
Mike Westerlund – Vice President, Investor Relations
 
Mr. Westerlund is a seasoned investor relations executive with 20 years' experience in the North American metals and mining industry. Most recently, Mr. Westerlund was Vice President, Investor Relations with Hecla Mining Company, a US$3 billion NYSE-listed precious metals company with five operating mines in Canada, the United States and Mexico, where he directed the investor relations department for eight years. Previously, Mr. Westerlund worked with a series of mineral exploration and mining firms with development stage and operating assets throughout North America.
 
Committees of the Board of Directors
 
The following committees have been established by the members of Northern Dynasty’s board of directors:
 
Committee
Membership
Audit and Risk Committee
Christian Milau (Chair)
Gordon Keep
Kenneth Pickering
Compensation Committee
Kenneth Pickering (Chair)
Gordon Keep
David Laing
Nominating and Governance Committee
David Laing (Chair)
Steven Decker
Christian Milau
Sustainability Committee
Kenneth Pickering (Chair)
David Laing
Christian Milau
 
The mandate of each of these committees is more particularly described in Northern Dynasty’s Corporate Governance Policies and Procedures Manual available on the Company’s website at: www.northerndynastyminerals.com.
 
Bankruptcies, Cease Trade Orders, Penalties or Sanctions
 
No director or officer of Northern Dynasty is, as of the date of this Annual Information Form, or has been within the ten years before the date of this Annual Information Form, a director or officer of any company that while that person was acting in that capacity, was the subject of a bankruptcy, cease trade order, penalties or sanctions, during the time the individual was a director or within a one year period thereafter, or was a director or officer of a company during the time in which an event occurred which led to a bankruptcy, cease trade order, penalties or sanctions subsequent to the individual ceasing to act as a director or officer. This information has been provided by each director or officer, as the Company is unable to verify these statements independently.
 
Exceptions
 
As publicly disclosed at www.sedar.com, Great Basin Gold Ltd. ("GBG"), a company for which Messrs. Kirk and Thiessen were at one time directors, became bankrupt due to heavy indebtedness, mine production issues and falling gold prices. GBG was liquidated, commencing in September 2012. Mr. Kirk resigned in January 2012 and Mr. Thiessen resigned in June 2013.
 
On May 21, 2013, the British Columbia Securities Commission ("BCSC") issued a cease trade order against Rusoro Mining Ltd. ("Rusoro"), a company for which Mr. Keep serves as a director. The cease order was for the failure by Rusoro to file its audited financial statements for the year ended December 31, 2012 and related MD&A ("2012 Year End Disclosure"). On June 5, 2013, and June 7, 2013, respectively, similar cease trade orders were issued against Rusoro by the Ontario Securities Commission ("OSC") and the Autorité des Marchés Financiers ("AMF"). On August 19, 2013, Rusoro filed its 2012 Year End Disclosure. On August 21, 2013, August 28, 2013 and September 4, 2013, BCSC, AMF and OSC respectively, granted full revocations of their cease trade orders. Rusoro was unable to file its 2012 Year End Disclosure by the required filing deadline because it experienced significant delays in preparing them due to the nationalization by the Venezuelan government of Rusoro’s gold mining assets in Venezuela.
 
 
2020 Annual Information Form
Page | 52
 
 
 

 
 
Potential Conflicts of Interest
 
Other than Mr. Decker, the directors of Northern Dynasty also serve as directors of other similar companies involved in natural resource development. It may occur from time to time that, as a consequence of a particular director’s activity in the mining and mineral industry and serving on such other boards, a director may become aware of potential resource property opportunities which are of interest to more than one of the companies on whose boards that person serves. Furthermore, it is possible that the directors Northern Dynasty and the directors of one or more such other companies (many of which are described herein) may also agree to allow joint participation on Northern Dynasty’s properties or the properties of that other company. Accordingly, situations may arise in the ordinary course which involve a director in an actual or potential conflict of interest as well as issues in connection with the general obligation of a director to make corporate opportunities available to Northern Dynasty and other companies on whose board the director serves. In all such events, any director is required to disclose a financial interest in a contract or transaction by virtue of office, employment or security holdings or other such interest in another company or in a property interest under consideration by the Board, and is obliged to abstain from voting as a director of Northern Dynasty in respect of any transaction involving that other company or in respect of any property in which an interest is held by said director. The directors will use their best business judgment to help avoid situations where conflicts or corporate opportunity issues might arise and they must at all times fulfil their duties to act honestly and in the best interests of Northern Dynasty as required by law.
 
Item 11.   Promoters
 
Not applicable.
 
