2. RATE AND REGULATORY MATTERS
 

Rate Case Settlement Filing

 

On April 26, 2012, the FERC unconditionally approved Northwest's Stipulation and Settlement Agreement (Settlement) filed on March 15, 2012. The supporting or non-opposing customers named in the Settlement represented approximately 99.5 percent of our long-term firm transportation and storage capacity. The Settlement specified an annual cost of service of $466.5 million and established a new general system firm transportation rate of $0.44 per dekatherm, a 7.4 percent increase over the previous rate. New rates became effective January 1, 2013, and will remain in effect for a minimum of 3 years and a maximum of 5 years.