Exelon Generation Nuclear Uprate Projects
June 12, 2009
Exhibit 99.2


2
This presentation includes forward-looking statements.  There are a number of risks and uncertainties that
could cause actual results to differ materially from the forward-looking statements made herein.  The
factors that could cause actual results to differ materially from these forward-looking statements include
Exelon’s ability to achieve the full additional capacity contemplated by the proposed uprates, the
availability of required components and raw materials, and the timing to complete the proposed uprates
and obtain required regulatory approvals as well as those discussed in (1) Exelon’s 2008 Annual Report
on Form 10-K in (a) ITEM 1A. Risk Factors, (b) ITEM 7. Management’s Discussion and Analysis of
Financial Condition and Results of Operation and (c) ITEM 8.  Financial Statements and Supplementary
Data: Note 18;  (2) Exelon’s First Quarter 2009 Quarterly Report on Form 10-Q in (a) Part II, Other
Information, ITEM 1A. Risk Factors and (b) Part I, Financial Information, ITEM 1. Financial Statements:
Note 13; and (3) other factors discussed in filings with the Securities and Exchange Commission by
Exelon Corporation or Exelon Generation Company LLC (Companies).
Readers are cautioned not to
place undue reliance on these forward-looking statements, which apply only as of the date of this
communication.  Neither of the Companies undertakes any obligation to publicly release any revision to its
forward-looking statements to reflect events or circumstances after the date of this communication, except
as required by law.
Forward-Looking Statements


3
A successful 38-megawatt power uprate at Quad Cities in June 2009 launched a series
of planned power uprates across Exelon’s nuclear fleet
Uprates equivalent in size of a new nuclear plant but significantly lower cost and shorter
timeline
1,300 –
1,500 MW
$3.5
billion
($2,200
2,500
/
kW)
1
through
2017
Positive
economics,
coming
on-line
between
2009
2017
Capitalizes on Exelon’s proven track record of executing uprates
Contributes to long-term asset management and equipment reliability
Cost-effective growth option
Key component of Exelon 2020 low carbon roadmap
Uprate projects on existing assets provide cost-effective growth and leverage
Exelon’s operational excellence
Exelon Generation Nuclear
Uprate Projects
1
Dollars shown are overnight cost, cost per kW are for MUR and EPU combined


MUR (Measurement Uncertainty Recapture)
Through the use of advanced techniques and more precise
instrumentation, reactor power can be more accurately calculated.
These uprates achieve up to 1.7 percent additional output. MUR
uprates require NRC approval.
Categories of Nuclear Power Uprates
Uprates
Overnight
Cost
187 –
234 MW
$300M
899 –
1016 MW
$2,400M
237 –
266 MW
$800M
EPU (Extended Power Uprate)
Through a combination of more sophisticated analysis and upgrades to
plant equipment, uprates can be obtained for as much as 20 percent of
original licensed power level. EPU uprates require NRC approval.
MW Recovery and Component Upgrades
Replacement
of
major
components
in
the
plant
occur
in
the
normal
life
cycle process –
with
newer technology, replacements result in increased
efficiency. Equipment includes generators, turbines, motors and
transformers. MW Recovery and Component Upgrades must conform to
NRC standards, but do not require additional NRC approval.
4
Project
Duration Time
2 years
3 -
5 years
2 -
3 years
~1,300 –
1,500 MW
$3.5B


Exelon conducts a rigorous engineering and economic
evaluation analysis for each project at each site
Parameters
Strategic
Value
Grow
Value
Regulatory
Feasibility
Execution
Feasibility
Supports Exelon 2020
Creates additional low-carbon generation capacity
Creates long-term value
Straightforward regulatory and environmental licenses,
permits and approvals
Dedicated project management team
Proven technology design
Evaluation Parameters
5


Exelon has substantial experience managing successful uprate projects
1,100 MWs of increased nuclear capacity over the past 10 years
Incremental 1,300 –
1,500 MWs of nuclear uprates are safe, economical and
proven methods to improve efficiency and output
Track Record of Execution
Staggered execution provides for continued re-evaluation of project economics
6
EPUs
MURs
MW Recovery and
Component Upgrades
Maximum Potential MWs
Year Uprates Become Operational
1,100 MW
1,300 –
1,500 MW


Uprate Execution Plan
Total Uprate
Projects 
2008
-
2009
2010
2011
2012
2013
2014
2015
2016
2017
2008
-
2017
$225
$350
$550
$675
$625
$725
$725
$400
$150
$4,425
Experienced project management organization in place
Engineering evaluation incorporates industry and Exelon
lessons learned
Project plan execution
Logically sequenced
Phased to leverage experience, ensure best use of
resources
Project offramps
in place as needed to defer or cancel
7
Exelon has an executable, strategically sequenced, project implementation plan
1
Dollars shown are nominal, reflecting 6% escalation, in millions
1


Locations of Nuclear Power
Uprate Projects
8
Nuclear uprates span across nine plants
Exelon’s $2,200 –
2,500 / kW overnight cost for its MUR and EPU projects
is better value than the cost for a nuclear new build that has been
estimated as high as $4,500 / kW (2007 dollars)
Base
Maximum
Case
Potential
MW
MW
Braidwood -
MUR
34
-
42
2012
Byron -
MUR
34
-
42
2012
Clinton -
EPU
17
-
17
2016
Clinton -
EPU
2
-
3
2010
Dresden -
MW Recovery & Component Upgrades
103
-
110
2012
Dresden -
MW Recovery & Component Upgrades
5
-
5
2011
Dresden -
MUR
25
-
31
2014
LaSalle -
MUR
32
-
40
2011
LaSalle -
EPU
303
-
336
2016
Limerick -
MUR
33
-
41
2011
Limerick -
MW Recovery & Component Upgrades
6
-
6
2012
Limerick -
EPU
306
-
340
2017
Peach Bottom -
MW Recovery & Component Upgrades
25
-
32
2012
Peach Bottom -
EPU
134
-
148
2015
Peach Bottom -
MW Recovery & Component Upgrades
3
-
3
2014
Quad Cities -
MUR
19
-
23
2013
Quad Cities -
MW Recovery & Component Upgrades
95
-
110
2011
TMI -
EPU
138
-
172
2016
TMI -
MUR
12
-
15
2014
Total
1,323
-
1,516
Year of Operation