Schedule of Acquisitions of Solar Projects (Detail)
$ in Millions
3 Months Ended
Mar. 31, 2021
USD ($)
MW
Mar. 31, 2020
USD ($)
Property Plant And Equipment [Line Items]    
Project Cost $ 23 $ 8
Acquisition of Nonregulated Solar Project Trask in South Carolina    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2020-05  
Date Agreement Closed 2020-10  
Project Cost [1] $ 22  
Date of Commercial Operations March 2021  
MW Capacity | MW 12  
Acquisition of Nonregulated Solar Project Hardin II in Ohio    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2020-08  
Project Cost [1] $ 300  
Date of Commercial Operations Expected 2023  
MW Capacity | MW 150  
Virginia Electric and Power Company    
Property Plant And Equipment [Line Items]    
Project Cost $ 10 $ 6
Virginia Electric and Power Company | Acquisition of Nonregulated Solar Project Bookers Mill in Virginia    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2021-02  
Project Cost [1] $ 200  
Date of Commercial Operations Expected 2023  
MW Capacity | MW 127  
[1] Includes acquisition cost