CALIFORNIA UTILITIES' REGULATORY MATTERS - MAJOR PROJECTS UPDATES (Details)
$ in Millions
9 Months Ended
Sep. 30, 2016
USD ($)
Oct. 31, 2016
USD ($)
Aug. 31, 2016
project
MW
Southern Gas System Member [Member]      
Public Utilities, General Disclosures [Line Items]      
Impairment charge after tax $ 13    
Impairment charge pre-tax 22    
Pipeline Safety And Reliability Project [Member]      
Public Utilities, General Disclosures [Line Items]      
Revised estimated project cost 633    
San Diego Gas and Electric Company [Member] | Cleveland National Forest Transmissions Projects [Member]      
Public Utilities, General Disclosures [Line Items]      
Estimated project cost 680    
San Diego Gas and Electric Company [Member] | Cleveland National Forest Projects Transmission Level Facilities [Member]      
Public Utilities, General Disclosures [Line Items]      
Estimated project cost 470    
San Diego Gas and Electric Company [Member] | Cleveland National Forest Projects Distribution Level Facilities [Member]      
Public Utilities, General Disclosures [Line Items]      
Estimated project cost 210    
San Diego Gas and Electric Company [Member] | Energy Storage Projects [Member]      
Public Utilities, General Disclosures [Line Items]      
Number of Projects | project     2
Energy Storage Capacity | MW     37.5
San Diego Gas and Electric Company [Member] | Maximum [Member] | Sycamore Penasquitos Transmission Project [Member] | Subsequent Event [Member]      
Public Utilities, General Disclosures [Line Items]      
Estimated project cost   $ 260  
San Diego Gas and Electric Company [Member] | Maximum [Member] | South Orange County Reliability Enhancement [Member]      
Public Utilities, General Disclosures [Line Items]      
Estimated project cost $ 381