Item 12.   Legal
 
Grand Jury Subpoena
 
On September 23, 2020, the Company announced that Tom Collier, the former Chief Executive Officer of the Pebble Partnership, had submitted his resignation in light of comments made about elected and regulatory officials in Alaska and the Pebble Project in private conversations covertly videotaped by an environmental activist group. Conversations with Mr. Collier, as well as others with Ron Thiessen, Northern Dynasty’s President and Chief Executive Officer, were secretly videotaped or audiotaped by unknown individuals posing as representatives of a Hong Kong-based investment firm, which represented that it was linked to a Chinese State-Owned Enterprise (SOE). The Company understands that a Washington DC-based environmental group, the Environmental Investigation Agency, released portions of the recordings online after obscuring the voices and identities of the individuals posing as investors. The Company is still considering its remedies, if any, with respect to the creation of these recordings.
 
Following the release of the recordings, the USACE issued a statement that, following a review of the transcripts of the recordings, they had “identified inaccuracies and falsehoods relating to the permit process and the relationship between our regulatory leadership and the applicant’s executives”. Further, the Pebble Partnership received a letter from the Committee on Transportation and Infrastructure of the United States House of Representatives on November 19, 2020 stating that the comments made by Mr. Collier and Mr. Thiessen regarding the expansion, capacity, size and duration were believed to be inconsistent with the testimony of Mr. Collier before the Committee and demanding production of documents apparently related to the comments.
 
On February 5, 2021, the Company announced that the Pebble Partnership and Tom Collier, the former Chief Executive Officer of the Pebble Partnership, had each been served with a subpoena issued by the United States Attorney’s Office for the District of Alaska to produce documents in connection with a grand jury investigation. The Company and the Pebble Partnership are cooperating with the investigation. The Company is not aware of any civil or criminal charges having been filed against any entity or individual in this matter. The Company also self-reported this matter to the US Securities and Exchange Commission (SEC), and there is a related informal inquiry being conducted by the enforcement staff of the San Francisco Regional Office.
 
 
2020 Annual Information Form
Page | 53
 
 
 

 
 
Class Action Litigation Relating to the USACE’s Record of Decision
 
On December 4 and December 17, 2020, separate putative shareholder class action lawsuits were filed against the Company and certain of its current and former officers and directors in the U.S. District Court for the Eastern District of New York regarding the drop in the price of the Company’s stock following the ROD by the USACE regarding the Pebble Project. These cases are captioned Darish v. Northern Dynasty Minerals Ltd. et al., Case No. 1:20-cv-05917-ENV-RLM, and Hymowitz v. Northern Dynasty Minerals Ltd. et al., Case No. 1:20-cv-06126-PKC-RLM. Each of the complaints was filed on behalf of a purported class of investors who purchased shares of the Company’s stock from December 21, 2017, through November 25, 2020, the date the USACE announced its decision, and seeks damages allegedly caused by violations of the federal securities laws.  On March 17, 2021, two cases were consolidated and a lead plaintiff and counsel were appointed.  The Company, which has yet been to be served with the complaint, intends to defend itself vigorously against these actions.
 
On December 3, 2020, a putative shareholder class action lawsuit was filed against the Company, certain of its current and former officers and directors, and one of its underwriters in the Supreme Court of British Columbia regarding the decrease in the price of the Company’s stock following the USACE’s November 25, 2020, decision regarding the Pebble Project. The case is captioned Haddad v. Northern Dynasty Minerals Ltd. et al., Case No. VLC-S-S-2012849. The claim was filed on behalf of a purported class of investors, wherever they may reside, who acquired common shares of the Company’s stock between December 21, 2017 and November 25, 2020, and seeks damages for (i) alleged misrepresentations in the Company’s primary market offering documents and continuous disclosure documents, and (ii) its allegedly oppressive conduct. The Company has been served the claim and intends to defend itself vigorously. The underwriter has asserted contractual rights of indemnification against the Company for any loss that the underwriter may incur in connection with the lawsuit.
 
On February 17, 2021, a putative shareholder class action lawsuit was filed against the Company, certain of its current and former officers and directors, and certain of its underwriters in the Supreme Court of British Columbia regarding the decrease in the price of the Company’s stock following (i) the USACE’s August 24, 2020 announcement that the Pebble Project could not be permitted as proposed, and (ii) the USACE’s November 25, 2020 decision regarding the Pebble Project. The case is captioned Woo v. Northern Dynasty Minerals Ltd. et al., Case No. VLC-S-S-211530. The claim was filed on behalf of a purported class of investors, wherever they may reside, who purchased securities of the Company between June 25, 2020 and November 25, 2020, and seeks damages for (i) alleged misrepresentations in the Company’s primary market offering documents and continuous disclosure documents, (ii) allegedly oppressive conduct, (iii) alleged unjust enrichment, and (iv) negligence. The Company has been served and intends to defend itself vigorously. One of the underwriters has asserted contractual rights of indemnification against the Company for any loss that the underwriter may incur in connection with the lawsuit.
 
