EX-99.1 2 d417839dex991.htm EX-99.1 EX-99.1

Exhibit 99.1

 

LOGO

Emera Incorporated

Annual Information Form

For the year ended December 31, 2022

February 23, 2023


ANNUAL INFORMATION FORM

For the year ended December 31, 2022

Dated: February 23, 2023

TABLE OF CONTENTS

 

PRESENTATION OF INFORMATION

     4  

CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION

     4  

CORPORATE STRUCTURE

     6  

Name and Incorporation

     6  

Amended Articles of Association

     6  

Intercorporate Relationships

     6  

INTRODUCTION

     7  

DESCRIPTION OF THE BUSINESS

     8  

Business Segments

     8  

Florida Electric Utility

     9  

Canadian Electric Utilities

     11  

Gas Utilities and Infrastructure

     14  

Other Electric Utilities

     17  

Other

     18  

GENERAL DEVELOPMENT OF THE BUSINESS

     19  

Florida Electric Utility

     19  

Canadian Electric Utilities

     21  

Gas Utilities and Infrastructure

     24  

Other Electric Utilities

     25  

USGAAP – Exemptive Relief

     27  

Financing Activity

     27  

RISK FACTORS

     28  

CAPITAL STRUCTURE

     28  

Common Shares

     29  

Emera First Preferred Shares

     29  

Emera Second Preferred Shares

     29  

Share Ownership Restrictions

     29  

CREDIT RATINGS

     30  

DIVIDENDS

     31  

MARKET FOR SECURITIES

     32  

Trading Price and Volume

     32  

At-The-Market Equity Program

     32  

DIRECTORS AND OFFICERS

     33  

Directors

     33  

Officers

     35  
AUDIT COMMITTEE      36  

Audit and Non-Audit Services Pre-Approval Process

     37  

 

Emera Incorporated – 2022 Annual Information Form    2


Auditors’ Fees      38  
CERTAIN PROCEEDINGS      38  
CONFLICTS OF INTEREST      39  
LEGAL PROCEEDINGS AND REGULATORY ACTIONS      39  
NO INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS      39  
MATERIAL CONTRACTS      39  
TRANSFER AGENT AND REGISTRAR      39  
EXPERTS      39  
ADDITIONAL INFORMATION      39  
APPENDIX “A” - DEFINITIONS OF CERTAIN TERMS      41  
APPENDIX “B” – SUMMARY OF TERMS AND CONDITIONS OF AUTHORIZED SERIES OF FIRST PREFERRED SHARES      46  
APPENDIX “C” - MONTHLY TRADING VOLUME AND HIGH AND LOW PRICE FOR EMERA’S SECURITIES IN 2022      49  
APPENDIX “D” - EMERA INCORPORATED AUDIT COMMITTEE CHARTER      50  

 

Emera Incorporated – 2022 Annual Information Form    3


PRESENTATION OF INFORMATION

Unless otherwise noted, the information contained in this Annual Information Form (“AIF”) is given at or for the year ended December 31, 2022. Amounts are expressed in Canadian dollars unless otherwise indicated. All financial information presented in millions of Canadian dollars is rounded to the nearest million unless otherwise stated. Unless otherwise indicated, all financial information is presented in accordance with United States’ generally accepted accounting principles (“USGAAP”). Emera Incorporated (“Emera” or “the Company”) uses Adjusted Net Income Attributable to Common Shareholders (“adjusted net income”) as a financial performance measure, which is not a defined financial measure according to USGAAP and does not have standardized meanings prescribed by USGAAP. For further information on the non-GAAP financial measure, adjusted net income, including a full description of the measure and a reconciliation to the nearest USGAAP measure, please refer to the Company’s MD&A section entitled “Non-GAAP Financial Measures and Ratios”, which is incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Certain capitalized terms used herein, and not otherwise defined herein, are defined under “Definitions of Certain Terms”, attached to this AIF as Appendix “A”. Reference to “including”, “include”, or “includes” means “including (or includes) but is not limited to” and shall not be construed to limit any general statement preceding it to the specific or similar items or matters immediately following it.

This AIF provides material information about the business and operations of Emera. The “Enterprise Risk and Risk Management” section of the Company’s MD&A is incorporated herein by reference and can be found on SEDAR at www.sedar.com.

CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION

This AIF, including the documents incorporated herein by reference, contains “forward-looking information” and “forward-looking statements” within the meaning of applicable securities laws (collectively, “forward-looking information”). The words “anticipates”, “believes”, “budget”, “could”, “estimates”, “expects”, “forecast”, “intends”, “may”, “might”, “plans”, “projects”, “schedule”, “should”, “targets”, “will”, “would” and similar expressions are often intended to identify forward-looking information, although not all forward-looking information contains these identifying words. References to “Emera” in this section include references to the subsidiaries of Emera.

The forward-looking information in this AIF, including the documents incorporated herein by reference, includes statements which reflect the current view of Emera’s management with respect to Emera’s objectives, plans, financial and operating performance, carbon dioxide emissions reduction goals, business prospects and opportunities. The forward-looking information reflects management’s current beliefs and is based on information currently available to Emera’s management and should not be read as guarantees of future events, performance or results, and will not necessarily be accurate indications of whether, or the time(s) at which, such events, performance or results will be achieved. All such forward-looking information in this AIF is provided pursuant to safe harbour provisions contained in applicable securities laws.

The forward-looking information in this AIF, including the documents incorporated herein by reference, includes, but is not limited to, statements regarding: Emera’s revenue, earnings and cash flow; the growth and diversification of Emera’s business and earnings base; future annual net income and dividend growth; expansion of Emera’s business; the expected compliance by Emera with the regulation of its operations; the expected timing of regulatory decisions; forecasted capital investments; the nature, timing and costs associated with certain capital projects; the expected impact on Emera of challenges in the global economy; estimated energy consumption rates; expectations related to annual operating cash flows; the expectation that Emera will continue to have reasonable access to capital in the near to medium term; expected debt maturities, repayments and renewals; expectations about increases in interest expense and/or fees associated with debt securities and credit facilities; no material adverse credit rating actions expected in the near term; the successful development of relationships with various stakeholders, the impact of currency

 

Emera Incorporated – 2022 Annual Information Form    4


fluctuations; expected changes in electricity rates; and the impacts of planned investment by the industry of gas transportation infrastructure within the United States.

The forecasts and projections that make up the forward-looking information are based on reasonable assumptions which include, but are not limited to: the receipt of applicable regulatory approvals and requested rate decisions; no significant operational disruptions or environmental liability due to a catastrophic event or environmental upset caused by severe weather or global climate change, other acts of nature or other major events; seasonal weather patterns remaining stable; no significant cyber or physical attacks or disruptions to Emera’s systems; the continued ability to maintain transmission and distribution systems to ensure their continued performance; continued investment in solar, wind and hydro generation; continued natural gas activity; no severe and/or prolonged downturn in economic conditions; sufficient liquidity and capital resources; the continued ability to hedge exposures to fluctuations in interest rates, foreign exchange rates and commodity prices; no significant variability in interest rates; expectations regarding the nature, timing and costs of capital investments of Emera and its subsidiaries; expectations regarding rate base growth; the continued competitiveness of electricity pricing when compared with other alternative sources of energy; the continued availability of commodity supply; the absence of significant changes in government energy plans and environmental laws and regulations that may materially affect Emera’s operations and cash flows; maintenance of adequate insurance coverage; the ability to obtain and maintain licenses and permits; no material decrease in market energy sales prices; favourable labour relations; and sufficient human resources to deliver service and execute Emera’s capital investment plan.

The forward-looking information is subject to risks, uncertainties and other factors that could cause actual results to differ materially from historical results or results anticipated by the forward-looking information. Factors that could cause results or events to differ from current expectations include, but are not limited to: regulatory and political risk; operating and maintenance risks; changes in economic conditions; commodity price and availability risk; liquidity and capital market risk; future dividend growth; timing and costs associated with certain capital investments; expected impacts on Emera of challenges in the global economy; estimated energy consumption rates; maintenance of adequate insurance coverage; changes in customer energy usage patterns; developments in technology that could reduce demand for electricity; global climate change; weather; unanticipated maintenance and other expenditures; system operating and maintenance risk; derivative financial instruments and hedging; interest rate risk; inflation risk; counterparty risk; disruption of fuel supply; country risks; environmental risks; foreign exchange (“FX”); regulatory and government decisions, including changes to environmental, financial reporting and tax legislation; risks associated with pension plan performance and funding requirements; loss of service area; risk of failure of information technology infrastructure and cybersecurity risks; uncertainties associated with infectious diseases, pandemics and similar public health threats, such as the COVID-19 novel coronavirus (“COVID-19”) pandemic; market energy sales prices; labour relations; and availability of labour and management resources.

Readers are cautioned not to place undue reliance on forward-looking information as actual results could differ materially from the plans, expectations, estimates or intentions and statements expressed in the forward-looking information. All forward-looking information in this AIF and in the documents incorporated herein by reference is qualified in its entirety by the above cautionary statements and, except as required by law, Emera undertakes no obligation to revise or update any forward-looking information as a result of new information, future events or otherwise.

 

Emera Incorporated – 2022 Annual Information Form    5


CORPORATE STRUCTURE

Name and Incorporation

Emera was incorporated on July 23, 1998 pursuant to the Companies Act (Nova Scotia). The Reorganization Act and the Privatization Act require the Company’s Articles of Association (the “Articles”) to contain provisions specifying that the head office and the principal executive offices of the Company are to be situated in the Province of Nova Scotia. The current address of the Company’s registered office, head office and principal executive offices is Emera Place, 5151 Terminal Road, Halifax, Nova Scotia, Canada, B3J 1A1.

Amended Articles of Association

On April 12, 2019, amendments to the Privatization Act and the Reorganization Act were enacted, removing the legislative restriction preventing non-Canadian residents from holding more than 25 per cent of Emera voting shares, in aggregate. These legislative amendments did not alter the existing 15 per cent individual share ownership restriction, as described below in the section entitled “Capital Structure – Share Ownership Restrictions”. The Board approved amendments to the Company’s Articles and on July 11, 2019, shareholders passed a special resolution to amend the Articles to remove this non-Canadian resident ownership restriction. For more information on these amendments to the Articles, please refer to Emera’s Management Information Circular dated May 31, 2019 distributed in connection with a special meeting of shareholders held on July 11, 2019, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Intercorporate Relationships

The following table sets forth the relationships among the Company and its principal subsidiaries, the percentage of votes attaching to all voting securities of its respective subsidiaries beneficially owned, or controlled or directed, directly or indirectly, by the Company, as well as their respective jurisdictions of incorporation, continuance, formation or organization. This table excludes certain subsidiaries, the assets and revenues of which did not individually exceed 10 per cent, or in the aggregate exceed 20 per cent, of the total consolidated assets or total consolidated revenues of the Company as at December 31, 2022.

 

  Subsidiaries   

    Percentage Ownership    

(%)

       Jurisdiction          

Tampa Electric Company1

   100    Florida                

Nova Scotia Power

   100    Nova Scotia     

New Mexico Gas Company

   100    Delaware     

 

  (1)

Tampa Electric Company (TEC) has historically included both its regulated electric and gas utilities, namely the Tampa Electric Division and the Peoples Gas System (PGS) Division. Effective January 1, 2023, PGS ceased to be a division of TEC and the gas utility was reorganized, resulting in a separate legal entity called Peoples Gas System, Inc. (PGSI), existing under the laws of the State of Florida, and a wholly-owned direct subsidiary of TECO Gas Operations, Inc.

 

Emera Incorporated – 2022 Annual Information Form    6


INTRODUCTION

Based in Halifax, Nova Scotia, Emera owns and operates cost-of-service rate-regulated electric and gas utilities in Canada, the United States and the Caribbean. Cost-of-service utilities provide essential electric and gas services in designated territories under franchises and are overseen by regulatory authorities. Emera’s strategic focus continues to be safely delivering cleaner, affordable and reliable energy to its customers.

The majority of Emera’s investment in rate-regulated businesses are located in Florida with other investments in Nova Scotia, New Mexico and the Caribbean. Emera’s portfolio of regulated utilities provides reliable earnings, cash flow and dividends. Earnings opportunities in regulated utilities are generally driven by the magnitude of net investment in the utility (known as “rate base”), and the amount of equity in the capital structure and the ROE as approved through regulation. Earnings are also affected by sales volumes and operating expenses.

Emera’s capital investment plan is $8-9 billion over the 2023-to-2025 period (including a $240 million equity investment in the LIL in 2023), mainly focused in Florida. This results in a forecasted rate base growth of approximately 7 per cent to 8 per cent through 2025. The capital investment plan continues to include significant investments across the portfolio in renewable and cleaner generation, reliability and integrity investments, infrastructure modernization and customer-focused technologies. Emera’s capital investment plan is being funded primarily through internally generated cash flows and debt raised at the operating company level. Equity requirements in support of the Company’s capital investment plan are expected to be funded through the issuance of preferred equity and the issuance of common equity through Emera’s DRIP and ATM Program. Maintaining investment-grade credit ratings is a priority of the Company.

Emera has provided annual dividend growth guidance of four to five per cent through 2025. The Company targets a long-term dividend payout ratio of adjusted net income of 70 to 75 per cent and, while the payout ratio is likely to exceed that target through and beyond the forecast period, it is expected to return to that range over time. For further information on the non-GAAP measure “Dividend Payout Ratio of Adjusted Net Income”, refer to the “Non-GAAP Financial Measures and Ratios” section of the MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Seasonal patterns and other weather events affect demand and operating costs. Similarly, mark-to-market adjustments and foreign currency exchange can have a material impact on financial results for a specific period. Emera’s consolidated net income and cash flows are impacted by movements in the USD relative to the Canadian dollar. Emera may hedge both transactional and translational exposure. These impacts, as well as the timing of capital investments and other factors, mean results in any one quarter are not necessarily indicative of results in any other quarter, or for the year as a whole.

Energy markets worldwide are facing significant change and Emera is well positioned to respond to shifting customer demands, digitization, decarbonization, complex regulatory environments and decentralized generation.

Customers are looking for more choice, better control, and enhanced reliability in a time where costs of decentralized generation and storage have become more competitive in some regions. Advancing technologies are transforming the way utilities interact with their customers and generate and transmit energy. In addition, climate change and extreme weather are shaping how utilities operate and how they invest in infrastructure. There is also an overall need to replace aging infrastructure and further enhance reliability. Emera will play a role in all of these trends. Emera’s strategy is to fund investments in renewable energy and technology assets which protect the environment and benefit customers through fuel or operating cost savings.

For example, significant investments to facilitate the use of renewable and low-carbon energy include the Maritime Link in Atlantic Canada, modernization of the Big Bend Power Station and the ongoing construction of solar generation at Tampa Electric. Emera’s utilities are also investing in reliability projects

 

Emera Incorporated – 2022 Annual Information Form    7


and replacing aging infrastructure. All of these projects demonstrate Emera’s strategy of safely delivering cleaner, reliable, and affordable energy for its customers.

Building on its decarbonization progress, Emera is continuing its efforts by establishing clear carbon reduction goals and a vision to achieve net-zero carbon dioxide emissions by 2050.

This vision is inspired by Emera’s strong track record, the Company’s experienced team, and a clear path to Emera’s interim carbon goals. With existing technologies and resources, and subject to supportive government and regulatory decisions, Emera is working to achieve the following goals compared to corresponding 2005 levels:

  ·  

A 55 per cent reduction in carbon dioxide emissions by 2025.

  ·  

The retirement of Emera’s last existing coal unit no later than 2040.

  ·  

An 80 per cent reduction in carbon dioxide emissions by 2040.

Achieving the above climate goals on these timelines is subject to the Company’s regulatory obligations and other external factors beyond Emera’s control.

Emera seeks to deliver on its Climate Commitment while maintaining its focus on investing in reliability and staying focused on the cost impacts for customers. Emera is also committed to identifying emerging technologies and continuing to work constructively with policymakers, regulators, partners, investors and customers to achieve these goals and realize its net-zero vision.

Emera is committed to world-class safety, operational excellence, good governance, excellent customer service, reliability, being an employer of choice, and building constructive relationships.

DESCRIPTION OF THE BUSINESS

Business Segments

Emera’s reportable segments are:

 

  ·  

Florida Electric Utility, which consists of Tampa Electric;

  ·  

Canadian Electric Utilities, which includes NSPI and ENL, a holding company with equity investments in NSPML (100 per cent) and the LIL (31.9 per cent);

  ·  

Gas Utilities and Infrastructure, which includes PGS, NMGC, Emera Brunswick Pipeline Company, SeaCoast and an 12.9 per cent equity investment in M&NP;

  ·  

Other Electric Utilities, which includes ECI, a holding company with regulated electric utilities which include BLPC, GBPC and a 19.5 per cent equity interest in Lucelec. On March 31 2022, Emera completed the sale of its 51.9 per cent interest in Domlec, which was previously included in this segment; and

  ·  

Other, which includes Emera Energy, ETL and corporate holding, financing companies and certain other investments.

General

Emera and its subsidiaries had 7,122 employees as at December 31, 2022, approximately 32 per cent of whom are unionized.

Operations by Segment

The following sections describe the operations included in each of the Company’s reportable segments.

 

Emera Incorporated – 2022 Annual Information Form    8


Florida Electric Utility

Florida Electric Utility consists of Tampa Electric, a vertically integrated regulated electric utility engaged in the generation, transmission and distribution of electricity, serving customers in West Central Florida. Tampa Electric has $12.1 billion USD of assets, approximately 827,000 customers and 2,469 employees as at December 31, 2022.

Tampa Electric is regulated by the FPSC and is also subject to regulation by the FERC. The FPSC sets rates at a level that allows utilities such as Tampa Electric to collect total revenues or revenue requirements equal to their cost of providing service, plus an appropriate return on invested capital. Base rates are determined in FPSC rate setting hearings which occur at the initiative of Tampa Electric, the FPSC or other interested parties. Tampa Electric’s approved regulated ROE range is 9.25 per cent to 11.25 per cent, based on an allowed equity capital structure of 54 per cent. An ROE of 10.20 per cent will be used for the calculation of the return on investments for clauses.

For further details on Tampa Electric’s regulatory environment, base rates and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which are hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Market and Sales

 

Tampa Electric Revenue and Sales Volumes by Customer Class
           Electric Revenues (%)           GWh Electric Sales Volumes (%)  
For the year ended December 31         2022               2021               2022             2021      

Residential

  54.7   53.2   48.4   49.2

Commercial

  26.4   27.7   30.2   30.4

Industrial

  7.0   7.9   10.1   10.5

Other

  11.9   11.2   11.3   9.9

Total

  100.0   100.0   100.0   100.0

Energy sources and generation

As at December 31, 2022, Tampa Electric owns 6,549 MW of generating capacity, of which 78 per cent is natural gas-fired, 15 per cent is solar and 7 per cent is coal. Tampa Electric owns 2,171 kilometres of transmission facilities and 19,916 kilometres of distribution facilities. Tampa Electric meets the planning criteria for reserve capacity established by the FPSC, which is a 20 per cent reserve margin over firm peak demand.

System Operations

Tampa Electric’s Energy Control Center co-ordinates and controls the electric generation, transmission and distribution facilities. The Energy Control Center is linked to the generating stations and other key facilities through the Supervisory Control and Data Acquisition system, a communication network used by system operators for remote monitoring and control of the power system assets.

Through interconnection agreements with our neighboring electric utilities within the Florida Region, Tampa Electric’s system has access to other regional power systems and the rest of the interconnected North American electric bulk power system. The interconnection of power systems enhances the cost effectiveness, reserve capacity and reliability of participating power systems. As a member of the Florida Reserve Sharing Group, Tampa Electric has immediate access to reserve generating capacity from all other group members.

 

Emera Incorporated – 2022 Annual Information Form    9


Contribution to Consolidated Net Income

Florida Electric Utility’s contribution to consolidated net income was $458 million USD in 2022 (2021 - $369 million USD).

