COMMITMENTS AND CONTINGENCIES
6 Months Ended
Jun. 30, 2022
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES
Sempra Infrastructure
Energía Costa Azul
We describe below certain land and customer disputes and permit challenges affecting our ECA Regas Facility. Certain of these land disputes involve land on which portions of the ECA LNG liquefaction facilities are proposed to be situated or on which portions of the ECA Regas Facility that would be necessary for the operation of the proposed ECA LNG liquefaction facilities are situated. One or more unfavorable final decisions on these disputes or challenges could materially adversely affect our existing natural gas regasification operations and proposed natural gas liquefaction projects at the site of the ECA Regas Facility and have a material adverse effect on Sempra’s business, results of operations, financial condition, cash flows and/or prospects.
Land Disputes. Sempra Infrastructure has been engaged in a long-running land dispute relating to property adjacent to its ECA Regas Facility that allegedly overlaps with land owned by the ECA Regas Facility (the facility, however, is not situated on the land that is the subject of this dispute), as follows:
A claimant to the adjacent property filed complaints in the federal Agrarian Court challenging the refusal of SEDATU in 2006 to issue title to him for the disputed property. In November 2013, the federal Agrarian Court ordered that SEDATU issue the requested title to the claimant and cause it to be registered. Both SEDATU and Sempra Infrastructure challenged the ruling due to lack of notification of the underlying process. In May 2019, a federal court in Mexico reversed the ruling and ordered a retrial, which is pending resolution.
In a separate proceeding, the claimant filed suit to reinitiate an administrative procedure at SEDATU to obtain the property title that was previously dismissed. In April 2021, the Agrarian Court ordered that the administrative procedure be restarted. The proceeding in the Agrarian Court has concluded; however, the administrative procedure at SEDATU may continue if SEDATU decides to reopen the matter.
In addition, four cases involving two adjacent areas of real property on which part of the ECA Regas Facility is situated, each brought by a single plaintiff or her descendants, remain pending against the facility, as follows:
The first disputed area is subject to a claim in the federal Agrarian Court that has been ongoing since 2006, in which the plaintiff seeks to annul the property title for a portion of the land on which the ECA Regas Facility is situated and to obtain possession of a different parcel that allegedly overlaps with the site of the ECA Regas Facility. The proceeding, which seeks an order that SEDATU annul the ECA Regas Facility’s competing property title, was initiated in 2006 and, in July 2021, a decision was issued in favor of the ECA Regas Facility. The plaintiff appealed, and in February 2022, the appellate court confirmed the ruling in favor of the ECA Regas Facility and dismissed the appeal. The plaintiff filed a final federal appeal against the appellate court ruling. A final ruling from the Federal Collegiate Circuit Court is pending.
The second disputed area is a parcel adjacent to the ECA Regas Facility that allegedly overlaps with land on which the ECA Regas Facility is situated, which is subject to a claim in the federal Agrarian Court and two claims in Mexican civil courts. The ECA Regas Facility first bought the property from the federal government in 2003; however, to resolve an ownership controversy, in 2008, the ECA Regas Facility reached a financial settlement with the plaintiff to eliminate an adverse claim to its title. Nevertheless, the plaintiff sued in 2013 for the nullity of both titles. The Agrarian Court ruled in favor of the plaintiff in May 2021, nullifying the first property title. Sempra Infrastructure appealed the ruling in July 2021. In May 2022, Sempra Infrastructure won the appeal and the plaintiff’s claims were dismissed, which the plaintiff has appealed. The ECA Regas Facility continues to hold the second property title to the land. The two civil court proceedings, which seek to invalidate the contract by which the ECA Regas Facility purchased for the second time the applicable parcel of land on which the ECA Regas Facility is situated on the grounds that the purchase price was allegedly unfair, are progressing at different stages. In the first civil case, initiated in 2013, the court ruled in favor of the ECA Regas Facility, and the final decision was affirmed on a federal appeal. The descendants of the same plaintiff filed the second civil case in 2019, which was dismissed by the court. However, the dismissal has been appealed, which is pending the appellate court’s ruling. In April 2022, the ECA Regas Facility entered into a settlement agreement with the plaintiff, whereby the plaintiff has agreed to recognize the ECA Regas Facility as the sole owner of the property and waive any current or future rights over the property, or any other properties related to the ECA Regas Facility. The settlement agreement is pending court approval and would definitively resolve all three pending cases.