On March 5, 2021, a putative shareholder class action lawsuit was filed against the Company, certain of its current and former officers and directors, and certain of its underwriters in the Ontario Superior Court of Justice regarding the decrease in the price of the Company’s stock following the USACE’s November 25, 2020 decision regarding the Pebble Project. The case is captioned Pirzada v. Northern Dynasty Minerals Ltd. et al., Case No. CV-21-00658284-00CP. The claim was filed on behalf of a purported class of investors, wherever they may reside, who acquired securities of the Company between June 25, 2020 and November 25, 2020, and seeks damages for (i) alleged misrepresentations in the Company’s primary market offering documents and continuous disclosure documents, (ii) allegedly oppressive conduct, and (iii) alleged negligence. The Company has not been served and intends to defend itself vigorously.
 
 
2020 Annual Information Form
Page | 54
 
 
 

 
 
Indemnification Obligations
 
The Company is subject to certain indemnification obligations to both present and former officers and directors, including Mr. Collier, in respect to the legal proceedings described above. These indemnification obligations will be subject to limitations prescribed by law and the articles of the Company, and may also be subject to contractual limitations.

Class Action Litigation Relating To Short Seller Investment Report
 
On February 14, 2017, short seller investment firm Kerrisdale Capital Management LLC published a negative piece (the "Kerrisdale Report") regarding the Pebble Project.  Three putative shareholder class actions were filed against the Company and certain of its current officers and directors in US federal courts. Two of the plaintiffs voluntarily dismissed their claims and were brought into the third action, captioned Victor Diaz v. Northern Dynasty Minerals Ltd., et al in the Central District of California, which was later dismissed by the courts. The time period for the plaintiffs to appeal has expired and there is no further opportunity for the plaintiffs to appeal the district court’s dismissal order or the appellate court’s affirmation of that decision.
 
Risk Factors
 
The outcomes of the legal proceedings described above cannot be predicted and resolution of these legal proceedings will likely involve significant expense to the Company. In addition, adverse outcomes in these legal proceedings may have a material adverse effect on the Company’s business, future prospects and financial condition. Investors should refer to the risk factors identified above under Item 5 – Description of Business – Risk Factors, starting on page 31, for a discussion of risks relating to the legal proceedings described above.
 
Regulatory Actions
 
There have been no:
 
(a)  penalties or sanctions imposed against the Company by a court relating to securities legislation or by a securities regulatory authority during the most recently completed financial year,
or
 
(b)  other material penalties or sanctions imposed by a court or regulatory body against the Company, or
 
(c)  settlement agreements the Company entered into before a court relating to securities legislation or with a securities regulatory authority during the most recently completed financial year.
 
 
2020 Annual Information Form
Page | 55
 
 
 

 
 
Item 13.  Interest of Management and Others in Material Transactions
 
None of the directors or senior officers of the Company, nor any person who has held such a position since the beginning of the last completed financial year end of the Company, nor any associate or affiliate of the foregoing persons, has any substantial or material interest, direct or indirect, by way of beneficial ownership of securities or otherwise, in any material transactions of the Company other than as set out herein.
 
Certain directors of a private company, HDSI, a wholly owned subsidiary of HDI (see Item 10) are also directors of the Company. Pursuant to a management services agreement with HDSI, HDSI provides geological, corporate development, administrative and management services to, and incurs third party costs on behalf of, the Company and its subsidiaries at annually set rates. During the year ended December 31, 2020, the Company paid HDSI approximately $5.6 million (2019 – $4.9 million) for services rendered by HDSI and reimbursed HDSI approximately $0.6 million (2019 – $0.9 million) for third party costs incurred on the Company’s behalf. Certain members of the Company’s senior management including the Company’s CFO are employed by HDSI rather than by Northern Dynasty directly.
 
Item 14.  Transfer Agent and Registrar
 
The Company's registrar and transfer agent is Computershare Trust Company of Canada, located in Vancouver, BC.
 
Item 15.  Material Contracts
 
Northern Dynasty's only material contract as of March 30, 2021 is:
 
● Corporate Services Agreement between Northern Dynasty and Hunter Dickinson Services Inc. dated July 2, 2010.
 
Other agreements are in the normal course of business.
 
Item 16.  Interests of Experts
 
David Gaunt, P.Geo., Eric Titley, P.Geo., and Stephen Hodgson, P.Eng2., of Hunter Dickinson Services Inc. ("HDSI"), and James Lang, P.Geo., and Ting Lu, P.Eng., consultants, are persons:
  
● who are named as in a report described in a filing, or referred to in a filing, made under National Instrument 51-102 by the Company during, or relating to, the Company’s most recently completed financial year; and
 
● whose profession or business gives authority to the report made by each of them.
 
Messrs. Gaunt, Titley and Hodgson, employees of HDSI, and Mr. Lang, a former employee and consultant to HDSI hold interests in the common shares of the Company, directly or indirectly, or through share purchase options, each representing less than 1% of the Company's outstanding share capital. Ms. Lu, a former employee of Tetra Tech Canada Inc., holds no interest in the Company.
 
