Commitments and Contingencies (Details 1) (USD $)
In Millions, unless otherwise specified
9 Months Ended9 Months Ended
Sep. 30, 2011
Sep. 30, 2010
Jul. 31, 2011
T
Sep. 30, 2011
Prarie State Energy Campus Member [Member]
Dec. 31, 2010
Prarie State Energy Campus Member [Member]
Sep. 30, 2011
Capital Additions [Member]
Long-term Purchase Commitment [Line Items]      
Expenditures for construction of Prairie State Energy Campus$ 29.8$ 52.5 $ 29.8  
Commitments outstanding for capital expenditures, Current     521.4
Investment in Prairie State Energy Campus included in Investments and Other Assets   232.3202.5 
Company's estimated share of total construction costs   250  
Number of tons of coal in the Powder River Basin of Wyoming in which the Company was named the winning bidder  220,000,000   
Commitments outstanding for capital expenditures next year     477.6
Subsidiary Company's Interest in Prairie State Energy Campus5.06%  5.06%  
First coal reserve payment made by the Company  42.1   
Annual coal reserve payments to be made by the Company in July of each of the next four years  $ 42.1