Seasonal Nature

Electric sales volumes are primarily driven by general economic conditions, population and weather. Residential and commercial electricity sales are seasonal. In Florida, Q3 is the strongest period for electricity sales, reflecting warmer weather and cooling demand.

Capital Investments

In 2022, capital investments (including AFUDC) in the Florida Electric Utility segment were $1.1 billion USD (2021 – $1.2 billion USD). In 2023, capital investment is expected to be approximately $1.3 billion USD, including AFUDC. Capital projects include solar investments, grid modernization and storm hardening investments.

Environmental Considerations

Tampa Electric has significant environmental considerations. Tampa Electric operates stationary sources with air emissions regulated by the Clean Air Act. Its operations are also impacted by provisions in the Clean Water Act and federal and state legislative initiatives on environmental matters.

Hazardous Air Pollutants

All of Tampa Electric’s conventional coal-fired units are already equipped with electrostatic precipitators, scrubbers and selective catalytic reduction systems, and the Polk Unit 1 integrated gasification combined-cycle unit emissions are minimized in the gasification process. Therefore, Tampa Electric has minimized the impact of the EPA’s current Mercury Air Toxics Standards (MATS) and has demonstrated compliance on all applicable units with the most stringent “Low Emitting Electric Generating Unit” classification for the EPA’s current MATS with nominal additional capital investment.

Carbon Reductions and GHG

In June 2019, the EPA released a final rule, named the Affordable Clean Energy (ACE) rule, to establish emission guidelines for states to address GHG emissions from existing coal-fired electric generating units (EGUs). As a result of legal challenges, a replacement rule is expected to be proposed in April 2023. Compliance with the terms of the new rule that replaces the ACE rule, once adopted and finalized, could cause an increase in costs or rates charged to customers, which could curtail sales.

Tampa Electric expects that the costs to comply with new environmental regulations would be eligible for recovery through the ECRC. If approved as prudent, the costs required to comply with CO2 emissions reductions would be reflected in customers’ bills. If the regulation allowing cost recovery is changed and the cost of compliance is not recovered through the ECRC, Tampa Electric could seek to recover those costs through a base-rate proceeding.

Ozone

On December 31, 2020, the EPA published a final rule to retain the national ambient air quality standards (NAAQS) for photochemical oxidants including ozone, originally adopted in 2012. Under the Clean Air Act, the EPA is required to review the NAAQS every five years and, if appropriate, revise it. The EPA has announced that the NAAQS is currently under review, which could result in revisions to the standard affecting compliance in Tampa Electric’s service territory. The impact of this potential new standard on the operations of Tampa Electric will depend on the standard that is ultimately adopted and on the outcome of any related litigation or other developments.

 

Emera Incorporated – 2022 Annual Information Form    10


Water Supply and Quality

The EPA’s final rule under 316(b) of the Clean Water Act (effective October 2014) addresses perceived impacts to aquatic life by cooling water intakes and is applicable to Tampa Electric’s Bayside and Big Bend Power Stations. Polk Power Station is not covered by this rule since it does not operate an intake on waters of the U.S. Tampa Electric has two ongoing projects (one for Bayside and one for Big Bend) that require compliance with the rule. The Florida Department of Environmental Protection (FDEP) agreed with Tampa Electric’s proposed plan for Bayside and Tampa Electric began a multi-year construction project to install new fish-friendly modified traveling screens and a fish return in 2022. Compliance study elements have been completed and submitted for Bayside. Tampa Electric is negotiating an alternative schedule for a portion of the compliance requirements with the Big Bend modernization project, with the remainder of the compliance requirements to be determined and completed at a later date. The full impact of the regulations on Tampa Electric will depend on the outcome of subsequent legal proceedings challenging the rule, the results of the study elements performed as part of the rules’ implementation, and the actual requirements established by FDEP.

The final EPA rule for existing steam electric effluent limit guidelines (ELGs) became effective January 4, 2016 and establishes limits for certain wastewater discharges. The ELGs are expected to be incorporated into National Pollutant Discharge Elimination System (NPDES) permit renewals for Big Bend Station and Polk Power Station to achieve compliance as soon as possible after November 1, 2018, but no later than December 31, 2023. The EPA has announced that this rule is currently under review, and a revised rule is expected to be proposed in 2023.

The preliminary draft of the NPDES Permit for Big Bend stated that effluent limitations for total recoverable arsenic, mercury, and selenium and total nitrate/nitrite for flue gas desulfurization wastewater are applicable no later than December 31, 2023. Big Bend will complete construction of a deep injection well system in December 2023 for disposal of various wastewaters. The effluent limitations do not apply to Polk Power Station.

Canadian Electric Utilities

Canadian Electric Utilities includes NSPI and ENL. NSPI is a vertically integrated regulated electric utility engaged in the generation, transmission and distribution of electricity and the primary electricity supplier to customers in Nova Scotia. ENL is a holding company with a 100 per cent equity investment in NSPML and a 31.9 per cent equity investment in LIL: two transmission investments related to the development of an 824 MW hydroelectric generating facility at Muskrat Falls hydroelectric project (“Muskrat Falls”) on the Lower Churchill River in Labrador.

NSPI

NSPI is the primary electricity supplier in Nova Scotia, providing electricity generation, transmission and distribution services to approximately 541,000 customers with $6.8 billion in assets and 2,138 employees as at December 31, 2022.

NSPI is a public utility as defined in the Public Utilities Act and is subject to regulation under the Public Utilities Act by the UARB. The Public Utilities Act gives the UARB supervisory powers over NSPI’s operations and expenditures. Electricity rates for NSPI’s customers are subject to UARB approval. NSPI is not subject to a general annual rate review process, but rather participates in hearings held from time to time at NSPI’s or the UARB’s request. On January 27, 2022, NSPI filed a General Rate Application (“GRA”) with the UARB. For more details regarding GRA, refer to the General Development of the Business section below, under the heading “Canadian Electric Utilities – NSPI - General Rate Application.”

For further details on NSPI’s regulatory environment and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which are hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

 

Emera Incorporated – 2022 Annual Information Form    11


Market and Sales

 

                                                                                                               
NSPI Revenue and Electricity Sales Volumes by Customer Class
         Electric Revenues (%)       GWh Electric Sales Volumes  (%)  
For the year ended December 31       2022           2021       2022   2021
Residential   50.8   54.3   46.1   45.7
Commercial   26.0   27.7   28.8   28.5
Industrial   21.5   16.2   23.7   24.3
Other   1.7   1.8   1.4   1.5
Total   100.0   100.0   100.0   100.0

Energy Sources and Generation

NSPI owns 2,420 MW of generating capacity, of which approximately 44 per cent is coal-fired, 28 per cent is natural gas and/or oil, 19 per cent is hydro and wind, 7 per cent is petcoke and 2 per cent is biomass-fueled generation. In addition, NSPI has contracts to purchase renewable energy from IPPs, including COMFIT participants, which own 546 MW of capacity. NSPI also has rights to 153 MW of Maritime Link capacity, representing Nalcor’s NS Block delivery obligations, as discussed below.

System Operations

NSPI’s Control Center Operations co-ordinates and controls the electric generation, transmission and distribution facilities with the goal of providing safe, reliable and efficient electricity supply while adhering to applicable environmental requirements and regulations. The Control Center is linked to the generating stations and other key facilities through the Supervisory Control and Data Acquisition system, a communication network used by system operators for remote monitoring and control of the power system assets.

Through interconnection agreements with NB Power and with Newfoundland and Labrador Hydro, NSPI’s system has access to other regional power systems and the interconnected North American electric bulk power system. The interconnection of power systems enhances the cost effectiveness, reserve capacity and reliability of participating power systems. The interconnection agreements also provide participating utilities with a source of reserve power, subject to availability, transmission line capacity and the requirements of the supplier.

Transmission and Distribution

NSPI transmits and distributes electricity from its generating stations to its customers. NSPI’s transmission system consists of approximately 5,000 km of transmission facilities. The distribution system consists of approximately 28,000 km of distribution facilities, which includes distribution supply substations.

ENL

NSPML

Equity earnings from the Maritime Link are dependent on the approved ROE and operational performance of NSPML. NSPML’s approved regulated ROE range is 8.75 per cent to 9.25 per cent, based on an actual five-quarter average regulated common equity component of up to 30 per cent.

The Maritime Link assets entered service on January 15, 2018 enabling the transmission of energy between Newfoundland and Nova Scotia, improved reliability and ancillary benefits, supporting the efficiency and reliability of energy in both provinces. Nalcor’s final commissioning of the LIL has experienced delays and it’s expected that final commissioning of the LIL will be completed in 2023. Nalcor’s NS Block delivery obligations commenced on August 15, 2021 and the NS Block will be delivered over the next 35 years pursuant to the project agreements. During these final stages of commissioning the LIL, there will be interruptions in supply, with any resultant delivery shortfalls being delivered on a timely basis in accordance

 

Emera Incorporated – 2022 Annual Information Form    12


with the Energy and Capacity Agreement. NSPI has the option of purchasing additional market-priced energy from Nalcor through the Energy Access Agreement. The Energy Access Agreement enables NSPI to access a market-priced bid from Nalcor for up to 1.8 Terawatt hours (“TWh”) of energy in any given year and, on average, 1.2 TWh of energy per year through August 31, 2041.

LIL

ENL is a limited partner with Nalcor in LIL. Construction of the LIL is complete and Nalcor is forecasting it will achieve final commissioning in 2023.

Equity earnings from the LIL investment are based upon the book value of the equity investment and the approved ROE. Emera’s current equity investment is $740 million, comprised of $410 million in equity contribution and $330 million of accumulated equity earnings. Emera’s total equity contribution in the LIL, excluding accumulated equity earnings, is estimated to be approximately $650 million after all Lower Churchill projects are completed.

Cash earnings and return of equity will begin after commissioning of the LIL by Nalcor, which is anticipated in 2023, and until that point Emera will continue to record AFUDC earnings.

Contribution to Consolidated Net Income and Adjusted Net Income

Canadian Electric Utilities contribution to consolidated net income was $215 million in 2022 (2021 - $241 million). Canadian Electric Utilities contribution to Emera’s consolidated adjusted net income was $222 million in 2022 (2021 - $241 million). For a reconciliation of Canadian Electric Utilities adjusted net income to consolidated net income, refer to the “Non-GAAP Financial Measures and Ratios” and “Financial Highlights – Canadian Electric Utilities” sections of Emera’s MD&A, which is incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com

Seasonal Nature

Electric sales volumes are primarily driven by weather, number of customers, general economic conditions, and demand side management activities. Residential and commercial electricity sales are seasonal in Nova Scotia, with Q1 historically generating the highest sales, reflecting colder weather and fewer daylight hours in the winter season.

Capital Investment

NSPI

NSPI’s capital investments in 2022 were $540 million (2021 - $388 million), including AFUDC. In 2023, NSPI expects to invest $375 million, including AFUDC, primarily in capital projects to support system reliability and reliable service for customers.

NSPML

NSPML’s capital investments in 2022 were $10 million (2021 – $6 million). NSPML does not anticipate any planned significant capital investment in 2023.

Environmental Considerations

NSPI is subject to environmental laws and regulations set by both the Government of Canada and the Province of Nova Scotia. NSPI continues to work with both levels of government to comply with these laws and regulations, to maximize efficiency of emission control measures and minimize customer cost. NSPI anticipates that costs prudently incurred to achieve legislated reductions will be recoverable under NSPI’s regulatory framework. NSPI faces risks associated with achieving climate-related and environmental legislative requirements, including the risk of non-compliance, which could adversely affect NSPI’s

 

Emera Incorporated – 2022 Annual Information Form    13


operations and financial performance. For further discussion on these risks and environmental legislation and regulations, refer to the “Enterprise Risk and Risk Management” section of the MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com. Recent developments related to provincial and federal environmental laws and regulations are referred to below in the “General Developments of the Business” section.

Nova Scotia Cap-and-Trade Program Regulations

NSPI is a participant in the Nova Scotia Cap-and-Trade Program (“Cap-and-Trade Program”) and is subject to the 2019 through 2022 compliance period. NSPI received granted emissions allowances under the Cap-and-Trade Program and is permitted to purchase up to five per cent of the credits available at provincial auctions. Any remaining allowance shortfall requires the purchase of reserve credits directly from the provincial government, which are anticipated to be priced at a premium to provincial auction pricing. Compliance is forecast to be achieved through granted emissions allowances and credit purchases under the Cap-and-Trade Program, including reserve credits. Lower than forecast Muskrat Falls energy received during the compliance period has resulted in the increased deployment of higher carbon-emitting generation sources. The Province of Nova Scotia has agreed to provide approximately $165 million of relief from the 2019 through 2022 compliance costs, which was equal to the total cost of compliance forecast at the time of the fuel update submitted by NSPI to the UARB in September 2022 as part of the GRA. Discussions related to the final amount of relief and how this relief will be provided are ongoing. Further, NSPI’s regulatory framework provides for the recovery of costs prudently incurred to comply with the Cap-and-Trade Program Regulations pursuant to NSPI’s FAM.

Nova Scotia Renewable Energy Regulations

Over the past several years, the requirement to reduce Nova Scotia’s reliance upon higher carbon and greenhouse gas emitting sources of energy has resulted in NSPI making significant investments in renewable energy sources, including energy from the Maritime Link, and purchasing renewable energy from IPPs.

Under the provincially legislated Renewable Energy Regulations, 40 per cent of electric sales must be generated from renewable sources. This standard was predicated on receipt of the full NS Block. Due to the delay of the NS Block, the provincial government provided NSPI with an alternative compliance plan that requires NSPI to achieve 40 per cent of electric sales generated from renewable sources over the 2020 through 2022 period. With delivery of the NS Block commencing later than anticipated, as well as further interruptions in supply due to delays in the LIL, NSPI did not achieve the requirements of the alternative compliance plan. The Renewable Energy Regulations require NSPI to have acted in a duly diligent manner. If NSPI is found not to have acted in a duly diligent manner, it could be subject to a maximum penalty of $10 million.

Other Environmental Legislation and Regulations

There have been several recent environmental developments at both the federal and provincial levels, as described below in the “General Development of the Business – Canadian Electric Utilities - NSPI” section. For additional information on environmental regulations affecting NSPI, see NSPI’s 2022 Annual Information Form, a copy of which is available electronically under NSPI’s profile on SEDAR at www.sedar.com.

Gas Utilities and Infrastructure

Gas Utilities and Infrastructure includes PGS, NMGC, SeaCoast, Brunswick Pipeline and Emera’s non-consolidated investment in M&NP. PGS is a regulated gas distribution utility engaged in the purchase, distribution and sale of natural gas serving customers in Florida. NMGC is an intrastate regulated gas distribution utility engaged in the purchase, transmission, distribution and sale of natural gas serving customers in New Mexico. SeaCoast is a regulated intrastate natural gas transmission company offering

 

Emera Incorporated – 2022 Annual Information Form    14


services in Florida. Brunswick Pipeline is a regulated 145-kilometre pipeline delivering re-gasified liquefied natural gas from Saint John, New Brunswick, to markets in the Northeastern United States.

PGS and NMGC purchase gas from various suppliers depending on the needs of their customers. In Florida, gas is delivered to the PGS distribution system through interstate pipelines on which PGS has firm transportation capacity for delivery by PGS to its customers. NMGC’s natural gas is transported on major interstate pipelines on which NMGC has transportation capacity and NMGC’s intrastate transmission and distribution system for delivery to customers.

Market and sales

 

                                                                                                               
PGS, NMGC and SeaCoast Revenue and Sales Volumes by Customer Class
         Gas Revenues (%)       Therms Gas Sales Volumes (%)   
For the year ended December 31   2022   2021   2022   2021
Residential   49.2   53.1   14.4   14.6
Commercial   28.3   31.4   28.7   28.8
Industrial   5.1   5.5   49.1   51.7
Other   17.4   10.0   7.8   4.9
Total   100.0   100.0   100.0   100.0

PGS

As at December 31, 2022, PGS serves approximately 468,000 customers with $2.5 billion USD in assets and 767 employees. The PGS system includes approximately 24,300 kilometres of natural gas mains and 13,500 kilometres of service lines. Natural gas throughput (the amount of gas delivered to its customers, including transportation-only service) was 2 billion therms in 2022.

PGS is regulated by the FPSC. NMGC is regulated by the NMPRC. Rates are set at a level that allow the utilities to collect total revenues or revenue requirements equal to their cost to provide service, plus an appropriate return on invested capital. As of 2022, the approved ROE range for PGS is 8.9 per cent to 11.0 per cent, based on an allowed equity capital structure of 54.7 per cent. An ROE of 9.9 per cent is used for the calculation of return on investments recovered through cost recovery clauses.

For further details on PGS’ regulatory environment and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which are hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

NMGC

As at December 31, 2022, NMGC serves approximately 545,000 customers with $2.0 billion USD in assets and 678 employees. NMGC’s system includes 2,426 km of transmission lines and 17,781 km of distribution lines. Annual natural gas throughput was 926 million therms in 2022.

NMGC is subject to regulation by the NMPRC. The NMPRC sets rates at a level that allows NMGC to collect total revenues equal to its cost of providing service, plus an appropriate return on invested capital. As of 2022, the approved ROE for NMGC is 9.375 per cent on an allowed equity capital structure of 52 per cent. For further details on NMGC’s regulatory environment and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which are hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

EBPC

EBPC owns Brunswick Pipeline, a regulated 145-km pipeline delivering re-gasified liquefied natural gas from the Saint John LNG import terminal near Saint John, New Brunswick to markets in the Northeastern

 

Emera Incorporated – 2022 Annual Information Form    15


United States. The pipeline travels through southwest New Brunswick and connects with M&NP at the Canada/U.S. border near Baileyville, Maine.

Since its commissioning in July 2009, the pipeline has been used solely to transport natural gas for RENAC under a 25-year firm service agreement, which expires in 2034. Brunswick Pipeline is regulated by the CER, which has classified it as a Group II pipeline. As a regulated Group II pipeline, the tolls of Brunswick Pipeline are regulated by the CER on a complaint basis, as opposed to a regulatory approval process. In the absence of a complaint, the CER does not normally undertake a detailed examination of Brunswick Pipeline’s tolls, which are subject to a firm service agreement with RENAC, as noted above. The firm service agreement provides for a predetermined toll increase in the fifth and fifteenth year of the contract.

SeaCoast

In 2018, SeaCoast executed an agreement with Seminole Electric Cooperative, Inc. (“Seminole”) to provide long-term firm gas transportation service to Seminole’s new gas-fired generating facility in Putnam County, Florida. SeaCoast operates a 21-mile, 30-inch pipeline lateral that is treated as a sales-type lease for accounting purposes. The lease of the pipeline lateral to Seminole commenced on January 1, 2022.

M&NP

Emera owns a 12.9 per cent interest in M&NP, which is a 1,400 km pipeline that transports natural gas throughout markets in Atlantic Canada and the Northeastern United States.

Contribution to Consolidated Net Income

Gas Utilities and Infrastructure’s contribution to consolidated net income was $170 million USD in 2022 (2021 – $157 million USD).

Seasonal Nature

Gas sales volumes are primarily driven by general economic conditions, population and weather. Residential and commercial gas sales are seasonal. In Florida and New Mexico, Q1 is the strongest period for gas sales due to colder weather and heating demand.

Capital Investment

Capital investments (including AFUDC) in the Gas Utilities and Infrastructure segment in 2022 were $436 million USD (2021 - $407 million USD). In 2023, capital investment is expected to be approximately $475 million USD, including AFUDC. PGS will make investments to expand its system and support customer growth. NMGC will continue to make investments to maintain the reliability of its system and support customer growth.

Environmental Considerations

Brunswick Pipeline is subject to both federal and provincial environmental regulations. Brunswick Pipeline has comprehensive integrity, safety and environmental programs in place, including an integrated management system to ensure compliance and continuous improvement of its integrity, safety and environmental programs. Brunswick Pipeline also conducts regularly scheduled physical inspections of the pipeline and its right-of-way.