Environmental and Social Impact Permits. Several administrative challenges are pending before Mexico’s Secretariat of Environment and Natural Resources (the Mexican environmental protection agency) and Federal Tax and Administrative Courts, seeking revocation of the environmental impact authorization issued to the ECA Regas Facility in 2003. These cases generally allege that the conditions and mitigation measures in the environmental impact authorization are inadequate and challenge findings that the activities of the terminal are consistent with regional development guidelines.
In 2018 and 2021, three related claimants filed separate challenges in the federal district court in Ensenada, Baja California in relation to the environmental and social impact permits issued by each of ASEA and SENER to ECA LNG authorizing natural gas liquefaction activities at the ECA Regas Facility, as follows:
In the first case, the court issued a provisional injunction in September 2018. In December 2018, ASEA approved modifications to the environmental permit that facilitate the development of the proposed natural gas liquefaction facility in two phases. In May 2019, the court canceled the provisional injunction. The claimant appealed the court’s decision canceling the injunction but was not successful. The claimant’s underlying challenge to the permits remains pending.
In the second case, the initial request for a provisional injunction was denied. That decision was reversed on appeal in January 2020, resulting in the issuance of a new injunction against the permits that were issued by ASEA and SENER. This injunction has uncertain application absent clarification by the court. The claimants petitioned the court to rule that construction of natural gas liquefaction facilities violated the injunction, and in February 2022, the court ruled in favor of the ECA Regas Facility, meaning that the natural gas liquefaction activities have not been affected. The claimants have appealed this ruling.
In the third case, a group of residents filed a complaint in June 2021 against various federal and state authorities alleging deficiencies in the public consultation process for the issuance of the permits. The request for an initial injunction was denied and the claimants have appealed, which is pending the appellate court’s ruling.
Customer Dispute. In May 2020, the two third-party capacity customers at the ECA Regas Facility, Shell Mexico and Gazprom, asserted that a 2019 update of the general terms and conditions for service at the facility, as approved by the CRE, resulted in a breach of contract by Sempra Infrastructure and a force majeure event. In July 2020, Shell Mexico submitted a request for arbitration of the dispute and Gazprom joined the proceeding, and a hearing was held in October 2021. The International Court of Arbitration issued a final, non-appealable decision dated April 27, 2022 in favor of Sempra Infrastructure dismissing all claims and confirming the contracts remain in force. Shell Mexico submitted a request to the International Court of Arbitration, and Gazprom joined the request, to issue an additional decision, asserting that two of the claims were not addressed in the ruling. Sempra Infrastructure filed a response and requested that any additional decision by the International Court of Arbitration be incorporated into the original decision as one, final ruling for clarity to aid in enforcement proceedings should they become necessary.
Citing the alleged breach, Shell Mexico stopped making payments under its LNG storage and regasification agreement. Due to nonpayment, Sempra Infrastructure drew against Shell Mexico’s letters of credit provided as payment security until they were fully exhausted in March 2022 and this customer has not resumed making payments. Although Gazprom had previously been making regular monthly payments under its LNG storage and regasification agreement, Sempra Infrastructure drew against and fully exhausted Gazprom’s letters of credit in April 2022 due to Gazprom’s non-renewal of such letters of credit as required under the agreement. Gazprom has not paid its invoices since March 2022, so funds drawn from the letters of credit have been used to fully offset such nonpayment. We expect that these funds will provide payment security from Gazprom through the end of 2024.
