Facility Activation, Developments, And Closures
3 Months Ended
Mar. 31, 2012
Facility Activation, Developments, And Closures [Abstract]  
Facility Activation, Developments, And Closures
4. FACILITY ACTIVATION, DEVELOPMENTS, AND CLOSURES

In February 2008, CCA announced its intention to construct a new correctional facility in Trousdale County, Tennessee. However, during the first quarter of 2009 CCA temporarily suspended the construction of this facility until there is greater clarity around the timing of future bed absorption by its customers. CCA will continue to monitor its customers' needs, and could promptly resume construction of the facility. As of March 31, 2012, CCA has capitalized $29.0 million related to the Trousdale facility, including $0.6 million in equipment and $15.2 million of pre-fabricated concrete cells that are constructed and being stored on this site but are generally transferable to other potential CCA development projects.

During December 2009, CCA announced its decision to idle its 1,600-bed Prairie Correctional Facility in Minnesota due to low inmate populations at the facility. During 2009, the Prairie facility housed offenders from the states of Minnesota and Washington. However, due to excess capacity in the states' systems, both states reduced the populations held at Prairie throughout 2009. The state of Washington removed all of its offenders from the Prairie facility by the end of 2009, and during January 2010, the final transfer of offenders from the Prairie facility to the state of Minnesota was completed.

On January 15, 2010, the Arizona Governor and Legislature proposed budgets that would phase out the utilization of private out-of-state beds due to in-state capacity coming on-line and severe budget conditions. During the first half of 2010, the Arizona Department of Corrections removed all of the inmates from CCA's 752-bed Huerfano County Correctional Center in Colorado and its 2,160-bed Diamondback Correctional Facility in Oklahoma upon expiration of the management contracts at each facility. As a result, CCA has idled both facilities. The Diamondback facility previously housed inmates from the states of Wisconsin, Hawaii, and Oklahoma, while the Huerfano facility previously housed inmates from the state of Colorado. CCA continues to manage inmate populations from the states of Oklahoma, Hawaii, and Colorado at other facilities it owns and operates.

In late January 2012, the governor of Kentucky submitted his proposed budget which included the transfer of the inmates currently held at one of CCA's facilities to a facility owned by the state of Kentucky that had previously been closed as the result of damage sustained during an inmate disturbance. Based on conversations with the Kentucky Department of Corrections, CCA expects Kentucky to remove inmates currently housed in the 656-bed Otter Creek Correctional Center, a facility CCA owns in Wheelwright, Kentucky, by the end of August 2012. CCA plans to idle the facility if it is unable to identify a partner to utilize the facility.

Additionally, CCA owns the Queensgate Correctional Facility in Ohio and Shelby Training Center in Tennessee that were both idled in 2008 and are currently available to potential customers. The carrying values of these six idle facilities totaled $129.1 million and $130.1 million as of March 31, 2012 and December 31, 2011, respectively, excluding equipment and other assets that could generally be transferred and used at other facilities CCA owns without significant cost. CCA tested each of the aforementioned six facilities for impairment when it was notified by the respective customers that they would no longer be utilizing such facility. CCA re-performs the impairment analyses on an annual basis for each of the idle facilities and for the suspended construction project in Trousdale County, Tennessee, and evaluates on a quarterly basis market developments for the potential utilization of each of these facilities in order to identify events that may cause CCA to reconsider its most recent assumptions. As a result of CCA's analyses, CCA determined each of these assets to have recoverable values in excess of the corresponding carrying values.

CCA commenced development of the new Jenkins Correctional Center in Georgia during the third quarter of 2010, pursuant to a construction and management contract awarded to CCA by the Georgia Department of Corrections in September 2010 to manage up to 1,150 male inmates. Construction was completed during the first quarter of 2012 at a total construction cost of approximately $51.0 million. The contract has an initial one-year base term with 24 one-year renewal options. Additionally, the contract provides for a population guarantee of 90% following a 120-day ramp-up period. The Georgia Department of Corrections began transferring inmates into the facility in March 2012.

In September 2011, CCA announced that it entered into a contract with the state of Ohio to purchase the 1,798-bed Lake Erie Correctional Institution located in Conneaut, Ohio. In December 2011, CCA completed the purchase of the Lake Erie facility, which was constructed in 1999, for a purchase price of approximately $73.0 million. CCA also entered into a management contract to manage state of Ohio inmates at this facility, which commenced on January 1, 2012 and has an initial term of twenty years with unlimited renewal options subject to appropriations and mutual agreement. The management contract also provides a guaranteed occupancy of 90% which commenced in March 2012 following a transition period.

In order to retain federal inmate populations CCA currently manages in the 1,154-bed San Diego Correctional Facility, CCA will be required to construct a new facility in the future at a site it is currently developing. The San Diego Correctional Facility is subject to a ground lease with the County of San Diego. Under the provisions of the lease, the facility is divided into different premises whereby, pursuant to an amendment to the ground lease executed in January 2010, ownership of the entire facility reverts to the County upon expiration of the lease on December 31, 2015. As of March 31, 2012, CCA has invested approximately $45.3 million to acquire property, conduct environmental studies, obtain building permits, and complete various other design activities. CCA has developed plans to build a detention facility and a construction timeline that coincides with the expiration of the ground lease with the County of San Diego. CCA currently estimates the total construction cost, inclusive of land and site development costs already incurred, will range from approximately $142.0 million to $150.0 million. CCA plans to use this new facility to house the existing federal inmate populations at the San Diego Correctional Facility. However, CCA can provide no assurance that it will be able to retain these inmate populations.