Property, Plant and Equipment
6 Months Ended
Jun. 30, 2014
Property, Plant and Equipment [Line Items]  
Property, Plant and Equipment
PROPERTY, PLANT AND EQUIPMENT
Environmental Compliance Plans Emission Controls Projects -
IPL’s George Neal Unit 3 - Construction of the scrubber and baghouse at George Neal Unit 3 was completed in May 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and IPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $58 million and AFUDC of $4 million for IPL’s allocated portion of the George Neal Unit 3 scrubber and baghouse.

WPL’s Columbia Units 1 and 2 - Construction of the scrubber and baghouse at Columbia Unit 2 was completed in April 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and WPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $152 million and AFUDC of $8 million for WPL’s allocated portion of the Columbia Unit 2 scrubber and baghouse and certain expenditures applicable to both Columbia Unit 1 and 2.

Construction of the scrubber and baghouse at Columbia Unit 1 was completed in July 2014. As of June 30, 2014, Alliant Energy and WPL recorded capitalized expenditures of $116 million and AFUDC of $7 million for WPL’s allocated portion of the Columbia Unit 1 scrubber and baghouse in “Construction work in progress - Other” on their balance sheets.
IPL [Member]
 
Property, Plant and Equipment [Line Items]  
Property, Plant and Equipment
PROPERTY, PLANT AND EQUIPMENT
Environmental Compliance Plans Emission Controls Projects -
IPL’s George Neal Unit 3 - Construction of the scrubber and baghouse at George Neal Unit 3 was completed in May 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and IPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $58 million and AFUDC of $4 million for IPL’s allocated portion of the George Neal Unit 3 scrubber and baghouse.

WPL’s Columbia Units 1 and 2 - Construction of the scrubber and baghouse at Columbia Unit 2 was completed in April 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and WPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $152 million and AFUDC of $8 million for WPL’s allocated portion of the Columbia Unit 2 scrubber and baghouse and certain expenditures applicable to both Columbia Unit 1 and 2.

Construction of the scrubber and baghouse at Columbia Unit 1 was completed in July 2014. As of June 30, 2014, Alliant Energy and WPL recorded capitalized expenditures of $116 million and AFUDC of $7 million for WPL’s allocated portion of the Columbia Unit 1 scrubber and baghouse in “Construction work in progress - Other” on their balance sheets.
WPL [Member]
 
Property, Plant and Equipment [Line Items]  
Property, Plant and Equipment
PROPERTY, PLANT AND EQUIPMENT
Environmental Compliance Plans Emission Controls Projects -
IPL’s George Neal Unit 3 - Construction of the scrubber and baghouse at George Neal Unit 3 was completed in May 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and IPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $58 million and AFUDC of $4 million for IPL’s allocated portion of the George Neal Unit 3 scrubber and baghouse.

WPL’s Columbia Units 1 and 2 - Construction of the scrubber and baghouse at Columbia Unit 2 was completed in April 2014, which resulted in a transfer of the capitalized project costs from “Construction work in progress - Other” to “Electric plant” on Alliant Energy’s and WPL’s balance sheets in 2014. As of June 30, 2014, the capitalized project costs consisted of capital expenditures of $152 million and AFUDC of $8 million for WPL’s allocated portion of the Columbia Unit 2 scrubber and baghouse and certain expenditures applicable to both Columbia Unit 1 and 2.

Construction of the scrubber and baghouse at Columbia Unit 1 was completed in July 2014. As of June 30, 2014, Alliant Energy and WPL recorded capitalized expenditures of $116 million and AFUDC of $7 million for WPL’s allocated portion of the Columbia Unit 1 scrubber and baghouse in “Construction work in progress - Other” on their balance sheets.