XML 16 R33.htm IDEA: XBRL DOCUMENT v2.4.0.8
Real Estate Activations, Acquisitions, Developments, and Closures - Additional Information (Detail) (USD $)
3 Months Ended 3 Months Ended 1 Months Ended 3 Months Ended 1 Months Ended 1 Months Ended 1 Months Ended
Mar. 31, 2014
Bed
Mar. 31, 2013
Dec. 31, 2013
Mar. 31, 2014
Idle Facilities
Mar. 31, 2013
Idle Facilities
Mar. 31, 2014
San Diego Correctional Facility
Facility
Mar. 31, 2014
Otay Mesa Detention Center
Sep. 30, 2012
Red Rock Correctional Center
RenewalOptions
Person
Mar. 31, 2014
Red Rock Correctional Center
Facility
Jun. 30, 2014
Red Rock Correctional Center
Scenario, Forecast
Sep. 30, 2012
Red Rock Correctional Center
Through February 2014
Person
Sep. 30, 2012
Red Rock Correctional Center
During the first quarter of 2015
Person
Oct. 31, 2013
California City Correctional Center
Facility
Oct. 31, 2013
State of California Department of Corrections and Rehabilitation
Mar. 31, 2014
Nov. 30, 2013
Facility
Jul. 31, 2013
Correctional Alternatives, Inc.
Facility Activations Developments And Closures [Line Items]                                  
Consideration paid                                 $ 36,500,000
Business acquisition transaction related expenses                                 800,000
Purchase price, goodwill 16,110,000   16,110,000                           7,000,000
Purchase price, identifiable intangible assets                                 26,900,000
Purchase price, intangible liabilities                                 7,900,000
Purchase price, net tangible assets                                 17,700,000
Purchase price, deferred tax liabilities                                 7,200,000
Operating Expense 287,380,000 298,222,000   2,500,000 1,700,000                        
Number of beds at the facility 86,500         1,154     1,596       2,304     2,552  
Lease expiration date           Dec. 31, 2015                      
Amount invested to acquire property             71,300,000                    
Expected additional number of offenders to be managed by the company               1,000     500 500          
Management contract, initial term               10 years                  
Management contract, number of renewal options               2                  
Management contract, renewal option term               5 years                  
Percentage of guaranteed occupancy under management contract               90.00%                  
Management contract term facility will revert to the state of Arizona               20 years                  
Capital improvements for certain physical plant modifications                 20,100,000                
Expected capital improvements cost for certain physical plant modifications                   800,000              
Maximum number of useful life in years                 20 years                
Lease agreement commencing date                           Dec. 01, 2013      
Lease term                           3 years      
Renewal options term                           2 years      
Annual rent                           28,500,000      
Rent increase percentage                           2.00%      
Tenant improvements expenses                           10,000,000      
Total cost of the project                             $ 140,000,000