COMMITMENTS AND CONTINGENCIES
3 Months Ended
Jun. 30, 2012
Notes to Consolidated Financial Statements [Abstract]  
Commitments and Contingencies

NOTE 10. COMMITMENTS AND CONTINGENCIES

LEGAL PROCEEDINGS

We accrue losses for legal proceedings when it is probable that a loss has been incurred and the amounts of the loss can be reasonably estimated. However, the uncertainties inherent in legal proceedings make it difficult to estimate with reasonable certainty the costs and effects of resolving these matters. Accordingly, actual costs incurred may differ materially from amounts accrued, may exceed applicable insurance coverages and could materially adversely affect our business, cash flows, results of operations, and financial condition. Unless otherwise indicated, we are unable to estimate reasonably possible losses in excess of any amounts accrued.

At June 30, 2012, Sempra Energy's accrued liabilities for material legal proceedings, on a consolidated basis, were $507 million. At June 30, 2012, accrued liabilities for material legal proceedings for SDG&E and SoCalGas were $476 million and $18 million, respectively. At June 30, 2012, liabilities of $476 million at Sempra Energy and SDG&E were related to wildfire litigation discussed below.

SDG&E

2007 Wildfire Litigation

In October 2007, San Diego County experienced several catastrophic wildfires. Reports issued by the California Department of Forestry and Fire Protection (Cal Fire) concluded that two of these fires (the Witch and Rice fires) were SDG&E “power line caused” and that a third fire (the Guejito fire) occurred when a wire securing a Cox Communications' (Cox) fiber optic cable came into contact with an SDG&E power line “causing an arc and starting the fire.” Cal Fire reported that the Rice fire burned approximately 9,500 acres and damaged 206 homes and two commercial properties, and the Witch and Guejito fires merged and eventually burned approximately 198,000 acres, resulting in two fatalities, approximately 40 firefighters injured and approximately 1,141 homes destroyed.

A September 2008 staff report issued by the CPUC's CPSD reached substantially the same conclusions as the Cal Fire reports, but also contended that the power lines involved in the Witch and Rice fires and the lashing wire involved in the Guejito fire were not properly designed, constructed and maintained. In April 2010, proceedings initiated by the CPUC to determine if any of its rules were violated were settled with SDG&E's payment of $14.75 million.

Numerous parties have sued SDG&E and Sempra Energy in San Diego County Superior Court seeking recovery of unspecified amounts of damages, including punitive damages, from the three fires. These include owners and insurers of properties that were destroyed or damaged in the fires and public entities seeking recovery of firefighting, emergency response, and environmental costs. They assert various bases for recovery, including inverse condemnation based upon a California Court of Appeal decision finding that another California investor-owned utility was subject to strict liability, without regard to foreseeability or negligence, for property damages resulting from a wildfire ignited by power lines.

In October 2010, the Court of Appeal affirmed the trial court's ruling that these claims must be pursued in individual lawsuits, rather than as class actions on behalf of all persons who incurred wildfire damages. In February 2011, the California Supreme Court denied a petition for review of the affirmance. No trial date is currently scheduled.

SDG&E filed cross-complaints against Cox seeking indemnification for any liability that SDG&E might incur in connection with the Guejito fire, two SDG&E contractors seeking indemnification in connection with the Witch fire, and one SDG&E contractor seeking indemnification in connection with the Rice fire.

In December 2010, SDG&E and Cox reached an agreement settling SDG&E's claims against Cox and Cox's insurers in the wildfire litigation (Cox Settlement). Among other things, the settlement agreement provided that SDG&E receive approximately $444 million for wildfire related expenditures, and SDG&E will defend and indemnify Cox against all compensatory damage claims and related costs arising out of the wildfires.

SDG&E has settled all of the approximately 19,000 claims brought by homeowner insurers for damage to insured property relating to the three fires. Under the settlement agreements, SDG&E has paid or will pay 57.5 percent of the approximately $1.6 billion paid or reserved for payment by the insurers to their policyholders and received an assignment of the insurers' claims against other parties potentially responsible for the fires.

