XML 100 R83.htm IDEA: XBRL DOCUMENT v3.23.1
Regulatory and Rate Matters - PNM (Details)
$ in Millions
3 Months Ended
Apr. 17, 2023
USD ($)
program
Apr. 15, 2023
USD ($)
GWh
Jan. 03, 2023
USD ($)
Dec. 05, 2022
USD ($)
MW
Jun. 01, 2021
USD ($)
Apr. 15, 2020
USD ($)
MMBTU
program
Mar. 31, 2023
USD ($)
lease
$ / MWh
MW
Mar. 31, 2022
USD ($)
Dec. 31, 2022
GWh
Jul. 29, 2020
MW
Public Utilities, Commitments And Contingencies [Line Items]                    
Excess return on jurisdictional equity that would require refund             0.50%      
Return on equity             10.173%      
Approved return on equity             10.075%      
Allowed return on equity             9.575%      
Allowed return on equity, additional             0.50%      
PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Approved equity capital structure             52.00%      
Approved debt capital structure             48.00%      
Number of leases renewed | lease             5      
Number of megawatts purchased (in megawatts) | MW             64.1      
Non-recurring costs     $ 98.3              
Solar generation capacity (in megawatts) | MW                   650
Renewable Portfolio Standard | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Number of megawatts of Solar PV facilities | MW             158      
Current output in the geothermal facility (in megawatts) | MW             11      
Solar generation capacity (in megawatts) | MW             250.1      
Energy Efficiency and Load Management Program | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Program costs related to energy efficiency, number of programs | program           12        
Program costs related to energy efficiency, in year one           $ 31.4        
Program costs related to energy efficiency, in year two           31.0        
Program costs related to energy efficiency, in year three           $ 29.6        
Energy efficiency and load management programs targeted energy savings (in Gigawatts) | MMBTU           94        
2024 Plan | PNM | Subsequent event                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Program costs related to energy efficiency, number of programs | program 10                  
Program costs related to energy efficiency, in year one $ 34.5                  
Program costs related to energy efficiency, in year two 35.4                  
Program costs related to energy efficiency, in year three $ 36.5                  
Integrated Resource Plan, 2011 | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Frequency of IRP filings             3 years      
Planning period covered of IRP             20 years      
NM 2022 Rate Case | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Recovery of base rate       $ 2,700.0            
Revenue deficiency driver, years of operation       6 years            
Leased PVNGS capacity, expiration | MW       114            
Request suspension period       9 months            
NM 2022 Rate Case | PNM | Non-Fuel Energy                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Requested rate increase (decrease)       $ 63.8            
NMPRC                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Requested return on equity       10.25%            
Action plan, covered period             4 years      
NMPRC | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Proposed revision to rider that will allow for recovery         $ 61.0          
NMPRC | Renewable Energy Rider | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Recorded revenues from renewable rider             $ 18.6 $ 14.5    
Minimum | Renewable Portfolio Standard | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Energy efficiency and load management programs targeted energy savings (in Gigawatts) | MMBTU           80        
Minimum | Energy Efficiency and Load Management Program | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Profit incentive sliding scale multiplier           0.071        
Minimum | Energy Efficiency and Load Management Program | PNM | Subsequent event                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Profit incentive sliding scale multiplier 0.071                  
Maximum | Renewable Portfolio Standard | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Reasonable cost threshold in megawatts per hour | $ / MWh             60      
Maximum | Energy Efficiency and Load Management Program | PNM | Subsequent event                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Profit incentive sliding scale multiplier 0.1073                  
New Mexico Wind | Renewable Portfolio Standard 2014 | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Number of megawatts for wind energy | MW             200      
Red Mesa Wind | Renewable Portfolio Standard 2014 | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Number of megawatts for wind energy | MW             102      
La Joya Wind | Renewable Portfolio Standard | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Number of megawatts for wind energy | MW             140      
Disincentives and Incentives Added | 2020 Energy Efficiency Annual Report | PNM                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Energy efficiency and load management programs additional incentive targeted energy savings (in Gigawatts) | GWh                 94  
Disincentives and Incentives Added | 2020 Energy Efficiency Annual Report | PNM | Subsequent event                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Energy efficiency and load management programs additional incentive targeted energy savings (in Gigawatts) | GWh   94                
Disincentives and Incentives Added | 2021 Energy Efficiency Annual Report | PNM | Subsequent event                    
Public Utilities, Commitments And Contingencies [Line Items]                    
Energy efficiency and load management programs   $ 0.3