Economic Dependence

Brunswick Pipeline has a 25-year firm service agreement with RENAC, which expires in 2034. The risk of non-payment is mitigated as Repsol, the parent company of RENAC, has provided EBPC with a guarantee for all RECL’s payment obligations under the firm service agreement.

 

Emera Incorporated – 2022 Annual Information Form    16


Other Electric Utilities

Other Electric Utilities includes ECI, a holding company with regulated electric utilities. ECI’s regulated utilities include vertically integrated regulated electric utilities of BLPC on the island of Barbados, GBPC on Grand Bahama Island and a 19.5 per cent interest in Lucelec on the island of St. Lucia which is accounted for on the equity basis.

On March 31, 2022, Emera completed the sale of Domlec. For further details, refer to refer to Note 4, Dispositions, in the Audited Financial Statements, which is, incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.emera.com

Market and Sales

Other Electric Utilities operating revenues for 2022 were $398 million USD (2020 – $355 million USD) and electric sales volumes were 1,239 GWh (2021 –1,262 GWh).

BLPC

As at December 31, 2022, BLPC serves approximately 133,000 customers with $505 million USD of assets and a workforce of 402 employees. BLPC owns 276 MW of generating capacity, of which 96 per cent is oil-fired and 4 per cent is solar. BLPC’s transmission system consists of 188 km of transmission lines, including major substations connected to the transmission and distribution system. The distribution system consists of 3,789 km of distribution lines which includes distribution supply substations.

BLPC currently operates pursuant to a franchise to generate, transmit and distribute electricity on the island of Barbados until 2028. In 2019, the Government of Barbados passed legislation amending the number of licenses required for the supply of electricity from a single integrated license which currently exists, to multiple licenses for Generation, Transmission and Distribution, Storage, Dispatch and Sales. In March 2021, BLPC reached commercial agreement with the Government of Barbados for each of the license types, subject to the passage of implementing legislation. For more details regarding the new licenses, refer to the General Development of the Business section below, under the heading “BLPC License Negotiations”.

BLPC is regulated by the FTC, an independent regulator. Rates are set to recover prudently incurred costs of providing electricity service to customers plus an appropriate return on capital invested. . BLPC’s approved regulated return on rate base was 10 per cent for 2022 and 2021. For further details on BLPC’s regulatory environment and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

GBPC

As at December 31, 2022, GBPC serves approximately 19,000 customers, with $338 million USD of assets and a workforce of 201 employees. GBPC owns 98 MW of oil-fired generation, approximately 90 kilometres of transmission facilities and 670 kilometers of distribution facilities.

GBPC is regulated by the GBPA. Rates are set to recover prudently incurred costs of providing electricity service to customers plus an appropriate return on rate base. For further details on GBPC’s regulatory environment and recovery mechanisms, refer to Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

System Operation

BLPC and GBPC have system control centres that co-ordinate and control their electric generation and transmission facilities with the goal of providing a reliable and secure electricity supply while maintaining

 

Emera Incorporated – 2022 Annual Information Form    17


economy of operations. The generation and transmission system control centres are linked to their generating stations and other key parts of their systems by the “Supervisory Control and Data Acquisition” systems, with fibre optic, voice and data communications networks.

Transmission and Distribution

BLPC and GBPC transmit and distribute electricity from their generating stations to their customers.

Contribution to Consolidated Net Income and Adjusted Net Income

Other Electric Utilities’ contribution to consolidated net income was a loss of $35 million USD in 2022 (2021 – income of $17 million USD). Other Electric Utilities’ contribution to consolidated adjusted net income was $23 million USD in 2022 (2021 – $16 million USD). For a reconciliation of Other Electric Utilities adjusted net income to consolidated net income, refer to the “Non-GAAP Financial Measures and Ratios” and “Financial Highlights – Other Electric Utilities” sections of Emera’s MD&A, which is incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Seasonal Nature

Electricity sales and related generation varies significantly over the year in the Caribbean; Q3 is typically the strongest period, reflecting warmer weather. Grand Bahama is also particularly prone to tropical storm and hurricane impacts during Q3.

Capital Investment

Other Electric Utilities capital investments (including AFUDC) for 2022 were $48 million USD (2021 – $88 million USD). In 2023, capital investment is expected to be approximately $65 million USD, primarily in more efficient and cleaner sources of generation, including renewables and battery storage.

Environmental Considerations

Emera’s Caribbean utilities have implemented formal health & safety and environmental and management systems to assist in safeguarding the health and safety of its employees, contractors and customers while ensuring protection of the environment.

Other

The Other segment includes those business operations that in a normal year are below the required threshold for reporting as separate segments; and corporate expense and revenue items that are not directly allocated to the operations of Emera’s subsidiaries and investments.

Business operations in the Other segment include Emera Energy and ETL. Emera Energy consists of EES, a wholly owned physical energy marketing and trading business and an equity investment in a 50 per cent joint venture ownership of Bear Swamp, a 660 MW pumped storage hydroelectric facility in northwestern Massachusetts. ETL is a wholly owned technology company focused on finding ways to deliver renewable and resilient energy to customers.

Corporate items included in the Other segment are certain corporate-wide functions including executive management, strategic planning, treasury services, legal, financial reporting, tax planning, corporate business development, corporate governance, investor relations, risk management, insurance, acquisition and disposition related costs, gains or losses on select assets sales, and corporate human resource activities. It includes interest revenue on intercompany financings and interest expense on corporate debt in both Canada and the US. It also includes costs associated with corporate activities that are not directly allocated to the operations of Emera’s subsidiaries and investments.

 

Emera Incorporated – 2022 Annual Information Form    18


Emera Energy

EES derives revenue and earnings from the wholesale marketing and trading of natural gas and electricity within the company’s risk tolerances, including those related to value-at-risk and credit exposure. EES purchases and sells physical natural gas and electricity, the related transportation and transmission capacity rights, and provides related energy asset management services. The primary market area for the natural gas and power marketing and trading business is northeastern North America, including the Marcellus and Utica shale supply areas. EES also participates in the Florida, United States Gulf Coast and Midwest/Central Canadian natural gas markets. Its counterparties include electric and gas utilities, natural gas producers, electricity generators and other marketing and trading entities. EES operates in a competitive environment, and the business relies on knowledge of the region’s energy markets, understanding of pipeline and transmission infrastructure, a network of counterparty relationships and a focus on customer service. EES manages its commodity risk by limiting open positions, utilizing financial products to hedge purchases and sales, and investing in transportation capacity rights to enable movement across its portfolio.

Earnings from EES are generally dependent on market conditions. In particular, volatility in natural gas and electricity markets, which can be influenced by weather, local supply constraints and other supply and demand factors, can provide higher levels of margin opportunity. The business is seasonal, with Q1 and Q4 usually providing the greatest opportunity for earnings. EES is generally expected to deliver annual adjusted net income within its guidance range of $15 to $30 million USD ($45 to $70 million USD of margin).

Contribution to Consolidated Net Income and Adjusted Net Income

Other’s contribution to consolidated net income was a loss of $39 million in 2022 (2021 - loss of $412 million). Other’s contribution to consolidated adjusted net income was a loss of $218 million    in 2022 (2021 – loss of $198 million).For further information on the non-GAAP measure adjusted net income, refer to the “Non-GAAP Financial Measures and Ratios” and “Financial Highlights – Other” sections of the MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Capital Investment

Capital investments in the Other segment were $6 million in 2022 (2021 – $5 million). In 2023, capital investment in the Other segment is not expected to be significant.

GENERAL DEVELOPMENT OF THE BUSINESS

Three Year History and Changes Expected in 2023

The following discussion summarizes key developments in Emera’s business and operations over the last three completed financial years and changes that are expected to occur during the current financial year.

Florida Electric Utility

Base Rate Adjustments – Approval of Settlement Agreement

On August 6, 2021, Tampa Electric filed with the FPSC a joint motion for approval of a settlement agreement by Tampa Electric and the intervenors in relation to its rate case filed with the FPSC in April 2021. On October 21, 2021, the FPSC approved a settlement agreement filed by Tampa Electric. The settlement agreement allows for an increase of $191 million USD annually, effective January 2022. This increase consisted of $123 million USD in base rate charges and $68 million USD to recover the costs of retiring assets, including Big Bend coal generation assets Units 1 through 3 and meter assets. The settlement agreement further includes two subsequent year adjustments of $90 million USD and $21 million USD, effective January 2023 and January 2024, respectively related to the recovery of future investments in the

 

Emera Incorporated – 2022 Annual Information Form    19


Big Bend Modernization project and solar generation. The allowed equity in the capital structure will continue to be 54 per cent from investor sources of capital. The settlement agreement includes an allowed regulated ROE range of 9.0 per cent to 11.0 per cent with a 9.95 per cent midpoint. For further information, refer to the “Regulatory Environments – Florida Electric Utility – Base Rates” section of Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

On August 16, 2022, the FPSC approved Tampa Electric’s request to increase revenue and ROE due to increases in the 30-year United States Treasury bond yield rate. Effective July 1, 2022, the new mid-point ROE is 10.20 per cent, and the range is 9.25 per cent to 11.25 per cent.

Fuel and Capacity Charges

On July 19, 2021, Tampa Electric requested a mid-course adjustment of $83 million USD to its fuel and capacity charges, effective with September 2021 customer bills, due to an increase in fuel commodity and capacity costs in 2021. On August 3, 2021, the FPSC approved the request to recover the costs during the months of September through December 2021.

On January 19, 2022, Tampa Electric requested a mid-course adjustment to its fuel and capacity charges to recover an additional $169 million USD, effective April 2022, due to an increase in fuel commodity and capacity costs. This was approved on March 1, 2022 and the rate increase was spread over customer bills from April 1, 2022 through December 2022.

On January 23, 2023, Tampa Electric requested an adjustment to its fuel charges to recover the 2022 fuel under-recovery of $518 million USD over a period of 21 months. The request also included an adjustment to 2023 projected fuel costs to reflect the reduction in natural gas prices since September 2022 for a projected reduction of $170 million USD for the balance of 2023. The proposed changes will be decided by the FPSC in March 2023, and recovery is expected to begin in April 2023.

Solar Projects

In September 2017, Tampa Electric announced its intention to invest approximately $850 million USD over four years in new utility-scale solar photovoltaic projects across its service territory. As of December 31, 2021, the full amount was invested and is recoverable through FPSC-approved SoBRAs. AFUDC was earned on these projects during construction. The FPSC has approved SoBRAs representing a total of 600 MW or $104 million USD annually in estimated revenue requirements for in-service projects.

During 2017 to 2021, Tampa Electric invested $850 million USD in 600 MW of utility-scale solar photovoltaic projects, which is recoverable through FPSC-approved SoBRAs. AFUDC was earned on these projects during construction. The FPSC has approved SoBRAs representing a total of 600 MW or $104 million USD annually in estimated revenue requirements for in-service projects.

On October 12, 2021, the FPSC approved the true-up filing for SoBRA tranche 3, included in base rates as of January 2020. A $4 million USD true-up was returned to customers during 2021. No true-up for SoBRA tranche 4 was required.

Big Bend Power Station Modernization

Tampa Electric invested $876 million USD, including $91 million USD of AFUDC, during 2018 through 2022 to modernize the Big Bend Power Station. The modernization project repowered Big Bend Unit 1 with natural gas combined-cycle technology and eliminated coal as this unit’s fuel. As part of the modernization project, Tampa Electric retired the Unit 1 components that will not be used in the modernized plant in 2020 and Big Bend Unit 2 in 2021. Tampa Electric plans to retire Big Bend Unit 3 in 2023 as it is in the best interest of the customers from an economic, environmental risk and operational perspective.

For more information on the modernization of the Big Bend Power Station, refer to the “Regulatory Environments – Big Bend Modernization Project” section of Note 7, Regulatory Assets and Liabilities, in the

 

Emera Incorporated – 2022 Annual Information Form    20


Audited Financial Statements, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Storm Protection Cost Recovery Clause and Settlement Agreement

On October 3, 2019, the FPSC issued a rule to implement a Storm Protection Plan (“SPP”) Cost Recovery Clause. This clause provides a process for Florida investor-owned utilities, including Tampa Electric, to recover transmission and distribution storm hardening costs for incremental activities not already included in base rates. Differences between prudently incurred clause-recoverable costs and amounts recovered from customers through electricity rates in a year are deferred and recovered from or returned to customers in a subsequent year. A settlement agreement was approved on August 10, 2020, and Tampa Electric’s cost recovery began in January 2021. The current approved plan addressed the years 2020 through 2022, and in April 2022 Tampa Electric submitted a new plan to determine cost recovery in 2023, 2024 and 2025. On October 4, 2022, the FPSC approved Tampa Electric’s SPP for those years.

Storm Reserve – Hurricane Ian

In September 2022, Tampa Electric was impacted by Hurricane Ian. Total restoration costs were $126 million USD, with $119 million USD of restoration costs charged against Tampa Electric’s FPSC approved storm reserve. Total restoration costs charged to the storm reserve have exceeded the reserve balance and have been deferred as a regulatory asset for future recovery. On January 23, 2023, Tampa Electric petitioned the FPSC for recovery of the storm reserve regulatory asset and the replenishment of the balance in the reserve to the previous approved reserve level of $56 million USD, for a total of approximately $131 million USD. The proposed changes will be decided by the FPSC in March 2023 and recovery is expected to begin in April 2023 through March 2024.

For more information on the SPP, refer to the “Regulatory Environments – Storm Protection Cost Recovery Clause and Settlement Agreement” section of Note 7, Regulatory Assets and Liabilities, in the Audited Financial Statements, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Canadian Electric Utilities

NSPI

Environmental Legislation and Regulations

There have been several recent environmental developments in Canada at both the federal and provincial levels, as described further below. NSPI continues to work with both the provincial and federal governments on measures to address their carbon reduction goals. Future compliance with provincial and federal GHG emission caps, coal phase out requirements and targets, and renewable standards has been challenged as a result of the constraints imposed by the enactment of Bill 212, “Public Utilities Act (amended)”.

On June 29, 2021, the federal government enacted Bill C-12 “Canadian Net-Zero Emissions Accountability Act” with the objective of attaining net-zero emissions by 2050.

On July 9, 2021, the Nova Scotia provincial government amended the Renewable Electricity Regulations, mandating that 80 per cent of electric sales be generated from renewable sources by 2030.

On August 5, 2021, the federal government issued an update to the Pan-Canadian Framework on Clean Growth and Climate Change under the “Greenhouse Gas Pollution Pricing Act”. This update (the “Federal Benchmark”) applies to the 2023 through 2030 period and puts in place the legal mechanism for increasing the carbon tax in Canada by $15 per tonne annually and reaching $170 per tonne by 2030. It also outlines the minimum compliance criteria for recognizing systems like the Nova Scotia Cap-and-Trade Program to be considered equivalent to the Federal Benchmark.

 

Emera Incorporated – 2022 Annual Information Form    21


On November 5, 2021, the Nova Scotia provincial government enacted Bill 57, “Environmental Goals and Climate Change Reduction Act,” which signals the provincial government’s intent to implement several climate change related goals and greenhouse gas reduction targets, many of which overlap with and replace provisions of pre-existing acts. The legislation also introduces a goal to phase out coal-fired electricity generation in Nova Scotia by 2030. Subsequent provincial regulations will be required to detail how these goals and targets will be achieved.

In March 2022 the federal government issued their 2030 Emission Reduction Plan required under the Canadian Net-Zero Emissions Accountability Act. The Emission Reduction Plan acknowledges the federal and provincial emission reduction goals and programs currently legislated and also signals the intention for implementation of further emission reduction goals, including the federal intention of attaining a net-zero electricity grid by 2035. Subsequent regulations will be required to detail how this goal will be achieved.

Carbon Pricing Regulations

On November 9, 2022, the Nova Scotia provincial government enacted Bill 208, “Environment Act (amended)”. The legislation provides the framework for Nova Scotia’s system to comply with the federal government’s 2023 through 2030 carbon pollution pricing regulations laid out in the Pan-Canadian Framework on Clean Growth and Climate Change. Nova Scotia’s proposed system utilizes an output-based pricing system that will implement performance standards for large industrial greenhouse gas emitters to achieve emission reduction goals. Subsequent regulations will be required to detail how the pricing system will operate. The Province of Nova Scotia’s proposed output-based pricing system is subject to the approval of the federal government. If an agreement is not reached between the federal and provincial governments on a Nova Scotia system that meets the federal compliance criteria, Nova Scotia will be subject to the federal carbon pollution pricing backstop which uses emissions performances standards that vary by fuel type, and a carbon price that will start at $65 per tonne in 2023 and increase by $15 per tonne annually, reaching $170 per tonne by 2030. NSPI’s regulatory framework provides for the recovery of costs prudently incurred to comply with carbon pricing programs pursuant to NSPI’s FAM.

General Rate Application

On November 9, 2022, the Nova Scotia provincial government enacted Bill 212, “Public Utilities Act (amended)”. The legislation limits non-fuel rate increases in NSPI’s GRA filed in 2022, excluding increases relating to demand-side management costs, to a total of 1.8 per cent between the effective date of the UARB’s decision and the end of 2024. The legislation also:

 

   

requires revenue generated from the non-fuel rate increase to be used only to improve the reliability of service to ratepayers,

   

limits NSPI’s return on equity to 9.25 per cent and equity ratio to 40 per cent, and

   

limits the rate used to accrue interest on regulatory deferrals to the Bank of Canada policy interest rate plus 1.75 per cent, unless otherwise directed by the UARB.

Actions required to address the impact of Bill 212, “Public Utilities Act (amended)”, include a material reduction in NSPI’s planned capital investments and operating costs over the 2023 through 2024 period. Such deferral of capital investment and operating costs may result in higher customer costs in future periods. The legislation will have a direct and negative impact on the financial performance of NSPI and has had a negative impact on NSPI’s credit quality. For more information on this risk, refer to the “Risk Management and Financial Instruments – Regulatory and Political Risk” section of the MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

 

Emera Incorporated – 2022 Annual Information Form    22


On November 24, 2022, NSPI filed with the UARB a comprehensive settlement agreement between NSPI, key customer representatives and participating interest groups (“NSPI Settlement Agreement”) in relation to its GRA filed in January 2022. The NSPI Settlement Agreement was structured to be consistent with the amendments to the Public Utilities Act made under Bill 212, including the 1.8 per cent cap on non-fuel rate increases for 2023 and 2024. Bill 212, “Public Utilities Act (amended)” is described further, above. The NSPI Settlement Agreement also addresses the recovery of fuel costs over the settlement period and establishes a demand-side management rider. This will result in a combined fuel and non-fuel rate increase of 6.9 per cent each year for 2023 and 2024, and annualised incremental revenue (fuel and non-fuel) of $105 million in 2023 and $115 million in 2024. In addition, any under or over recovery of fuel costs will be addressed through the UARB’s established FAM process. NSPI’s ROE range will continue to be 8.75 per cent to 9.25 per cent, based on an actual five-quarter average regulated common equity component of up to 40 per cent. The NSPI Settlement Agreement also establishes a storm rider for each of 2023, 2024 and 2025, which gives NSPI the option to apply to the UARB for recovery of costs if major storm restoration expense exceeds approximately $10 million in a given year. On February 2, 2023, NSPI received the UARB’s decision, which substantially approved the NSPI Settlement Agreement as filed. Approved rate increases will be effective as of the date of the decision.

Hurricane Fiona

On September 24, 2022, Nova Scotia was struck by Hurricane Fiona, which made landfall as a post-tropical storm equivalent to a Category 2 hurricane. The storm had sustained winds of over 100 kilometres per hour and peak gusts of approximately 180 kilometres per hour. This historic storm for Nova Scotia caused significant and widespread damage to NSPI’s transmission and distribution system and at the height of the storm approximately 415,000 customers lost power. The total cost of the restoration was approximately $115 million, of which $91 million was capitalized to Property, plant and equipment (“PP&E”) and $24 million deferred to Other long-term assets for future amortization, subject to UARB approval. NSPI intends to submit an application to the UARB requesting to defer the recognition of incremental operating costs related to storm restoration. If the deferral is approved, this balance will be reclassified to “Regulatory assets” and amortized over the UARB approved recognition period.