Deloitte LLP, Independent Registered Public Accounting Firm, is the auditor of Northern Dynasty and is independent of Northern Dynasty within the meaning of the Rules of Professional Conduct of the Chartered Professional Accountants of British Columbia and within the meaning of U.S. Securities Exchange Act of 1933, as amended, and the applicable rules and regulations thereunder adopted by the SEC and the Public Company Accounting Oversight Board (United States).
 
2 An employee of Hunter Dickinson US Servicepay Inc. until February 28, 2021
 
 
2020 Annual Information Form
Page | 56
 
 
 

 
 
Item 17.    Additional Information
 
Additional information, including directors' and officers' remuneration, indebtedness of officers, executive stock options and interests of management and others in material transactions, where applicable, is contained in annual financial statements, management’s discussion and analysis, proxy circulars and interim financial statements of the Company, available under the Company’s profile on SEDAR at www.sedar.com and from the SEC’s Electronic Document Gathering and Retrieval System ("EDGAR") at www.sec.gov.
 
The following documents can be obtained upon request from Northern Dynasty’s Shareholder Communication Department by calling (604) 684-6365:
 
● this AIF, together with any document incorporated herein by reference;
 
● interim consolidated financial statements filed with Securities Commissions subsequent to the audited consolidated financial statements for the Company's most recently completed financial year; and
 
● the Proxy Circular for the annual general meeting of the Company when available.
 
The Company may require the payment of a reasonable charge from persons, other than security holders of the Company, requesting copies of these documents.
 
Item 18.     Disclosure for Companies not Sending Information Circulars
 
Not applicable.
 
Item 19.    Audit and Risk Committee, Auditor Fees, Exemptions, Code of Ethics
 
Audit and Risk Committee (the "Audit Committee")
 
Audit Committee Charter
 
The Audit Committee has adopted a charter that sets out its mandate and responsibilities, and is attached to this AIF as Appendix A.
 
Composition of the Audit Committee
 
The Audit Committee currently consists of Christian Milau (Chair), Ken Pickering and Gordon Keep. The Audit Committee reviews all financial statements of the Company prior to their publication, reviews audits performed, considers the adequacy of audit procedures, recommends the appointment of independent auditors, reviews and approves the professional services to be rendered by them and reviews fees for audit services. The Audit Committee Charter has set criteria for membership which all committee members are required to meet, consistent with National Instrument 52-110, Audit Committees ("NI 51-110"), and other applicable regulatory requirements. The Audit Committee, as needed, meets separately (without management present) with the Company’s auditors to discuss the various aspects of the Company’s financial statements and the independent audit.
 
Each Audit Committee member is an independent director and is financially literate. Mr. Keep has extensive business knowledge and is a director of a number of companies. Mr. Pickering has been a member on other audit committees of publicly listed companies. Mr. Milau, the Audit and Risk Committee Chairman is a Chartered Professional Accountant and is a financial expert.
 
 
2020 Annual Information Form
Page | 57
 
 
 

 
 
Relevant Education and Experience
 
As a result of their education and experience, each member of the Audit Committee has familiarity with, an understanding of, or experience in:
 
● the accounting principles used by the Company to prepare its financial statements, and the ability to assess the general application of those principles in connection with estimates, accruals and reserves;
 
● reviewing or evaluating financial statements that present a breadth and level of complexity of accounting issues that are generally comparable to the breadth and complexity of issues that can reasonably be expected to be raised by the Company's financial statements, and
 
● an understanding of internal controls and procedures for financial reporting.
 
See disclosure regarding biographical information in Item 10.
 
Reliance on Certain Exemptions Available in NI 52-110
  
The Company’s auditor, Deloitte LLP, has not provided any non-audit services during the most recently completed fiscal year.
 
Pre-Approval Policies and Procedures
 
The Company has procedures for the review and pre-approval of any services performed by its auditor. The procedures require that all proposed engagements of its auditor for audit and non-audit services be submitted to the Audit Committee for approval prior to the beginning of any such services. The Audit Committee considers such requests and, if acceptable to a majority of the Audit Committee members, pre-approves such audit and non-audit services by a resolution authorizing management to engage the Company’s auditor for such audit and non-audit services, with set maximum dollar amounts for each itemized service. During such deliberations, the Audit Committee assesses, among other factors, whether the services requested would be considered "prohibited services" as contemplated by the regulations of the SEC, and whether the services requested and the fees related to such services could impair the independence of the auditors.
 
