XML 28 R17.htm IDEA: XBRL DOCUMENT v3.4.0.3
Commitments and Contingencies
3 Months Ended
Mar. 31, 2016
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES
COMMITMENTS AND CONTINGENCIES

We have significant commitments and contingencies arising from our operations, including those related to unconditional purchase obligations, environmental matters, and enforcement and litigation matters.

Energy Related Purchased Power Agreements

We have obligations to distribute and sell electricity and natural gas to our customers and expect to recover costs related to these obligations in future customer rates. In order to meet these obligations, we routinely enter into long-term purchase and sale commitments for various quantities and lengths of time. Our minimum future commitments related to these purchase obligations as of March 31, 2016, were $10,630.9 million.

Environmental Matters

Consistent with other companies in the energy industry, we face significant ongoing environmental compliance and remediation obligations related to current and past operations. Specific environmental issues affecting us include, but are not limited to, current and future regulation of air emissions such as SO2, NOx, fine particulates, mercury, and GHGs; water discharges; disposal of coal combustion products such as fly ash; and remediation of impacted properties, including former manufactured gas plant sites.

Air Quality

Sulfur Dioxide National Ambient Air Quality Standards

The EPA issued a revised 1-Hour SO2 NAAQS that became effective in August 2010. The EPA issued a final rule in August 2015 describing the implementation requirements and established a compliance timeline for the revised standard. The final rule affords state agencies some latitude in rule implementation. A nonattainment designation could have negative impacts for a localized geographic area, including additional permitting requirements for new or existing sources in the area.

In March 2015, a federal court entered a consent decree between the EPA and the Sierra Club and others agreeing to specific actions related to implementing the revised standard for areas containing large sources emitting above a certain threshold level of SO2. The consent decree requires the EPA to complete attainment designations for certain areas with large sources by no later than July 2, 2016. SO2 emissions from PIPP are above the consent decree emission threshold, which means that the Marquette area required action earlier than would otherwise have been required under the revised NAAQS. However, we were able to show through modeling that the area should be designated as attainment. Based upon this modeling, the state of Michigan recommended to the EPA that the Marquette area be designated as attainment, and in February 2016, the EPA issued a draft recommendation to have the Marquette area classified as unclassified/attainment. We expect the EPA recommendation to be finalized in 2016.

We believe our fleet overall is well positioned to meet the new regulation.

8-Hour Ozone National Ambient Air Quality Standards

The EPA completed its review of the 2008 8-hour ozone standard in November 2014, and announced a proposal to tighten (lower) the NAAQS. In October 2015, the EPA released the final rule, which lowered the limit for ground-level ozone. This is expected to cause nonattainment designations for some counties in Wisconsin with potential future impacts for our fossil-fueled power plant fleet. For nonattainment areas, the state will have to develop a state implementation plan to bring the areas back into attainment. We will be required to comply with this state implementation plan no earlier than 2020 and are in the process of reviewing and determining potential impacts resulting from this rule.

Mercury and Other Hazardous Air Pollutants

In December 2011, the EPA issued the final MATS rule, which imposes stringent limitations on emissions of mercury and other hazardous air pollutants from coal and oil-fired electric generating units beginning in April 2015. In addition, both Wisconsin and Michigan have state mercury rules that require a 90% reduction of mercury; however, these rules are not in effect as long as MATS is in place. In June 2015, the United States Supreme Court (Supreme Court) ruled on a challenge to the MATS rule and remanded the case back to the United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit Court of Appeals), ruling that the EPA failed to appropriately consider the cost of the regulation. The MATS rule has been remanded to the EPA to address the Supreme Court decision, but remains in effect until the D.C. Circuit Court of Appeals takes action on the EPA's April 2016 updated cost evaluation.

Our fleet is well positioned to comply with this regulation. In April 2013, we received a one year MATS compliance extension from the MDEQ for PIPP through April 2016. The addition of a dry sorbent injection system for further control of mercury and acid gases at PIPP was placed into service in March 2016, and PIPP is in compliance with MATS.

