Regulatory Matters - Summary of Virginia Power Electric Transmission Project Applied (Detail) - Virginia Electric and Power Company - Virginia Regulation
$ in Millions
1 Months Ended 12 Months Ended
Jun. 30, 2018
kV
Dec. 31, 2018
USD ($)
mi
kV
Jan. 31, 2019
USD ($)
Public Utilities, General Disclosures [Line Items]      
Capacity of transmission line (kV)   115  
Transmission Lines Between Possum Point Switching Station And Novec's Smoketown Delivery Point [Member]      
Public Utilities, General Disclosures [Line Items]      
Application Date   2017-06  
Approval Date   2018-02  
Capacity of transmission line (kV)   230  
Length of kV line (miles) | mi   9  
The total estimated capital investment | $   $ 20  
Transmission Line Between Dooms Substation And Valley Substation [Member]      
Public Utilities, General Disclosures [Line Items]      
Application Date   2017-09  
Approval Date   2018-09  
Capacity of transmission line (kV)   500  
Length of kV line (miles) | mi   18  
The total estimated capital investment | $   $ 65  
Transmission Line Between Idylwood and Tysons Substations      
Public Utilities, General Disclosures [Line Items]      
Application Date   2017-11  
Approval Date   2018-09  
Capacity of transmission line (kV) 230 230  
Length of kV line (miles) | mi   4  
The total estimated capital investment | $   $ 125 $ 68
Transmission Lines Between Chesterfield and Hopewell Substations      
Public Utilities, General Disclosures [Line Items]      
Application Date   2018-05  
Approval Date   2018-11  
Capacity of transmission line (kV)   230  
Length of kV line (miles) | mi   8  
The total estimated capital investment | $   $ 30  
Transmission Lines Between Chesterfield and Lakeside Substations      
Public Utilities, General Disclosures [Line Items]      
Application Date   2018-05  
Approval Date   2018-12  
Capacity of transmission line (kV)   230  
Length of kV line (miles) | mi   21  
The total estimated capital investment | $   $ 35  
Transmission Lines Between Landstown and Thrasher Substations      
Public Utilities, General Disclosures [Line Items]      
Application Date   2018-06  
Approval Date   2018-12  
Capacity of transmission line (kV)   230  
Length of kV line (miles) | mi   8.5  
The total estimated capital investment | $   $ 20  
Transmission Line In Alleghany Country Virginia And Covington Virginia      
Public Utilities, General Disclosures [Line Items]      
Application Date   2018-08  
Capacity of transmission line (kV)   138  
Length of kV line (miles) | mi   5  
The total estimated capital investment | $   $ 15  
Build a new substation and connect three existing transmission lines thereto in Fluvanna County, Virginia      
Public Utilities, General Disclosures [Line Items]      
Application Date   2018-10  
Capacity of transmission line (kV)   230  
The total estimated capital investment | $   $ 30  
Maximum | Build a new substation and connect three existing transmission lines thereto in Fluvanna County, Virginia      
Public Utilities, General Disclosures [Line Items]      
Length of kV line (miles) | mi   1