Principal Accountant Fees and Services
 
The Audit Committee has reviewed the nature and amount of the audit and non-audit services provided by Deloitte LLP to the Company to ensure auditor independence. Fees incurred with Deloitte LLP for audit and non-audit services in the last two fiscal years are outlined in the following table:
 
Nature of Services
 
Year ended
December 31
2020
Year ended
December 31
2019
Audit Fees
the aggregate fees billed by our independent auditor for the audit of our annual consolidated financial statements, reviews of interim consolidated financial statements and attestation services that are provided in connection with statutory and regulatory filings or engagements.
$ 182,000
$ 145,000
Audit-Related Fees1
include services that are traditionally performed by the auditor. These audit-related services include employee benefit audits, due diligence assistance, accounting consultations on proposed transactions, internal control reviews and audit or attest services not required by legislation or regulation.
74,000
158,000
Tax Fees
include fees for all tax services other than those included in “Audit Fees” and “Audit-Related Fees”. This category includes fees for tax compliance, tax planning and tax advice. Tax planning and tax advice includes assistance with tax audits and appeals, tax advice related to mergers and acquisitions, and requests for rulings or technical advice from tax authorities.
All Other Fees
include all other non-audit services.
Total
 
$ 256,000
$ 303,000
 
Note
1 Audit related fees relate to assistance with the Company's prospectus supplements filed in December/January 2019/2020 and April/May 2020, the short form base shelf prospectus filed in June 2020 and the prospectus supplement filed in July 2020.
 
2020 Annual Information Form
Page | 58
 
 
 

 
 
From time to time, management of the Company recommends to and requests approval from the Audit Committee for audit and non-audit services to be provided by the Company's auditors. The Audit Committee routinely considers such requests at committee meetings, and if acceptable to a majority of the Audit Committee members, pre-approves such audit and non-audit services by a resolution authorizing management to engage the Company's auditors for such non-audit services, with set maximum dollar amounts for each itemized service. During such deliberations, the Audit Committee assesses, among other factors, whether the non-audit services requested would be considered "prohibited services" as contemplated by the SEC, and whether the non-audit services requested and the fees related to such services could impair the independence of the auditors.
 
Code of Ethics
 
The Company has adopted a code of ethics that applies to all directors, officers and employees of the Company. A copy of the Code of Ethics, which is included as part of the Company’s Governance Policies and Procedures Manual is available for download from the Company’s website at www.northerndynastyminerals.com and under the Company’s profile on SEDAR at www.sedar.com.
 
 
2020 Annual Information Form
Page | 59
 
 
 

 
 
Appendix A - Audit and Risk Committee Charter
 
1. Purpose: Responsibilities and Authority
 
The Audit and Risk Committee (the “Audit Committee” or “Committee”) shall carry out its responsibilities under applicable laws, regulations and stock exchange requirements with respect to the employment, compensation and oversight of the Company’s independent auditor, and other matters under the authority of the Committee. The Committee also shall assist the Board of Directors in carrying out its oversight responsibilities relating to the Company’s financial, accounting and reporting processes, the Company’s system of internal accounting and financial controls, the Company’s compliance with related legal and regulatory requirements, and the fairness of transactions between the Company and related parties. In furtherance of this purpose, the Committee shall have the following responsibilities and authority:
 
(a) Relationship with Independent Auditor.
 
(i) Subject to the law of British Columbia as to the role of the Shareholders in the appointment of independent auditors, the Committee shall have the sole authority to appoint or replace the independent auditor.
 
(ii) The Committee shall be directly responsible for the compensation and oversight of the work of the independent auditor (including resolution of disagreements between management and the independent auditor regarding financial reporting) for the purpose of preparing or issuing an audit report or related work.
 
(iii) The independent auditor shall report directly to the Committee.
 
(iv) The Committee shall approve in advance all audit and permitted non-audit services with the independent auditor, including the terms of the engagements and the fees payable; provided that the Committee Chair may approve services to be performed by the independent auditors and the fee therefor between Committee meetings if the amount of the fee does not exceed $50,000, provided that any such approval shall be reported to the Committee at the next meeting thereof. The Committee may delegate to a subcommittee the authority to grant pre-approvals of audit and permitted non-audit services, provided that the decision of any such subcommittee shall be presented to the full Committee at its next scheduled meeting.
 
(v) At least annually, the Committee shall review and evaluate the experience and qualifications of the lead partner and senior members of the independent auditor team.
 
(vi) At least annually, the Committee shall obtain and review a report from the independent auditor regarding:
 
(A) the independent auditor’s internal quality-control procedures;
 
(B) any material issues raised by the most recent internal quality-control review, or peer review, of the auditor, or by any inquiry or investigation by governmental or professional authorities within the preceding five years respecting one or more independent audits carried out by the firm;
 
(C) any steps taken to deal with any such issues; and
 
(D) all relationships between the independent auditor and the Company.
 
 
2020 Annual Information Form
Page | 60
 
 
 

 
 
(vii) At least annually, the Committee shall evaluate the qualifications, performance and independence of the independent auditor, including considering whether the auditor’s quality controls are adequate and the provision of permitted non-audit services is compatible with maintaining the auditor’s independence.
 
(viii) The Committee shall ensure the rotation of the lead (or coordinating) audit partner having primary responsibility for the audit, the concurring partner responsible for reviewing the audit, and other audit partners as required by law.
 