The wildfire litigation also includes claims of non-insurer plaintiffs for damage to uninsured and underinsured structures, business interruption, evacuation expenses, agricultural damage, emotional harm, personal injuries and other losses. SDG&E has settled the claims of approximately 4,400 of these plaintiffs. Approximately 700 of the approximately 1,950 remaining individual and business plaintiffs have submitted settlement demands and damage estimates totaling approximately $860 million. SDG&E does not expect significant additional plaintiffs to file lawsuits given the applicable statutes of limitation, but does expect to receive additional settlement demands and damage estimates from existing plaintiffs as settlement negotiations continue. SDG&E has established reserves for the wildfire litigation as we discuss below.

SDG&E's settled claims and defense costs have exceeded its $1.1 billion of liability insurance coverage and the approximately $455 million it has received from third parties, including Cox. It expects that its wildfire reserves and amounts paid to resolve wildfire claims will continue to increase as it obtains additional information.

SDG&E has concluded, however, that it is probable that it will be permitted to recover from its utility customers substantially all reasonably incurred costs of resolving wildfire claims in excess of its liability insurance coverage and any amounts recovered from other potentially responsible parties. Accordingly, although such recovery will require future regulatory actions, at June 30, 2012, SDG&E recorded assets of $722 million in regulatory and balancing accounts, which represents the amount substantially equal to the aggregate amount it has paid or reserved for payment for the resolution of wildfire claims and related costs in excess of its liability insurance coverage and amounts received from third parties. SDG&E will increase the regulatory assets and balancing accounts as additional amounts are paid or reserves are recorded and reduce them by any amounts recovered from other potentially responsible parties.

As a consequence of the expected recovery of wildfire costs from utility customers, Sempra Energy and SDG&E expect no significant earnings impact from the resolution of the remaining wildfire claims. However, SDG&E's cash flow may be materially adversely affected due to the timing differences between the resolution of claims and the recoveries from other potentially responsible parties and utility customers, which may extend over a number of years. Also, recovery from customers will require future regulatory actions, and a failure to obtain substantial or full recovery, or any negative assessment of the likelihood of recovery, would likely have a material adverse effect on Sempra Energy's and SDG&E's financial position, cash flows and results of operations.

SDG&E will continue to gather information to evaluate and assess the remaining wildfire claims and the likelihood, amount and timing of related recoveries from other potentially responsible parties and utility customers and will make appropriate adjustments to wildfire reserves and the related regulatory assets and balancing accounts as additional information becomes available.

Since 2010, as liabilities for wildfire litigation have become reasonably estimable in the form of settlement demands, damage estimates, and other damage information, SDG&E has recorded related reserves as a liability. The impact of this liability at June 30, 2012 is offset by the recognition of regulatory assets and balancing accounts, as discussed above, for reserves in excess of the insurance coverage and recoveries from third parties. The impact of the reserves on SDG&E's and Sempra Energy's after-tax earnings was $3 million and $1 million for the three months ended June 30, 2012 and 2011, respectively, and $5 million and $2 million for the six months ended June 30, 2012 and 2011, respectively. At June 30, 2012, wildfire litigation reserves were $476 million ($305 million in current and $171 million in long-term). Additionally, through June 30, 2012, SDG&E has expended $314 million (excluding amounts covered by insurance and amounts recovered from other responsible third parties) to pay costs associated with the settlement of wildfire claims.

Sunrise Powerlink Electric Transmission Line

SDG&E commenced construction on the Sunrise Powerlink in the fall of 2010. The Sunrise Powerlink is a new 117-mile, 500-kilovolt (kV) electric transmission line between the Imperial Valley and the San Diego region, along a route that generally runs south of the Anza-Borrego Desert State Park. Construction of the transmission line has been completed and the line was energized and placed in service in June 2012. Through June 30, 2012, total capital investment in the Sunrise Powerlink is $1.8 billion. SDG&E's rate base investment as of June 30, 2012 was $1.6 billion, with a projected rate base investment of approximately $1.4 billion by the end of the year. While there are still incremental costs to be charged to the project, management believes that the final total investment in the Sunrise Powerlink will be below the CPUC-established cost cap of $1.9 billion.