In addition to the arbitration proceeding, Shell Mexico also filed constitutional claims against the CRE’s approval of the general terms and conditions for service at the facility and against the issuance of the liquefaction permit. Shell Mexico’s request for an injunction against the general terms and conditions was denied, and the ruling was upheld on appeal. The request for an injunction against the liquefaction permit was denied, and the decision was vacated and remanded on appeal to the First District Court in Administrative Matters, which again denied the injunction. The case on the injunction request was then heard again by the appellate court. A hearing was held on the merits and a decision is pending.
Sonora Pipeline
Guaymas-El Oro Segment. Sempra Infrastructure’s Sonora natural gas pipeline consists of two segments, the Sasabe-Puerto Libertad-Guaymas segment and the Guaymas-El Oro segment. Each segment has its own service agreement with the CFE. In 2015, the Yaqui tribe, with the exception of some members living in the Bácum community, granted its consent and a right-of-way easement agreement for the construction of the Guaymas-El Oro segment of the Sonora natural gas pipeline that crosses its territory. Representatives of the Bácum community filed a legal challenge in Mexican federal court demanding the right to withhold consent for the project, the stoppage of work in the Yaqui territory and damages. In 2016, the judge granted a suspension order that prohibited the construction of such segment through the Bácum community territory. Because the pipeline does not pass through the Bácum community, Sempra Infrastructure did not believe the 2016 suspension order prohibited construction in the remainder of the Yaqui territory. Construction of the Guaymas-El Oro segment was completed, and commercial operations began in May 2017.
Following the start of commercial operations of the Guaymas-El Oro segment, Sempra Infrastructure reported damage to the Guaymas-El Oro segment of the Sonora pipeline in the Yaqui territory that has made that section inoperable since August 2017 and, as a result, Sempra Infrastructure declared a force majeure event. In 2017, an appellate court ruled that the scope of the 2016 suspension order encompassed the wider Yaqui territory, which has prevented Sempra Infrastructure from making repairs to put the pipeline back in service. In July 2019, a federal district court ruled in favor of Sempra Infrastructure and held that the Yaqui tribe was properly consulted and that consent from the Yaqui tribe was properly received. Representatives of the Bácum community appealed this decision, causing the suspension order preventing Sempra Infrastructure from repairing the damage to the Guaymas-El Oro segment of the Sonora pipeline in the Yaqui territory to remain in place until the appeals process is exhausted. In December 2021, the court of appeals referred the matter to Mexico’s Supreme Court. In June 2022, the Supreme Court remanded the case back to the court of appeals for final resolution.
Sempra Infrastructure exercised its rights under the contract, which included seeking force majeure payments for the two-year period such force majeure payments were required to be made, which ended in August 2019.
In July 2019, the CFE filed a request for arbitration generally to nullify certain contract terms that provide for fixed capacity payments in instances of force majeure and made a demand for substantial damages in connection with the force majeure event. In September 2019, the arbitration process ended when Sempra Infrastructure and the CFE reached an agreement to restart natural gas transportation service on the earlier of completion of repair of the damaged pipeline or January 15, 2020, and to modify the tariff structure and extend the term of the contract by 10 years. Subsequently, Sempra Infrastructure and the CFE agreed to extend the service start date multiple times, most recently to November 30, 2022. Under the revised agreement, the CFE will resume making payments only when the damaged section of the Guaymas-El Oro segment of the Sonora pipeline is repaired. If the pipeline is not repaired by November 30, 2022, and the parties do not agree on a new service start date, Sempra Infrastructure retains the right to terminate the contract and seek to recover its reasonable and documented costs and lost profits. Discussions with the CFE regarding the future of the pipeline are underway in accordance with a non-binding MOU announced in January 2022 that, among other matters, addresses efforts to restart service on the pipeline. In July 2022, Sempra Infrastructure and the CFE entered into a Shareholders’ Agreement that establishes a framework for a JV between the parties to work on restarting service on the pipeline, including the potential re-routing of a portion of the pipeline. This agreement is subject to a number of conditions to be satisfied before it becomes effective, including regulatory and corporate authorizations.
