XML 37 R20.htm IDEA: XBRL DOCUMENT v3.8.0.1
Regulation and Rates Public Utilities, Regulatory Proceeding (Tables) - Subsidiaries [Member]
9 Months Ended
Sep. 30, 2017
Decoupling Mechanism [Member]  
Regulation and Rates [Line Items]  
Schedule of Deferrals Not Included in Rate Increases
As noted earlier, the Company is also limited to a 3.0% annual decoupling related cap on increases in total revenue. This limitation has been triggered as follows for natural gas with no impacts to electric:
Effective Date Accrued Through
Deferrals not Included in Annual Rate Increases
(Dollars in Millions)
Natural Gas:
 
2016
$47.4
2015
28.7
Schedule of Graduated Scale of Rate Adjustment Mechanisms
The Washington Commission approved the following PSE requests to change rates under its electric and natural gas decoupling mechanisms:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)1
Electric:
 
 
 
May 1, 2017
2.0%
 
$41.9
May 1, 2016
1.0
 
20.8
Natural Gas:
 
 
 
May 1, 2017
2.4%
 
$22.4
May 1, 2016
2.8
 
25.4

_______________
1 
The increase in revenue is net of reductions from excess earnings of $11.9 million for electric and $2.2 million for natural gas in 2017, and $11.9 million for electric and $5.5 million for natural gas in 2016.
PCA Mechanism [Member] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
On August 7, 2015, the Washington Commission issued an order approving the settlement proposing changes to the PCA mechanism. The settlement agreement took effect January 1, 2017 and applies the following graduated scale:
 
Company's Share
 
Customers' Share
Annual Power Cost Variability
Over
 
Under
 
Over
 
Under
Over or Under Collected by up to $17 million
100%
 
100%
 
—%
 
—%
Over or Under Collected by between $17 million - $40 million
35
 
50
 
65
 
50
Over or Under Collected beyond $40 + million
10
 
10
 
90
 
90
The graduated scale that was applicable through December 31, 2016 was as follows:
Annual Power Cost Variability
Company’s Share
 
Customers' Share
+/- $20 million
100%
 
—%
+/- $20 million - $40 million
50
 
50
+/- $40 million - $120 million
10
 
90
+/- $120 + million
5
 
95

Property tax tracker [Member] [Domain] | Natural Gas [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth property tax tracker mechanism rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
May 1, 2017
(0.1)%
 
$(1.1)
May 1, 2016
0.4
 
3.5
Property tax tracker [Member] [Domain] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth property tax tracker mechanism rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
May 1, 2017
(0.04)%
 
$(0.9)
May 1, 2016
0.3
 
5.7
Conservation Rider [Member] | Natural Gas [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth conservation rider rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
 
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
 
 
 
 
May 1, 2017
(0.1)%
 
$(1.0)
 
May 1, 2016
0.3
 
2.9
Conservation Rider [Member] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth conservation rider rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase
(Decrease)
in Revenue
(Dollars in Millions)
May 1, 2017
0.7%
 
$16.5
May 1, 2016
(0.5)
 
(11.7)
Treasury Grants [Member] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth the federal incentive tracker tariff revenue requirement proposed, as originally filed, by PSE and/or approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates from prior year
 
Total credit to be passed back to eligible customers
(Dollars in Millions)
January 1, 2018, proposed
0.2%
 
$(48.2)
January 1, 2017
0.3
 
(51.7)
January 1, 2016
(0.2)
 
(57.3)

Residential Exchange Benefit [Member] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth residential exchange benefit adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Total credit to be passed back to eligible customers
(Dollars in Millions)
October 1, 2017
(0.6)%
 
$(80.8)
October 1, 2015
2.4
 
(76.4)
Power Cost Only Rate Case (PCORC) [Member] | Electric [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth the updated compliance filing rate adjustment that became effective on December 1, 2016, by operation of law and the corresponding expected annual impact on PSE's revenue based on the effective date:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
December 1, 2016
(1.7)%
 
$(37.3)
Cost recovery mechanism [Member] | Natural Gas [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth CRM rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective dates:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
November 1, 2017
0.5%
 
$4.9
November 1, 2016
0.6
 
5.6
Purchased Gas Adjustment (PGA) [Member] | Natural Gas [Member]  
Regulation and Rates [Line Items]  
Schedule of Effects on Annual Revenue Due to Approved Rate Adjustments
The following table sets forth the PGA rate adjustments approved by the Washington Commission and the corresponding expected annual impact on PSE’s revenue based on the effective date:
Effective Date
Average
Percentage
Increase (Decrease)
in Rates
 
Increase (Decrease)
in Revenue
(Dollars in Millions)
November 1, 2017
(3.3)%
 
$(30.8)
November 1, 2016
(0.4)
 
(4.1)