(ix) The Committee shall consider whether, in order to assure continuing auditor independence, it is appropriate to adopt a policy of rotating the independent auditing firm on a regular basis.
 
(x) The Committee shall recommend to the Board policies for the Company’s hiring of employees or former employees of the independent auditor who were engaged on the Company’s account or participated in any capacity in the audit of the Company.
 
(xi) The Committee shall oversee the implementation by management of appropriate information technology systems for the Company, including as required for proper financial reporting and compliance.
 
(b) Financial Statement and Disclosure Review.
 
(i) The Committee shall review and discuss with management and the independent auditor the annual audited financial statements, including disclosures made in management’s discussion and analysis, and recommend to the Board whether the audited financial statements should be filed with applicable securities regulatory authorities and included in the Company’s annual reports.
 
(ii) The Committee shall review and discuss with management (and, to the extent the Committee deems it necessary or appropriate, the independent auditor) the Company’s quarterly financial statements, including disclosures made in management’s discussion and analysis, and recommend to the Board whether such financial statements should be filed with applicable securities regulatory authorities.
 
(iii) The Committee shall review and discuss with management and the independent auditor significant financial reporting issues and judgments made in connection with the preparation of the Company’s financial statements, including the independent auditor’s assessment of the quality of the Company’s accounting principles, any significant changes in the Company’s selection or application of accounting principles, any major issues as to the adequacy of the Company’s internal controls over financial reporting, and any special steps adopted in light of material control deficiencies.
 
(iv) At least annually and prior to the publication of annual audited financial statements, the Committee shall review and discuss with management and the independent auditor a report from the independent auditor on:
 
(A) all critical accounting policies and practices used by the Company;
 
(B) all alternative accounting treatments of financial information that have been discussed with management since the prior report, ramifications of the use of such alternative disclosures and treatments, the treatment preferred by the independent auditor, and an explanation of why the independent auditor’s preferred method was not adopted; and.
 
 
2020 Annual Information Form
Page | 61
 
 
 

 
 
(C) other material written communications between the independent auditor and management since the prior report, such as any management letter or schedule of unadjusted differences, the development, selection and disclosure of critical accounting estimates, and analyses of the effect of alternative assumptions, estimates or GAAP methods on the Company’s financial statements.
 
(v) Prior to their filing or issuance, the Committee shall review the Company’s Annual Information Form/Annual Report to the SEC, quarterly and annual earnings press releases, and other financial press releases, including the use of “pro forma” or “adjusted” non-GAAP information.
 
(vi) The Committee shall review and discuss with management the financial information and earnings guidance provided to analysts and rating agencies. Such discussion may be specific or it may be in general regarding the types of information to be disclosed and the types of presentations to be made.
 
(c) Conduct of the Annual Audit.
 
The Committee shall oversee the annual audit, and in the course of such oversight the Committee shall have the following responsibilities and authority:
 
(i) The Committee shall meet with the independent auditor prior to the audit to discuss the planning and conduct of the annual audit, and shall meet with the independent auditor as may be necessary or appropriate in connection with the audit.
 
(ii) The Committee shall ascertain that the independent auditor is registered and in good standing with the Canadian Public Accountability Board and the Public Company Accounting Oversight Board (“PCAOB”) and that the independent auditor satisfies all applicable Canadian independence standards (Canadian Auditing Standard 200), PCAOB Rule 3526 and SEC Regulation S-X, Section 2-01. The Committee shall obtain from the auditor a written description of all relationships between the auditor and the Company and persons in a financial reporting oversight role at the Company as per PCAOB Rule 3526 that may reasonably be thought to bear on independence.
 
(iii) The Committee shall discuss with the independent auditor the matters required to be discussed by PCAOB Auditing Standard No. 16 and Canadian Auditing Standard 260 relating to the conduct of the audit.
 
(iv) The Committee shall obtain from the independent auditor assurance that the audit was conducted in a manner consistent with Section 10A of the Securities Exchange Act of 1934 and that, in the course of conducting the audit, the independent auditor has not become aware of information indicating that an illegal act has or may have occurred or, if such an act may have occurred, that the independent auditor has taken all action required by Section 10A(b) of the Securities Exchange Act of 1934.
 
(v) The Committee shall make such inquiries to the management and the independent auditor as the Committee members deem necessary or appropriate to satisfy themselves regarding the efficacy of the Company’s financial and internal controls and procedures and the auditing process.
 
(d) Compliance and Oversight.
 
(i) The Committee shall meet periodically with management and the independent auditor in separate executive sessions. The Committee may also, to the extent it deems necessary or appropriate, meet with the Company’s investment bankers and financial analysts who follow the Company.
 
 
2020 Annual Information Form
Page | 62
 
 

 
 
(ii) The Committee shall discuss with management and the independent auditor the effect of regulatory and accounting initiatives as well as off-balance sheet structures on the Company’s financial statements.
 