Regulatory Matters – General

NSPI operated under a three-year fuel stability plan which resulted in an average annual overall rate increase of 1.5 per cent to recover fuel costs for the period of 2020 through 2022. These rates included recovery of Maritime Link costs, as discussed below. Differences between actual fuel costs and fuel revenues recovered from customers during 2020 to 2022 will be recovered or returned to customers after 2022, as required under NSPI’s fuel stability plan. The UARB’s decision to approve NSPI’s fuel stability plan directed that annual non-fuel revenues above NSPI’s approved range of ROE are to be applied to the FAM.

Pursuant to the FAM Plan of Administration, NSPI’s Fuel Costs are subject to independent audit every two years. On April 6, 2021, the UARB’s decision on the FAM audit findings and recommendations relating to fiscal 2018 and 2019 was publicly released. The final recommendations were endorsed by the UARB and included two disallowances. The impacts of the disallowances were not material to NSPI’s financial results.

Nova Scotia Cap-and-Trade Program Regulations

NSPI is a participant in the Nova Scotia Cap-and-Trade Program and is subject to the 2019 through 2022 compliance period. For more information, refer to the “Description of the Business – Canadian Electric Utilities - Environmental Considerations” section above.

Regulatory Matters – Maritime Link

The Maritime Link entered service on January 15, 2018 and NSPI started interim assessment payments to NSPML at that time. As part of a three-year fuel stability plan, electricity rates were set to include amounts of $164 million and $162 million for 2021 and 2022, respectively. Any difference between the amounts

 

Emera Incorporated – 2022 Annual Information Form    23


included in the fuel stability plan and those approved by the UARB through the NSPML interim assessment application will be addressed through the FAM.

For more information, refer to the “Regulatory Assets and Liabilities – Regulatory Environments – Canadian Electric Utilities – NSPI” section of the Audited Financial Statements, which are incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

ENL

Maritime Link Project

The Maritime Link entered service on January 15, 2018 and provides for the transmission of energy as well as improved reliability and ancillary benefits, supporting the efficiency and reliability of both provinces. The Maritime Link will transmit at greater capacity when the Lower Churchill projects (including Muskrat Falls and LIL) are complete, which is currently anticipated to take place in 2023.

On August 9, 2021, NSPML filed a final capital cost application with the UARB seeking approval to recover capital costs associated with the Maritime Link and approval of NSPML’s 2022 assessment. In December 2021, NSPML obtained an interim decision from the UARB approving interim rates beginning January 1, 2022, until receipt of the UARB’s decision on the application.

In February 2022, the UARB issued its decision and Board Order approving NSPML’s requested rate base of approximately $1.8 billion less $9 million of costs ($7 million after-tax) that would not have otherwise been recoverable if incurred by NSPI. NSPML also received approval to collect up to $168 million (2021 – $172 million) from NSPI for the recovery of costs associated with the Maritime Link in 2022. This was subject to a holdback of up to $2 million per month, beginning April 2022, release of which was contingent on receiving in that month at least 90 per cent of NS Block deliveries, including supplemental Energy deliveries.

In December 2022, NSPML received UARB approval to collect up to $164 million from NSPI for the recovery of costs associated with the Maritime Link in 2023. This continues to be subject to a holdback up to $2 million a month, on the same terms described above. On December 22, 2022, the UARB clarified its earlier direction regarding the holdback and NSPI can now release the holdback to NSPML when 90 per cent of the NS Block deliveries, including Supplemental Energy deliveries, is achieved. This enabled NSPI to pay NSPML approximately $4 million of the 2022 holdback. As of December 31, 2022, an additional $14 million in aggregate has been held back by NSPI. Allocation of the $14 million between NSPML and NSPI will be subject to a regulatory process that is expected to commence in early 2023 to review the holdback mechanism.

Delivery of NS Block

Nalcor’s NS Block delivery obligations commenced on August 15, 2021, and delivery will continue over the next 35 years pursuant to the project agreements. For further information on the NS Block, refer to the “Business Overview and Outlook – Canadian Electric Utilities” and “Contractual Obligations” sections of the MDA, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

Gas Utilities and Infrastructure

PGS

Settlement Agreement

On November 19, 2020, the FPSC approved a settlement agreement filed by PGS. The settlement agreement allows for an increase to base rates by $58 million USD annually effective January 1, 2021, which is a $34 million USD increase in revenue and $24 million USD increase of revenues previously recovered through the cast iron and bare steel replacement rider. It provides PGS the ability to reverse a

 

Emera Incorporated – 2022 Annual Information Form    24


total of $34 million USD of accumulated depreciation through 2023 and sets new depreciation rates effective January 1, 2021. During 2022, PGS reversed $14 million USD of the $34 million USD accumulated depreciation. No amounts were reversed prior to 2022.

Under the agreement base rates are frozen from January 1, 2021 to December 31, 2023, unless its earned ROE were to fall below 8.9 per cent before that time with an allowed equity in the capital structure of 54.7 per cent from investor sources of capital. The settlement agreement provides for the deferral of income taxes as a result of changes in tax laws. The changes would be reflected as a regulatory asset or liability and either result in an increase or a decrease in customer rates through a subsequent regulatory process.

Base Rate

On February 3, 2023, PGS notified the FPSC that it is planning to file a base rate proceeding in April 2023 for new rates effective January 2024. For more information refer to the “Business Overview and Outlook – Gas Utilities and Infrastructure - Gas Utilities and Infrastructure Outlook” section of the MDA, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

NMGC

Settlement Agreements

On December 16, 2020, the NMPRC approved a settlement agreement for new rates that became effective on January 1, 2021. The new rates reflect the recovery of capital investment in pipelines and related infrastructure and resulted in an increase in revenue of approximately $5 million USD annually.

On December 13, 2021, NMGC filed a rate case with the NMPRC for new rates to become effective January 2023. On May 20, 2022, NMGC filed an unopposed settlement agreement with the NMPRC for an increase of $19 million USD in annual base revenues. The rates reflect the recovery of increased operating costs and capital investments in pipelines and related infrastructure. The NMPRC approved the settlement agreement on November 30, 2022.

NMGC Winter Event Gas Cost Recovery

In February 2021, the State of New Mexico experienced an extreme cold weather event that resulted in an incremental $108 million USD for gas costs above what it would normally have paid during this period. NMGC normally recovers gas supply and related costs through a purchased gas adjustment clause. On April 16, 2021, NMGC filed a Motion for Extraordinary Relief, as permitted by the NMPRC rules, to extend the terms of the repayment of the incremental gas costs and to recover a carrying charge. On June 15, 2021, the NMPRC approved the recovery of $108 million USD and related borrowing costs over a period of 30 months beginning July 1, 2021.

Other Electric Utilities

Sale of Emera Maine

On March 24, 2020, Emera completed the sale of Emera Maine for a total enterprise value of $2.0 billion ($1.4 billion USD).

ECI

BLPC General Rate Review

On October 4, 2021 BLPC submitted a general rate review application to the FTC. The application seeks a rate adjustment and the implementation of a cost reflective rate structure that will facilitate the changes expected in the newly reformed electricity market and the country’s transition toward 100 per cent

 

Emera Incorporated – 2022 Annual Information Form    25


renewable energy generation. The application seeks recovery of capital investment in plant, equipment and related infrastructure and results in an increase in annual non-fuel revenue of approximately $23 million USD upon approval. The application includes a request for an allowed regulatory ROE of 12.50 per cent on an allowed equity capital structure of 65 per cent.

On September 16, 2022, the FTC granted BLPC interim rate relief, allowing an increase in base rates of approximately $3 million USD for the remainder of 2022 and approximately $1 million USD per month for 2023. Interim rate relief is effective from September 16, 2022 until the implementation of final rates. The hearing concluded in October 2022. On February 15, 2023, the FTC issued a decision on the BLPC rate review application which included the following significant items: an allowed regulatory ROE of 11.75 per cent, an equity capital structure of 55 per cent, a directive to update the major components of rate base to September 16, 2022, and a directive to establish regulatory liabilities of approximately $70 million USD related to the self-insurance fund, accumulated depreciation, and taxes. The impacts to BLPC’s rate base and final rates are not yet determinable but management does not expect the decision to have a material impact on Emera’s adjusted net income. BLPC will seek to clarify aspects of the FTC decision in its compliance filing and is also considering filing a submission to the FTC for a review of the decision. BLPC expects a decision on final rates from the FTC in 2023.

BLPC Licenses

BLPC is regulated by the Fair Trading Commission (“FTC”), an independent regulator, under the Utilities Regulation (Procedural) Rules 2003. BLPC currently operates pursuant to a franchise to generate, transmit and distribute electricity on the island until 2028. In 2019, the Government of Barbados passed legislation amending the number of licenses required for the supply of electricity from a single integrated license which currently exists to multiple licenses for Generation, Transmission and Distribution, Storage, Dispatch and Sales. In March 2021, BLPC reached commercial agreement with the Government of Barbados for each of the license types, subject to the passage of implementing legislation. The new licenses are expected to take effect in 2023 on completion of the legislative process. The Dispatch license will have a term of five years with the remaining licenses having terms ranging from 25-30 years. BLPC anticipates that any increased costs associated with the implementation of the new multi-licensed structure will be recoverable through BLPC’s regulatory framework. BLPC is awaiting final enactment and will work towards implementation of the licenses once received.

BLPC Fuel Hedging

On October 21, 2021 the FTC approved BLPC’s application to implement a fuel hedging program which will be incorporated into the calculation of the fuel clause adjustment. On November 10, 2021 BLPC requested the FTC review the required 50/50 cost sharing arrangement between BLPC and customers in relation to the hedging administrative costs, or any gains and losses associated with the hedging program. A decision is expected from the FTC in 2023.

GBPC Storm Restoration Costs – Hurricane Matthew

In 2017, as part of the recovery of costs incurred as a result of Hurricane Matthew, the GBPA approved a fixed per kWh fuel charge and allowed the difference between this and the actual cost of fuel to be applied to the Hurricane Matthew regulatory asset. As part of its decision on GBPC’s application for rate review, issued January 14, 2022, and effective April 1, 2022, the GBPA approved the continued amortization of the remaining regulatory asset over the three year period ending December 31, 2024.

GBPC Base Rates

On January 14, 2022, the GBPA issued its decision on GBPC’s application for rate review that was filed with the GBPA on September 23, 2021. The decision, which became effective April 1, 2022, allows for an increase in revenues of $3.5 million USD. The new rates include a regulatory ROE of 12.84 per cent.

 

Emera Incorporated – 2022 Annual Information Form    26


GBPC Fuel Recovery

Effective November 1, 2022, GBPC’s fuel pass through charge was increased due to an increase in global oil prices impacting the unhedged fuel cost. In 2023 the fuel pass through charge will be adjusted monthly, in-line with actual fuel costs.

USGAAP – Exemptive Relief

On January 28, 2021, the International Accounting Standards Board (“IASB”) published an Exposure Draft: Regulatory Assets and Regulatory Liabilities, which proposes the accounting model under which a company subject to rate regulation that meets the scope criteria would recognize regulatory assets and liabilities. The proposed effective date is annual reporting periods beginning on or after a date 18-24 months from the date of publication of the standard. Emera was granted exemptive relief by Canadian securities regulators on September 13, 2022, and under the Companies Act (Nova Scotia) on October 12, 2022, each allowing Emera to continue to report its financial results in accordance with USGAAP (collectively the “Exemptive Relief”). The Exemptive Relief will terminate on the earliest of: (i) January 1, 2027; (ii) if the Company ceases to have rate-regulated activities, the first day of the Company’s financial year that commences after the Company ceases to have rate-regulated activities; and (iii) the first day of the Company’s financial year that commences on or following the later of: (a) the effective date prescribed by the IASB for the mandatory application of a standard within IFRS specific to entities with rate-regulated activities (“Mandatory Rate-regulated Standard”); and (b) two years after the IASB publishes the final version of a Mandatory Rate-regulated Standard. The Exemptive Relief replaces similar relief that had been granted to Emera in 2018 and would have expired by no later than January 1, 2024.

The Company will continue to monitor the development of the Mandatory Rate-regulated Standard and assess the impact on the existing Exemptive Relief.

Financing Activity

At-The-Market Equity Program

During 2020, approximately 4.5 million common shares were issued under the ATM Program at an average price of $56.04 per share for gross proceeds of $255 million ($251 million net of after-tax issuance costs). As at December 31, 2020, an aggregate gross sales limit of $245 million remained available for issuance under the ATM Program.

On August 12, 2021, Emera renewed its ATM Program that allows the Company to issue up to $600 million of common shares from treasury to the public from time to time, at the Company’s discretion, at the prevailing market price. The ATM Program was renewed pursuant to a prospectus supplement to the Company’s short form base shelf prospectus dated August 5, 2021. The ATM program is expected to remain in effect until September 5, 2023.

During 2021, approximately 4.99 million common shares were issued under the ATM Program at an average price of $57.63 per share for gross proceeds of $287 million ($284 million net of after-tax issuance costs). As at December 31, 2021, an aggregate gross sales limit of $457 million remained available for issuance under the ATM Program.

During 2022, approximately 4.07 million common shares were issued under the ATM Program at an average price of $61.31 per share for gross proceeds of $250 million ($248 million net of after-tax issuance costs). As at December 31, 2022, an aggregate gross sales limit of $207 million remained available for issuance under the ATM Program.

During 2023, up to and including February 22, 2023, no common shares were issued under the ATM Program and an aggregate gross sales limit of $207 million remains available for issuance under the ATM Program.

 

Emera Incorporated – 2022 Annual Information Form    27


Preferred Share Issuances

On January 7, 2020, Emera announced it would not redeem the 8,000,000 Series F First Preferred Shares. The holders of the Series F First Preferred Shares had the right, at their option, to convert all or any of their Series F First Preferred Shares, on a one-for-one basis, into Series G First Preferred Shares on February 15, 2020 or to continue to hold their Series F First Preferred Shares. On February 6, 2020, Emera announced that, after having taken into account all conversion notices received from holders, no Series F First Preferred Shares would be converted into Series G First Preferred Shares.

On July 9, 2020, Emera announced it would not redeem Series A First Preferred Shares or the Series B First Preferred Shares. On August 17, 2020, Emera announced 128,610 of its 3,864,636 issued and outstanding Series A First Preferred Shares were tendered for conversion into Series B First Preferred Shares and 1,130,788 of its 2,135,364 issued and outstanding Series B First Preferred Shares were tendered for conversion into Series A First Preferred Shares, all on a one-for-one basis. As a result of the conversion, Emera has 4,866,814 Series A First Preferred Shares and 1,133,186 Series B First Preferred Shares issued and outstanding.

On April 6, 2021, Emera issued 8 million Series J First Preferred Shares at $25.00 per share at an initial dividend rate of 4.25 per cent. The aggregate gross and net proceeds from the offering were $200 million and $196 million, respectively. The net proceeds of the preferred share offering were used for general corporate purposes.

On September 24, 2021, Emera issued 9 million Series L First Preferred Shares, at $25.00 per share at an annual yield of 4.60 per cent. The aggregate gross and net proceeds from the offering were $225 million and $222 million, respectively. The net proceeds of the preferred share offering were used for general corporate purposes.

Senior Notes

On June 4, 2021, Emera US Finance LP completed an issuance of $750 million USD senior notes. The issuance included $450 million USD senior notes that bear interest at a rate of 2.64 per cent with a maturity date of June 15, 2031 and $300 million USD senior notes that bear interest at a rate of 0.83 per cent with a maturity date of June 15, 2024. The USD senior notes are guaranteed by Emera and Emera US Holdings Inc., a wholly owned Emera subsidiary.

From the $750 million USD senior notes issuance discussed above, on June 15, 2021, Emera US Finance LP repaid its previously outstanding $750 million USD senior notes on maturity.

For more information on financing activities for Emera and its subsidiaries, please refer to the “Liquidity and Capital Resources” section of Emera’s MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

RISK FACTORS

For Emera’s risk factors, refer to the “Enterprise Risk and Risk Management” section of the MD&A and the “Principal Financial Risks and Uncertainties” section of Note 27, Commitments and Contingencies, to the Audited Financial Statements, which are each incorporated herein by reference, copies of which are available electronically under Emera’s profile on SEDAR at www.sedar.com.

CAPITAL STRUCTURE

The authorized capital of Emera consists of an unlimited number of common shares, an unlimited number of first preferred shares and an unlimited number of second preferred shares. Each class of preferred shares is issuable in series.

 

Emera Incorporated – 2022 Annual Information Form    28


As at December 31, 2022, 269,944,308 common shares, 4,866,814 Series A First Preferred Shares, 1,133,186 Series B First Preferred Shares, 10,000,000 Series C First Preferred Shares, 5,000,000 Series E First Preferred Shares, 8,000,000 Series F First Preferred Shares, 12,000,000 Series H First Preferred Shares, 8,000,000 Series J First Preferred Shares, 9,000,000 Series L First Preferred Shares, 2,200,525 Barbados DRs and 1,814,135 Bahamas DRs were issued and outstanding.

Common Shares

The holders of common shares are entitled to receive notice of and to attend all annual and special meetings of the shareholders of Emera, other than separate meetings of holders of any other class or series of shares, and to one vote in respect of each common share held at such meetings.

The holders of common shares are entitled to dividends on a pro rata basis, as and when declared by the Board. Subject to the rights of the holders of the first preferred shares and second preferred shares, if any, who are entitled to receive dividends in priority to the holders of the common shares, the Board may declare dividends on the common shares to the exclusion of any other class of shares of Emera.

On the liquidation, dissolution or winding-up of Emera, holders of common shares are entitled to participate rateably in any distribution of assets of Emera, subject to the rights of holders of first preferred shares and second preferred shares, if any, who are entitled to receive the assets of the Company on such a distribution in priority to the holders of the common shares.

There are no pre-emptive, redemption, purchase or conversion rights attaching to the common shares. The foregoing description is subject to the “Share Ownership Restrictions” section below.

Emera First Preferred Shares

The first preferred shares of each series rank on parity with the first preferred shares of every other series and are entitled to a preference over the second preferred shares, the common shares, and any other shares ranking junior to the first preferred shares with respect to the payment of dividends and the distribution of the remaining property and assets or return of capital of the Company in the liquidation, dissolution or wind-up, whether voluntary or involuntary.

In the event the Company fails to pay, in aggregate, eight quarterly dividends on any series of the first preferred shares, the holders of the first preferred shares will be entitled, for only as long as the dividends remain in arrears, to attend any meeting of shareholders of the Company at which directors are to be elected and to vote for the election of two directors out of the total number of directors elected at any such meeting.

The first preferred shares of each series are not redeemable at the option of their holders. For a summary of the terms and conditions of the Company’s authorized First Preferred Shares as of December 31, 2022, refer to Appendix “B” of this AIF.

Emera Second Preferred Shares

The second preferred shares have special rights, privileges, restrictions and conditions substantially similar to the first preferred shares, except that the second preferred shares rank junior to the first preferred shares with respect to the payment of dividends, repayment of capital and the distribution of assets of Emera in the event of liquidation, dissolution or winding-up of Emera. As at December 31, 2022, Emera had not issued any second preferred shares.

Share Ownership Restrictions

As required by the Reorganization Act and pursuant to the Privatization Act, the Articles of Emera provide that no person, together with associates thereof, may subscribe for, have transferred to that person, hold, beneficially own or control, directly or indirectly, otherwise than by way of security only, or vote, in the

 

Emera Incorporated – 2022 Annual Information Form    29


aggregate, voting shares of Emera to which are attached more than 15 per cent of the votes attached to all outstanding voting shares of Emera.