The Sunrise Powerlink project was originally approved by the CPUC in December 2008, including approval of the environmental impact review conducted jointly with the BLM. The CPUC subsequently denied or dismissed all requests for rehearing of its approval of the project. In February 2011, the California Supreme Court denied a petition filed jointly by the Utility Consumers' Action Network (UCAN) and the Center for Biological Diversity/Sierra Club challenging the CPUC's decision with regard to implementation of the California Environmental Quality Act (CEQA).

In January 2009, the BLM issued its decision approving the portions of the project, route and environmental review within its jurisdiction. The Interior Board of Land Appeals subsequently denied or dismissed all administrative appeals that were filed challenging the BLM's approval of the project.

In February 2010, parties opposed to the project filed a lawsuit in Federal District Court in San Diego alleging that the BLM failed to properly address the environmental impacts of the approved Sunrise Powerlink route and the related potential development of renewable resources in east San Diego County and Imperial County. In July 2012, the U.S. Court of Appeals for the Ninth Circuit affirmed the District Court's grant of the defendants' motion for summary judgment.

In July 2010, the United States Forest Service (USFS) issued its decision approving the portions of the project, route and environmental review within its jurisdiction. The USFS subsequently denied all administrative appeals challenging its approval of the project.

The CPUC and BLM jointly approved the final Project Modification Report for Sunrise Powerlink in September 2010, accepting all of the proposed modifications to the approved route and finding that no additional environmental review was required. In March 2011, opponents of the Sunrise Powerlink filed a petition with the California Supreme Court challenging the CPUC's acceptance of the Project Modification Report. The California Supreme Court denied the petition in April 2011.

In January 2011, project opponents filed a lawsuit in Federal District Court in San Diego alleging that the federal approvals for construction of the project on USFS land and BLM land violated the National Environmental Policy Act and other federal environmental laws. In June 2012, the U.S. Court of Appeals for the Ninth Circuit affirmed the District Court's denial of plaintiffs' motion for a preliminary injunction.

In February 2011, opponents of the Sunrise Powerlink filed a lawsuit in Sacramento County Superior Court against the State Water Resources Control Board and SDG&E alleging that the water quality certification issued by the Board under the Federal Clean Water Act violated CEQA. In July 2012, the Superior Court denied the plaintiff's petition.

September 2011 Power Outage

In September 2011, a power outage lasting approximately 12 hours affected millions of people from Mexico to southern Orange County, California. Within several days of the outage, several SDG&E customers filed a class action lawsuit in Federal District Court against Arizona Public Service Company, Pinnacle West, and SDG&E alleging that the companies failed to prevent the outage. The lawsuit seeks recovery of unspecified amounts of damages, including punitive damages. In July 2012, the court granted SDG&E's motion to dismiss the punitive damages request and dismissed Arizona Public Service Company and Pinnacle West from the lawsuit. In addition, more than 7,000 customers' claims, primarily related to food spoilage, have been submitted directly to SDG&E. The Federal Energy Regulatory Commission (FERC) and North American Electric Reliability Corp. (NERC) conducted a joint inquiry to determine the cause of the power failure and issued a report in May 2012 regarding their findings. The report does not include any findings of failure on SDG&E's part that led to the power failure.

Smart Meters Patent Infringement Lawsuit

In October 2011, SDG&E was sued by a Texas design and manufacturing company in Federal District Court alleging that SDG&E's recently installed smart meters infringed certain patents. The meters were purchased from a third party vendor that has agreed to defend and indemnify SDG&E. The lawsuit seeks injunctive relief and recovery of unspecified amounts of damages.

