XML 39 R16.htm IDEA: XBRL DOCUMENT v3.8.0.1
REGULATORY MATTERS
9 Months Ended
Sep. 30, 2017
Regulated Operations [Abstract]  
Regulatory Matters SAN ONOFRE NUCLEAR GENERATING STATION
We provide below updates to ongoing matters related to SONGS, a nuclear generating facility near San Clemente, California that ceased operations in June 2013, and in which SDG&E has a 20-percent ownership interest. We discuss SONGS further in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report.
REPLACEMENT STEAM GENERATORS
As part of the Steam Generator Replacement Project, the steam generators were replaced in SONGS Units 2 and 3, and the Units returned to service in 2010 and 2011, respectively. Both Units were shut down in early 2012 after a water leak occurred in the Unit 3 steam generator. Edison, the majority owner and operator of SONGS, concluded that the leak was due to unexpected wear from tube-to-tube contact. At the time the leak was identified, Edison also inspected and tested Unit 2 and subsequently found unexpected tube wear in Unit 2’s steam generator. These issues with the steam generators ultimately resulted in Edison’s decision to permanently retire SONGS in June 2013.
The replacement steam generators were designed and provided by MHI. In July 2013, SDG&E filed a lawsuit against MHI seeking to recover damages SDG&E has incurred and will incur related to the design defects in the steam generators. In October 2013, Edison instituted arbitration proceedings against MHI seeking recovery of damages. The other SONGS co-owners, SDG&E and the City of Riverside, participated as claimants and respondents.
On March 13, 2017, the Tribunal overseeing the arbitration found MHI liable for breach of contract, subject to a contractual limitation of liability, and rejected claimants’ other claims. The Tribunal awarded $118 million in damages to the SONGS co-owners, but determined that MHI was the prevailing party and awarded it 95 percent of its arbitration costs. The damage award is offset by these costs, resulting in a net award of approximately $60 million in favor of the SONGS co-owners. SDG&E’s specific allocation of the
damage award is $24 million reduced by costs awarded to MHI of approximately $12 million, resulting in a net damage award of $12 million, which was paid by MHI to SDG&E in March 2017. These amounts include certain adjustments to calculations supporting the Tribunal’s findings. In accordance with the Amended Settlement Agreement discussed below, which may be modified or set aside, SDG&E recorded the proceeds from the MHI arbitration by reducing Operation and Maintenance for previously incurred legal costs of $11 million, and shared the remaining $1 million equally between ratepayers and shareholders.
SETTLEMENT AGREEMENT TO RESOLVE THE CPUC’S ORDER INSTITUTING INVESTIGATION INTO THE SONGS OUTAGE
In November 2012, in response to the outage, the CPUC issued the SONGS OII, which was intended to determine the ultimate recovery of the investment in SONGS and the costs incurred since the commencement of this outage.
In November 2014, the CPUC issued a final decision approving an Amended and Restated Settlement Agreement (Amended Settlement Agreement) in the SONGS OII proceeding executed by SDG&E along with Edison, TURN, ORA and two other intervenors. The Amended Settlement Agreement does not affect ongoing or future proceedings before the NRC, or any litigation or arbitration related to potential future recoveries from third parties (except for the allocation to ratepayers of any recoveries addressed in the final decision) or any proceedings addressing decommissioning activities and costs. We describe the terms and provisions of the Amended Settlement Agreement in Note 13 of the Notes to Consolidated Financial Statements in the Annual Report.
In May 2016, following the filing of petitions for modification by various parties, the CPUC issued a procedural ruling reopening the record of the OII to address the issue of whether the Amended Settlement Agreement is reasonable and in the public interest.
In December 2016, the CPUC issued another procedural ruling directing parties to the SONGS OII to determine whether an agreement could be reached to modify the Amended Settlement Agreement previously approved by the CPUC, to resolve allegations that unreported ex parte communications between Edison and the CPUC resulted in an unfair advantage at the time the settlement agreement was negotiated. Pursuant to the December ruling and a subsequent procedural ruling, the parties met to confer, engaged a mediator and held confidential mediation discussions in June, July and August of 2017.
In August 2017, the parties filed status reports providing their recommendations for resolving the OII given their unsuccessful efforts at reaching a settlement through mediation. SDG&E and Edison recommend that the Amended Settlement Agreement, as adopted by the CPUC, should be affirmed and the pending intervenor petitions dismissed. Intervening parties recommend various alternative courses of action, including modifying the Amended Settlement Agreement or rejecting it in favor of litigation. In October 2017, the CPUC issued a ruling establishing a process to bring the proceeding to a conclusion. This ruling establishes a status conference and includes a preliminary schedule for additional testimony, hearings and briefings. The CPUC has not announced the expected timing for a decision. The ruling indicates that the record is adequate to allow the CPUC to determine whether the Amended Settlement Agreement should be reaffirmed. The ruling also provides for an expedited process to further develop the record in the event that the CPUC ultimately decides not to reaffirm the Amended Settlement Agreement, and instead determines a different allocation of costs to ratepayers as a result of the premature shutdown of SONGS Units 2 and 3.