The common shares, and in certain circumstances the Series A First Preferred Shares, Series B First Preferred Shares, Series C First Preferred Shares, Series E First Preferred Shares, Series F First Preferred Shares, Series H First Preferred Shares, Series J First Preferred Shares and Series L First Preferred Shares are considered to be voting shares for purposes of the constraints on share ownership.

Emera’s Articles contain provisions for the enforcement of these constraints on share ownership including provisions for suspension of voting rights, forfeiture of dividends, prohibitions of share transfer and issuance, compulsory sale of shares and redemption, and suspension of other shareholder rights. The Board may require shareholders to furnish statutory declarations as to matters relevant to enforcement of the restrictions.

CREDIT RATINGS

Emera has the following credit ratings by the Rating Agencies:

 

                  Moody’s                             S&P                              Fitch            

Corporate

   Baa3    BBB    BBB

Outlook

   Negative    Negative    Negative

Senior unsecured debt program

   Baa3    BBB-    BBB

Hybrid Notes

   Ba2    BB+    BB+

First Preferred Shares

   N/A    P-3 (high)    N/A

Ratings are intended to provide investors with an independent measure of the credit quality of an issue of securities and are indicators of the likelihood of the payment capacity and willingness of an issuer to meet its financial commitment in accordance with the terms of the obligation. The credit ratings assigned by the Rating Agencies are not recommendations to buy, sell, or hold securities in as much as such ratings are not a comment upon the market price of the securities or their stability for a particular investor. The credit ratings assigned to the securities may not reflect the potential impact of all risks on the value of the securities. There is no assurance that any rating will remain in effect for any given period of time or that any rating will not be revised or withdrawn entirely by a Rating Agency in the future if in its judgment circumstances so warrant.

Moody’s

Moody’s credit ratings are on a long-term debt rating scale that ranges from Aaa to C, representing the range from highest to lowest quality of such rated securities. The rating of Baa3 obtained from Moody’s in respect of the senior unsecured debt is the fourth highest of nine available rating categories and indicates that the obligations are subject to moderate credit risk. As such, they are considered medium-grade and may possess speculative characteristics. The rating of Ba2 from Moody’s in respect of the Hybrid Notes is characterized as having speculative elements and being subject to substantial credit risk. It is the fifth highest of nine available rating categories. Moody’s appends numerical modifiers 1, 2 and 3 to each generic rating classification from Aa through Caa. The modifier 1 indicates that the obligation ranks in the higher end of its generic rating category; the modifier 2 indicates a mid-range ranking; and the modifier 3 indicates a ranking in the lower end of that generic rating category.

S&P

S&P’s credit ratings are on a long-term debt scale that ranges from AAA to D, representing the range from highest to lowest quality of such rated securities. The issuer rating of BBB obtained from S&P in respect of the corporate rating indicates that the issuer has adequate capacity to meet its financial commitments. The issue rating of BBB- from S&P in respect of the senior unsecured debt indicates that the obligations exhibit adequate protection parameters. The issue rating of BB+ from S&P in respect of the Hybrid Notes indicates that the obligations exhibit adequate projection parameters in the near term however the obligor may not

 

Emera Incorporated – 2022 Annual Information Form    30


have the capacity to meet its obligations in the long term. The issue and issuer ratings of BBB and BB are the fourth and fifth highest, respectively, of ten available ratings categories and the addition of either a “(+)” or a “(-)” designation after a rating indicates the relative standing within a particular category. In each case, however, adverse economic conditions or changing circumstances are more likely to lead to weakened capacity of the obligor to meet its financial commitments on the obligation.

A P-3 (high) rating with respect to Emera’s issued and outstanding First Preferred Shares is the third highest of the eight standard categories of ratings utilized by S&P for preferred shares.

Fitch

Fitch’s credit ratings are on a long-term debt scale that ranges from AAA to D, representing the range from highest to lowest quality of such rated securities. The rating of BBB obtained from Fitch in respect of the senior unsecured debt is the fourth highest of nine available rating categories and indicates that the issuer has adequate capacity to meet its financial commitments. The rating of BB from Fitch in respect of the Hybrid Notes is characterized as having elevated default risk however business or financial flexibility exists that support servicing the financial commitments. The BB rating from Fitch is the fifth highest of nine available ratings categories and the addition of either a “(+)” or a “(-)” designation after a rating indicates the relative standing within a particular category. In each case, however, adverse economic conditions or changing circumstances are more likely to lead to weakened capacity of the obligor to meet its financial commitments on the obligation.

Emera has made, or will make, payments in the ordinary course to the Rating Agencies in connection with the assignment of ratings on both Emera and its securities. In addition, Emera has made customary payments in respect of certain subscription services provided to Emera by the Rating Agencies during the last two years.

For further information on the credit ratings of Emera and its subsidiaries, including the recent downgrades from both S&P and DBRS of NSPI, refer to the “Credit Ratings” section of the MD&A, which is hereby incorporated by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com.

DIVIDENDS

Any dividend payments will be at the Board’s discretion based upon earnings and capital requirements and any other factors as the Board may consider relevant. On September 22, 2022 Emera extended its annual dividend growth rate target of four to five per cent through 2025. The Company targets a long-term dividend payout ratio of 70 to 75 per cent, and while the payout ratio is likely to exceed that target through and beyond the forecast period, it is expected to return to that range over time.

Emera maintains the Dividend Reinvestment Plan, which provides an opportunity for shareholders to reinvest dividends and to participate in optional cash contributions for the purpose of purchasing common shares. This plan provides for a discount of up to 5 per cent from the average market price of Emera’s common shares for common shares purchased in connection with the reinvestment of cash dividends. The discount was 2 per cent in 2022.

 

Emera Incorporated – 2022 Annual Information Form    31


The Board approved the payment of the following dividends during the last three completed fiscal years, as summarized in the following table:

 

       
Class of Shares      2022        2021        2020   
       

Common Shares(1), (2), (3)

       $2.6775           $2.5750           $2.4750   
       

Series A First Preferred Shares(4)

       $0.5456           $0.5456           $0.6155   
       

Series B First Preferred Shares

       $0.6869           $0.4873           $0.6965   
       

Series C First Preferred Shares(5)

       $1.18024           $1.18024           $1.18024   
       

Series E First Preferred Shares

       $1.1250           $1.1250           $1.1250   
       

Series F First Preferred Shares(6)

       $1.05052           $1.05052           $1.053515   
       

Series H First Preferred Shares(7)

       $1.2250           $1.2250           $1.2250   
       

Series J First Preferred Shares(8)

       $1.0625           $0.646965           -          
       

Series L First Preferred Shares(9)

       $1.1500           $0.1638           -          

 

  (1)

On September 16, 2020, Emera approved an increase in the annual common share dividend rate from $2.45 to $2.55. The first payment was effective November, 2020.

 
  (2)

On September 24, 2021, Emera approved an increase in the annual common share dividend rate from $2.55 to $2.65. The first payment was effective November 15, 2021.

 
  (3)

On September 22, 2022, Emera approved an increase in the annual common share dividend rate from $2.65 to $2.76. The first payment was effective November 15, 2022.

 
  (4)

The Series A First Preferred Shares annual dividend rate was reset from $0.6388 to $0.5456 for the five year period commencing August 15, 2020 and ending on (and inclusive of) August 14, 2025.

 
  (5)

The Series C First Preferred Shares annual dividend rate was reset from $1.0250 to $1.18024 for the five year period commencing August 15, 2018 and ending on (and inclusive of) August 14, 2023.

 
  (6)

The Series F First Preferred Shares annual dividend rate was reset from $1.0625 to $1.0505 for the five year period commencing February 15, 2020 and ending on (and inclusive of) February 14, 2025.

 
  (7)

The Series H First Preferred Shares with an annual dividend rate of $1.2250 (per share) were issued May 31, 2018.

 
  (8)

The Series J First Preferred Shares with an annual dividend rate of $1.0625 (per share) were issued April 6, 2021.

 
  (9)

The Series L First Preferred Shares with an annual dividend rate of $1.150 (per share) were issued September 24, 2021.

 

Pursuant to the Income Tax Act (Canada) and corresponding provincial legislation, all dividends paid on Emera’s common shares and first preferred shares qualify as eligible dividends.

MARKET FOR SECURITIES

Trading Price and Volume

Emera’s common shares, Series A First Preferred Shares, Series B First Preferred Shares, Series C First Preferred Shares, Series E First Preferred Shares, Series F First Preferred Shares, Series H First Preferred Shares, Series J First Preferred Shares and Series L First Preferred Shares are listed and posted for trading on the TSX under the symbols “EMA”, “EMA.PR.A”, “EMA.PR.B”, “EMA.PR.C”, “EMA.PR.E”, “EMA.PR.F”, “EMA.PR.H”, “EMA.PR.J” and “EMA.PR.L”, respectively. The Barbados DRs are listed on the BSE under the symbol EMABDR. The Bahamas DRs are listed on the BISX under the symbol EMAB. The trading volume and high and low price for Emera’s securities for each month of 2022 are set out In Appendix “C” of this AIF.

At-The-Market Equity Program

On August 12, 2021, Emera renewed its ATM Program that allows the Company to issue up to $600 million of common shares from treasury to the public from time to time, at the Company’s discretion, at the prevailing market price. The ATM Program was renewed pursuant to a prospectus supplement to the Company’s short form base shelf prospectus dated August 5, 2021. The ATM program is expected to

 

Emera Incorporated – 2022 Annual Information Form    32


remain in effect until September 5, 2023. As at December 31, 2022, an aggregate gross sales limit of approximately $207 million remains available for issuance under the ATM program. For more information on the ATM Program, refer to “General Development of the Business – Financing Activity – At-The-Market Equity Program” above.

DIRECTORS AND OFFICERS

Directors

The following information is provided for each Director of Emera as at December 31, 2022(1):

 

     
Name, Residence, Principal Occupations During the Past Five Years    Director
Since(2)
  Committees(3)    

M. Jacqueline Sheppard (Chair), Calgary, Alberta, Canada

Chair of the Board since May 2014. Director of Suncor Energy Inc., a Canadian integrated energy company and of ARC Resources Ltd., a publicly traded Canadian energy company. Director of Alberta Investment Management Corporation (AIMCo), an institutional investment manager.(1) Former Executive Vice President, Corporate and Legal of Talisman Energy Inc. Founder and former Lead Director of Black Swan Energy Inc., an Alberta upstream energy company, which was sold in July 2021. Former Director of Cairn Energy PLC, a publicly traded UK-based international upstream company and Chair of the Research and Development Corporation of the Province of Newfoundland and Labrador, a provincial Crown corporation, until June 2014.

   2009   (4)  

Scott C. Balfour, Halifax, Nova Scotia, Canada

A Director and President and Chief Executive Officer of Emera since March 29, 2018. Mr. Balfour is a Director of many Emera subsidiaries, including being Chair of Tampa Electric Company and Nova Scotia Power Inc. He is a former director of Martinrea International Inc. He was Chief Operating Officer from 2016 to 2018 and was Executive Vice President and Chief Financial Officer of Emera from April 2012 to March 2016. From 1994 to 2011 he was Chief Financial Officer and then President of Aecon Group Inc., a Canadian publicly traded construction and infrastructure development company. He is also past Chair of the Ontario Energy Association.

   2018   (5)  

James V, Bertram Calgary, Alberta, Canada

Chair of the Board, Keyera Corporation. Formerly President, and Chief Executive Officer of Keyera from its inception in 1998 until 2015, when he became Executive Chair. Previously Vice President – Marketing for the worldwide operations of Gulf Canada. Director of Methanex Corporation, the world’s largest producer and supplier of methanol to major international markets.

   2018  

Chair of HSEC and Member of MRCC

 

Henry E. Demone, Lunenburg, Nova Scotia, Canada

Former Chair of High Liner Foods, the leading North American processor and marketer of value-added frozen seafood. Mr. Demone was President of High Liner Foods since 1989 and its President and Chief Executive Officer from 1992 to May 2015. He was interim Chief Executive Officer of High Liner Foods from August 2017 until April 2018. A Director of Saputo Inc.

   2014  

Chair of MRCC and Member of

NCGC

 

Paula Y. Gold-Williams, San Antonio, Texas, U.S.

Former President and CEO of CPS Energy, a fully integrated electric and natural gas municipal utility based in San Antonio, Texas. Currently serves as the Chair of the Keystone Policy Center, having been a member of both the Policy Center and its Energy Board since 2016. Board member and Treasurer of EPIcenter, an innovation think tank; incubator and accelerator; and strategic advisory organization. Energy Pillar Co-Chair of Dentons’ Global Smart Cities & Communities Initiatives and Think Tank. Advisory Board Member of iEmpower, an all-inclusive organization that optimizes the concept of community to engage and inspire women. Serves on the US Secretary of Energy’s Advisory Board.

   2022  

Member of AC and HSEC

 

 

Emera Incorporated – 2022 Annual Information Form    33


     
Name, Residence, Principal Occupations During the Past Five Years    Director
Since(2)
  Committees(3)    

Kent M. Harvey, New York, New York, U.S.

Former Chief Financial Officer for PG&E Corporation, an energy-based holding company, and the parent of Pacific Gas and Electric Company, an energy company that provides gas and electric service to approximately 16 million Californians across a 70,000 square-mile service area in Northern and Central California.

   2017  

Chair of AC and Member of HSEC

 

B. Lynn Loewen, FCPA, FCA, Westmount, Quebec, Canada

Former President of Minogue Medical Inc., a healthcare organization which delivers innovative medical technologies to hospitals and clinics. President of Expertech Network Installation Inc. from 2008 to 2011. Member of the Board of Directors of National Bank of Canada, a Canadian Chartered Bank. Director of Xplore Communications Inc., a Canadian broadband service provider, and Chair of its Audit Committee.

   2013  

Member of AC, HSEC and RSC

 

Ian E. Robertson, Oakville, Ontario, Canada

Principal of the Northern Genesis group of special purpose acquisition companies focused on identifying and acquiring energy transition businesses which demonstrate strong sustainability and Environmental, Social and Governance (ESG) alignment. Former CEO of Algonquin Power & Utilities Corp. (Algonquin Power. Member of the Board of Directors of Northern Genesis Acquisition Corp. III and a Director of Embark Technology, Inc., an autonomous vehicle company. Former Director of Largo Resources Ltd., Algonquin Power. and Atlantica Sustainable Infrastructure plc.

   2022  

Member of AC and RSC

 

Andrea S. Rosen, Toronto, Ontario, Canada

Former Vice-Chair of TD Bank Financial Group and President of TD Canada Trust. Director of Manulife Financial Corporation, a Canadian multinational insurance company and financial services provider; Ceridian HCM Holding Inc., a global human capital management software company and Element Fleet Management Corp., a global fleet management company, providing services and financing for commercial vehicle fleets. Former Director of Alberta Investment Management Corporation. Former Director of Hiscox Ltd., a Bermuda-incorporated specialty insurer listed on the London Stock Exchange.

   2007  

Chair of NCGC and Member of AC

 

Richard P. Sergel, Boston, Massachusetts, U.S.

Former President and Chief Executive Officer of the North American Electric Reliability Corporation (NERC). Former President and Chief Executive Officer of National Grid USA from 2000 to 2004. Also former President and Chief Executive Officer of the New England Electric System. Presently a Director of State Street Corporation. Has also served on the boards of the Edison Electric Institute and the Consortium for Energy Efficiency.

   2010  

Member of AC and NCGC

 

Karen H. Sheriff, Picton, Ontario, Canada

Ms. Sheriff is past President and CEO of Q9 Networks Inc., and prior to that, President and CEO of Bell Aliant, Inc., from 2008 to 2014. She held senior leadership positions for more than nine years with BCE Inc. and currently serves on the BCE Inc. Board of Directors. She spent over 10 years at United Airlines in the areas of marketing, strategy, human resources, and finance. She is a former member of the Board of Directors of CPP Investments and WestJet Airlines Ltd.

   2021  

Member of MRCC and RSC

 

Jochen E. Tilk, Toronto, Ontario, Canada

Former Executive Chair of Nutrien Ltd., a Canadian global supplier of agricultural products and services based in Saskatoon, Saskatchewan. Former President and Chief Executive Officer of Potash Corporation of Saskatchewan. Previously President and Chief Executive Officer of Inmet Mining Corporation, a Canadian-based, international metals company. Mr. Tilk is a director of AngloGold Ashanti Limited, a publicly listed international gold mining company, headquartered in Johannesburg, South Africa. He is also Vice-Chair of the Princess Margaret Cancer Foundation, a not-for-profit organization. He is the former Chair of the board of directors of Canpotex Limited. Former Director of the Fertilizer Institute and the International Fertilizer Association.

   2018  

Chair of RSC and Member of MRCC and NCGC

 

 

  (1)

Effective May 26, 2022, John B. Ramil retired from the Emera Board of Directors. Effective January 1, 2023, Ms. Sheppard retired from the AIMCo Board of Directors.

 

Emera Incorporated – 2022 Annual Information Form    34


  (2)

Denotes the year the individual became a Director of Emera. Directors are elected for a one year term which expires at the termination of Emera’s annual general meeting;

  (3)

Audit Committee (AC), Health, Safety and Environment Committee (HSEC), Management Resources and Compensation Committee (MRCC), Nominating and Corporate Governance Committee (NCGC), and Risk and Sustainability Committee (RSC);

  (4)

Ms. Sheppard is not a member of any committee but attends all committee meetings as Chair of the Board;

  (5)

Mr. Balfour is not a member of any committee as he is the President and Chief Executive Officer of the Company but attends all committee meetings.

Officers

The Officers of Emera as at December 31, 2022 were as follows:

 

   
Name and Residence    Principal Occupations During the Past Five Years

Scott C. Balfour

President and Chief Executive Officer

Halifax, Nova Scotia, Canada

  

A Director and President and Chief Executive Officer of Emera since March 29, 2018.(1)

Gregory W. Blunden, FCPA

Chief Financial Officer

Halifax, Nova Scotia, Canada

  

Chief Financial Officer of Emera since March 2016.

Karen E. Hutt

Executive Vice-President, Business Development and Strategy

Halifax, Nova Scotia, Canada

  

Executive Vice-President, Business Development and Strategy of Emera since October 21, 2019. Previously, President and Chief Executive Officer of NSPI since August 2016.

Richard C. Janega (2)

Chief Operating Officer, Electric Utilities, Canada and Caribbean

Halifax, Nova Scotia, Canada

  

Chief Operating Officer, Electric Utilities, Canada, US Northeast, and Caribbean of Emera since March 31, 2018. Director of NSPI since May 2018. Interim President and Chief Executive Officer of NSPI from June to October 2020. Director and President and CEO of NSPML. Former Chair of the Board of Emera Maine from March 2018 until March 2020. Chief Executive Officer of ENL since 2014. Chair and President of ECI and Chair of both GBPC and BLPC. Former Chief Operating Officer for NSPI.

Bruce A. Marchand

Chief Risk and Sustainability Officer Halifax, Nova Scotia, Canada

  

Chief Risk and Sustainability Officer of Emera since June 30, 2022. Prior to this Chief Legal and Compliance Officer of Emera and NSPI since December 1, 2014 and Chief Legal Officer of Emera and NSPI since January 2012.

R. Michael Roberts

Chief Human Resources Officer

Halifax, Nova Scotia, Canada

  

Chief Human Resources Officer of Emera and NSPI since December 1, 2014.

Daniel P. Muldoon

Executive Vice-President Project Development and Operations Support

Halifax, Nova Scotia, Canada

  

Executive Vice-President Project Development and Operations Support of Emera. Chair of the Boards of ENL, EBPC, Emera Technologies LLC and NMGC. Former Director of Emera Maine from August 2013 until March 2020. Director of TEC and NSPML. Formerly Executive Vice-President, Major Renewables and Alternative Energy since May 2014.

Michael R. Barrett

Executive Vice-President and General Counsel

Halifax, Nova Scotia, Canada

  

Executive Vice-President and General Counsel of Emera since July 1, 2022. Prior to this, General Counsel of Emera since November 20, 2017. Prior to joining Emera, Senior Partner and head of the power and climate change practice groups at Bennett Jones LLP in Toronto.

