XML 82 R64.htm IDEA: XBRL DOCUMENT v3.21.2
Regulatory and Rate Matters - SJGS, Fours Corners and PVNGS Leased Interest Abandonment Applications (Details)
$ in Thousands
1 Months Ended 3 Months Ended 9 Months Ended
Apr. 02, 2021
lease
MW
Feb. 03, 2021
Jan. 08, 2021
USD ($)
Nov. 01, 2020
USD ($)
Jul. 01, 2019
USD ($)
Nov. 30, 2020
USD ($)
Sep. 30, 2021
USD ($)
MW
power_purchase_agreement
Sep. 30, 2021
USD ($)
MW
Oct. 01, 2021
MW
Jul. 28, 2021
MW
Jul. 22, 2021
resource_project
MW
Jun. 23, 2021
MW
May 27, 2021
MW
Mar. 12, 2021
MW
Feb. 08, 2021
MW
Jan. 28, 2021
MW
Dec. 31, 2020
USD ($)
Dec. 18, 2020
USD ($)
Nov. 13, 2020
MW
Sep. 28, 2020
USD ($)
Jul. 29, 2020
MW
Mar. 31, 2020
USD ($)
Feb. 21, 2020
USD ($)
Public Utilities, General Disclosures [Line Items]                                              
Number of purchase power agreements | power_purchase_agreement             3                                
Regulatory time frame for proposed PPAs and battery storage agreements 6 months                                            
Ownership             50.00% 50.00%                              
Regulatory assets             $ 544,432 $ 544,432                 $ 557,790            
Regulatory liabilities             $ 855,855 855,855                 850,228            
COVID-19                                              
Public Utilities, General Disclosures [Line Items]                                              
Temporary mandatory moratorium on disconnection period   100 days                                          
Disconnection transition period   90 days                                          
Facebook Data Center                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW                   190         190                
Number of megawatts in battery storage facilities (in megawatts) | MW                   100   100     100                
Solar generation capacity expected to be operational (in megawatts) | MW                   50         50                
Number of megawatts in battery storage facilities approved (in megawatts) | MW                   50                          
Facebook Data Center | Subsequent event                                              
Public Utilities, General Disclosures [Line Items]                                              
Number of megawatts in battery storage facilities (in megawatts) | MW                 100                            
Number of megawatts in battery storage facilities approved (in megawatts) | MW                 50                            
PNM                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW                                         650    
Number of megawatts in battery storage facilities (in megawatts) | MW                                         300    
Number of additional approved replacement resource projects | resource_project                     2                        
Number of purchase power agreements | power_purchase_agreement             3                                
Number of leases under which lease term was extended | lease 5                                            
Regulatory assets             $ 452,596 452,596                 457,953            
Regulatory liabilities             661,272 661,272                 664,873            
Solar generation capacity related to unexecuted transmission service agreement (in megawatts) | MW                           145                  
PNM | Four Corners                                              
Public Utilities, General Disclosures [Line Items]                                              
Request issuance of energy transition bonds     $ 300,000                                        
Forecasted undepreciated investment     272,000                                        
Plant decommissioning and coal mine reclamation costs     4,600                                        
Upfront financing costs     7,300                                        
Proceeds from securitization bonds     $ 16,500                                        
Solar generation capacity (in megawatts) | MW                               200              
Payments for relief from obligations       $ 75,000   $ 15,000                                  
Final payment for relief from obligations           60,000                                  
Initial payment for relief from obligations           $ 15,000                                  
PNM | Four Corners | PNM                                              
Public Utilities, General Disclosures [Line Items]                                              
Noncontrolling interest, ownership percentage by noncontrolling owners       13.00%                                      
PNM | COVID-19 | COVID-19 Costs Savings                                              
Public Utilities, General Disclosures [Line Items]                                              
Regulatory liabilities                                 900            
PNM | Deferred COVID-19 Costs | COVID-19                                              
Public Utilities, General Disclosures [Line Items]                                              
Regulatory assets             $ 13,200 $ 13,200                 8,800            
PNM | NMPRC                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity, amount requested for approval to abandon (in megawatts) | MW 114                                            
PNM | Leased Interest Termination on January 15, 2023                                              
Public Utilities, General Disclosures [Line Items]                                              
Number of leases under which lease term was extended | lease 4                                            
PNM | Leased Interest Termination on January 15, 2023 | NMPRC                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW 104                                            
PNM | Leased Interest Termination on January 15, 2024 | NMPRC                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW 10                                            
PNM | Replacement Resource Portfolio One                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW 150                   200               200        
Number of megawatts in battery storage facilities (in megawatts) | MW 40                   100               100        
Number of megawatts available in battery storage facilities (in megawatts) | MW                     50                        
PNM | Replacement Resource Portfolio Two                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW                     300   100           100        
Number of megawatts in battery storage facilities (in megawatts) | MW 100                   150   30           30        
Number of megawatts available in battery storage facilities (in megawatts) | MW                     150                        
Number of megawatts available in solar facilities (in megawatts) | MW                     150                        
PNM | Replacement Resource Portfolio Three                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW 300                                            
Number of megawatts in battery storage facilities (in megawatts) | MW 150                                            
PNM | Transportation Electrification Program                                              
Public Utilities, General Disclosures [Line Items]                                              
Expected budgeted expenditures                                   $ 8,400          
Budget flexibility                                   25.00%          
Budget portion dedicated to low and moderate income customers                                   25.00%          
PNM | Portfolio One                                              
Public Utilities, General Disclosures [Line Items]                                              
Number of megawatts available in purchase power agreement | MW             85 85                              
PNM | Portfolio Two                                              
Public Utilities, General Disclosures [Line Items]                                              
Number of megawatts available in purchase power agreement | MW             150 150                              
PNM | Portfolio Three                                              
Public Utilities, General Disclosures [Line Items]                                              
Number of megawatts available in purchase power agreement | MW             40 40                              
PNMR Development                                              
Public Utilities, General Disclosures [Line Items]                                              
Solar generation capacity (in megawatts) | MW             130 130                              
Ownership             50.00% 50.00%                              
San Juan Generating Station                                              
Public Utilities, General Disclosures [Line Items]                                              
Estimated costs of replacement resources                                       $ 8,100      
San Juan Generating Station | Other deferred credits                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                 38,100            
San Juan Generating Station | Employee Severance                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                           $ 9,400  
San Juan Generating Station | PNM                                              
Public Utilities, General Disclosures [Line Items]                                              
Request issuance of energy transition bonds         $ 361,000                                    
Forecasted undepreciated investment         283,000                                   $ 361,000
Plant decommissioning and coal mine reclamation costs         28,600                                    
Upfront financing costs         9,600                                    
Severance costs         20,000                                    
Proceeds from securitization bonds         $ 19,800                                    
San Juan Generating Station | PNM | Other deferred credits                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                 $ 36,800            
San Juan Generating Station | PNM | Employee Severance                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                           8,100  
San Juan Generating Station | PNM | Other Restructuring                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                           8,900  
San Juan Generating Station | PNM | Economic Development and Workforce Training Costs                                              
Public Utilities, General Disclosures [Line Items]                                              
Restructuring reserve                                           $ 19,800