There is no assurance that the Amended Settlement Agreement will not be modified or set aside as a result of the OII proceeding, which could result in a substantial reduction in our expected recovery or in payments to customers. These outcomes could have a material adverse effect on Sempra Energy’s and SDG&E’s results of operations, financial condition and cash flows.
Accounting and Financial Impacts
Through September 30, 2017, the cumulative after-tax loss from plant closure recorded by Sempra Energy and SDG&E is $125 million. The remaining regulatory asset for the expected recovery of SONGS costs, consistent with the Amended Settlement Agreement, is $158 million ($35 million current and $123 million long-term) at September 30, 2017. The amortization period prescribed for the regulatory asset is 10 years, ending in January 2022.
NUCLEAR DECOMMISSIONING AND FUNDING
As a result of Edison’s decision to permanently retire SONGS Units 2 and 3, Edison began the decommissioning phase of the plant. Decommissioning of Unit 1, removed from service in 1992, is largely complete. The remaining work for Unit 1 will be done once Units 2 and 3 are dismantled. In December 2016, Edison announced that, following a 10-month competitive bid process, it had contracted with a joint venture of AECOM and EnergySolutions (known as SONGS Decommissioning Solutions) as the general contractor to complete the dismantlement of SONGS. The majority of the dismantlement work is expected to take 10 years. SDG&E is responsible for approximately 20 percent of the total contract price.
In accordance with state and federal requirements and regulations, SDG&E has assets held in the NDT to fund its share of decommissioning costs for SONGS Units 1, 2 and 3. The amounts collected in rates for SONGS’ decommissioning are invested in the
NDT, which is comprised of externally managed trust funds. Amounts held by the NDT are invested in accordance with CPUC regulations. The NDT assets are presented on the Sempra Energy and SDG&E Condensed Consolidated Balance Sheets at fair value with the offsetting credits recorded in Regulatory Liabilities Arising from Removal Obligations.
In April 2016, the CPUC adopted a decision approving a total decommissioning cost estimate for SONGS Units 2 and 3 of $4.4 billion (in 2014 dollars), of which SDG&E’s share is $899 million. Except for the use of funds for the planning of decommissioning activities or NDT administrative costs, CPUC approval is required for SDG&E to access the NDT assets to fund SONGS decommissioning costs for Units 2 and 3. SDG&E has received authorization from the CPUC to access NDT funds of up to $302 million for 2013 through 2017 (2017 forecasted) SONGS decommissioning costs. This includes up to $84 million authorized by the CPUC in February 2017 to be withdrawn from the NDT for forecasted 2017 SONGS Units 2 and 3 costs as decommissioning costs are incurred.
In December 2016, the IRS and the U.S. Department of the Treasury issued proposed regulations that clarify the definition of “nuclear decommissioning costs,” which are costs that may be paid for or reimbursed from a qualified trust fund. The proposed regulations state that costs related to the construction and maintenance of independent spent fuel management installations are included in the definition of “nuclear decommissioning costs.” The proposed regulations will be effective prospectively once they are finalized; however, the IRS has stated that it will not challenge taxpayer positions consistent with the proposed regulations for taxable years ending on or after the date the proposed regulations were issued. SDG&E is seeking further clarification of the proposed regulations to confirm that the proposed regulations will allow SDG&E to access the NDT funds for reimbursement or payment of the spent fuel management costs that were or will be incurred in 2016 and subsequent years. Further clarification of the proposed regulations could enable SDG&E to access the NDT to recover spent fuel management costs before Edison reaches final settlement with the DOE regarding the DOE’s reimbursement of these costs. Historically, the DOE’s reimbursements of spent fuel storage costs have not resulted in timely or complete recovery of these costs. We discuss the DOE’s responsibility for spent nuclear fuel in Note 11. It is unclear when clarification of the proposed regulations might be provided or when the proposed regulations will be finalized.
The following table shows the fair values and gross unrealized gains and losses for the securities held in the NDT. We provide additional fair value disclosures for the NDT in Note 8.
NUCLEAR DECOMMISSIONING TRUSTS
(Dollars in millions)
 
