Prarie State Energy Campus [Member]
mW
Jun. 30, 2014
Monto Coal Pty Limited [Member]
AUD
Jun. 30, 2014
Wilkie Creek [Member]
USD ($)
Jan. 19, 2012
Gulf Power Company Litigation [Member]
USD ($)
Dec. 31, 2007
Gulf Power Company Litigation [Member]
T
Jun. 30, 2014
Oklahoma Lead Litigation [Member]
USD ($)
sites
Dec. 31, 2013
Oklahoma Lead Litigation [Member]
USD ($)
Dec. 31, 2017
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2016
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2015
Scenario, Forecast [Member]
USD ($)
Dec. 31, 2017
Scenario, Forecast [Member]
USD ($)
Loss Contingency [Abstract]                                    
Ownership percentage in subsidiaries                 51.00%                  
Damages sought                 1,193.2 $ 113.1                
Class B shareholders claim for unpaid dividends     29.6                              
Interest on Class B shareholders claim for unpaid dividends     5.8                              
Requisite security filed with the court     49.6                              
Damages awarded by the arbitrator to Eagle on some of Eagle's claims         23.4                          
Estimated loss associated with Eagle Mining arbitration           7.8                        
Additional charge recorded as a result of the damages awarded to Eagle in arbitration     15.6                              
Damages sought for alleged past and future tonnage shortfalls                       5,000,000            
Litigation settlement damages awarded to plaintiff             20.6                      
Prejudgement interest                     6.9              
Charge recorded for settlement damages   20.6   20.6                            
Charge recorded for prejudgement interest   6.9   6.9                            
Number of national priority list sites based on the Superfund Amendments and Reauthorization Act of 1986 at which Gold Fields or the former affiliate, has been named a potentially responsible party (PRP)                         5          
Number of additional national priority list sites in which CERCLA claims were asserted                         13          
Total number of national priority list sites                         18          
Reduced number of national priority list sites due to completion of work, transfer or regulatory inactivity                         8          
Undiscounted environmental clean-up liabilities, total                         60.6 63.8        
Undiscounted environmental clean-up liabilities, current                         15.2 18.3        
Funding of the newly established VEBA                                   310
Initial payment based on the construct of the negotiated settlement 90                                  
Payment to Patriot based on the construct of the negotiated settlement 70.0                                  
Payment to the VEBA based on the construct of the negotiated settlement $ 20                           $ 70 $ 75 $ 75  
Capacity of new electricity generation project               1,600                    
Undivided interest percent of new electricity generation project               5.06%