At June 30, 2022, Sempra Infrastructure had $426 million in PP&E, net, related to the Guaymas-El Oro segment of the Sonora pipeline, which could be subject to impairment if Sempra Infrastructure is unable to make such repairs (which have not
commenced) or re-route a portion of the pipeline (which has not been agreed to by the parties, but is subject to negotiation pursuant to a non-binding MOU and a Shareholders’ Agreement, as described above) and resume operations or if Sempra Infrastructure terminates the contract and is unable to obtain recovery, which in each case could have a material adverse effect on Sempra’s business, results of operations, financial condition, cash flows and/or prospects.Sasabe-Puerto Libertad-Guaymas Segment. In June 2014, Sempra Infrastructure and a landowner agreed to enter into a voluntary right-of-way easement agreement for the construction and operation of a seven-mile section of the 314-mile Sasabe-Puerto Libertad-Guaymas segment of the Sonora natural gas pipeline on the landowner’s property. However, in 2015, the landowner filed a complaint demanding the easement agreement be nullified. In September 2021, a definitive and non-appealable judgment was issued declaring the easement agreement nullified and ordering the removal of the pipeline from the landowner’s property. The execution of the judgment is suspended as a result of an amparo lawsuit filed by the CFE as an interested third party that did not participate in the litigation. Sempra Infrastructure filed a special judicial action asking the civil court to acknowledge the existence of the easement and to determine the consideration the landowner should receive in exchange for the easement. In July 2022, Sempra Infrastructure and the landowner entered into a new easement agreement approved by the court for the seven-mile section on the landowner’s property, thus bringing this case to definitive conclusion.
Regulatory and Other Actions by the Mexican Government
We describe below certain actions by the Mexican government that could have a material impact on the energy sector in Mexico. Sempra Infrastructure and other parties affected by these resolutions, orders, decrees, regulations and proposed amendments to Mexican law have challenged them by filing amparo and other claims, some of which have been granted injunctive relief. The court-ordered injunctions or suspensions provide temporary relief until Mexico’s federal district court or Supreme Court ultimately resolves the amparo and other claims. An unfavorable decision on one or more of these amparo or other challenges or the potential for extended disputes may impact our ability to operate our facilities at existing levels or at all, may result in increased costs for Sempra Infrastructure and its customers, may adversely affect our ability to develop new projects, may result in decreased revenues and cash flows, and may negatively impact our ability to recover the carrying values of our investments in Mexico, any of which may have a material adverse effect on our business, results of operations, financial condition, cash flows and/or prospects.
Transmission Rates for Legacy Generation Facilities. In May 2020, the CRE approved an update to the transmission rates included in legacy renewable and cogeneration energy contracts based on the claim that the legacy transmission rates did not reflect fair and proportional costs for providing the applicable services and, therefore, created inequitable competitive conditions. Three of Sempra Infrastructure’s renewable energy facilities (Don Diego Solar, Border Solar and Ventika) are currently holders of contracts with such legacy rates, and under the terms of these contracts any increases in the transmission rates would be passed through directly to their customers. These renewable energy facilities sought and obtained injunctive relief but were required to guarantee the difference in tariffs. The three facilities obtained favorable resolutions from a lower court and the CRE appealed those decisions, which were definitively affirmed in favor of the Don Diego Solar, Border Solar and Ventika facilities, whereby the injunctions were made permanent, the regulations were declared unconstitutional, and the guarantee was determined to not be required. The resolution is definitive and final.
