XML 27 R71.htm IDEA: XBRL DOCUMENT v2.4.0.8
Commitments and Contingencies (Details 2)
In Millions, unless otherwise specified
1 Months Ended 9 Months Ended 9 Months Ended 9 Months Ended 12 Months Ended 48 Months Ended
Jan. 31, 2014
USD ($)
Sep. 30, 2014
USD ($)
T
Mar. 18, 2014
USD ($)
Dec. 31, 2013
USD ($)
Sep. 30, 2014
Prarie State Energy Campus [Member]
mW
Sep. 30, 2014
Monto Coal Pty Limited [Member]
AUD
Sep. 30, 2014
Wilkie Creek [Member]
AUD
Sep. 30, 2013
Gulf Power Company Litigation [Member]
USD ($)
Jan. 19, 2012
Gulf Power Company Litigation [Member]
USD ($)
Sep. 30, 2011
Gulf Power Company Litigation [Member]
USD ($)
Dec. 31, 2007
Gulf Power Company Litigation [Member]
T
Sep. 30, 2014
Oklahoma Lead Litigation [Member]
USD ($)
sites
Dec. 31, 2013
Oklahoma Lead Litigation [Member]
USD ($)
Dec. 31, 2017
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2016
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2015
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2017
Scenario, Forecast [Member]
USD ($)
Loss Contingency [Abstract]                                  
Ownership percentage in subsidiaries           51.00%                      
Damages sought           1,193.2 113.1                    
Class B shareholders claim for dividends payable   42.5                              
Interest on Class B shareholders claim   10.0                              
Damages awarded by the arbitrator to Eagle on some of Eagle's claims     23.4                            
Estimated loss associated with Eagle Mining arbitration       7.8                          
Additional charge recorded as a result of the damages awarded to Eagle in arbitration   15.6                              
Tons shipped subject to contract pricing arbitration   3,600,000                              
Amount disputed pursuant to a contract pricing arbitration proceeding   35.00%                              
Damages sought for alleged past and future tonnage shortfalls                     5,000,000            
Litigation settlement damages awarded to plaintiff                   20.6              
Prejudgement interest                 6.9                
Charge recorded for settlement damages               20.6                  
Charge recorded for prejudgement interest               6.9                  
Number of national priority list sites based on the Superfund Amendments and Reauthorization Act of 1986 at which Gold Fields or the former affiliate, has been named a potentially responsible party (PRP)                       5          
Number of additional national priority list sites in which CERCLA claims were asserted                       13          
Total number of national priority list sites                       18          
Reduced number of national priority list sites due to completion of work, transfer or regulatory inactivity                       8          
Undiscounted environmental clean-up liabilities, total                       70.3 63.8        
Undiscounted environmental clean-up liabilities, current                       29.6 18.3        
Funding of the newly established VEBA                                 310
Initial payment based on the construct of the negotiated settlement 90                                
Payment to Patriot based on the construct of the negotiated settlement 70                                
Payment to the VEBA based on the construct of the negotiated settlement $ 20                         $ 70 $ 75 $ 75  
Capacity of new electricity generation project         1,600                        
Undivided interest percent of new electricity generation project         5.06%