Coronavirus Disease – 2019

The global outbreak of COVID-19 was declared a pandemic by the WHO and the CDC. COVID-19 has spread globally, including throughout the United States and, in turn, our service territory. Wisconsin has declared a public health emergency and has issued a shelter-in-place order in response to the COVID-19 pandemic. In addition, on March 24, 2020, the PSCW issued two orders regarding certain actions to be taken for purposes of ensuring that essential utility services are available to our customers during the public health emergency.

The first order requires all public utilities in the state of Wisconsin, including us, to temporarily suspend disconnections, the assessment of late fees, and deposit requirements for all customer classes. In addition, it requires utilities to reconnect customers that were previously disconnected, offer deferred payment arrangements to all customers, and streamline the application process for customers applying for utility service. The order will remain in effect during the public health emergency and until further notice from the PSCW.

In the second order, the PSCW authorized Wisconsin utilities to defer expenditures and certain foregone revenues resulting from compliance with the first order, and expenditures as otherwise incurred to ensure safe, reliable, and affordable access to utility services during the declared public health emergency. The PSCW has affirmed that this authorization for deferral includes the incremental increase in uncollectible expense above what is currently being recovered in rates. As we already have a cost recovery mechanism in place to recover uncollectible expense for residential customers, this new deferral will only impact the recovery of uncollectible expense for our commercial and industrial customers. The PSCW will review the recoverability and examine the prudency of any deferred amounts in future rate proceedings.

As of March 31, 2020, we had not recorded any deferrals related to the COVID-19 pandemic. A limited number of expenditures have been identified, and we anticipate amounts will be deferred in the second quarter of 2020. We have begun to experience foregone revenues related to our inability to charge late fees as a result of the PSCW order, and will continue to evaluate future incremental costs and foregone revenues for potential recovery as they arise.

2020 and 2021 Rates

In March 2019, we filed an application with the PSCW to increase our retail electric, natural gas, and steam rates, effective January 1, 2020. In August 2019, we filed an application with the PSCW for approval of a settlement agreement entered into with certain intervenors to resolve several outstanding issues in our rate case. In December 2019, the PSCW issued a written order that approved the settlement agreement without material modification and addressed the remaining outstanding issues that were not included in the settlement agreement. The new rates became effective January 1, 2020. The final order reflects the following:
2020 Effective rate increase
 
 
 
 
Electric (1)
 
$
15.3
 million
/
0.5%
Gas (2)
 
$
10.4
 million
/
2.8%
Steam
 
$
1.9
 million
/
8.6%
 
 
 
 
 
ROE
 
10.0%
 
 

 

Common equity component average on a financial basis
 
52.5%

(1) 
Amount is net of certain deferred tax benefits from the Tax Legislation that were utilized to reduce near-term rate impacts to our customers. The rate order reflects the majority of the unprotected deferred tax benefits from the Tax Legislation being amortized evenly over two years, which results in approximately $65 million of tax benefits being amortized in each of 2020 and 2021. The unprotected deferred tax benefits
related to the unrecovered balances of our recently retired plants and our SSR regulatory asset are being used to reduce the related regulatory asset. Unprotected deferred tax benefits by their nature are eligible to be returned to customers in a manner and timeline determined to be appropriate by the PSCW.

(2) 
Amount includes certain deferred tax expense from the Tax Legislation. The rate order reflects all of the unprotected deferred tax expense from the Tax Legislation being amortized evenly over four years, which results in approximately $5 million of previously deferred tax expense being amortized each year. Unprotected deferred tax expense by its nature is eligible to be recovered from customers in a manner and timeline determined to be appropriate by the PSCW.

In accordance with our rate order, we will seek a financing order from the PSCW to securitize $100 million of Pleasant Prairie power plant's book value, plus the carrying costs accrued on the $100 million during the securitization process and related fees. The securitization will reduce the carrying costs for the $100 million, benefiting customers.

We will continue having an earnings sharing mechanism through 2021. The earnings sharing mechanism was modified from its previous structure to one that is consistent with other Wisconsin investor-owned utilities. Under the new earnings sharing mechanism, if we earn above our authorized ROE: (i) we retain 100.0% of earnings for the first 25 basis points above the authorized ROE; (ii) 50.0% of the next 50 basis points is refunded to customers; and (iii) 100.0% of any remaining excess earnings is refunded to customers. In addition, the rate order also requires us to maintain residential and small commercial electric and natural gas customer fixed charges at previously authorized rates and to maintain the status quo for our electric market-based rate programs for large industrial customers through 2021.

2018 and 2019 Rates

During April 2017, we, along with Wisconsin Public Service Corporation and WG, filed an application with the PSCW for approval of a settlement agreement we made with several of our commercial and industrial customers regarding 2018 and 2019 base rates. In September 2017, the PSCW issued an order that approved the settlement agreement, which froze base rates through 2019 for our electric, natural gas, and steam customers. Based on the PSCW order, our authorized ROE remained at 10.2% and our capital cost structure remained unchanged through 2019.

In addition to freezing base rates, the settlement agreement extended and expanded the electric real-time market pricing program options for large commercial and industrial customers and mitigated the continued growth of certain escrowed costs during the base rate freeze period by accelerating the recognition of certain tax benefits. We were flowing through the tax benefit of our repair-related deferred tax liabilities in 2018 and 2019, to maintain certain regulatory asset balances at their December 31, 2017 levels. While we would typically follow the normalization accounting method and utilize the tax benefits of the deferred tax liabilities in rate making as an offset to rate base, benefiting customers over time, the federal tax code does allow for passing these tax repair-related benefits to ratepayers much sooner using the flow through accounting method. The flow through treatment of the repair-related deferred tax liabilities offset the negative income statement impact of holding the regulatory assets level, resulting in no change to net income.

Pursuant to the settlement agreement, we also agreed to keep our earnings sharing mechanism in place through 2019. Under this earnings sharing mechanism, if we earned above our authorized ROE, 50% of the first 50 basis points of additional utility earnings were required to be refunded to customers. All utility earnings above the first 50 basis points were also required to be refunded to customers.

Liquefied Natural Gas Facility

In November 2019, we filed an application with the PSCW requesting approval to construct a LNG facility. If approved, the facility would provide us with approximately one billion cubic feet of natural gas supply to meet anticipated peak demand without requiring the construction of additional interstate pipeline capacity. This facility is expected to reduce the likelihood of constraints on our natural gas system during the highest demand days of winter. The project is estimated to cost approximately $185 million. Commercial operation for the LNG facility is targeted for the end of 2023.

Solar Generation Project

In August 2019, we, along with an unaffiliated utility, filed an application with the PSCW for approval to acquire an ownership interest in a proposed solar project, Badger Hollow II, that will be located in Iowa County, Wisconsin. Once constructed, we will own 100 MW of the output of this project. Our share of the cost of this project is estimated to be $130 million. The PSCW issued a written order approving the acquisition of this project on March 6, 2020.