Offtakers of Legacy Generation Permits. In October 2020, the CRE approved a resolution to amend the rules for the inclusion of new offtakers of legacy generation and self-supply permits (the Offtaker Resolution), which became effective immediately. The Offtaker Resolution prohibits self-supply permit holders from adding new offtakers that were not included in the original development or expansion plans, making modifications to the amount of energy allocated to the named offtakers, and including load centers that have entered into a supply arrangement under Mexico’s Electricity Industry Law. Don Diego Solar, Border Solar and Ventika are holders of self-supply permits and are impacted by the Offtaker Resolution. In January 2022, Don Diego Solar and Border Solar obtained a favorable resolution from a Mexican federal district court and the CRE appealed that decision. If Sempra Infrastructure is not able to obtain legal protection for these impacted facilities, Sempra Infrastructure expects it will sell Border Solar’s capacity and a portion of Don Diego Solar’s capacity affected by the Offtaker Resolution into the spot market. Currently, prices in the spot market are higher than the fixed prices in the PPAs that were entered into through self-supply permits, but these markets are subject to significant volatility. At June 30, 2022, Sempra Infrastructure had $14 million in other intangible assets, net, related to these self-supply permits previously granted by the CRE and impacted by the Offtaker Resolution that could be subject to impairment if Sempra Infrastructure is unable to obtain adequate legal protection. Sempra Infrastructure has filed lawsuits against the Offtaker Resolution and received injunctive relief pending final resolution.Amendments to Mexico’s Electricity Industry Law. In March 2021, the Mexican government published a decree with amendments to Mexico’s Electricity Industry Law that include some public policy changes, including establishing priority of dispatch for CFE plants over privately owned plants. According to the decree, these amendments were to become effective on March 10, 2021, and SENER, the CRE and CENACE were to have 180 calendar days to modify, as necessary, all resolutions, policies, criteria, manuals and other regulations applicable to the power industry to conform with this decree. However, a Mexican court issued a suspension of the amendments on March 19, 2021. In April 2022, the Mexican Supreme Court resolved an action of unconstitutionality filed by a group of senators against the amended Electricity Industry Law, but the qualified majority of eight votes out of 11 as is required in matters involving constitutionality was not reached and the proceeding was dismissed, which means that the Mexican Supreme Court did not issue a binding precedent and the amended Electricity Industry Law remains in force. Sempra Infrastructure filed three lawsuits against the amendments to the Electricity Industry Law and, in each of them, Sempra Infrastructure obtained a favorable judgment of the first instance in the lower courts, which has been appealed. If the proposed amendments are affirmed by the lower courts or by the Mexican Supreme Court (which in these cases would only require a simple majority vote), the CRE may be required to revoke self-supply permits granted under the former electricity law, which were grandfathered when the new Electricity Industry Law was enacted, under a legal standard that is ambiguous and not well defined under the law.Amendments to Mexico’s Hydrocarbons Law. In May 2021, amendments to Mexico’s Hydrocarbons Law were published and became effective. The amendments grant SENER and the CRE additional powers to suspend and revoke permits related to the midstream and downstream sectors. Suspension of permits will be determined by SENER or the CRE when a danger to national security, energy security, or to the national economy is foreseen. Likewise, new grounds for the revocation of permits are in place if the permit holder (i) carries out its activity with illegally imported products; (ii) fails, on more than one occasion, to comply with the provisions applicable to quantity, quality and measurement of the products; or (iii) modifies the technical conditions of its infrastructure without authorization. Additionally, in the case of existing permits, authorities will revoke those permits that fail to comply with the minimum storage requirements established by SENER or fail to comply with requirements or violate provisions established by the amended Hydrocarbons Law. All the Sempra Infrastructure entities participating in the Mexico hydrocarbons sector filed lawsuits against the initiative to reform the Hydrocarbons Law. In 2021, district courts issued judgments that the amendments do not affect the interests of the companies at this time and, as a result, dismissed the amparo lawsuits, including the lawsuits filed by Sempra Infrastructure entities. The Sempra Infrastructure entities have appealed these judgments. The Circuit Courts upheld the dismissal of the amparo lawsuits, except one that is pending resolution.Proposed Constitutional Reform in Mexico. In September 2021, the President of Mexico presented a constitutional reform initiative with the stated goal of preserving energy security and self-sufficiency, and a continuous supply of electricity to the country’s population, as a condition for guaranteeing national security and the human right to a decent life. The CRE and the National Commission of Hydrocarbons would be dissolved, and their functions would be carried out by SENER. CENACE would be reinstated to the CFE, and the CFE would be responsible for generating, conducting, transforming, distributing and supplying electricity, and would be the only entity allowed to commercialize electric energy in Mexico. Electricity generation permits and contracts for the sale of electricity and RECs to the CFE, including permits at all of Sempra Infrastructure’s operational power generation facilities, would be canceled. The public electricity supply service would be provided exclusively by the CFE, which may acquire up to 46% of required energy from the private sector. Only certain private power plants would be permitted to continue generating electricity and compete to offer the CFE the lowest production costs. On April 17, 2022, the Chamber of Deputies in Mexico rejected the proposed constitutional reform.