Climate Change

In 2015, the EPA issued the Clean Power Plan, a final rule regulating GHG emissions from existing generating units, a proposed federal plan and model trading rules as alternatives or guides to state compliance plans, and final performance standards for modified and reconstructed generating units and new fossil-fueled power plants. In October 2015, following publication of the final rule for existing fossil generating units, numerous states (including Wisconsin and Michigan), trade associations, and private parties filed lawsuits challenging the final rule, including a request to stay the implementation of the final rule pending the outcome of these legal challenges. The D.C. Circuit Court of Appeals denied the stay request, but in February 2016, the Supreme Court stayed the effectiveness of the rule until disposition of the litigation in the D.C. Circuit Court of Appeals and to the extent that review is sought, at the Supreme Court. In addition, in February 2016, the Governor of Wisconsin issued Executive Order 186, which prohibits state agencies, departments, boards, commissions, or other state entities from developing or promoting the development of a state plan.

The final rule for existing fossil generating units seeks to achieve state-specific GHG emission reduction goals by 2030, and would have required states to submit plans by September 6, 2016. States submitting initial plans and requesting an extension would have been required to submit final plans by September 2018, either alone or in conjunction with other states. The timelines for the 2022 through 2029 interim goals and the 2030 final goal for states, as well as all other aspects of the rule, may be changed due to the stay and subsequent legal proceedings.

The goal of the final rule is to reduce nationwide GHG emissions by 32% from 2005 levels. The rule is seeking GHG emission reductions in Wisconsin and Michigan of 41% and 39%, respectively, below 2012 levels by 2030. The building blocks used by the EPA to determine each state's emission reduction requirements include a combination of improving power plant efficiency, increasing reliance on combined cycle natural gas units, and adding new renewable energy resources. We are in the process of reviewing the final rule for existing fossil generating units to determine the potential impacts to our operations. The rule could result in significant additional compliance costs, including capital expenditures, could impact how we operate our existing fossil-fueled power plants and biomass facility, and could have a material adverse impact on our operating costs.

Draft Federal Plan and Model Trading Rules were also published in October 2015 for use in developing state plans or for use in states where a plan is not submitted or approved. In December 2015, the state of Wisconsin submitted petitions for review to the EPA of the final standards for existing as well as new, modified, and reconstructed generating units. A petition for review was also submitted jointly by the Wisconsin utilities. Among other things, the petitions narrowly ask the EPA to consider revising the state goal for existing units to reflect the 2013 retirement of the Kewaunee Power Station, which could lower the state's CO2 equivalent reduction goal by about 10%. Michigan state agencies announced modeling results that suggest that the state will be able to meet existing source requirements until 2025, based on planned coal plant retirements, along with a continuation of state renewable standards and current levels of energy efficiency.

We are required to report our CO2 equivalent emissions from our electric generating facilities under the EPA Greenhouse Gases Reporting Program. For 2015, we reported CO2 equivalent emissions of 25.3 million metric tonnes to the EPA. The level of CO2 and other GHG emissions vary from year to year and are dependent on the level of electric generation and mix of fuel sources, which is determined primarily by demand, the availability of the generating units, the unit cost of fuel consumed, and how our units are dispatched by MISO.

We are also required to report CO2 equivalent amounts related to the natural gas that our natural gas operations distribute and sell. For 2015, we reported CO2 equivalent emissions of 3.7 million metric tonnes to the EPA related to our distribution and sale of natural gas.

Water Quality

Clean Water Act Cooling Water Intake Structure Rule

In August 2014, the EPA issued a final regulation under Section 316(b) of the Clean Water Act, which requires that the location, design, construction, and capacity of cooling water intake structures at existing power plants reflect the Best Technology Available (BTA) for minimizing adverse environmental impacts from both impingement and entrainment. The rule became effective in October 2014, and applies to all of our existing generating facilities with cooling water intake structures, except for the Oak Creek expansion units, which were permitted under the rules governing new facilities.

Facility owners must select from seven compliance options available to meet the impingement mortality (IM) reduction standard. The rule requires state permitting agencies to make BTA determinations, subject to EPA oversight, for IM reduction over the next several years as facility permits are reissued. Based on our assessment, we believe that existing technologies at our generating facilities, except for VAPP Unit 1, satisfy the IM BTA requirements. For VAPP Unit 2, a project to install fish protection screens to meet the IM BTA standard was completed in October 2015. The same types of screens are scheduled to be installed on VAPP Unit 1 starting in September 2016.

BTA determinations must also be made by the WDNR and MDEQ to address entrainment mortality (EM) reduction on a site-specific basis taking into consideration several factors. We have received an EM BTA determination by the WDNR, with EPA concurrence, for our proposed intake modification at VAPP. BTA determinations for EM will be made in future permit reissuances for Port Washington Generating Station, Pleasant Prairie Power Plant, PIPP, and Oak Creek Power Plant Units 5 through 8. 