Cost
 
Gross
unrealized
gains
 
Gross
unrealized
losses
 
Estimated
fair
value
At September 30, 2017:
 
 
 
 
 
 
 
Debt securities:
 
 
 
 
 
 
 
Debt securities issued by the U.S. Treasury and other
 
 
 
 
 
 
 
U.S. government corporations and agencies(1)
$
51

 
$

 
$

 
$
51

Municipal bonds(1)
238

 
7

 

 
245

Other securities(2)
207

 
4

 
(1
)
 
210

Total debt securities
496

 
11

 
(1
)
 
506

Equity securities
189

 
321

 
(2
)
 
508

Cash and cash equivalents
27

 

 

 
27

Total
$
712

 
$
332

 
$
(3
)
 
$
1,041

At December 31, 2016:
 
 
 
 
 
 
 
Debt securities:
 
 
 
 
 
 
 
Debt securities issued by the U.S. Treasury and other
 
 
 
 
 
 
 
U.S. government corporations and agencies
$
52

 
$

 
$

 
$
52

Municipal bonds
203

 
4

 
(1
)
 
206

Other securities
141

 
2

 
(2
)
 
141

Total debt securities
396

 
6

 
(3
)
 
399

Equity securities
143

 
366

 
(1
)
 
508

Cash and cash equivalents
119

 

 

 
119

Total
$
658

 
$
372

 
$
(4
)
 
$
1,026

(1)
Maturity dates are 2017-2047.
(2)
Maturity dates are 2017-2066.

The following table shows the proceeds from sales of securities in the NDT and gross realized gains and losses on those sales:
SALES OF SECURITIES IN THE NDT
(Dollars in millions)
 
Three months ended
September 30,
 
Nine months ended
September 30,
 
2017
 
2016
 
2017
 
2016
Proceeds from sales(1)
$
259

 
$
282

 
$
1,082

 
$
486

Gross realized gains
8

 
24

 
132

 
32

Gross realized losses
(3
)
 
(3
)
 
(11
)
 
(14
)
(1)
Excludes securities that are held to maturity.

