COMMITMENTS AND CONTINGENCIES - LOSS ON CONTINGENCIES (Details)
$ in Thousands, € in Millions, £ in Millions
12 Months Ended
Dec. 31, 2015
EUR (€)
Dec. 31, 2015
GBP (£)
Dec. 31, 2015
USD ($)
Bcf
Oct. 23, 2015
Bcf
Dec. 31, 2014
USD ($)
Loss Contingencies [Line Items]          
Loss Contingency Accrual, at Carrying Value     $ 49,000    
Insurance receivable for Aliso Canyon costs     325,000   $ 0 [1]
Reserve for Aliso Canyon costs     274,000   0 [2]
San Diego Gas and Electric Company [Member]          
Loss Contingencies [Line Items]          
Loss Contingency Accrual, at Carrying Value     26,000    
Southern California Gas Company [Member]          
Loss Contingencies [Line Items]          
Loss Contingency Accrual, at Carrying Value     21,000    
Insurance receivable for Aliso Canyon costs     325,000   0 [1]
Reserve for Aliso Canyon costs     274,000   $ 0 [1]
Loss from Catastrophes, 2007 Wildfire [Member] | San Diego Gas and Electric Company [Member]          
Loss Contingencies [Line Items]          
Regulatory Assets Arising From Wildfire Litigation Costs     362,000    
Portion of Regulatory Assets Arising From Wildfire Litigation Related To CPUC-Regulated Operations     359,000    
Potential After-Tax Earnings Impact     $ 213,000    
Number Of Remaining Cases 1 1 1    
Number of Appeals Pending 2 2 2    
Rim Rock Wind Farm [Member] | San Diego Gas and Electric Company [Member]          
Loss Contingencies [Line Items]          
Estimated Tax Equity Investment     $ 285,000    
Loss from Catastrophes, Aliso Canyon Natural Gas Storage Facility Gas Leak [Member] | Southern California Gas Company [Member]          
Loss Contingencies [Line Items]          
Number Of Lawsuits 83 83 83    
Number Of Lawsuits Filed In Los Angeles County 81 81 81    
Number Of Lawsuits Filed In San Diego County 2 2 2    
Liability insurance coverage     $ 1,000,000    
Civil Penalties Per Day     250    
Net Book Value Of Aliso Canyon Natural Gas Storage Facility     243,000    
Construction in Work Progress Of Aliso Canyon Natural Gas Storage Facility     162,000    
Recorded Estimated Costs     $ 330,000    
Estimated Costs Related To Temporary Relocation, Percentage     70.00%    
Estimated Costs Related To Controlling Well And Stopping Leak And Emissions, Percentage     20.00%    
Operation And Maintenance Expense, Pretax, Aliso Canyon     $ 4,000    
Initial Gas Volume Stored | Bcf       77  
Gas Volume Delivered Or Moved | Bcf     57    
Minimum Working Gas Volume For Reliability | Bcf     15    
Storage Facility Maximum Capacity | Bcf     86    
Aliso Canyon Facility As A Percentage of SoCalGas Total Storage Capacity     63.00%    
Number Of Days Temporary Relocation Extended     22    
So Cal Gas PCB Litigation [Member] | Southern California Gas Company [Member]          
Loss Contingencies [Line Items]          
Number Of Lawsuits 7 7 7    
Number of Lawsuits Settled 6 6 6    
Sempra Mexico Property Disputes [Member]          
Loss Contingencies [Line Items]          
Number Of Lawsuits 2 2 2    
Mobile Gas Litigation [Member]          
Loss Contingencies [Line Items]          
Number Of Plaintiffs 250 250 250    
Number Of Lawsuits 14 14 14    
Number of Lawsuits Settled 11 11 11    
Number of Lawsuits Remaining 3 3 3    
HMRC VAT Claim [Member] | Parent Company [Member]          
Loss Contingencies [Line Items]          
VAT Tax Claim Paid Upon Appeal | £   £ 86      
R B S Sempra Commodities [Member]          
Loss Contingencies [Line Items]          
Damages Sought in VAT Litigation | € € 156        
Investment in RBS Sempra Commodities LLP     $ 67,000    