During 2016–2018, we will be completing studies and evaluating options to address the EM BTA requirements at our plants. With the exception of Pleasant Prairie Power Plant (which has existing cooling towers that meet EM BTA requirements), and VAPP, we cannot yet determine what, if any, intake structure or operational modifications will be required to meet the new EM BTA requirements at our facilities. In addition, the rule allows the EM BTA requirements to be waived in cases of pending facility retirements, which we are currently considering for PIPP. Based on discussions with the MDEQ, if we submit a signed certification with our next National Pollutant Discharge Elimination System permit application stating that PIPP will be retired no later than the end of the next permit cycle (assumed to be October 1, 2022), then the EM BTA requirements will be waived. Entrainment studies are currently underway at PIPP.

Steam Electric Effluent Guidelines

The EPA's final steam electric effluent guidelines rule took effect in January 2016 and applies to discharges of wastewater from our power plant processes in Wisconsin and Michigan. Unless pending challenges to the final guidelines are successful, the WDNR and MDEQ will modify the state rules and incorporate the new requirements into our facility permits, which are renewed every five years. We expect the new requirements to be phased in between 2018 and 2023 as our permits are renewed. Our power plant facilities already have advanced wastewater treatment technologies installed that meet many of the discharge limits established by this rule. However, these standards will require additional wastewater treatment retrofits as well as installation of other equipment to minimize process water use. The final rule phases in new or more stringent requirements related to limits of arsenic, mercury, selenium, and nitrogen in wastewater discharged from wet scrubber systems. New requirements for wet scrubber wastewater treatment will require additional zero liquid discharge or other advanced treatment capital improvements for the Oak Creek and Pleasant Prairie facilities. The rule also requires dry fly ash handling, which is already in place at all of our power plants. Dry bottom ash transport systems are required by the new rule, and modifications will be required at Oak Creek Units 5 and 6, the Pleasant Prairie units, and the PIPP units. We are beginning preliminary engineering for compliance with the rule and estimate a total cost range of $70 million to to $95 million for these advanced treatment and bottom ash transport systems.

Valley Power Plant Wisconsin Pollutant Discharge Elimination System Permit

The WDNR issued a Wisconsin Pollutant Discharge Elimination System permit for VAPP that became effective in January 2013. The permit contains several additional requirements including effluent toxicity testing and monitoring for additional parameters (phosphorous, mercury, and ammonia-nitrogen), and a new heat addition limit from the cooling water discharges that all took effect immediately. Other long-term compliance requirements include thermal discharge studies, phosphorous evaluation and feasibility for reduction, mercury minimization planning, and the installation of new cooling water intake fish protection screens. Installation of wedge wire screens for fish protection on the VAPP Unit 2 cooling water intake structure is complete. An identical modification is scheduled to begin for VAPP Unit 1 in the third quarter of 2016. We are also currently working on plans to meet the remaining long-term requirements.

Manufactured Gas Plant Remediation

We have identified sites at which we or a predecessor company owned or operated a manufactured gas plant or stored manufactured gas. We have also identified other sites that may have been impacted by historical manufactured gas plant activities. We are responsible for the environmental remediation of these sites. We are also working with various state jurisdictions in our investigation and remediation planning. These sites are at various stages of investigation, monitoring, remediation, and closure.

The future costs for detailed site investigation, future remediation, and monitoring are dependent upon several variables including, among other things, the extent of remediation, changes in technology, and changes in regulation. Historically, our regulators have allowed us to recover incurred costs, net of insurance recoveries and recoveries from potentially responsible parties, associated with the remediation of manufactured gas plant sites. Accordingly, we have established regulatory assets for costs associated with these sites.

We have established the following regulatory assets and reserves related to manufactured gas plant sites:
(in millions)
 
March 31, 2016
 
December 31, 2015
Regulatory assets
 
$
17.0

 
$
16.9

Reserves for future remediation
 
5.6

 
5.6

Enforcement and Litigation Matters

We are involved in legal and administrative proceedings before various courts and agencies with respect to matters arising in the ordinary course of business. Although we are unable to predict the outcome of these matters, management believes that appropriate reserves have been established and that final settlement of these actions will not have a material effect on our financial condition or results of operations.

Consent Decree

In April 2003, we entered into a Consent Decree with the EPA, in which we agreed to significantly reduce air emissions from our coal-fired power plants. Under the terms of the Consent Decree, we could request its termination after December 31, 2015. We made this termination request in March 2016, and the request is currently under review.