Net unrealized gains and losses, as well as realized gains and losses that are reinvested in the NDT, are included in Regulatory Liabilities Arising from Removal Obligations on Sempra Energy’s and SDG&E’s Condensed Consolidated Balance Sheets. We determine the cost of securities in the trusts on the basis of specific identification. In the nine months ended September 30, 2017, sale and purchase activities in our NDT increased significantly compared to the same period in 2016 as a result of continuing changes to our asset allocations initiated in the fourth quarter of 2016 to reduce our equity volatility, lower our duration risk, and increase exposure to municipal bonds and intermediate credit. This shift in our asset mix is intended to reduce the overall risk profile of the NDT in anticipation of significant cash withdrawals over the next 10 years to fund the SONGS decommissioning.REGULATORY MATTERS
We discuss regulatory matters in Note 14 of the Notes to Consolidated Financial Statements in the Annual Report, and provide updates to those discussions and information about new regulatory matters below.
CALIFORNIA UTILITIES MATTERS
CPUC General Rate Case
The CPUC uses a GRC proceeding to set sufficient rates to allow the California Utilities to recover their reasonable cost of O&M and to provide the opportunity to realize their authorized rates of return on their investment.
2019 General Rate Case
On October 6, 2017, SDG&E and SoCalGas filed their 2019 GRC applications requesting CPUC approval of test year revenue requirements for 2019 and attrition year adjustments for 2020 through 2022. SDG&E and SoCalGas requested revenue requirements for 2019 of $2,199 million and $2,989 million, respectively, which is an increase of $218 million and $480 million over their respective estimated 2018 revenue requirements. The California Utilities are proposing post-test year revenue requirement changes using various adjustment factors which are estimated to result in annual increases of approximately 5 percent to 7 percent at SDG&E and approximately 6 percent to 8 percent at SoCalGas.
As part of the 2019 GRC, the CPUC will review the California Utilities’ interim accountability reports which compare the authorized and actual spending for certain safety-related activities for 2014 through 2016. In June 2017, SDG&E and SoCalGas filed their first interim accountability reports comparing authorized and actual spending in 2014 and 2015 for certain safety-related activities. Similar data for 2016 was provided with the 2019 GRC filings in a second interim accountability report. The stated purpose of the interim accountability reports is to provide data and metrics for key safety and risk mitigation areas that will be considered in the 2019 GRC.
The results of the rate case may materially and adversely differ from what is contained in the GRC applications.
Risk Assessment Mitigation Phase Reporting and Impact on the 2019 GRC Filings
In December 2014, the CPUC issued a decision incorporating a risk-based decision-making framework into all future GRC application filings for major natural gas and electric utilities in California. The framework is intended to assist in assessing safety risks and the utilities’ plans to help ensure that such risks are adequately addressed. In advance of filing the California Utilities’ 2019 GRC applications discussed above, two proceedings occurred: the Safety Model Assessment Proceeding and the RAMP. In the Safety Model Assessment Proceeding, the California Utilities demonstrated the models used to prioritize and mitigate risks in order for the CPUC to establish guidelines and standards for these models.
In November 2016, as part of the new framework, SDG&E and SoCalGas filed their first RAMP report presenting a comprehensive assessment of their key safety risks and proposed activities for mitigating such risks. The report details these key safety risks, which include critical operational issues such as natural gas pipeline safety and wildfire safety, and addresses their classification, scoring, mitigation, alternatives, safety culture, quantitative analysis, data collection and lessons learned.
In March 2017, the CPUC’s Safety and Enforcement Division issued its evaluation report providing generally favorable feedback on the California Utilities’ RAMP report, but recommending more detailed analysis of the risks the California Utilities presented in the report. The new GRC framework does not require the CPUC to adopt the RAMP report. However, SDG&E and SoCalGas included funding requests in their respective 2019 GRC filings for proposed projects or activities outlined in their RAMP reports.
Senate Bill 549. In September 2017, SB 549 was signed into law, requiring that SDG&E and SoCalGas (as electric and gas corporations) annually notify the CPUC when revenue authorized by the CPUC for maintenance, safety or reliability is redirected to other purposes. This requirement is effective beginning January 1, 2018. The form of this reporting is not yet defined by the CPUC, though it could be incorporated into an ongoing proceeding or report otherwise required to be submitted to the CPUC.
2016 General Rate Case
In June 2016, the CPUC issued the 2016 GRC FD, the details of which are discussed in Note 14 of the Notes to Consolidated Financial Statements in the Annual Report. The 2016 GRC FD was effective retroactive to January 1, 2016.
The 2016 GRC FD required the establishment of two-way income tax expense memorandum accounts to track any revenue variances resulting from certain differences between the income tax expense forecasted in the GRC and the income tax expense incurred by SDG&E and SoCalGas from 2016 through 2018. The variances to be tracked include tax expense differences relating to:
net revenue changes;
mandatory tax law, tax accounting, tax procedural, or tax policy changes; and
elective tax law, tax accounting, tax procedural, or tax policy changes.
Starting in the second quarter of 2016, SDG&E and SoCalGas began tracking the differences in the income tax expense forecasted in the GRC proceedings and the income tax expense incurred. At September 30, 2017, the recorded regulatory liability associated with these tracked amounts totaled $45 million and $58 million for SDG&E and SoCalGas, respectively. The recorded liability is primarily related to lower income tax expense incurred than was forecasted in the GRC relating to tax repairs deductions, self-developed software deductions and certain book-over-tax depreciation. The tracking accounts will remain open, and we expect they will be reviewed in the 2019 GRC proceedings. As of September 2017, there have been no mandatory or elective tax law, tax accounting, tax procedural, or tax policy changes that could give rise to a regulatory liability and as such, no amount has been recorded to this memorandum account related to these items.
CPUC Cost of Capital
In July 2017, the CPUC issued a final decision adopting, with certain modifications, the joint petition filed in February 2017 by SDG&E, SoCalGas, PG&E and Edison, along with ORA and TURN. The final decision provides a two-year extension for each of the utilities to file its next respective cost of capital application, extending the filing date to April 2019 for a 2020 test year. The final decision also reduces the ROE for SDG&E from 10.30 percent to 10.20 percent and for SoCalGas from 10.10 percent to 10.05 percent, effective from January 1, 2018 through December 31, 2019. SDG&E’s and SoCalGas’ ratemaking capital structures will remain at current levels until modified, if at all, by a future cost of capital decision by the CPUC. In September 2017, SDG&E and SoCalGas filed advice letters to update their cost of capital for the actual cost of long-term debt through August 2017 and forecasted cost through 2018. SDG&E and SoCalGas did not file for changes to preferred stock costs, because no issuances of preferred stock through 2018 are anticipated.
In October 2017, the CPUC approved the embedded cost of debt presented in the filed advice letters, resulting in a revised return on rate base for SDG&E and SoCalGas of 7.55 percent and 7.34 percent, respectively, effective January 1, 2018, as depicted in the table below:
AUTHORIZED COST OF CAPITAL AND RATE STRUCTURE  CPUC
 