Stephen D. Aftanas

Corporate Secretary

Halifax, Nova Scotia, Canada

  

Corporate Secretary of Emera since September 2008. Corporate Secretary of NSPI from September 2008 to December 2019.

 

  (1)

Mr. Balfour’s principal occupations during the past five years are described above in the Directors table.

  (2)

Effective December 31, 2022, Mr. Janega retired from Emera and certain subsidiaries and/or subsidiary boards. Following his retirement, Mr. Janega will serve or continue to serve on the following subsidiary boards: BLPC, ECI, ENLH, GBPC and NSPI.

 

Emera Incorporated – 2022 Annual Information Form    35


As at December 31, 2022, the Directors and Officers, in total, beneficially owned or controlled, directly or indirectly, 204,365 common shares or less than 1 per cent of the issued and outstanding shares of Emera.

AUDIT COMMITTEE

The Audit Committee of Emera is composed of the following six members, all of whom are independent Directors: Kent M. Harvey (Chair), Paula Gold-Williams, B. Lynn Loewen, Ian E. Robertson, Andrea S. Rosen and Richard P. Sergel. The responsibilities and duties of the Audit Committee are set out in the Audit Committee’s Charter, a copy of which is attached as Appendix “D” to this AIF.

The Board believes that the composition of the Audit Committee reflects a high level of financial literacy and experience. Each member of the Audit Committee has been determined by the Board to be “financially literate” as such term is defined under Canadian securities laws. The Board has made these determinations based on the education and breadth and depth of experience of each member of the Audit Committee. The following is a description of the education and experience of each member of the Audit Committee that is relevant to the performance of his or her responsibilities as a member of the Audit Committee:

Kent M. Harvey, Committee Chair

Former Chief Financial Officer for PG&E Corporation, an energy-based holding company headquartered in San Francisco. PG&E Corporation is the parent company of Pacific Gas and Electric Company, one of the largest combined natural gas and electric energy companies in the United States. In over 33 years with PG&E Corporation, Mr. Harvey held progressively senior roles, including Senior Vice President and Chief Financial Officer 2009 to 2015, Senior Vice President, Chief Risk and Audit Officer 2005 to 2009. He was Senior Vice President, Chief Financial Officer and Treasurer with Pacific Gas and Electric Company, a subsidiary of PG&E Corporation, from 2000 to 2005. He holds a Bachelor’s degree in Economics and a Master’s degree in Engineering – Economic Systems, both from Stanford University.

Paula Y. Gold-Williams

She is the former President and CEO of CPS Energy, a fully integrated electric and natural gas municipal utility based in San Antonio, Texas. Ms. Gold-Williams served in positions of increasing responsibility at CPS Energy before becoming CEO in 2015. She held multiple other positions during her 17-year career at CPS Energy, including Group EVP – Financial & Administrative Services, CFO and Treasurer. Chair of the Keystone Policy Center, and member of both the Policy Center and its Energy Board since 2016. Board member and Treasurer of EPIcenter, an innovation think tank; incubator and accelerator; and strategic advisory organization. Formerly, First Vice Chair of the Electric Power Resource Institute (EPRI); a member and designated Chair Pro Tem of the Federal Reserve Bank of Dallas’ San Antonio Branch; and a past-Chair of the San Antonio Chamber of Commerce. She holds an Associate Degree in Fine Arts from San Antonio College and a BBA in accounting from St. Mary’s University. She earned a Finance and Accounting MBA from Regis University in Denver, Colorado. She is a Certified Public Accountant and a Chartered Global Management Accountant.

B. Lynn Loewen, FCPA, FCA

Former President of Minogue Medical Inc., a healthcare organization which delivers innovative medical technologies to hospitals and clinics. Fellow of the Institute of Chartered Accountants, she has served in a number of senior roles at Bell Canada, Air Canada Jazz and Air Nova, and also was the Vice President, Financial Controls for BCE. She has served as Chair of the Audit Committee on the Public Sector Pension Investment Board and was Chair of the Finance and Administration Committee of Mount Allison University. Chancellor of Mount Allison University since 2018 and was a member of the Board from 1998 to 2008. Served as Chair from 2007 to 2008.. She holds a Bachelor of Commerce from Mount Allison University. Fellow of the Chartered Professional Accountants and has received the Institute of Corporate Directors, Directors Designation.

 

Emera Incorporated – 2022 Annual Information Form    36


Ian E. Robertson

Principal of the Northern Genesis group of special purpose acquisition companies focused on identifying and acquiring energy transition businesses which demonstrate strong sustainability and Environmental, Social and Governance (ESG) alignment. Former CEO of Algonquin Power & Utilities Corp. (Algonquin Power), a publicly traded, diversified international generation, transmission, and distribution utility. Founder and principal of Algonquin Power Corporation Inc., a private independent power developer formed in 1988 and predecessor organization to Algonquin Power. Over 30 years of experience in the development of electric power generating projects and the operation of diversified regulated utilities. Member of the Board of Directors of Northern Genesis Acquisition Corp. III and a Director of Embark Technology, Inc., an autonomous vehicle company. Former Director of Largo Resources Ltd., Algonquin Power and Atlantica Sustainable Infrastructure plc. Mr. Robertson is an electrical engineer and holds a Professional Engineering designation through his Bachelor of Applied Science degree awarded by the University of Waterloo. He earned a Master of Business Administration degree from York University’s Schulich School of Business. He holds a Chartered Financial Analyst designation, as well as a global professional Master of Laws degree from the University of Toronto. He received a Chartered Director designation from the Directors College of McMaster University. Since 2013, Mr. Robertson is a former member of the board of directors of the American Gas Association.

Andrea S. Rosen

Vice-Chair of TD Bank Financial Group and President, TD Canada Trust from 2002 to 2005. From 2001 to 2002, Executive Vice President of TD Commercial Banking and Vice Chair TD Securities. Before joining TD Bank, was Vice President of Varity Corporation from 1991 to 1994 and worked at Wood Gundy Inc. (later CIBC-Wood Gundy) in a variety of roles from 1981 to 1990, eventually becoming Vice President and Director. Holds a Bachelor of Laws from Osgoode Hall Law School and a Masters of Business Administration from the Schulich School of Business at York University. She received a Bachelor of Arts from Yale University. Ms. Rosen is a Director and member of the Audit Committee of Ceridian HCM Holding Inc., a global human capital management software company, and Director and member of the Audit Committee of Manulife Financial Corporation, an issuer listed on The Toronto Stock Exchange, New York Stock Exchange, The Stock Exchange of Hong Kong, and the Philippine Stock Exchange. She is a Director of Element Fleet Management Corp., a global fleet management company. Former Director and member of the Audit Committee of Hiscox Ltd., a Bermuda-incorporated specialty insurer listed on the London Stock Exchange, and former Director of Alberta Investment Management Corporation. Member of the Board of Directors of the Institute of Corporate Directors.

Richard P. Sergel

Former President and Chief Executive Officer of the North American Electric Reliability Corporation (NERC), a regulatory authority for the bulk electricity system in North America. Before that he served as President and Chief Executive Officer of National Grid USA, and its predecessor, New England Electric System, from 1998 to 2004. Mr. Sergel is a Director and a member of the Examining and Audit Committee of State Street Corporation, a provider of financial services to institutional investors including investment servicing, investment management and investment research and trading. He previously served on the Boards of the Edison Electric Institute and the United Way of the Merrimac Valley. He was also Chair of the Consortium for Energy Efficiency. Mr. Sergel holds a Bachelor of Science in Mathematics from Florida State University, a Master of Science in Applied Mathematics from North Carolina State University and a Master of Business Administration from the University of Miami.

Audit and Non-Audit Services Pre-Approval Process

The Audit Committee is responsible for the oversight of the work of the external auditors. As part of this responsibility, the Audit Committee is required to pre-approve the audit and non-audit services performed by the external auditors in order to assure that they do not impair the external auditors’ independence from the Company. Accordingly, the Audit Committee has adopted an Audit and Non-Audit Pre-Approval Policy,

 

Emera Incorporated – 2022 Annual Information Form    37


which sets forth the procedures and the conditions pursuant to which services proposed to be performed by the external auditors may be pre-approved.

Unless a type of service has received the pre-approval of the Audit Committee, it will require specific approval by the Audit Committee if it is to be provided by the external auditors. Any proposed services exceeding the pre-approved cost levels will also require specific approval by the Audit Committee.

Auditors’ Fees

The aggregate fees billed by Ernst & Young LLP, the Company’s external auditors, during the fiscal years ended December 31, 2022 and 2021 respectively, were as follows:

 

   Service Fee      2022 ($)              2021 ($)        

Audit Fees

                                        2,018,989                                                 2,078,760        

Audit-Related Fees

       19,600                19,600        

Tax Fees

       337,999                372,618        

All Other Fees

       -                -        

Total

       2,376,588                2,470,978        

Audit-related fees for Emera relate to fees associated with the audit of pension plans. Tax fees for Emera relate to the structuring of cross-border financing of Emera’s subsidiaries and affiliates as well as tax compliance services and general tax consulting advice on various matters.

CERTAIN PROCEEDINGS

To the knowledge of Emera, none of the Directors or Officers of the Company:

 

(1)

are, as at the date of this AIF, or have been, within ten years before the date of this AIF, a director, chief executive officer or chief financial officer of any company that:

 

  (a)

was subject to an Order that was issued while the Director or Officer was acting in the capacity as director, chief executive officer or chief financial officer; or

 

  (b)

was subject to an Order that was issued after the Director or Officer ceased to be a director, chief executive officer or chief financial officer and which resulted from an event that occurred while that person was acting in the capacity as director, chief executive officer of chief financial officer;

 

(2)

are, as at the date of this AIF, or have been within ten years before the date of this AIF, a director or executive officer of any company that, while that person was acting in that capacity, or within a year of that person ceasing to act in that capacity, became bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency or was subject to or instituted any proceedings, arrangements or compromise with creditors or had a receiver, receiver manager or trustee appointed to hold its assets;

 

(3)

have, within the ten years before the date of this AIF, become bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency, or become subject to or instituted any proceedings, arrangement or compromise with creditors, or had a receiver, receiver manager or trustee appointed to hold the assets of the proposed nominee; or

 

(4)

have been subject to any penalties or sanctions imposed by a court relating to securities legislation or by a securities regulatory body or has entered in a settlement agreement with a securities regulatory body, or is subject to any penalties or sanctions imposed by a court or regulatory body that would likely be considered important to a reasonable investor making an investment decision.

 

Emera Incorporated – 2022 Annual Information Form    38


CONFLICTS OF INTEREST

There are no existing or potential material conflicts of interest between Emera or any of its subsidiaries and any Director or Officer of Emera or any of its subsidiaries.

LEGAL PROCEEDINGS AND REGULATORY ACTIONS

To the knowledge of Emera, there are no legal proceedings that individually or together could potentially involve claims against Emera or its subsidiaries for damages totaling 10 per cent or more of the current assets of Emera, exclusive of interest and costs.

During Emera’s most recently completed financial year, there have been no (a) penalties or sanctions imposed against Emera by a court relating to securities legislation or by a securities regulatory authority, (b) other penalties or sanctions imposed by a court or regulatory body against Emera that would likely be considered important to a reasonable investor in making an investment decision, and (c) settlement agreements entered into by Emera before a court relating to securities legislation or with a securities

regulatory authority.

NO INTEREST OF MANAGEMENT AND OTHERS IN MATERIAL TRANSACTIONS

None of the following persons or companies, namely (a) a Director or Officer of Emera, (b) a person or company that is the direct or indirect beneficial owner of, or who exercises control or direction over, more than 10 per cent of any class or series of Emera’s outstanding voting securities, or (c) an associate or affiliate of any person or company named in (a) or (b), had a material interest in any transaction involving Emera within Emera’s last three completed financial years or during the current financial year that has materially affected or is reasonably expected to materially affect Emera.

MATERIAL CONTRACTS

Emera did not enter into any material contracts outside the ordinary course of business during the year ended December 31, 2022, nor has it entered into any material contracts outside the ordinary course of business prior to the year ended December 31, 2022 that are still in effect as at the date of this AIF.

TRANSFER AGENT AND REGISTRAR

TSX Trust Company acts as Emera’s transfer agent and registrar for Emera’s common shares and first preferred shares. Registers for the registration and transfer of these securities of Emera are kept at TSX Trust Company’s principal offices in Halifax, Montreal and Toronto.

EXPERTS

Ernst & Young LLP are the external auditors of Emera. Ernst & Young LLP report that they are independent in the context of the CPA Code of Professional Conduct of the Chartered Professional Accountants of Nova Scotia and are in compliance with Rule 3520 of the Public Company Accounting Oversight Board (United States).

ADDITIONAL INFORMATION

Additional information relating to Emera may be found on SEDAR at www.sedar.com or upon request to the Corporate Secretary, Emera Incorporated, P.O. Box 910, Halifax, N.S., B3J 2W5, telephone (902) 428-6096 or fax (902) 428-6171. Additional information, including Directors’ and Officers’ remuneration and indebtedness, principal holders of Emera’s securities and securities authorized for issuance under equity compensation plans, is contained in Emera’s information circular for the most recent annual meeting of

 

Emera Incorporated – 2022 Annual Information Form    39


Emera’s common shareholders. Additional financial information is provided in Emera’s Audited Financial Statements and MD&A.

At any time, Emera will provide to any person upon request to the Corporate Secretary, a copy of the Emera Code of Conduct. Alternatively, a copy of the Emera Code of Conduct is available electronically under Emera’s profile on SEDAR at www.sedar.com and on its corporate website at www.emera.com.

 

Emera Incorporated – 2022 Annual Information Form    40


APPENDIX “A” - Definitions of Certain Terms

 

For convenience, certain terms used throughout this AIF shall have the following meanings:

adjusted net income has the meaning ascribed to it in the “Non-GAAP Financial Measures and Ratios” section of the MD&A, which is incorporated herein by reference, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com;

“AFUDC” means allowance for funds used during construction and represents the cost of financing regulated construction projects and is capitalized to the cost of property, plant and equipment, where permitted by the regulator;

“AIF” or “Annual Information Form” means this 2022 Annual Information Form of Emera;

AMI” means advanced metering infrastructure;

“Atlantic Canada” means the region of Canada consisting of the Provinces of New Brunswick, Newfoundland and Labrador, Nova Scotia and Prince Edward Island;

“ATM Program” means an at-the-market distribution program allowing Emera to issue common shares from treasury at the prevailing market price.

“Audited Financial Statements” means the audited consolidated financial statements of Emera as at and for the years ended December 31, 2022 and December 31, 2021, together with the auditors’ report thereon, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com;

“Bahamas DRs” means the DRs listed on BISX;

“Barbados DRs” means the DRs listed on the BSE;

“BBD” means Barbadian dollars;

“BISX” means The Bahamas International Securities Exchange;

“Bear Swamp” means Bear Swamp Power Company, LLC, a 633 MW pumped storage hydroelectric company incorporated under the laws of the State of Delaware in which Emera indirectly holds a 50 per cent interest;

“BLPC” means Barbados Light & Power Company Limited, a vertically integrated electric utility company incorporated under the laws of Barbados and a wholly-owned, direct subsidiary of ECI;

“Board” means the Board of Directors of Emera;

“Brooklyn Energy” means Brooklyn Power Corporation, a 30 MW biomass co-generation company incorporated under the laws of the Province of Nova Scotia and a wholly-owned direct subsidiary of Emera;

“Brunswick Pipeline” means the pipeline delivering re-gasified natural gas from the Saint John LNG gas terminal near Saint John, New Brunswick to markets in the Northeastern United States, which is owned directly by EBPC;

“BSD” means Bahamian dollars;

“BSE” means the Barbados Stock Exchange;

“CAD” means Canadian dollars;

“CAIR” means the Clean Air Interstate Rule;

“CER” or “Canada Energy Regulator”, the independent regulator of EBPC.

“COVID-19” means an infectious respiratory illness caused by the 2019 novel coronavirus;

“COMFIT” means the Nova Scotia Community Feed-in Tariff program which is offered by the Province of Nova Scotia and enables community organizations to be involved in renewable electricity generation;

“Company” means Emera;

“CSAPR” means Cross-State Air Pollution Rule;

“Directors” mean the directors of Emera and “Director” means any one of them;

“Dividend Reinvestment Plan” or “DRIP” means the Company’s Common Shareholders’ Dividend Reinvestment and Share Purchase Plan;

“Domlec” means Dominica Electricity Services Limited, an integrated electric utility on the island of Dominica, incorporated under the laws of the Commonwealth of Dominica, and formerly an indirect subsidiary of Emera, through ECI;

“DR” means a depositary receipt representing common shares of Emera;

“EBPC” or “Emera Brunswick Pipeline Company means Emera Brunswick Pipeline Company Ltd., a company incorporated under the federal laws of Canada and a wholly-owned, indirect subsidiary of Emera;

ECI means Emera (Caribbean) Incorporated, a company incorporated under the laws of Barbados and

 

 

Emera Incorporated – 2021 Annual Information Form    41


an indirect subsidiary of Emera and the parent company of BLPC and GBPC;

“ECRC” means the environmental cost recovery clause;

“Electricity Plan Act” means the Electricity Plan Implementation (2015) Act (Nova Scotia);

“Emera” means Emera Incorporated, a public company incorporated under the laws of the Province of Nova Scotia and traded on the TSX under the symbol “EMA”;

Emera Energy means the businesses of Emera Energy Services, Brooklyn Energy and Bear Swamp;

Emera Energy LP” means a wholly-owned subsidiary of Emera formed under the laws of the Province of Nova Scotia;

“Emera Energy Services” or “EES” means Emera Energy LP and Emera Energy Services, Inc., a natural gas and electricity marketing and trading company and a wholly-owned, indirect subsidiary of Emera incorporated under the laws of the State of Delaware, which together form a natural gas and electricity marketing and trading business;

“Emera Maine” means the company existing under the laws of the State of Maine and formerly a wholly-owned indirect subsidiary of Emera;

“ENL” or “Emera Newfoundland and Labrador” means Emera Newfoundland and Labrador Holdings Incorporated, a company incorporated under the laws of the Province of Newfoundland and Labrador and a wholly-owned, direct subsidiary of Emera, and the parent company of NSP Maritime Link Inc. and ENL Island Link Inc.;

“ENL Island Link Inc.” means ENL Island Link Incorporated, a company incorporated under the laws of the Province of Newfoundland and Labrador and a wholly-owned, direct subsidiary of ENL;

EPA” means the U.S. Environmental Protection Agency;

“ETL” means Emera Technologies LLC, a limited liability company incorporated under the laws of Delaware and a wholly-owned, indirect subsidiary of Emera.

