XML 490 R8.htm IDEA: XBRL DOCUMENT v3.22.0.1
Mergers, Acquisitions and Dispositions (Exelon)
12 Months Ended
Dec. 31, 2021
Mergers, Acquisitions, and Dispositions [Abstract]  
Mergers, Acquisitions, and Dispositions (Exelon) Mergers, Acquisitions, and Dispositions (Exelon)
CENG Put Option
Prior to August 6, 2021, Generation owned a 50.01% membership interest in CENG, a joint venture with EDF, which wholly owns the Calvert Cliffs and Ginna nuclear stations and Nine Mile Point Unit 1, in addition to an 82% undivided ownership interest in Nine Mile Point Unit 2. CENG is 100% consolidated in Exelon's financial statements. See Note 23 — Variable Interest Entities for additional information.
On April 1, 2014, Generation and EDF entered into various agreements including a NOSA, an amended LLC Operating Agreement, an Employee Matters Agreement, and a Put Option Agreement, among others. Under the amended LLC Operating Agreement, CENG made a $400 million special distribution to EDF and committed to make preferred distributions to Generation until Generation has received aggregate distributions of $400 million plus a return of 8.50% per annum.
Under the terms of the Put Option Agreement, EDF had the option to sell its 49.99% equity interest in CENG to Generation exercisable beginning on January 1, 2016 and thereafter until June 30, 2022.
On November 20, 2019, Generation received notice of EDF’s intention to exercise the put option to sell its interest in CENG to Generation, and the put automatically exercised on January 19, 2020 at the end of the sixty-day advance notice period. The transaction required approval by FERC and the NYPSC, which approvals were received on July 30, 2020 and April 15, 2021, respectively. On August 6, 2021, Generation and EDF entered into a settlement agreement pursuant to which Generation purchased EDF’s equity interest in CENG for a net purchase price of $885 million, which includes, among other things, an adjustment for EDF’s share of the balance of the preferred distribution payable by CENG to Generation. The difference between the net purchase price and EDF’s noncontrolling interest as of August 6, 2021 was recorded in Common stock in Exelon’s Consolidated Balance Sheet. As a result of the transaction, Exelon recorded deferred tax liabilities of $290 million in Common stock in the Consolidated Balance Sheet. See Note 14 — Income Taxes for additional information.
The following table summarizes the effects of the changes in Generation's ownership interest in CENG in Exelon's Shareholders' Equity:

For the Year Ended December 31, 2021
Net income attributable to Exelon's common shareholders$1,706 
Pre-tax increase in Exelon's common stock for purchase of EDF's 49.99% equity interest(a)
1,080 
Decrease in Exelon's common stock due to deferred tax liabilities resulting from purchase of EDF's 49.99% equity interest(a)
(290)
Change from net income attributable to common stock and transfers from noncontrolling interest$2,496 
_________
(a)Represents non-cash activity in Exelon’s consolidated financial statements.
Agreement for Sale of Generation’s Solar Business
On December 8, 2020, Generation entered into an agreement with an affiliate of Brookfield Renewable, for the sale of a significant portion of Generation’s solar business, including 360 MW of generation in operation or under construction across more than 600 sites across the United States. Generation will retain certain solar assets not included in this agreement, primarily Antelope Valley.
Completion of the transaction contemplated by the sale agreement was subject to the satisfaction of several closing conditions which were satisfied in the first quarter of 2021. The sale was completed on March 31, 2021 for a purchase price of $810 million. Exelon received cash proceeds of $675 million, net of $125 million long-term debt assumed by the buyer and certain working capital and other post-closing adjustments. Exelon recognized a pre-tax gain of $68 million which is included in Gain on sales of assets and businesses in the Consolidated Statements of Operations and Comprehensive Income.
See Note 17 — Debt and Credit Agreements for additional information on the SolGen nonrecourse debt included as part of the transaction.
Agreement for the Sale of a Generation Biomass Facility
On April 28, 2021, Generation and ReGenerate entered into a purchase agreement, under which ReGenerate agreed to purchase Generation’s interest in the Albany Green Energy biomass facility. As a result, in the second quarter of 2021, Exelon recorded a pre-tax impairment charge of $140 million in Operating and maintenance expense in the Consolidated Statement of Operations and Comprehensive Income. Completion of the transaction was subject to the satisfaction of various customary closing conditions which were satisfied in the second quarter of 2021. The sale was completed on June 30, 2021 for a net purchase price of $36 million.
Disposition of Oyster Creek
On July 31, 2018, Generation entered into an agreement with Holtec and its indirect wholly owned subsidiary, OCEP, for the sale and decommissioning of Oyster Creek located in Forked River, New Jersey, which permanently ceased generation operations on September 17, 2018. Completion of the transaction contemplated by the sale agreement was subject to the satisfaction of several closing conditions, including approval of the license transfer from the NRC and other regulatory approvals, and a private letter ruling from the IRS, which were satisfied in the second quarter of 2019. The sale was completed on July 1, 2019. Exelon recognized a loss on the sale in the third quarter of 2019, which was immaterial.
Under the terms of the transaction, Generation transferred to OCEP substantially all the assets associated with Oyster Creek, including assets held in NDT funds, along with the assumption of liability for all responsibility for the site, including full decommissioning and ongoing management of the SNF until it is moved offsite. The terms of the transaction also include various forms of performance assurance for the obligations of OCEP to timely complete the required decommissioning, including a parental guaranty from Holtec for all performance and payment obligations of OCEP, and a requirement for Holtec to deliver a letter of credit to Generation upon the occurrence of specified events.