SoCalGas

SoCalGas, along with Monsanto Co., Solutia, Inc., Pharmacia Corp., and Pfizer, Inc., are defendants in five Los Angeles County Superior Court lawsuits filed beginning in April 2011 seeking recovery of unspecified amounts of damages, including punitive damages, as a result of plaintiffs' exposure to PCBs (polychlorinated biphenyls). The lawsuits allege plaintiffs were exposed to PCBs not only through the food chain and other various sources but from PCB-contaminated natural gas pipelines owned and operated by SoCalGas. This contamination allegedly caused plaintiffs to develop cancer and other serious illnesses. Plaintiffs assert various bases for recovery, including negligence and products liability.

Sempra Natural Gas

Liberty Gas Storage, LLC (Liberty) received a demand for arbitration from Williams Midstream Natural Gas Liquids, Inc. (Williams) in February 2011 related to a sublease agreement. Williams alleges that Liberty was negligent in its attempt to convert certain salt caverns to natural gas storage and seeks damages of $56.7 million. Liberty filed a counterclaim alleging breach of contract in the inducement and seeks damages of more than $215 million.

Sempra Mexico

Sempra Mexico has been engaged in a long-running land dispute relating to property adjacent to its Energía Costa Azul liquefied natural gas (LNG) terminal near Ensenada, Mexico. The adjacent property is not required by environmental or other regulatory permits for the operation of the terminal. A claimant to the adjacent property has nonetheless asserted that his health and safety are endangered by the operation of the facility. In June 2010, a Mexican federal appeals court revoked a district court order, issued at the behest of the claimant, directing Mexican regulatory authorities to provisionally suspend authorizations for the operation of the LNG terminal. In February 2011, based on a complaint by the claimant, the new Ensenada Mayor attempted to temporarily close the terminal based on claims of irregularities in municipal permits issued six years earlier. This attempt was promptly countermanded by Mexican federal and Baja California state authorities. No terminal permits or operations were affected as a result of these proceedings or events and the terminal has continued to operate normally. Sempra Mexico expects additional Mexican court proceedings and governmental actions regarding the claimant's assertions as to whether the terminal's permits should be modified or revoked in any manner.

The property claimant also filed a lawsuit in July 2010 against Sempra Energy in Federal District Court in San Diego seeking compensatory and punitive damages as well as the earnings from the Energía Costa Azul LNG terminal based on his allegations that he was wrongfully evicted from the adjacent property and that he has been harmed by other allegedly improper actions.

Additionally, several administrative challenges are pending in Mexico before the Mexican environmental protection agency (SEMARNAT) and/or the Federal Tax and Administrative Courts seeking revocation of the environmental impact authorization, or EIA, issued to Energía Costa Azul in 2003. These cases generally allege that the conditions and mitigation measures in the EIA are inadequate and challenge findings that the activities of the terminal are consistent with regional development guidelines. Also, there are two real property cases pending against Energía Costa Azul in which the plaintiffs seek to annul the recorded property titles for parcels on which the Energía Costa Azul LNG terminal is situated and to obtain possession of different parcels that allegedly sit in the same place. Sempra Mexico expects further proceedings on each of these matters.

In July 2012, a Mexicali state court issued a ruling declaring the purchase contract by which Termoeléctrica de Mexicali (TDM) acquired the property on which the facility is located to be invalid, on the grounds that the proceeding in which the seller acquired title was invalid. TDM has appealed the ruling, and it is not enforceable while the appeal is pending. In accordance with Mexican law, TDM remains in possession of the property, and its operations have not been affected.

