Rate Case Settlement Filing
On January 23, 2017, we filed for FERC approval a Stipulation and Settlement Agreement (Settlement) and were assigned Docket No. RP17-346. The Settlement specified an annual cost of service of $440 million and established a new general system firm Rate Schedule TF-1 (Large Customer) demand rate of $0.39294/Dth with a $0.00832 commodity rate (Phase 1) and a demand rate of $0.39033/Dth with a $0.00832 commodity rate (Phase 2). Phase 1 rates became effective January 1, 2018, with the Phase 2 rates becoming effective October 1, 2018. The annual cost of service does not change from Phase 1 to Phase 2, but the Phase 2 rates reflect the termination of fifteen-year levelized contracts that will now become Rate Schedule TF-1 (Large Customer) contracts. Provisions were included in the Settlement that we can file a general rate case to place new rates into effect after October 1, 2018, and that a general rate case must be filed for new rates to become effective no later than January 1, 2023.
Tax Reform
Rates charged to our customers are subject to the rate-making policies of the FERC. These policies permit an interstate pipeline to include in its cost-of-service an income tax allowance that includes a deferred income tax component. The recently enacted Tax Cuts and Jobs Act signed into law on December 22, 2017 (Tax Reform), among other things, reduces the corporate federal income tax rates. As part of our Settlement discussed above, we agreed with our customers to record a regulatory asset or liability for federal income tax rate increases or decreases due to subsequent legislation, such as Tax Reform. Therefore, we have established a regulatory liability of $5.8 million as of March 31, 2018, included within Regulatory Liabilities in our Balance Sheet. This liability will be amortized over a five-year period, coincidental with the next rate case going into effect.

Recent FERC Developments
On March 15, 2018, the FERC issued a policy statement regarding the recovery of income tax costs in rates of natural gas pipelines. The FERC found that an impermissible double recovery results from granting a Master Limited Partnership (MLP) pipeline both an income tax allowance and a return on equity pursuant to the discounted cash flow methodology. The FERC will no longer permit a MLP pipeline to recover an income tax allowance in its cost of service. The FERC further stated it will address the application of this policy to non-MLP partnership forms as those issues arise in subsequent proceedings. The FERC also issued a Notice of Proposed Rulemaking proposing a process that will allow it to determine which natural gas pipelines may be collecting unjust and unreasonable rates in light of the recent reduction in the corporate income tax rate in Tax Reform and this policy statement. Furthermore, the FERC issued a Notice of Inquiry seeking comments on the additional impacts of Tax Reform on jurisdictional rates, particularly whether, and if so how, the FERC should address changes relating to accumulated deferred income tax amounts after the corporate income tax rate reduction and bonus depreciation rules, as well as whether other features of Tax Reform require FERC action. We are evaluating the impact of these developments and currently expect any associated impacts would be prospective and determined through subsequent rate proceedings. We also continue to monitor developments that may impact our regulatory liabilities resulting from Tax Reform. It is reasonably possible that our future tariff-based rates collected may be adversely impacted.