Commitments and Contingencies (Details Textual)
1 Months Ended 6 Months Ended 12 Months Ended
Oct. 16, 2018
USD ($)
Oct. 16, 2018
CNY (¥)
Jul. 07, 2016
USD ($)
Jul. 07, 2016
CNY (¥)
Dec. 31, 2018
CNY (¥)
Dec. 31, 2017
USD ($)
Dec. 31, 2017
CNY (¥)
Dec. 19, 2017
USD ($)
Dec. 19, 2017
CNY (¥)
Jun. 30, 2017
USD ($)
Jun. 30, 2017
CNY (¥)
May 31, 2017
USD ($)
May 31, 2017
CNY (¥)
Jun. 30, 2018
USD ($)
Jun. 30, 2018
CNY (¥)
Dec. 31, 2017
USD ($)
Jun. 30, 2019
USD ($)
Jun. 30, 2019
CNY (¥)
May 20, 2019
USD ($)
May 20, 2019
CNY (¥)
Dec. 31, 2018
USD ($)
Nov. 08, 2018
USD ($)
Nov. 08, 2018
CNY (¥)
Sep. 07, 2016
USD ($)
Commitments and contingencies                                            
Construction cost                                 1,593,728              
Interest [Member]                                                
Contract amount                       $ 124,074                        
RMB [Member]                                                
Construction cost | ¥                                   ¥ 10,962,140            
RMB [Member] | Interest [Member]                                                
Contract amount | ¥                         ¥ 851,858                      
Anyuan Bus [Member]                                                
Contract amount                           $ 2,538,416   $ 2,633,185                
Anyuan Bus [Member] | Goods Amount [Member]                                                
Contract amount                       $ 2,538,416                        
Litigation fees               $ 19,150                                
Anyuan Bus [Member] | RMB [Member]                                                
Contract amount | ¥         ¥ 17,428,000                                      
Power sought a total amount | ¥                         18,279,858                      
Anyuan Bus [Member] | RMB [Member] | Goods Amount [Member]                                                
Contract amount | ¥                 ¥ 17,428,000       ¥ 17,428,000                      
Litigation fees | ¥                 ¥ 131,480                              
Shenzhen Huijie [Member]                                                
Plaintiff sought a total amount     $ 1,227,964                                          
Shenzhen Huijie [Member] | Interest [Member]                                                
Plaintiff sought a total amount     30,934                                          
Shenzhen Huijie [Member] | Compensation [Member]                                                
Plaintiff sought a total amount     300,000                                          
Shenzhen Huijie [Member] | Remaining Contract Amount [Member]                                                
Contract amount                   $ 900,000                            
Shenzhen Huijie [Member] | Other Expense [Member]                                                
Contract amount                           $ 100,000                    
Shenzhen Huijie [Member] | Construction costs [Member]                                                
Plaintiff sought a total amount     900,000                                          
Shenzhen Huijie [Member] | RMB [Member]                                                
Plaintiff sought a total amount | ¥       ¥ 8,430,792                                        
Shenzhen Huijie [Member] | RMB [Member] | Interest [Member]                                                
Plaintiff sought a total amount | ¥       200,000                                        
Shenzhen Huijie [Member] | RMB [Member] | Compensation [Member]                                                
Plaintiff sought a total amount | ¥       ¥ 100,000                                        
Shenzhen Huijie [Member] | RMB [Member] | Remaining Contract Amount [Member]                                                
Contract amount | ¥                     ¥ 6,135,860                          
Shenzhen Huijie [Member]                                                
Plaintiff sought a total amount           $ 35,676                                    
Shenzhen Huijie [Member] | Interest [Member]                                                
Plaintiff sought a total amount           904                                    
Shenzhen Huijie [Member] | Construction costs [Member]                                                
Plaintiff sought a total amount           $ 34,772                                    
Shenzhen Huijie [Member] | RMB [Member]                                                
Plaintiff sought a total amount | ¥             ¥ 244,942                                  
Shenzhen Huijie [Member] | RMB [Member] | Interest [Member]                                                
Plaintiff sought a total amount | ¥                             ¥ 6,207                  
Shenzhen Huijie [Member] | RMB [Member] | Construction costs [Member]                                                
Plaintiff sought a total amount | ¥                             ¥ 238,735                  
Shenzhen Huijie [Member]                                                
Plaintiff sought a total amount     $ 1,227,964                                          
Bank deposits frozen                                               $ 1,227,964
Litigation fees $ 11,221                                              
Construction cost                                 $ 900,000   $ 258,435     $ 1,329,780    
Shenzhen Huijie [Member] | RMB [Member]                                                
Litigation fees | ¥   ¥ 77,042                                            
Construction cost | ¥                                   ¥ 6,100,000   ¥ 1,774,337     ¥ 129,868