Other Litigation

In August 2007, the U.S. Court of Appeals for the Ninth Circuit issued a decision reversing and remanding certain FERC orders declining to provide refunds regarding short-term bilateral sales up to one month in the Pacific Northwest for the December 2000 to June 2001 time period. In December 2010, the FERC approved a comprehensive settlement previously reached by Sempra Energy and RBS Sempra Commodities with the State of California. The settlement resolves all issues with regard to sales between the California Department of Water Resources (DWR) and Sempra Commodities in the Pacific Northwest, but potential claims may exist regarding sales between Sempra Commodities and other buyers in the Pacific Northwest. The FERC is in the process of addressing these potential claims on remand. Pursuant to the agreements related to the formation of RBS Sempra Commodities, we have indemnified RBS should the liability from the final resolution of these matters be greater than the reserves related to Sempra Commodities. Pursuant to our agreement with the Noble Group Ltd., one of the buyers of RBS Sempra Commodities' businesses, we have also indemnified Noble Americas Gas & Power Corp. and its affiliates for all losses incurred by such parties resulting from these proceedings as related to Sempra Commodities.

Sempra Energy and several subsidiaries, along with three oil and natural gas companies, the City of Beverly Hills, and the Beverly Hills Unified School District, are defendants in toxic tort lawsuits filed beginning in 2003 in Los Angeles County Superior Court by approximately 1,000 plaintiffs. These lawsuits claim that various emissions resulted in cancer or fear of cancer. In November 2006, the court granted the defendants' summary judgment motions based on lack of medical causation for the 12 initial plaintiffs scheduled to go to trial first. The court also granted summary judgment excluding punitive damages. The court has stayed the lawsuits as to the remaining plaintiffs pending the appeal of the rulings. A mediation occurred in June 2010, after which the plaintiffs' counsel agreed to recommend a settlement of the lawsuits as to Sempra Energy and its subsidiaries for an amount that is not significant and has been recorded. Any such settlement will require approval by each of the plaintiffs. If approval is obtained, finalization of the settlement is expected to occur within six months.

As described in Note 4, we hold a noncontrolling interest in RBS Sempra Commodities, a limited liability partnership in the process of being liquidated. In March 2012, RBS received a letter from the United Kingdom's Revenue and Customs Department (HMRC) regarding a value-added-tax (VAT) matter related to RBS Sempra Energy Europe (RBS SEE), a former indirect subsidiary of RBS Sempra Commodities that was sold to JP Morgan. The letter states that HMRC is conducting a number of investigations into VAT tax refund claims made by various businesses related to the purchase and sale of carbon credit allowances. The letter also states that HMRC believes it has grounds to deny RBS the ability to reduce its VAT liability by VAT paid during 2009 because it knew or should have known that certain vendors in the trading chain did not remit their own VAT to HMRC. The letter states that VAT paid in connection with these transactions totals £86 million. While RBS has not yet responded to the letter and there has been no formal tax assessment issued by HMRC, it is possible that RBS Sempra Commodities could incur losses as a result of this matter that were not previously anticipated.

We are also defendants in ordinary routine litigation incidental to our businesses, including personal injury, product liability, property damage and other claims. California juries have demonstrated an increasing willingness to grant large awards, including punitive damages, in these types of cases.

NUCLEAR INSURANCE

SDG&E and the other owners of SONGS have insurance to cover claims from nuclear liability incidents arising at SONGS. This insurance provides $375 million in coverage limits, the maximum amount available, including coverage for acts of terrorism. In addition, the Price-Anderson Act provides for up to $12.2 billion of secondary financial protection (SFP). If a nuclear liability loss occurring at any U.S. licensed/commercial reactor exceeds the $375 million insurance limit, all nuclear reactor owners could be required to contribute to the SFP. SDG&E's contribution would be up to $47 million. This amount is subject to an annual maximum of $7 million, unless a default occurs by any other SONGS owner. If the SFP is insufficient to cover the liability loss, SDG&E could be subject to an additional assessment.

The SONGS owners, including SDG&E, also have $2.75 billion of nuclear property, decontamination, and debris removal insurance. In addition, the SONGS owners have up to $490 million insurance coverage for outage expenses and replacement power costs due to accidental property damage. This coverage is limited to $3.5 million per week for the first 52 weeks, then $2.8 million per week for up to 110 additional weeks. There is a 12-week waiting period deductible. These insurance coverages are provided through a mutual insurance company. Insured members are subject to retrospective premium assessments. SDG&E could be assessed up to $9.7 million.