Other Litigation
RBS Sempra Commodities
Sempra holds an equity method investment in RBS Sempra Commodities, a limited liability partnership in the process of being liquidated. In 2015, liquidators filed a claim in the High Court of Justice against RBS (now NatWest Markets plc, our partner in the JV) and Mercuria Energy Europe Trading Limited (the Defendants) on behalf of 10 companies (the Liquidating Companies) that engaged in carbon credit trading via chains that included a company that traded directly with RBS SEE, a subsidiary of RBS Sempra Commodities. The claim alleges that the Defendants’ participation in the purchase and sale of carbon credits resulted in the Liquidating Companies’ carbon credit trading transactions creating a VAT liability they were unable to pay, and that the Defendants are liable to provide for equitable compensation due to dishonest assistance and compensation under the U.K. Insolvency Act of 1986. Trial on the matter was held in June and July of 2018. In March 2020, the High Court of Justice rendered its judgment mostly in favor of the Liquidating Companies and awarded damages of approximately £45 million (approximately $55 million in U.S. dollars at June 30, 2022), plus costs and interest. In October 2020, the High Court of Justice assessed costs and interest to be approximately £21 million (approximately $26 million in U.S. dollars at June 30, 2022) as of that date, with interest continuing to accrue. The Defendants appealed and, in May 2021, the Court of Appeal set aside the High Court of Justice’s decision and ordered a retrial. In July 2022, the Supreme Court of the U.K. denied the Liquidating Companies application for permission to appeal the Court of Appeal’s decision. No date has been scheduled for the retrial. J.P. Morgan Chase & Co., which acquired RBS SEE and later sold it to Mercuria Energy Group, Ltd., previously notified us that Mercuria Energy
Group, Ltd. has sought indemnity for the claim, and J.P. Morgan Chase & Co. has in turn sought indemnity from Sempra and RBS.
In the second quarter of 2021, we reduced our estimate of our obligations to settle pending VAT matters and related legal costs by $50 million in Equity Earnings on Sempra’s Condensed Consolidated Statement of Operations based on the settlement with Her Majesty’s Revenue and Customs (U.K.’s Revenue and Customs Department) on the First-Tier Tribunal case and revised assumptions on the High Court of Justice case.
Asbestos Claims Against EFH Subsidiaries
Certain EFH subsidiaries that we acquired as part of the merger of EFH with an indirect subsidiary of Sempra were defendants in personal injury lawsuits brought in state courts throughout the U.S. These cases alleged illness or death as a result of exposure to asbestos in power plants designed and/or built by companies whose assets were purchased by predecessor entities to the EFH subsidiaries, and generally assert claims for product defects, negligence, strict liability and wrongful death. They sought compensatory and punitive damages. As of August 1, 2022, one lawsuit is pending. Additionally, in connection with the EFH bankruptcy proceeding, approximately 28,000 proofs of claim were filed on behalf of persons who allege exposure to asbestos under similar circumstances and assert the right to file such lawsuits in the future. None of these claims or lawsuits were discharged in the EFH bankruptcy proceeding. The costs to defend or resolve these lawsuits and the amount of damages that may be imposed or incurred could have a material adverse effect on Sempra’s results of operations, financial condition, cash flows and/or prospects.