(iii) The Committee shall discuss with management the Company’s major financial risk exposures and the steps management has taken to monitor and control such exposures, including the Company’s risk assessment and risk management policies, and regularly review the top risks identified by management and the policies and practices adopted by the Company to mitigate those risks.
 
(iv) At least annually and prior to the filing of the AIF/Annual Report to the SEC, the Committee shall review with management and the independent auditor the disclosure controls and procedures and confirm that the Company (with CEO and CFO participation) has evaluated the effectiveness of the design and operation of the controls within 90 days prior to the date of filing of the AIF/Annual Report to the SEC. The Committee also shall review with management and the independent auditor any deficiencies in the design and operation of internal controls and significant deficiencies or material weaknesses therein and any fraud involving management or other employees who have a significant role in the Company’s internal controls. As a part of that review, the Committee shall review the process followed in preparing and verifying the accuracy of the required CEO and CFO annual certifications.
 
(v) At least annually and prior to the filing of the AIF/Annual Report to the SEC, the Committee shall review with management and the independent auditor management’s internal control report and assessment of the internal controls and procedures, and the independent auditor’s report on and assessment of the internal controls and procedures. In connection with its review of interim and annual financial statements and related management’s discussion and analysis, the Committee shall confirm with management that the Company (with CEO and CFO participation) has taken all actions required in connection with the certifications required by National Instrument NI 52-109, Certification of Disclosure in Issuers’ Annual and Interim Filings.
 
(vi) The Committee shall establish procedures for the receipt, retention and treatment of complaints received by the Company regarding accounting, internal accounting controls or auditing matters, and the confidential, anonymous submission by employees of concerns regarding questionable accounting or auditing matters.
 
(vii) The Committee shall discuss with management and the independent auditor any correspondence with regulators or governmental agencies and any employee complaints or reports which raise material issues regarding the Company’s financial statements or accounting policies.
 
(viii) At least annually, the Committee shall meet with the Company’s legal counsel and discuss any legal matters that may have a material impact on the financial statements or the Company’s compliance policies.
 
(ix) The Committee shall oversee the preparation of reports relating to the Audit Committee required under applicable laws, regulations and stock exchange requirements.
 
(x) The Committee shall exercise oversight with respect to anti-fraud programs and controls
 
 
2020 Annual Information Form
Page | 63
 
 
 

 
 
(e) Related Party Transactions.
 
(i) The Committee shall review for fairness to the Company proposed transactions, contracts and other arrangements between the Company and its subsidiaries and any related party or affiliate, and make recommendations to the Board whether any such transactions, contracts and other arrangements should be approved or continued. The foregoing shall not include any compensation payable pursuant to any plan, program, contract or arrangement subject to the authority of the Company’s Compensation Committee.
 
(ii) As used herein the term “related party” means any officer or director of the Company or any subsidiary, or any shareholder holding a greater than 10% direct or indirect financial or voting interest in the Company, and the term “affiliate” means any person, whether acting alone or in concert with others, that controls, is controlled by or is under common control with another person. "Related party" includes Hunter Dickinson Services Inc., its principals, and their affiliates.
 
(f) Additional duties. The Committee shall perform the following additional duties:
 
(i) The Committee shall review and recommend dividend policies.
 
(ii) The Committee shall oversee the Company’s insurance program..
 
(iii) The Committee shall review the appointment of senior financial personnel and make recommendations to the Board of Directors regarding the appointment of the Chief Financial Officer.
 
(iv) The Committee shall recommend to the Nominating and Governance Committee the qualifications and criteria for membership on the Committee.
 
(v) The Committee shall review and discuss with management the requirement for annual public disclosure pursuant to the Extractive Sector Transparency Measures Act and shall be responsible for approving such disclosures.
 
2. Structure and Membership
 
(a) Number and qualification.
 
The Committee shall consist of three persons unless the Board should from time to time otherwise determine. All members of the Committee shall meet the experience and financial literacy requirements of National Instrument NI 52-110 and the rules of the Toronto Stock Exchange and the NYSE American. At least one member of the Committee shall be a “financial expert” as defined in Item 407 of SEC Regulation S-K.
 
(b) Selection and Removal.
 
Members of the Committee shall be appointed by the Board, upon the recommendation of the Nominating and Governance Committee. The Board may remove members of the Committee at any time with or without cause.
 
(c) Independence.
 
All of the members of the Committee shall be “independent” as required for audit committees by National Instrument NI 52-110, the rules of the Toronto Stock Exchange and the NYSE American, and SEC Rule 10A-3.
 
 
2020 Annual Information Form
Page | 64
 
 
 

 
 
(d) Chair.
 
Unless the Board elects a Chair of the Committee, the Committee shall elect a Chair by majority vote.
 
(e) Compensation.
 
The compensation of the Committee shall be as determined by the Board.
 
(f) Term.
 
