13.   Contingencies and Commitments

        The company and certain of its subsidiaries are involved in various litigation matters. Additionally, the company and certain of its subsidiaries are contingently liable for commitments and performance guarantees arising in the ordinary course of business. The company and certain of its clients have made claims arising from the performance under its contracts. The company recognizes revenue, but not profit, for certain significant claims when it is determined that recovery of incurred costs is probable and the amounts can be reliably estimated. Under ASC 605-35-25, these requirements are satisfied when (a) the contract or other evidence provides a legal basis for the claim, (b) additional costs were caused by circumstances that were unforeseen at the contract date and not the result of deficiencies in the company's performance, (c) claim-related costs are identifiable and considered reasonable in view of the work performed, and (d) evidence supporting the claim is objective and verifiable. Recognized claims against clients amounted to $20 million and $298 million as of December 31, 2012 and 2011, respectively, and are included in contract work in progress in the accompanying Condensed Consolidated Balance Sheet. Claim revenue of $278 million for the Greater Gabbard Project was reversed in the fourth quarter of 2012 when the company no longer believed the recovery of its incurred cost was probable, as result of the unexpected adverse arbitration ruling discussed below. The company periodically evaluates its position and the amounts recognized in revenue with respect to all its claims. Amounts ultimately realized from claims could differ materially from the balances included in the financial statements. The company does not expect that the ultimate resolution of the remaining outstanding matters will have a material adverse effect on its consolidated financial position or results of operations.

        As of December 31, 2012, several matters were in the litigation and dispute resolution process. The following discussion provides a background and current status of these matters:

Greater Gabbard Offshore Wind Farm Project

        The company is involved in a dispute in connection with the Greater Gabbard Project, a $1.8 billion lump-sum project to provide engineering, procurement and construction services for the client's offshore wind farm project in the United Kingdom. The primary dispute related to the company's claim for additional compensation for schedule and cost impacts arising from delays in the fabrication of monopiles and transition pieces, along with certain disruption and productivity issues associated with construction activities and weather-related delays that the company anticipated would be recovered in arbitration due to the company's belief the schedule and cost impacts were attributable to the client and other third parties. On November 16, 2012, the company received an unexpected decision from the arbitration panel, dismissing the company's claims for additional compensation. The decision resulted in a pre-tax charge of $416 million against the company's earnings in the fourth quarter, which included claim revenue previously recorded and the remaining liquidated damages withheld by the client and not previously charged against the company's earnings, as well as additional costs expected to be incurred through close-out of the project.

        The client has filed a counterclaim against the company seeking to recover approximately $100 million for past and future costs associated with, among other things, monitoring certain monopiles and transition pieces for alleged defects. The counterclaim is currently scheduled for hearing in April 2013. While the ultimate outcome of the hearing is uncertain,  the company believes that the monopiles and transition pieces meet applicable performance requirements and therefore does not believe that a loss associated with the counterclaim is probable. As a result, the company has not recorded a charge under ASC 450. To the extent the client's counterclaim is successful, there could be a substantial charge to earnings.

St. Joe Minerals Matters

        Since 1995, the company has been named as a defendant in a number of lawsuits alleging injuries resulting from the lead business of St. Joe Minerals Corporation ("St. Joe") and The Doe Run Company ("Doe Run") in Herculaneum, Missouri, which are discontinued operations. The company was named as a defendant in these lawsuits as a result of its ownership or other interests in St. Joe and Doe Run in the period between 1981 and 1994. In 1994, the company sold its interests in St. Joe and Doe Run, along with all liabilities associated with the lead business, pursuant to a sale agreement in which the buyer agreed to indemnify the company for those liabilities. Until December 2010, substantially all the lawsuits were settled and paid by the buyer; and in all cases the company was fully released.

        In December 2010, the buyer settled with certain plaintiffs without obtaining a release for the benefit of the company, leaving the company to defend its case with these plaintiffs in the City of St. Louis Circuit Court. In late July 2011, the jury reached an unexpected verdict in this case, ruling in favor of 16 of the plaintiffs and against the company and certain former subsidiaries for $38.5 million in compensatory and economic damages and $320 million in punitive damages. In August 2011, the court entered judgments based on the verdict.

        In December 2011, the company appealed the judgments of the court. The company strongly believes that the judgments are not supported by the facts or the law and that it is probable that such judgments will be overturned. Therefore, based upon the present status of this matter, the company does not believe it is probable that a loss will be incurred. Accordingly, the company has not recorded a charge as a result of the judgments. The company has also taken steps to enforce its rights to the indemnification described above.

        The company, the buyer and other entities are defendants in 22 additional lawsuits relating to the lead business of St. Joe and Doe Run. The company believes it has strong defenses to these lawsuits and is vigorously defending its position. In addition, the company has filed claims for indemnification under the sale agreement for other matters raised in these lawsuits. While we believe we will be ultimately successful in these various matters, if we were unsuccessful in our appeal of the ruling referenced above or in any of the other lawsuits, or in the prosecution of and collection on our indemnity claims, we could recognize a substantial charge to our earnings.