Ordinary Course Litigation
We are also defendants in ordinary routine litigation incidental to our businesses, including personal injury, employment litigation, product liability, property damage and other claims. Juries have demonstrated an increasing willingness to grant large awards, including punitive damages, in these types of cases.
LEASES
We discuss leases further in Note 16 of the Notes to Consolidated Financial Statements in the Annual Report.
Lessee Accounting
We have operating and finance leases for real and personal property (including office space, land, fleet vehicles, machinery and equipment, warehouses and other operational facilities) and PPAs with renewable energy, energy storage and peaker plant facilities.
Leases That Have Not Yet Commenced
SDG&E has entered into three energy storage tolling agreements, of which SDG&E expects two will commence in the third quarter of 2022 and one will commence in the second quarter of 2023. SDG&E expects the future minimum lease payments to be $7 million in 2022, $18 million in each of 2023 through 2026 and $101 million thereafter until expiration at various dates from 2032 through 2033.
SoCalGas has entered into a fleet vehicle agreement, under which SoCalGas expects leases will commence in the second half of 2022 through the first half of 2023. SoCalGas expects the future minimum lease payments to be $2 million in each of 2023 through 2026 and $10 million thereafter until expiration at various dates from 2030 through 2031.
Lessor Accounting
Sempra Infrastructure is a lessor for certain of its natural gas and ethane pipelines, compressor stations, liquid petroleum gas storage facilities, a rail facility and liquid fuels terminals, which we account for as operating or sales-type leases.
We provide information below for leases for which we are the lessor.
LESSOR INFORMATION ON THE CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS – SEMPRA
(Dollars in millions)
Three months ended June 30,Six months ended June 30,
2022202120222021
Sales-type leases:
Interest income$$— $$— 
Total revenues from sales-type leases(1)
$$— $$— 
Operating leases:
Fixed lease payments$70 $59 $140 $112 
Variable lease payments
Total revenues from operating leases(1)
$73 $60 $144 $113 
Depreciation expense$14 $12 $27 $22 
(1)    Included in Revenues: Energy-Related Businesses on the Condensed Consolidated Statements of Operations.
CONTRACTUAL COMMITMENTS
We discuss below significant changes in the first six months of 2022 to contractual commitments discussed in Notes 1 and 16 of the Notes to Consolidated Financial Statements in the Annual Report.
LNG Purchase Agreement
Sempra Infrastructure has a SPA for the supply of LNG to the ECA Regas Facility. The commitment amount is calculated using a predetermined formula based on estimated forward prices of the index applicable from 2022 to 2029. Although this agreement specifies a number of cargoes to be delivered, under its terms, the supplier may divert certain cargoes, which would reduce amounts paid under the agreement by Sempra Infrastructure. At June 30, 2022, we expect the commitment amount to decrease by $208 million in 2022 and then increase by $227 million in 2023, $203 million in 2024, $191 million in 2025, $175 million in 2026 and by $421 million thereafter (through contract termination in 2029) compared to December 31, 2021, reflecting changes in estimated forward prices since December 31, 2021 and actual transactions for the first six months of 2022. These LNG commitment amounts are based on the assumption that all LNG cargoes, less those already confirmed to be diverted, under the agreement are delivered. Actual LNG purchases in the current and prior years have been significantly lower than the maximum amount provided under the agreement due to the customer electing to divert cargoes as allowed by the agreement.
ENVIRONMENTAL ISSUES
We disclose any proceeding under environmental laws to which a government authority is a party when the potential monetary sanctions, exclusive of interest and costs, exceed the lesser of $1 million or 1% of current assets, which was $59 million for Sempra, $18 million for SDG&E and $15 million for SoCalGas at June 30, 2022.