“Fair Trading Commission, Barbados” or “FTC” means the independent regulator of BLPC;

“FAM” means the fuel adjustment mechanism established by the UARB;

“FCM” means forward capacity market;

“FERC” means the United States Federal Energy Regulatory Commission;

“Fitch” means the credit rating agency Fitch Ratings Inc;

First Preferred Shares” means each series of Emera’s authorized first preferred shares, namely its Series 2016-A Conversion, First Preferred Shares, Series A First Preferred Shares, Series B First Preferred Shares, Series C First Preferred Shares, Series D First Preferred Shares, Series E First Preferred Shares, Series F First Preferred Shares, Series G First Preferred Shares Series H First Preferred Shares, Series I First Preferred Shares Series J First Preferred Shares and Series L First Preferred Shares;

“FPSC” means the Florida Public Service Commission, the regulator of Tampa Electric and PGS;

“GBPA” means The Grand Bahama Port Authority, the regulator of GBPC;

“GBPC” or “Grand Bahama Power Company” means Grand Bahama Power Company Limited, a vertically integrated electric utility company incorporated under the laws of the Commonwealth of The Bahamas and an indirect subsidiary of ECI;

“Government of Canada Bond Yield” on any date means the yield to maturity on such date (assuming semi-annual compounding) of a Canadian dollar denominated non-callable Government of Canada bond with a term to maturity of five years as quoted as of 10:00 a.m. (Toronto time) on such date and which appears on the Bloomberg Screen GCAN5YR Page on such date; provided that, if such rate does not appear on the Bloomberg Screen GCAN5YR Page on such date, the Government of Canada Bond Yield will mean the average of the yields determined by two registered Canadian investment dealers selected by the Company as being the yield to maturity on such date (assuming semi-annual compounding) which a Canadian dollar denominated non-callable Government of Canada bond would carry if issued in Canadian dollars at 100 per cent of its principal amount on such date with a term to maturity of five years;

“Government of Canada T-Bill Rate” means, for any quarterly floating rate period, the average yield expressed as a percentage per annum on three month Government of Canada treasury bills, as reported by the Bank of Canada, for the most recent treasury bills auction preceding the applicable floating rate calculation date;

“GWh” means the amount of electricity measured in gigawatt hours;

 

 

Emera Incorporated – 2022 Annual Information Form    42


“Hybrid Notes” means the $1.2 billion USD unsecured, fixed-to-floating subordinated notes of Emera due 2076;

“IFRS” means International Financial Reporting Standards;

“Interest Reset Date” means June 15, 2026, and on every quarter thereafter that the Hybrid Notes are outstanding until their maturity on June 15, 2076;

IMP” means integrity management programs;

“IPPs” means independent power producers;

“ISO-NE” means ISO-New England, an independent, non-profit regional transmission organization which oversees the operation of New England’s bulk electric power system and transmission lines, generated and transmitted by its member utilities;

“km” means kilometre(s);

“Labrador-Island Transmission Link Project” or “LIL” means an electricity transmission project in Newfoundland and Labrador being developed by Nalcor, which will enable the transmission of the Muskrat Falls energy between Labrador and the island of Newfoundland;

“LNG” means liquefied natural gas;

“Lucelec” means St. Lucia Electricity Services Limited, a company incorporated under the laws of St. Lucia in which Emera holds an indirect 19.1% interest through ECI;

“M&NP” means the Maritimes & Northeast Pipeline, a pipeline that transports natural gas between the Maritime Provinces and New England, in which Emera holds an indirect 12.9 per cent interest;

“Maritime Link” means the transmission project which includes two 170-km sub-sea cables between the island of Newfoundland and the Province of Nova Scotia, developed by NSP Maritime Link Inc.;

“Maritime Provinces” means the region of Canada consisting of the Provinces of Nova Scotia, New Brunswick and Prince Edward Island;

MD&A means Emera’s Management’s Discussion and Analysis for the fiscal year ended December 31, 2022, a copy of which is available electronically under Emera’s profile on SEDAR at www.sedar.com;

Moodys” means the credit rating agency Moody’s Investor Services, Inc. a subsidiary of Moody’s Corporation;

“MW” means the amount of power measured in megawatts;

“Nalcor” means Nalcor Energy, a company that is incorporated under a special act of the Legislature of the Province of Newfoundland and Labrador as a Crown corporation;

“NB Power” means New Brunswick Power Corporation, a provincial Crown corporation formed under the laws of the Province of New Brunswick, responsible for the generation, transmission and distribution of electricity in the Province of New Brunswick;

“New England” means the region of the United States consisting of the States of Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island and Vermont;

“NMGC” means New Mexico Gas Company, Inc., a regulated gas distribution utility incorporated under the laws of Delaware and serving customers across New Mexico;

“NMPRC” means the New Mexico Public Regulation Commission, the regulator of NMGC;

“Northeastern United States” means the region of the United States consisting of New England and the States of New Jersey, New York and Pennsylvania;

“NS Block” means the electricity transmitted through the Maritime Link from the Muskrat Falls hydroelectric project

“NSP Maritime Link Inc.” or “NSPML” means NSP Maritime Link Incorporated, a wholly-owned direct subsidiary of ENL, incorporated under the laws of the Province of Newfoundland and Labrador, that developed the Maritime Link;

“NSPI” or “Nova Scotia Power” means Nova Scotia Power Incorporated, a vertically integrated electric utility incorporated under the laws of the Province of Nova Scotia and a wholly-owned direct and indirect subsidiary of Emera;

“Officers” mean the executive officers of Emera and “Officer” means any one of them;

“OM&G” means operating, maintenance and general;

“Order” means a cease trade order, an order similar to a cease trade order or an order that denies a company access to any exemption under securities legislation that is in effect for a period of more than 30 consecutive days;

“PGAC” means purchased gas adjustment clause;

PGS means the Peoples Gas System Division of TEC, a regulated gas distribution utility, serving customers across Florida, which effective January 1,

 

 

Emera Incorporated – 2022 Annual Information Form    43


2023, ceased to be a division of TEC as a result of the gas utility being reorganized, resulting in a separate legal entity, PGSI;

PGSI” means Peoples Gas System, Inc. (PGSI), the successor to PGS, existing under the laws of the State of Florida, and a wholly-owned direct subsidiary of TECO Gas Operations, Inc.;

Privatization Act” means the Nova Scotia Power Privatization Act, S.N.S., 1992, c.8 - and all amendments thereto;

“Public Utilities Act” means the Public Utilities Act (Nova Scotia);

“Rating Agencies” means collectively Fitch, Moody’s and S&P, and “Rating Agency” means any one of the Rating Agencies;

“RENAC” means Repsol Energy North America Canada Partnership;

Reorganization Act” means the Nova Scotia Power Reorganization (1998) Act, S.N.S., 1998, c.19 - and all amendments thereto;

“Repsol” means Repsol S.A, the parent company of RENAC;

“ROE” means return on equity;

“S&P” means the credit rating agency S&P Global Ratings, a division of S&P Global Inc.;

“Sable Wind Project” means a 14 MW wind farm near Canso, Nova Scotia;

SeaCoast” means SeaCoast Gas Transmission, LLC, a company incorporated under the laws of the State of Delaware and a wholly-owned subsidiary of TECO Energy;

“Securities Act” United States Securities Act of 1933, as amended;

“SEDAR” means the System for Electronic Documents Analysis and Retrieval, which can be found at www.sedar.com;

Series 2016-A Conversion, First Preferred Shares means the cumulative preferential first preferred shares, Series 2016-A of Emera;

“Series A First Preferred Shares” means the cumulative 5-year rate reset first preferred shares, Series A of Emera;

“Series B First Preferred Shares” means the cumulative floating rate first preferred shares, Series B of Emera;

 

“Series C First Preferred Shares” means the cumulative rate reset first preferred shares, Series C of Emera;

“Series D First Preferred Shares” means the cumulative floating rate first preferred shares, Series D of Emera;

“Series E First Preferred Shares” means the cumulative redeemable first preferred shares, Series E of Emera;

“Series F First Preferred Shares” means the cumulative rate reset first preferred shares, Series F of Emera;

“Series G First Preferred Shares” means the cumulative floating rate first preferred shares, Series G of Emera;

“Series H First Preferred Shares” means the cumulative minimum rate reset first preferred shares, Series H of Emera;

Series I First Preferred Shares means the cumulative floating rate first preferred shares, Series I of Emera;

“Series J First Preferred Shares” means the cumulative minimum rate reset first preferred shares, Series J of Emera;

“Series K First Preferred Shares” means the cumulative floating rate first preferred shares, Series K of Emera;

“Series L First Preferred Shares” means the cumulative redeemable first preferred shares, Series L of Emera;

SO2” means sulphur dioxide;

“SoBRA” means solar base rate adjustment;

Tampa Electric means the Tampa Electric Division of TEC, an integrated regulated electric utility, serving customers in West Central Florida;

TEC means Tampa Electric Company, a wholly-owned subsidiary of TECO Energy, incorporated under the laws of the State of Florida with regulated electric and gas utilities in Florida, collectively, Tampa Electric and PGS;

“TECO Energy” means TECO Energy, Inc., an energy-related holding company incorporated under the laws of the State of Florida with regulated electric and gas utilities in Florida and a regulated gas utility in New Mexico;

“TECO Gas Operations, Inc.” means the wholly-owned subsidiary of TECO Energy, incorporated under

 

 

Emera Incorporated – 2022 Annual Information Form    44


the laws of the State of Florida, and the parent company of PGSI, which as of January 1, 2023, currently owns the regulated gas utility known as PGS, formerly a division of TEC;

“TSX” means The Toronto Stock Exchange;

“UARB” means the Nova Scotia Utility and Review Board, the independent regulator of NSPI;

“USD” means U.S. dollars; and

“USGAAP” means the accounting principles which are recognized as being generally accepted and which are in effect from time to time in the U.S. as codified by the Financial Accounting Standards Board, or any successor institute

 

 

Emera Incorporated – 2022 Annual Information Form    45


APPENDIX “B” – Summary of Terms and Conditions of Authorized Series of First Preferred Shares

As of December 31, 2022, the following series of First Preferred Shares have been authorized:

Series A, B, C, D, E, F, G, H, I, J, K and L First Preferred Shares

Holders of the First Preferred Shares are not entitled to attend any meetings of the shareholders of Emera or to vote at any such meeting, except: (i) where entitled by law; (ii) for meetings of the holders of first preferred shares as a class and holders of First Preferred Shares as a series; and (iii) in situations when Emera fails to pay, in the aggregate, eight quarterly dividends on the First Preferred Shares.

In any instance where the holders of First Preferred Shares are entitled to vote, each holder shall have one vote for each Preferred Share, subject to the restrictions described under “Share Ownership Restrictions” below.

Holders of Series A, C, F, H and J First Preferred Shares are entitled to receive fixed cumulative preferential cash dividends, as and when declared by the Board, to be reset periodically on established dates to an annualized rate equal to the sum of the then five-year Government of Canada Bond Yield, calculated at the start of the applicable five-year period, and a spread as set forth in the table below (subject, (i) in the case of the Series H preferred shares, to a fixed minimum reset of 4.90 per cent and (ii) in the case of the Series J preferred shares, to a fixed minimum reset of 4.25 per cent). Holders of the Series A, C, F, H and J First Preferred Shares have the right to convert their shares into an equal number of Series B, D, G, I and K First Preferred Shares, respectively, subject to certain conditions, on such conversion dates as set forth in the table below.

Holders of Series B, D, G, I and K First Preferred Shares will be entitled to receive floating rate cumulative preferential cash dividends, as and when declared by the Board. The dividends are payable quarterly, in the amount per share determined by multiplying the applicable quarterly floating dividend rate, which is the sum of the three-month Government of Canada T-Bill Rate , recalculated quarterly, on the applicable reset date plus a spread as set forth in the table below.

The Series A, C, F, H and J First Preferred Shares are redeemable by Emera, in whole or in part under certain circumstances by the payment of cash on the dates set forth in the table below at a price of $25.00 per share plus any accrued and unpaid dividends.

The Series B, D, G, I and K First Preferred Shares are redeemable by Emera, in whole or in part under certain circumstances after their respective initial redemption dates by payment in cash as set forth in the table below at a price equal to (i) $25.00 per share together with all accrued and unpaid dividends up to but excluding the date fixed for redemption in the case of redemptions as set out in the table below or (ii) $25.50 per share together with all accrued and unpaid dividends up to but excluding the date fixed for redemption in the case of redemptions on any other date.

Subject to certain conditions including the right of Emera to redeem, holders of the Series A, C, F, H and J First Preferred Shares, have the right to convert any or all of their Series A, C, F, H and J First Preferred Shares into an equal number of Series B, D, G, I and K First Preferred Shares, respectively. In addition, the Series A, C, F, H and J First Preferred Shares may be automatically converted by Emera into Series B, D, G, I and K First Preferred Shares, respectively if Emera determines that, following conversion by the holders, there would be less than 1,000,000 Series A, C, F, H and J First Preferred Shares outstanding, respectively.

Subject to automatic conversion conditions including the right of Emera to redeem the Series B, D, G, I and K First Preferred Shares, the holders of Series B, D, G, I and K First Preferred Shares have the right to convert any or all of their Series B, D, G, I and K First Preferred Shares into an equal number of Series A, C, F, H and J First Preferred Shares respectively. In addition, Series B, D, G, I and K First Preferred Shares may be automatically converted by Emera into Series A, C, F, H and J First Preferred Shares, respectively if Emera determines that, following conversion by the holders, there would be less than 1,000,000 Series B, D, G, I and K First Preferred Shares outstanding.

 

Emera Incorporated – 2022 Annual Information Form    46


Holders of Series E First Preferred Shares will be entitled to receive fixed cumulative preferential cash dividends as and when declared by the Board in the amount of $1.125 per share per annum in perpetuity, subject to certain redemption rights. The Series E First Preferred Shares were not redeemable by the Company prior to August 18, 2018. The Series E First Preferred Shares are redeemable on or after August 18, 2018 by Emera in whole or in part, at the Company’s option without the consent of the holder, by the payment of: $26.00 per share if redeemed before August 15, 2019; $25.75 per share if redeemed on or after August 15, 2019 but before August 15, 2020; $25.50 per share if redeemed on or after August 15, 2020 but before August 15, 2021; $25.25 per share if redeemed on or after August 15, 2021 but before August 15, 2022; and $25.00 per share if redeemed on or after August 15, 2022; together, in each case, with all accrued and unpaid dividends up to but excluding the date fixed for redemption.

Holders of Series L First Preferred Shares will be entitled to receive fixed cumulative preferential cash dividends as and when declared by the Board in the amount of $1.150 per share per annum in perpetuity, subject to certain redemption rights. The Series L First Preferred Shares were not redeemable by the Company prior to November 15, 2026. The Series L First Preferred Shares are redeemable on or after November 15, 2026 by Emera in whole or in part, at the Company’s option without the consent of the holder, by the payment of: $26.00 per share if redeemed before November 15, 2027; $25.75 per share if redeemed on or after November 15, 2027 but before November 15, 2028; $25.50 per share if redeemed on or after November 15, 2028 but before November 15, 2029; $25.25 per share if redeemed on or after November 15, 2029 but before November 15, 2030; and $25.00 per share if redeemed on or after November 15, 2030; together, in each case, with all accrued and unpaid dividends up to but excluding the date fixed for redemption.

Applicable redemption, conversion, interest and reset dates and spreads are listed in the following table:

 

       
Series of First
Preferred Shares
   Initial Redemption /
Interest Reset Date
  

Subsequent Redemption / Conversion /

Interest Reset Dates

       Spreads    
       

Series A

   August 15, 2015    August 15, 2020 and every fifth year thereafter    1.84%
       

Series B

   August 15, 2020    August 15, 2025 and every fifth year thereafter    1.84%
       

Series C

   August 15, 2018    August 15, 2023 and every fifth year thereafter    2.65%
       

Series D

      August 15, 2023 and every fifth year thereafter    2.65%
       

Series E

   August 15, 2018      
       

Series F

   February 15, 2020    February 15, 2025 and every fifth year thereafter    2.63%
       

Series G

      February 15, 2025 and every fifth year thereafter    2.63%
       

Series H

   August 15, 2023    August 15, 2028 and every fifth year thereafter    2.54%
       

Series I

      August 15, 2028 and every fifth year thereafter    2.54%
       

Series J

   May 15, 2026    May 15, 2031 and every fifth year thereafter    3.28%
       

Series K

      May 15, 2031 and every fifth year thereafter    3.28%
       

Series L

   November 15, 2026      

Series 2016-A Conversion, First Preferred Shares

The Series 2016-A Conversion, First Preferred Shares were authorized pursuant to the Hybrid Notes offering in June 2016. As at December 31, 2022, there were no Series 2016-A Conversion, First Preferred Shares issued and outstanding.

Holders of Series 2016-A Conversion, First Preferred Shares are not entitled to attend any meetings of the shareholders of Emera or to vote at any such meeting, except: (i) where entitled by law; (ii) for meetings of the holders of first preferred shares as a class and holders of Series 2016-A Conversion, First Preferred Shares as a series; and (iii) in situations when Emera fails to pay, in the aggregate, eight quarterly dividends on the Series 2016-A Conversion, First Preferred Shares.

 

Emera Incorporated – 2022 Annual Information Form    47


In any instance where the holders of Series 2016-A Conversion, First Preferred Shares are entitled to vote, each holder shall have one vote for each Series 2016-A Conversion, First Preferred Share, subject to the restrictions described under “Share Ownership Restrictions” below.

Holders of each series of Series 2016-A Conversion, First Preferred Shares will be entitled to receive cumulative preferential cash dividends, if, as and when declared by the Board, at the same rate as would have accrued on the related series of Hybrid Notes (had such Hybrid Notes remained outstanding). The Series 2016-A Conversion, First Preferred Shares do not have a fixed maturity date.

The Series 2016-A Conversion, First Preferred Shares are redeemable by Emera on June 15, 2026. After that date, Emera may redeem at any time all, or from time to time any part, of the outstanding Series 2016-A Conversion, First Preferred Shares, without the consent of the holders, by the payment of an amount in cash for each such share so redeemed of USD$1,000 per share together with an amount equal to all accrued and unpaid dividends thereon.

 

Emera Incorporated – 2022 Annual Information Form    48


APPENDIX “C” - MONTHLY TRADING VOLUME AND HIGH AND LOW PRICE FOR EMERA’S SECURITIES IN 2022

 

    

  Common      

Shares      

 

Depositary Receipts

 

 

 

Series of First Preferred Shares

 

 

 Barbados  

 BBD (1)  

 

 

 

Bahamas  

 BSD (2)  

 

           A                     B                     C                     E                     F                     H                     J                     L         

December

High ($)

Low ($)

Volume

  54.71

51.14

19,587,632

  20.17

18.77

0

  10.09

9.39

0

  13.75

13.05

45,091

  16.00

14.60

17,212

  19.24

18.00

115,362

  17.75

16.75

90,125

  17.45

16.76

69,655

  21.20

19.62

247,927

  22.42

20.82

191,540

  18.00

16.99

173,128

November

High ($)

Low ($)

Volume

  52.87

48.80

39,025,989

  19.76

18.08

0

  9.50

9.50

5000

  13.77

13.20

30,682

  16.19

15.25

12,864

  19.19

17.87

137,332

  17.84

16.23

211,732

  17.70

16.72

156,761

  21.99

20.02

171,893

  23.17

20.70

81,698

  17.64

16.40

226,364

October

High ($)

Low ($)

Volume

  57.60

48.63

43,502,499

  21.22

17.65

0

  9.16

9.16

182

  14.60

13.21

32,029

  16.84

16.00

6,750

  19.32

18.02

109,413

  17.74

16.51

258,806

  18.25

17.16

121,392

  23.00

21.26

105,017

  23.78

22.61

59,088

  18.00

16.55

99,867

September

High ($)

Low ($)

Volume

  62.92

55.81

18,860,229

  24.24

20.36

0

  11.52

11.52

91

  15.01

13.69

64,662

  16.77

16.05

16,400

  20.65

17.75

159,037

  18.86

17.25

61,824

  19.90

17.50

92,499

  24.23

22.15

74,408

  25.05

23.15

132,314

  19.12

17.40

56,642

August

High ($)

Low ($)

Volume

  63.20

59.05

27,425,695

  24.33

22.83

0

  11.67

11.67

274

  15.60

14.17

16,091

  16.76

15.65

4,913

  21.27

19.65

152,090

  19.88

18.80

46,908

  20.41

18.63

47,430

  24.78

23.65

57,246

  25.48

24.61

53,042

  19.88

18.90

182,656

July

High ($)

Low ($)

Volume

  62.21

59.05

23,355,538

  23.86

22.90

0

  11.93

11.45

0

  15.00

13.51

4,569

  16.26

15.90

3,505

  21.56

18.67

59,348

  19.72

18.60

57,915

  19.80

17.99

34,075

  25.09

24.10

100,647

  25.59

24.80

49,494

  19.75

18.65

147,790

June

High ($)

Low ($)

Volume

  63.76

57.13

18,849,884

  25.34

21.98

0

  12.67

10.99

0

  17.00

15.22

9,784

  17.50

17.00

2,318

  23.50

20.52

95,397

  20.61

18.75

30,649

  22.92

19.56

48,315

  25.30

24.32

106,515

  25.97

25.03

68,631

  20.76

19.00

88,280

May

High ($)

Low ($)

Volume

  64.93

60.63

31,789,311

  25.29

23.66

0

  12.65

11.83

0

  16.48

15.71

4,632

  16.95

16.49

4,230

  23.40

21.54

93,901

  20.27

19.15

136,272

  22.98

21.05

72,372

  25.00

24.27

155,320

  25.96

25.00

57,205

  20.55

19.60

369,608

April

High ($)

Low ($)

Volume

  65.23

61.53

30,128,700

  26.09

24.59

0

  13.04

12.29

0

  16.97

15.46

11,622

  17.44

16.50

3,908

  23.50

21.00

321,752

  22.19

19.85

256,144

  22.96

20.87

237,026

  25.35

23.99

180,511

  25.65

24.90

168,498

  22.50

19.92

1,971,593

March

High ($)

Low ($)

Volume

  62.54

58.82

19,922,299

  24.48

23.14

0

  11.25

11.25

1000

  17.17

16.05

20,242

  17.60

17.31

4,432

  24.01

22.81

117,977

  23.90

22.28

40,237

  24.38

22.60

56,476

  25.60

24.75

102,465

  25.70

24.91

218,688

  24.44

22.51

107,549

February

High ($)

Low ($)

Volume

  60.51

57.87

22,888,998

  23.83

22.81

0

  11.92

11.40

0

  18.60

17.00

20,310

  18.10

18.02

7,716

  24.40

23.11

62,044

  24.33

23.00

45,298

  24.25

23.30

48,131

  25.83

24.83

52,126

  26.51

25.07

88,177

  24.80

23.95

64,611

January

High ($)

Low ($)

Volume

  63.49

58.57

25,752,083

  24.98

23.14

0

  12.49

11.57

0

  18.60

18.01

18,874

  19.68

18.00

22,004

  24.64

23.45

128,831

  25.04

23.85

54,888

  24.56

23.72

59,256

  26.60

25.51

80,033

  27.98

26.07

107,204

  25.54

24.40

393,203

 

(1)

The Barbados DRs trade on the BSE. During those months in 2022 when the Volume Traded was zero (0), the table above indicates the high and low trading prices of the Barbados DRs relative to those of Emera’s common shares on the TSX.