Embassy Projects

        The company constructed 11 embassy projects for the U.S. Department of State under fixed-price contracts. Some of these projects were adversely impacted by higher costs due to schedule extensions, scope changes causing material deviations from the Standard Embassy Design, increased costs to meet client requirements for additional security-cleared labor, site conditions at certain locations, subcontractor and teaming partner difficulties and the availability and productivity of construction labor. All embassy projects were completed prior to 2011.

        The company had previously recognized claim revenue of $33 million for outstanding claims on two embassy projects. During the first quarter of 2012, the company received an adverse judgment from the Board of Contract Appeals associated with a claim on one embassy project and, as a result, recorded a charge of $13 million. The company believes that the decision was incorrect and has filed an appeal with the Federal Circuit. Total claims-related costs incurred to date for the last remaining claim, along with requests for equitable adjustment, exceed the amount recorded in claim revenue. All claims have been certified in accordance with federal contracting requirements. A hearing on the final embassy claim was held during the second quarter of 2012 and final written submissions were completed in the fourth quarter of 2012. The results of this hearing are expected during 2013.

Conex International v. Fluor Enterprises, Inc.

        In November 2006, a Jefferson County, Texas, jury reached an unexpected verdict in the case of Conex International ("Conex") v. Fluor Enterprises Inc. ("FEI"), ruling in favor of Conex and awarding $99 million in damages related to a 2001 construction project.

        In 2001, Atofina (now part of Total Petrochemicals Inc.) hired Conex International to be the mechanical contractor on a project at Atofina's refinery in Port Arthur, Texas. FEI was also hired to provide certain engineering advice to Atofina on the project. There was no contract between Conex and FEI. Later in 2001 after the project was complete, Conex and Atofina negotiated a final settlement for extra work on the project. Conex sued FEI in September 2003, alleging damages for interference and misrepresentation and demanding that FEI should pay Conex the balance of the extra work charges that Atofina did not pay in the settlement. Conex also asserted that FEI interfered with Conex's contract and business relationship with Atofina. The jury verdict awarded damages for the extra work and the alleged interference.

        The company appealed the decision and the judgment against the company was reversed in its entirety in December 2008. Both parties appealed the decision to the Texas Supreme Court, and the court denied both petitions. The company requested rehearing on two issues to the Texas Supreme Court, and that request was denied. The Texas Supreme Court remanded the matter back to the trial court for a new trial. The matter was stayed, pending resolution of certain technical issues associated with the 2011 bankruptcy filing by the plaintiff's parent. These issues have been resolved. The matter has been remanded to the court in Jefferson County, Texas. Based upon the present status of this matter, the company does not believe that there is a reasonable possibility that a loss will be incurred.

  • Guarantees

        In the ordinary course of business, the company enters into various agreements providing performance assurances and guarantees to clients on behalf of certain unconsolidated and consolidated partnerships, joint ventures and other jointly executed contracts. These agreements are entered into primarily to support the project execution commitments of these entities. The performance guarantees have various expiration dates ranging from mechanical completion of the facilities being constructed to a period extending beyond contract completion in certain circumstances. The maximum potential payment amount of an outstanding performance guarantee is the remaining cost of work to be performed by or on behalf of third parties under engineering and construction contracts. Amounts that may be required to be paid in excess of estimated cost to complete contracts in progress are not estimable. For cost reimbursable contracts, amounts that may become payable pursuant to guarantee provisions are normally recoverable from the client for work performed under the contract. For lump-sum or fixed-price contracts, the performance guarantee amount is the cost to complete the contracted work, less amounts remaining to be billed to the client under the contract. Remaining billable amounts could be greater or less than the cost to complete. In those cases where costs exceed the remaining amounts payable under the contract, the company may have recourse to third parties, such as owners, co-venturers, subcontractors or vendors for claims. Performance guarantees outstanding as of December 31, 2012 were estimated to be $3.8 billion. The company assessed its performance guarantee obligation as of December 31, 2012 and 2011 in accordance with ASC 460, "Guarantees" and the carrying value of its liability was not material.

        Financial guarantees, made in the ordinary course of business in certain limited circumstances, are entered into with financial institutions and other credit grantors and generally obligate the company to make payment in the event of a default by the borrower. These arrangements generally require the borrower to pledge collateral to support the fulfillment of the borrower's obligation.

Other Matters

        The company's operations are subject to and affected by federal, state and local laws and regulations regarding the protection of the environment. The company maintains reserves for potential future environmental cost where such obligations are either known or considered probable, and can be reasonably estimated.

        The company believes, based upon present information available to it, that its reserves with respect to future environmental cost are adequate and such future cost will not have a material effect on the company's consolidated financial position, results of operations or liquidity. However, the imposition of more stringent requirements under environmental laws or regulations, new developments or changes regarding site cleanup cost or the allocation of such cost among potentially responsible parties, or a determination that the company is potentially responsible for the release of hazardous substances at sites other than those currently identified, could result in additional expenditures, or the provision of additional reserves in expectation of such expenditures.