XML 101 R77.htm IDEA: XBRL DOCUMENT v3.23.2
Commitments and Contingencies - Additional Information (Details)
1 Months Ended 6 Months Ended
Apr. 30, 2022
USD ($)
a
Jul. 31, 2021
USD ($)
Sep. 30, 2020
a
Aug. 31, 2019
USD ($)
Jun. 30, 2023
Lawsuit
Plaintiff
Sep. 30, 2022
May 31, 2021
a
Building
Sep. 02, 2020
a
Building
Washington [Member]                
Loss Contingencies [Line Items]                
Wildfires covered area which damaged several residential structures, (in acres) | a     5          
Natural and Cultural Damage Claim [Member]                
Loss Contingencies [Line Items]                
Litigation settlement damages claim amount | $   $ 2,000,000            
Boyds Fire [Member] | Damage from Fire [Member] | Maximum [Member]                
Loss Contingencies [Line Items]                
Loss contingency, damages sought, value | $       $ 4,400,000        
Labor Day Windstorm [Member] | Damage from Fire [Member]                
Loss Contingencies [Line Items]                
Number of residential, commercial and other structures impacted | Building               230
Road fire covered area | a               25,000
Road 11 Fire [Member] | Damage from Fire [Member] | Avista Corp [Member]                
Loss Contingencies [Line Items]                
Loss contingency, damages sought, value | $ $ 5,000,000              
Road fire covered area | a 10,000              
Babb Road Fire [Member] | Damage from Fire [Member]                
Loss Contingencies [Line Items]                
Number of residential, commercial and other structures impacted | Building             220  
Road fire covered area | a             15,000  
Number of lawsuits filed seeking unspecified damages | Lawsuit         9      
Number of subrogation actions filed | Lawsuit         6      
Number of actions on behalf of individual plaintiffs | Plaintiff         2      
Number of class action lawsuit | Lawsuit         1      
System Unit Resource Protection Act [Member] | Natural and Cultural Damage Claim [Member]                
Loss Contingencies [Line Items]                
Increased potential claim | $   $ 6,000,000            
Colstrip [Member]                
Loss Contingencies [Line Items]                
Agreement voting requirement         NorthWestern has initiated arbitration pursuant to the O&O Agreement to resolve these business disagreements, and two actions have been initiated to compel arbitration of those disputes: one by Talen in the Montana Thirteenth Judicial District Court for Yellowstone County, and one by the Western Co-Owners, which is pending in Montana Federal District Court. In light of the ownership transfer agreements discussed below, the Colstrip owners agreed to stay both the litigation and the arbitration through September 29, 2023, at which time the proceedings would resume absent further agreement between the owners.      
Colstrip [Member] | PSE [Member] | Unit 4 [Member]                
Loss Contingencies [Line Items]                
Owners percentage interest         25.00% 25.00%