(2)

The Bahamas DRs trade on the BISX. During those months in 2022 when the Volume Traded was zero (0), the table above indicates the high and low trading prices of the Bahamas DRs relative to those of Emera’s common shares on the TSX.

 

Emera Incorporated – 2022 Annual Information Form    49


February 2023    LOGO

APPENDIX “D” - EMERA INCORPORATED AUDIT COMMITTEE CHARTER

 

 

 

PART I

MANDATE AND RESPONSIBILITIES

Committee Purpose

There shall be a committee of the Board of Directors (the “Board”) of Emera Inc. (“Emera”) which shall be known as the Audit Committee (the “Committee”). The Committee shall assist the Board in discharging its oversight responsibilities concerning:

 

-

the quality and integrity of Emera’s financial statements;

-

the effectiveness of Emera’s internal control systems over financial reporting;

-

the internal audit and assurance process;

-

the qualifications, independence and performance of the external auditors;

-

major financial risk exposures;

-

Emera’s compliance with legal requirements and securities regulations in respect of financial statements and financial reporting; and

-

any other duties set out in this Charter or delegated to the Committee by the Board.

 

1.

Financial Reporting

 

  (a)

The Committee shall be responsible for reviewing, assessing the completeness and clarity of the disclosures in, and recommending to the Board for approval:

 

  (i)

the audited annual financial statements of Emera, all related Management’s Discussion and Analysis, and earnings press releases;

 

  (ii)

any documents containing Emera’s audited financial statements; and,

 

  (iii)

the quarterly financial statements, all related Management’s Discussion and Analysis, and earnings press releases.

 

  (b)

The Board may delegate the approval of the quarterly financial statements, all related Management’s Discussion and Analysis, and earnings press releases to the Committee.

 

  (c)

The Committee shall oversee and assess that adequate procedures are in place for the review of public disclosure of financial information.

 

2.

External Auditors

 

  (a)

The Committee shall evaluate and recommend to the Board the external auditor to be nominated for the purpose of preparing or issuing the auditor’s report or performing other audit, review, or attest services for Emera, and the compensation of such external auditors.

 

  (b)

Once appointed, the external auditor shall report directly to the Committee, and the Committee shall oversee the work of the external auditor concerning the preparation or

 

Emera Incorporated – 2020 Annual Information Form    50


 

issuance of the auditor’s report or the performance of other audit, review or attest services for Emera.

 

  (c)

The Committee shall be responsible for resolving disagreements between management and the external auditor concerning financial reporting.

 

  (d)

At least annually, the Committee shall obtain and review a report by the external auditors describing: (i) the firm’s internal quality control procedures; (ii) any material issues raised by the most recent internal quality control review, or peer review, of the firm, or by any inquiry or investigation by governmental or professional authorities, within the preceding five years, with respect to one or more external audits carried out by the firm, and any steps taken to deal with any such issues; and (iii) all relationships between the external auditors and Emera (to assess the auditors’ independence).

 

  (e)

The Committee shall annually evaluate the auditors’, including the lead audit partner’s, qualifications, performance, professional skepticism and independence.

 

  (f)

The Committee shall determine that the external audit firm has a process in place to address the rotation of the lead audit partner and other audit partners serving the account as required under prescribed independence rules.

 

  (g)

Every five (5) years, the Committee shall perform a comprehensive review of the performance of the external auditors over multiple years to provide further insight on the audit firm, its independence and application of professional standards.

 

  (h)

The Committee will review differences that were noted or proposed by the external auditors, but that were considered immaterial or insignificant; and any “management” or “internal control” letter issued, or proposed to be issued.

 

3.

Non-Audit Services

 

  (a)

The Committee shall be responsible for reviewing and pre-approving all non-audit services to be provided to Emera, or any of its subsidiaries, by the external auditor.

 

  (b)

The Committee may establish specific policies and procedures concerning the performance of non-audit services by the external auditor so long as the requirements of applicable legislation and regulation are satisfied.

 

  (c)

In accordance with policies and procedures established by the Committee, and applicable legislation and regulation, the Committee may delegate the pre-approval of non-audit services to a member of the Committee or a sub-committee thereof.

 

4.

Oversight and Monitoring of Audits

 

  (a)

The Committee shall meet with the external auditor prior to the audit to discuss the planning and staffing of the audit, including the general approach, scope, areas subject to significant risk of material misstatement, estimated fees and other terms of engagement.

 

Emera Incorporated – 2022 Annual Information Form    51


  (b)

The Committee shall discuss with the external auditor any issues that arise with Management or the internal auditors during the course of the audit and the adequacy of Management’s responses in addressing audit-related deficiencies.

 

  (c)

The Committee shall regularly review with the external auditors any audit problems or difficulties encountered during the course of the audit work, including any restrictions on the scope of the external auditors’ activities or access to requested information, and Management’s response.

 

  (d)

The Committee shall review with Management the results of internal and external audits.

 

  (e)

The Committee shall take such other reasonable steps as it may deem necessary to oversee that the audit was conducted in a manner consistent with applicable legal requirements and auditing standards of applicable professional or regulatory bodies.

 

5.

Oversight and Review of Accounting Principles and Practices

The Committee shall oversee, review and discuss with Management, the external auditor and the internal auditors:

 

  (a)

the quality, appropriateness and acceptability of Emera’s accounting principles and practices used in its financial reporting, changes in Emera’s accounting principles or practices and the application of particular accounting principles and disclosure practices by Management to new transactions or events;

 

  (b)

all significant financial reporting issues and judgments made in connection with the preparation of the financial statements, including the effects of alternative methods within generally accepted accounting principles on the financial statements and any “other opinions” sought by Management from an independent auditor, other than the Company’s external auditors, with respect to the accounting treatment of a particular item, and other material written communications between the external auditors and management;

 

  (c)

disagreements between Management and the external auditor or the internal auditors regarding the application of any accounting principles or practices;

 

  (d)

any material change to Emera’s auditing and accounting principles and practices as recommended by Management, the external auditor or the internal auditors or which may result from proposed changes to applicable generally accepted accounting principles;

 

  (e)

the effect of regulatory and accounting initiatives on Emera’s financial statements and other financial disclosures;

 

  (f)

any reserves, accruals, provisions, estimates or Management programs and policies, including factors that affect asset and liability carrying values and the timing of revenue and expense recognition, that may have a material effect upon the financial statements of Emera;

 

  (g)

the use of special purpose entities and the business purpose and economic effect of off-balance sheet transactions, arrangements, obligations, guarantees and other relationships of Emera and their impact on the reported financial results of Emera;

 

Emera Incorporated – 2022 Annual Information Form    52


  (h)

any legal matter, claim or contingency that could have a significant impact on the financial statements, Emera’s compliance policies and any material reports, inquiries or other correspondence received from regulators or governmental agencies and the manner in which any such legal matter, claim or contingency has been disclosed in Emera’s financial statements;

 

  (i)

the treatment for financial reporting purposes of any significant transactions which are not a normal part of Emera’s operations.

 

6.

Hiring Policies

The Committee shall review and approve Emera’s hiring policy concerning partners or employees, as well as former partners and employees, of the present or former external auditors of Emera.

 

7.

Pension Plans

The Committee shall exercise oversight of the pension plans in accordance with the Pension Oversight Framework adopted by Emera.

 

8.

Oversight of Finance Matters

 

  (a)

The Committee shall review the appointments of key financial executives involved in the financial reporting process of Emera, including the Chief Financial Officer.

 

  (b)

The Committee may request for review, and shall receive when requested, material tax policies and tax planning initiatives, tax payments and reporting and any pending tax audits or assessments. The Committee shall review Emera’s compliance with tax and financial reporting laws and regulations.

 

  (c)

The Committee shall meet at least annually with Management to review and discuss Emera’s major financial risk exposures and the policy steps Management has taken to monitor and control such exposures, including the use of financial derivatives, hedging activities, and credit and trading risks.

 

  (d)

The Committee may review any investments or transactions that the Committee wishes to review, or which the internal or external auditor, or any officer of Emera, may bring to the attention of the Committee within the context of this charter.

 

  (e)

The Committee shall review financial information of material subsidiaries of Emera and any auditor recommendations concerning such subsidiaries.

 

  (f)

The Committee may request for review, and shall receive when requested, all related party transactions required to be disclosed pursuant to generally accepted accounting principles, and discuss with Management the business rationale for the transactions and whether appropriate disclosures have been made.

 

Emera Incorporated – 2022 Annual Information Form    53


9.

Internal Controls

The Committee shall oversee:

 

  (a)

the adequacy and effectiveness of the Company’s internal accounting and financial controls and the recommendations of Management, the external auditor and the internal auditors for the improvement of accounting practices and internal controls; and

 

  (b)

management’s compliance with the Company’s processes, procedures and internal controls.

In exercising such oversight, the Committee shall review and discuss each of the foregoing with Management, the external auditor and the internal auditor.

The Committee will carry out the following specific duties:

 

  (c)

Review and discuss with the Chief Executive Officer and the Chief Financial Officer the procedures undertaken in connection with the Chief Executive Officer and Chief Financial Officer certifications for the annual and interim filings with applicable securities regulatory authorities.

 

  (d)

Review disclosures made by Emera’s Chief Executive Officer and Chief Financial Officer during their certification process for the annual and interim filing with applicable securities regulatory authorities about any significant deficiencies in the design or operation of internal controls which could adversely affect Emera’s ability to record, process, summarize and report financial data or any material weaknesses in the internal controls, and any fraud involving management or other employees who have a significant role in the Emera’s internal controls.

 

  (e)

Discuss with Emera’s Chief Legal Officer at least annually any legal matters that may have a material impact on the financial statements, operations, assets or compliance policies and any material reports or inquiries received by Emera or any of its subsidiaries from regulators or governmental agencies.

 

10.

Internal Auditor

 

  (a)

The lead internal auditor shall report directly to the Committee. The Committee shall approve the appointment, removal and replacement of the lead internal auditor. The Committee shall approve the remuneration of the lead internal auditor on appointment.

 

  (b)

The Committee shall review and approve the internal audit plan, including activities, organizational structure, staffing, qualifications and budget, and shall review all major changes to the plan. The Committee shall review and discuss with the internal auditor the scope, progress, and results of executing the internal audit plan. The Committee shall receive reports on the status of significant findings, recommendations, and management’s responses.

 

  (c)

The Committee shall meet periodically with the internal auditor to discuss the progress of their activities, any significant findings stemming from internal audits, any issues that arise with Management, and the adequacy of Management’s responses in addressing audit-related deficiencies.

 

Emera Incorporated – 2022 Annual Information Form    54


  (d)

The Committee shall obtain from the internal auditor and review summaries of the significant reports to Management prepared by the internal auditor, and the actual reports if requested by the Committee, and Management’s responses to such reports.

 

  (e)

The Committee shall annually receive and review a report on the Chief Executive Officers’ expense accounts.

 

  (f)

The Committee may communicate with the internal auditor with respect to their reports and recommendations, the extent to which prior recommendations have been implemented and any other matters that the internal auditor brings to the attention of the Committee.

 

  (g)

The Committee shall, at least biennially or more frequently as it deems necessary, approve the internal audit charter. The internal auditor shall confirm to the Committee annually that the function adheres to applicable professional standards. The Committee may provide feedback on the performance of the lead internal auditor as deemed necessary.

 

  (h)

The Committee shall, biennially or more frequently as it deems necessary, review the independence of the internal audit function and shall make recommendations to the Board on appropriate actions to be taken which the Committee deems necessary to protect and enhance the independence of the internal audit function.

 

  (i)

The Committee shall review the results of an external assessment, performed every five years by a qualified independent assessor or assessment team, of the internal audit function in conformance with International Standards for the Professional Practice of Internal Auditing (IPPF Standards).

 

11.

Complaints

The Committee shall oversee procedures relating to the receipt, retention, and treatment of complaints received concerning accounting, internal accounting controls, or auditing matters. The Committee shall also review procedures concerning the confidential, anonymous submission of concerns by Emera’s employees relating to questionable accounting or auditing matters. Without limiting the foregoing, the Committee shall receive periodic ethics updates under Emera’s Code of Conduct which relate to matters within the scope of responsibility of the Committee as defined in this Charter, and the Committee shall review the related activities within that scope under Emera’s Ethics Program, such as financial reporting, accounting and auditing, business integrity, and corporate assets and infrastructure.

 

12.

Other Responsibilities

The Committee shall:

 

  (a)

Periodically review Management’s process for identifying non-compliance with legal and regulatory requirements;

 

  (b)

Annually receive and review a report on executive officers’ compliance with the Company’s Code of Conduct;

 

  (c)

Annually provide feedback on the performance of the Chief Financial Officer;

 

Emera Incorporated – 2022 Annual Information Form    55


  (d)

Review actions taken by the Company to identify and manage risks related to the Audit Committee mandate, including Primary Enterprise Risks, which may have the potential to adversely impact the Company’s operations, strategy or reputation; and

 

  (e)

Perform such other duties and exercise such powers as may be directed or delegated to the Committee by the Board.

 

13.

Limitation on Authority

Nothing articulated herein is intended to assign to the Committee the Board’s responsibility to oversee Emera’s compliance with applicable laws or regulations or to expand applicable standards of liability under statutory or regulatory requirements for the Directors or the members of the Committee.

PART II

COMPOSITION

 

14.

Composition

 

  (a)

Emera’s Articles of Association require that the Committee shall be comprised of no less than three directors none of whom may be officers or employees of Emera nor may they be an officer or employee of any affiliate of Emera. In addition, all members of the Committee shall be independent as required by applicable legislation.

 

  (b)

The Board shall appoint members to the Committee who are financially literate, as required by applicable legislation, which at a minimum requires that Committee members have the ability to read and understand a set of financial statements that present a breadth and level of complexity of accounting issues that are generally comparable to the breadth and complexity of issues that can reasonably be expected to be raised by Emera’s financial statements.

 

  (c)

Committee members shall be appointed at the Board meeting following the election of Directors at Emera’s annual shareholders’ meeting and membership may be based upon the recommendation of the Nominating and Corporate Governance Committee.

 

  (d)

Pursuant to Emera’s Articles of Association, the Board may appoint, remove, or replace any member of the Committee at any time, and a member of the Committee shall cease to be a member of the Committee upon ceasing to be a Director. Subject to the foregoing, each member of the Committee shall hold office as such until the next annual meeting of shareholders after the member’s appointment to the Committee.

 

  (e)

The Secretary of the Committee shall advise Emera’s internal and external auditors of the names of the members of the Committee promptly following their election.

 

Emera Incorporated – 2022 Annual Information Form    56


PART III

COMMITTEE PROCEDURE

 

15.

Meetings

 

  (a)

Meetings of the Committee may be called by the Chair or at the request of any member. The Committee shall meet at least quarterly.

 

  (b)

The timing and location of meetings of the Committee, and the calling of and procedure at any such meeting, shall be determined from time to time by the Committee.

 

  (c)

Emera’s internal and external auditors shall be notified of all meetings of the Committee and shall have the right to appear before and be heard by the Committee.

 

  (d)

Emera’s internal or external auditors may request the Chair of the Committee to consider any matters which the internal or external auditors believe should be brought to the attention of the Committee or the Board.

 

16.

Separate Sessions

 

  (a)

The Committee Chair shall meet periodically with the Chief Financial Officer, the lead internal auditor and the external auditor in separate executive sessions to discuss any matters that the Committee or each of these groups believes should be discussed privately.

 

  (b)

The Chief Financial Officer, the lead internal auditor and the external auditor shall have access to the Committee to bring forward matters requiring its attention.

 

  (c)

The Committee shall meet periodically without Management present.

 

17.

Quorum

A majority of the members of the Committee present in person, by teleconferencing, or by videoconferencing, or by a combination thereof, will constitute a quorum.

 

18.

Chair

Pursuant to Emera’s Articles of Association, the Committee shall choose one of its members to act as Chair of the Committee, which person shall not be the Chair of Nova Scotia Power Inc.’s Audit Committee. In selecting a Committee Chair, the Committee may consider any recommendation made by the Nominating and Corporate Governance Committee.

 

19.

Secretary and Minutes

Pursuant to Emera’s Articles of Association, the Corporate Secretary of Emera shall act as the Secretary of the Committee. Emera’s Articles of Association require that the Minutes of the Committee be in writing and duly entered into Emera’s records, and the Minutes shall be circulated to all members of the Committee. The Secretary shall maintain all Committee records.

 

Emera Incorporated – 2022 Annual Information Form    57


20.

Board Relationships and Reporting

The Committee shall:

 

  (a)

Review annually the Committee’s Charter;

 

  (b)

Oversee the appropriate disclosure of the Committee’s Charter as well as other information concerning the Committee which is required to be disclosed by applicable legislation in Emera’s Annual Information Form and any other applicable disclosure documents;

 

  (c)

Report to the Board at the next following board meeting on any meeting held by the Committee, and as required, regularly report to the Board on Committee activities, issues, and related recommendations; and

 

  (d)

Maintain free and open communication between the Committee, the external auditors, internal auditors, and Management, and determine that all parties are aware of their responsibilities.

 

21.

Powers

The Committee shall:

 

  (a)

examine and consider such other matters, and meet with such persons, in connection with the internal or external audit of Emera’s accounts, which the Committee in its discretion determines to be advisable;

 

  (b)

have the authority to communicate directly with the internal and external auditors; and

 

  (c)

have the right to inspect all records of Emera or its affiliates and may elect to discuss such records, or any matters relating to the financial affairs of Emera with the officers or auditors of Emera and its affiliates.

 

22.

Experts and Advisors

The Committee may, in consultation with the Chairman of the Board, engage and compensate any outside adviser that it determines necessary in order to carry out its duties.

 

Emera Incorporated – 2022 Annual Information Form    58