XML 49 R13.htm IDEA: XBRL DOCUMENT v2.4.0.6
Utility Plant
12 Months Ended
Dec. 31, 2011
Regulated Operations [Abstract]  
Utility Plant
(6)  Utility Plant

      
Puget Energy
  
Puget Sound Energy
 
Utility Plant
 
Estimated
Useful
Life
  
At December 31,
  
At December 31,
 
(Dollars In Thousands)
 
(Years)
  
2011
  
2010
  
2011
  
2010
 
Electric, gas and common utility plant classified by prescribed accounts :
               
Distribution plant
 10-50  $4,552,087  $4,313,447  $6,279,340  $6,054,961 
Production plant
 25-125   1,618,196   1,575,694   2,616,855   2,585,864 
Transmission plant
 45-65   391,080   337,163   516,461   463,546 
General plant
 5-35   442,216   390,732   499,559   449,980 
Intangible plant (including capitalized software)
 3-50   112,118   97,458   187,948   184,706 
Plant acquisition adjustment
 7-30   188,628   183,142   228,593   223,108 
Underground storage
 25-60   27,139   26,869   40,815   40,558 
Liquefied natural gas storage
 25-45   12,622   12,440   14,492   14,310 
Plant held for future use
 
NA
   18,381   53,945   18,534   54,098 
Recoverable Cushion Gas
 
NA
   8,514   8,058   8,514   8,057 
Plant not classified
 
NA
   38,998   58,822   38,998   58,822 
Capital leases, net of accumulated amortization 1
 1-5   32,207   15,444   32,207   -- 
Less: accumulated provision for depreciation
     (674,782)  (429,038)  (3,714,912)  (3,509,277)
Subtotal
    $6,767,404  $6,644,176  $6,767,404  $6,628,733 
Construction work in progress
 
NA
   1,282,463   628,387   1,282,463   628,387 
Net utility plant
    $8,049,867  $7,272,563  $8,049,867  $7,257,120 
_______________
1
Accumulated amortization of capital leases at Puget Energy was $5.7 million in 2011 and $29.6 million in 2010.  Accumulated amortization of capital leases at PSE was $5.7 million in 2011.  PSE did not have any capital leases in 2010.

Jointly owned generating plant service costs are included in utility plant service cost.  The following table indicates the Company's percentage ownership and the extent of the Company's investment in jointly owned generating plants in service at December 31, 2011.  These amounts are also included in the Utility Plant table above.

        
Puget Energy's Share
  
Puget Sound Energy's Share
 
Jointly Owned Generating Plants
(Dollars in Thousands)
Energy Source (Fuel)
 
Company's Ownership Share
  
Plant in Service at Cost
  
Accumulated Depreciation
  
Plant in Service at Cost
  
Accumulated Depreciation
 
Colstrip Units 1 & 2
Coal
  50% $135,623  $(5,153) $279,391  $(148,922)
Colstrip Units 3 & 4
Coal
  25%  217,813   (16,246)  501,837   (300,269)
Colstrip Units 1 - 4 Common Facilities 1
 
Coal
 
various
   83   (10)  252   (179)
Frederickson 1
Gas
  49.85%  62,146   570   71,095   (8,379)
_______________
1
The Company's ownership is 50% for Colstrip Units 1 & 2 and 25% for Colstrip Units 3 & 4.

There were no valuation adjustments to asset retirement obligations (ARO) in conjunction with the merger in 2009.  The Company recognized a new ARO in 2011 in the amount of $0.4 million.  The Company did not recognize any new AROs in 2010.
The following table describes all changes to the Company's ARO liability:

   
At December 31,
 
(Dollars in Thousands)
 
2011
  
2010
 
Asset retirement obligation at beginning of period
 $25,416  $24,095 
New asset retirement obligation recognized in the period
  350   -- 
Liability settled in the period
  (1,722)  (2,341)
Revisions in estimated cash flows
  1,154   2,413 
Accretion expense
  1,342   1,249 
Asset retirement obligation at end of period
 $26,540  $25,416 

The Company has identified the following obligations, as defined by ASC 410, "Asset Retirement and Environmental Obligations," which were not recognized at December 31, 2011 and 2010:
-
a legal obligation under Federal Dangerous Waste Regulations to dispose of asbestos-containing material in facilities that are not scheduled for remodeling, demolition or sales. The disposal cost related to these facilities could not be measured since the retirement date is indeterminable; therefore, the liability cannot be reasonably estimated;
-
an obligation under Washington state law to decommission the wells at the Jackson Prairie natural gas storage facility upon termination of the project.  Since the project is expected to continue as long as the Northwest pipeline continues to operate, the liability cannot be reasonably estimated;
-
an obligation to pay its share of decommissioning costs at the end of the functional life of the major transmission lines.  The major transmission lines are expected to be used indefinitely; therefore, the liability cannot be reasonably estimated;
-
a legal obligation under Washington state environmental laws to remove and properly dispose of certain under and above ground fuel storage tanks.  The disposal costs related to under and above ground storage tanks could not be measured since the retirement date is indeterminable; therefore, the liability cannot be reasonably estimated;
-
a potential legal obligation may arise upon the expiration of an existing FERC hydropower license if FERC orders the project to be decommissioned, although PSE contends that FERC does not have such authority.  Given the value of ongoing generation, flood control and other benefits provided by these projects, PSE believes that the potential for decommissioning is remote and cannot be reasonably estimated;