Equity Return (CenterPoint Energy and Houston Electric)

As of September 30, 2020, CenterPoint Energy and Houston Electric have not recognized an allowed equity return of $144 million on Houston Electric’s true-up balance and certain storm restoration balances because such return will be recognized as it is recovered in future rates. The timing of CenterPoint Energy’s and Houston Electric’s recognition of the equity return will vary each period based on amounts actually collected during that period. The unrecognized equity return will be recognized as it is recovered in rates through 2024. The actual amounts recognized are adjusted at least annually to correct any over-collections or under-collections during the preceding 12 months.
CenterPoint Energy and Houston Electric
Three Months Ended September 30,Nine Months Ended September 30,
2020201920202019
(in millions)
Allowed equity return recognized
$10 $14 $24 $38 

Houston Electric Base Rate Case (CenterPoint Energy and Houston Electric)

On April 5, 2019, and subsequently adjusted in errata filings in May and June 2019, Houston Electric filed its base rate application with the PUCT and the cities in its service area to change its rates, seeking approval for revenue increases of approximately $194 million, among other requests. On January 23, 2020, Houston Electric filed a Stipulation and Settlement Agreement with the PUCT that provided for the following, among other things:

an overall revenue requirement increase of approximately $13 million;

an ROE of 9.4%;

a capital structure of 57.5% debt/42.5% equity;

a refund of unprotected EDIT of $105 million plus carrying costs over approximately 30-36 months; and

recovery of all retail transmission related costs through the TCRF.

Also, Houston Electric is not required to make a one-time refund of capital recovery from its TCOS and DCRF mechanisms. Future TCOS filings will take into account both ADFIT and EDIT until the final order from Houston Electric’s next base rate proceeding. No rate base items are required to be written off; however, approximately $12 million in rate case expenses were written off in 2019. A base rate application must be filed for Houston Electric no later than four years from the date of the PUCT’s final order in the proceeding. Additionally, Houston Electric will not file a DCRF in 2020, nor will a subsequent separate proceeding with the PUCT be instituted regarding EDIT on Houston Electric’s securitized assets. Furthermore, under the terms of the Stipulation and Settlement Agreement, Houston Electric agreed to adopt certain ring-fencing measures to increase its financial separateness from CenterPoint Energy. The PUCT approved the Stipulation and Settlement Agreement at its February 14, 2020 open meeting and issued a final order on March 9, 2020. The PUCT declined to impose a dividend restriction in the final order. The rates were implemented on April 23, 2020.

CenterPoint Energy and Houston Electric record pre-tax expense for (i) probable disallowances of capital investments and (ii) customer refund obligations and costs deferred in regulatory assets when recovery of such amounts is no longer considered probable.
COVID-19 Regulatory Matters

Governors, public utility commissions and other authorities in the states in which the Registrants operate have issued a number of different orders related to the COVID-19 pandemic, including orders addressing customer non-payment and disconnection. Although the disconnect moratoriums have either expired or will expire during the fourth quarter of 2020 in certain of the Registrants’ service territories, CenterPoint Energy continues to support those customers who may need payment assistance, arrangements or extensions.

On March 26, 2020, the PUCT issued two orders related to COVID-19 issues that affect Houston Electric. First, the PUCT issued an order related to accrual of regulatory assets granting authority for utilities to record as a regulatory asset expenses resulting from the effects of COVID-19. In the order, the PUCT noted that it will consider whether a utility’s request for recovery of the regulatory asset is reasonable and necessary in a future proceeding. Second, the PUCT issued an order related to the COVID-19 ERP, as modified, which, in light of the disaster declarations issued by the governor of Texas, authorized a customer assistance program for certain residential customers of electric service in areas of Texas open to customer choice, which includes Houston Electric’s service territory. 

The PUCT issued an order on August 27, 2020 to conclude the COVID-19 ERP. The PUCT determined that enrollment in the COVID-19 ERP would end on August 31, 2020 and benefits under the program ended on September 30, 2020. Final claims for reimbursement must be submitted to the transmission and distribution utilities by November 30, 2020. The transmission and distribution utilities must file a tariff rider cancellation seven days before the date on which it is estimated that revenues from the COVID-19 ERP are approximately equal to its program expenses. Final program reports must be submitted to the PUCT by January 15, 2021. The COVID-19 ERP allows for any over/under collection of program expenses to be recorded as a regulatory asset or liability. Houston Electric may seek recovery of such regulatory asset or liability in its next DCRF, TCRF or base rate case proceeding. CenterPoint Energy’s and Houston Electric’s COVID-19 ERP regulatory assets were $10 million as of September 30, 2020.

Commissions in all of Indiana Electric’s and CenterPoint Energy’s and CERC’s NGD service territories have either (1) issued orders to record a regulatory asset for incremental bad debt expenses related to COVID-19, including costs associated with the suspension of disconnections and payment plans or (2) provided authority to recover bad debt expense through an existing tracking mechanism. CenterPoint Energy and CERC have recorded estimated incremental uncollectible receivables to the associated regulatory asset of $16 million and $14 million, respectively, as of September 30, 2020.

In some of the states in which the Registrants operate, public utility commissions have authorized utilities to employ deferred accounting authority for certain COVID-19 related costs which ensure the safety and health of customers, employees, and contractors, that would not have been incurred in the normal course of business. CERC’s NGD service territories in Minnesota and Arkansas will include any offsetting savings in the deferral. Other jurisdictions where the Registrants operate may require them to offset the deferral with savings as well.

ERCOT Loan Agreement (CenterPoint Energy and Houston Electric)

On April 13, 2020, in connection with the PUCT’s COVID-19 ERP, Houston Electric entered into a no-interest loan agreement with ERCOT pursuant to which ERCOT loaned Houston Electric approximately $5 million to provide for an initial fund balance for reimbursement. As of September 30, 2020, $5 million of the loan was still outstanding. The ERCOT loan repayment date is on or before December 15, 2020.