 
 
 
 
 
 
 
 
 
 
 
 
SDG&E
 
SoCalGas
Authorized weighting
Return on
rate base
Weighted
return on
rate base
 
Authorized weighting
Return on
rate base
Weighted
return on
rate base
45.25
%
4.59
%
2.08
%
Long-Term Debt
45.60
%
4.33
%
1.97
%
2.75
%
6.22
%
0.17
%
Preferred Stock
2.40
%
6.00
%
0.14
%
52.00
%
10.20
%
5.30
%
Common Equity
52.00
%
10.05
%
5.23
%
100.00
%
 
 
7.55
%
 
100.00
%
 
 
7.34
%

As a result of the updates included in the filed advice letters, the impact of the changes to the embedded cost of debt and return on rate base is summarized below:
IMPACT OF THE EMBEDDED COST OF DEBT
 
 
 
 
SDG&E
 
SoCalGas
 
Cost of
debt
Return on
rate base
 
Cost of
debt
Return on
rate base
Current
5.00

%
7.79

%
 
5.77

%
8.02

%
Authorized, effective January 1, 2018
4.59

%
7.55

%
 
4.33

%
7.34

%
Differences
(41
)
bps
(24
)
bps
 
(144
)
bps
(68
)
bps

The automatic CCM will be in effect to adjust 2019 cost of capital, if necessary. Unless changed by the operation of the CCM, the updated costs of long-term debt and the new ROEs will remain in effect through December 31, 2019. The cost of capital changes will also apply to capital expenditures in 2018 and 2019 for incremental projects not funded through the GRC revenue requirement.