Members of the Committee shall be appointed for one-year terms. Each member shall serve until his or her replacement is appointed, or until he or she resigns or is removed from the Board or the Committee.
 
3. Procedures and Administration
 
(a) Meetings.
 
The Committee shall meet as often as it deems necessary in order to perform its responsibilities, but not less than quarterly. The Committee shall keep minutes of its meetings and any other records as it deems appropriate.
 
(b) Subcommittees.
 
The Committee may form and delegate authority to one or more subcommittees, consisting of at least one member, as it deems appropriate from time to time under the circumstances.
 
(c) Reports to the Board.
 
The Committee shall regularly report to the Board with respect to such matters as are relevant to the Committee’s discharge of its responsibilities, and shall report in writing on request of the Chair of the Board.
 
(d) Charter.
 
The Committee shall, at least annually, review and reassess the adequacy of this Charter and recommend any proposed changes to the Board for approval.
 
(e) Independent Advisors.
 
The Committee shall have the authority to engage such independent legal and other advisors as it deems necessary or appropriate to carry out its responsibilities. Such independent advisors may be regular advisors to the Company. The Committee is empowered, without further action by the Board, to cause the Company to pay appropriate compensation to advisors engaged by the Committee.
 
(f) Investigations.
 
The Committee shall have the authority to conduct or authorize investigations into any matters within the scope of its responsibilities as it deems appropriate, including the authority to request any Officer or other person to meet with the Committee and to access all Company records.
 
(g) Annual Self-Evaluation.
 
The Committee shall evaluate its own performance at least annually.
 
 
2020 Annual Information Form
Page | 65
 
 
 

 
 
4. Additional Powers
 
The Committee shall have such other duties as may be delegated from time to time by the Board of Directors.
 
5. Limitation of Committee’s Role
 
While the Committee has the responsibilities and powers set forth in this Charter, it is not the duty of the Committee to plan or conduct audits or to determine that the Company’s financial statements and disclosures are complete and accurate and are in accordance with GAAP and applicable rules and regulations. These are the responsibilities of management and the independent auditor.
 
6. Committee Member Independence, Financial Literacy and Financial Expert Requirements
 
A.      Independence
 
(a) See Appendix 2 of the Company’s Corporate Governance Overview and Guidelines.
 
B.      Financial Literacy and Financial Expert Requirements
 
NI 52-110
 
Section 3.1(4) states that each audit committee member must be financially literate.
 
Section 1.6 defines the meaning of financial literacy as follows:
 
“For the purposes of this Instrument, an individual is financially literate if he or she has the ability to read and understand a set of financial statements that present a breadth and level of complexity of accounting issues that are generally comparable to the breadth and complexity of the issues that can reasonably be expected to be raised by the issuer’s financial statements.”
 
NYSE AMERICAN Section 803(B)(2)(a)(iii)
 
Each issuer must have an Audit Committee of at least three members, each of whom:
 
“is able to read and understand fundamental financial statements, including a company’s balance sheet, income statement, and cash flow statement. Additionally, each issuer must certify that it has, and will continue to have, at least one member of the audit committee who is financially sophisticated, in that he or she has past employment experience in finance or accounting, requisite professional certification in accounting, or any other comparable experience or background which results in the individual’s financial sophistication, including but not limited to being or having been a chief executive officer, chief financial officer, other senior officer with financial oversight responsibilities. A director who qualifies as an audit committee financial expert under Item 407(d)(5)(ii) of Regulation S-K is presumed to qualify as financially sophisticated.”
 
ITEM 407(d)(5)(ii) 0F REGULATION S-K, DEFINITION OF FINANCIAL EXPERT
 
For purposes of this Item, an audit committee financial expert means a person who has the following attributes:
 
(A)  An understanding of generally accepted accounting principles and financial statements;
 
(B)  The ability to assess the general application of such principles in connection with the accounting for estimates, accruals and reserves;
 
(C)  Experience preparing, auditing, analyzing or evaluating financial statements that present a breadth and level of complexity of accounting issues that are generally comparable to the breadth and complexity of issues that can reasonably be expected to be raised by the registrant’s financial statements, or experience actively supervising one or more persons engaged in such activities;
 
 
2020 Annual Information Form
Page | 66
 
 
 

 
 
(D)  An understanding of internal control over financial reporting; and
 
(E)  An understanding of audit committee functions.
 
A person shall have acquired such attributes through:
 
(A)  Education and experience as a principal financial officer, principal accounting officer, controller, public accountant or auditor or experience in one or more positions that involve the performance of similar functions;
 
(B)  Experience actively supervising a principal financial officer, principal accounting officer, controller, public accountant, auditor or person performing similar functions;
 
(C)  Experience overseeing or assessing the performance of companies or public accountants with respect to the preparation, auditing or evaluation of financial statements; or
 
 
 
 
 
 
 
 
 
 
 
 
2020 Annual Information Form
Page | 67