Exploratory Well Costs
12 Months Ended
Dec. 31, 2020
Extractive Industries [Abstract]  
Exploratory Well Costs Exploratory Well Costs
The Company capitalizes exploratory well and project costs until a determination is made that the well or project has either found proved reserves, is impaired or is sold. The Company's capitalized exploratory well and project costs are included in proved properties in the consolidated balance sheets. If the exploratory well or project is determined to be impaired, the impaired costs are recorded as exploration and abandonments expense.
The changes in capitalized exploratory well cost are as follows:
 Year Ended December 31,
 20202019
 (in millions)
Beginning capitalized exploratory well costs$660 $509 
Additions to exploratory well costs pending the determination of proved reserves1,163 2,172 
Reclassification due to determination of proved reserves(1,325)(2,011)
Disposition of assets— (6)
Exploratory well costs charged to exploration and abandonment expense— (4)
Ending capitalized exploratory well costs$498 $660 
Aging of capitalized exploratory costs and the number of projects for which exploratory well costs have been capitalized for a period greater than one year, based on the date of drilling was completed, are as follows:
 Year Ended December 31,
 202020192018
 (in millions, except well counts)
Capitalized exploratory well costs that have been suspended:
One year or less$495 $660 $509 
More than one year— — 
$498 $660 $509 
Number of projects with exploratory well costs that have been suspended for a period greater than one year (a)— — 
______________________
(a)The one exploratory well that has been suspended for a period greater than one year is scheduled to be completed during the first half of 2021.