The nuclear property insurance program includes an industry aggregate loss limit for non-certified acts of terrorism (as defined by the Terrorism Risk Insurance Act). The industry aggregate loss limit for property claims arising from non-certified acts of terrorism is $3.24 billion. This is the maximum amount that will be paid to insured members who suffer losses or damages from these non-certified terrorist acts.

We provide additional information about SONGS in Note 9.

CONTRACTUAL COMMITMENTS

We discuss below significant changes in the first six months of 2012 to contractual commitments discussed in Note 15 of the Notes to Consolidated Financial Statements in the Updated Annual Report.

Natural Gas Contracts

SoCalGas' natural gas purchase and pipeline capacity commitments have increased by $81 million since December 31, 2011. The increase, primarily due to new natural gas purchase and pipeline capacity contracts of $372 million, is offset by a reduction of $291 million from fulfillment of commitments in the first six months of 2012. Net future payments are expected to decrease by $108 million in 2012 and increase by $116 million in 2013, $9 million in 2014, $7 million in 2015, $5 million in 2016 and $52 million thereafter compared to December 31, 2011.

Sempra Mexico's natural gas purchase commitments have decreased by $135 million since December 31, 2011, primarily due to changes in forward prices and fulfillment of commitments in the first six months of 2012. Net future payments are therefore expected to decrease by $71 million in 2012, $32 million in 2013 and $32 million in 2014 compared to December 31, 2011.

Sempra Natural Gas' natural gas purchase and storage capacity commitments have increased by $62 million since December 31, 2011, primarily due to new storage capacity contracts in the first six months of 2012. Net future payments are expected to decrease by $8 million in 2012, and increase by $16 million in 2013, $11 million in 2014, $9 million in 2015, $8 million in 2016 and $26 million thereafter compared to December 31, 2011.

LNG Purchase Agreements

At June 30, 2012, Sempra Natural Gas has various purchase agreements with major international companies for the supply of LNG to the Energía Costa Azul and Cameron receipt terminals. We discuss these agreements further in Note 15 of the Notes to Consolidated Financial Statements in the Updated Annual Report. Sempra Natural Gas' commitments under all LNG purchase agreements, reflecting changes in forward prices since December 31, 2011 and actual transactions for the first six months of 2012, are expected to decrease by $282 million in 2012, $54 million in 2013, $55 million in 2014, $65 million in 2015, $76 million in 2016 and $1.8 billion thereafter compared to December 31, 2011.

The LNG commitment amounts above are based on Sempra Natural Gas' commitment to accept the maximum possible delivery of cargoes under the agreements. Actual LNG purchases for the six months ended June 30, 2012 have been significantly lower than the maximum amounts possible.

Purchased-Power Contracts

SDG&E's commitments under purchased-power contract commitments have decreased by $207 million since December 31, 2011. The decrease is primarily due to cancellation of certain contracts associated with renewables development projects and changes in expected prices. Net future payments are therefore expected to decrease by $37 million in 2012, increase by $1 million in 2013, and decrease by $4 million in 2014, $4 million in 2015, $4 million in 2016 and $159 million thereafter compared to December 31, 2011.

Sempra South American Utilities' purchased-power contracts have increased by $102 million since December 31, 2011, primarily due to foreign currency translation (as the contracts are denominated in the local currency), offset by changes in expected prices and fulfillment of commitments in the first six months of 2012. Net future payments for the purchased-power contracts at Luz del Sur are expected to decrease by $186 million in 2012, increase by $1 million in 2013, and decrease by $6 million in 2014, $6 million in 2015, $6 million in 2016 and $51 million thereafter. Net future payments for the purchased-power contracts at Chilquinta Energía are expected to decrease by $127 million in 2012, and increase by $31 million in 2013, $34 million in 2014, $37 million in 2015, $37 million in 2016 and $344 million thereafter. These amounts are based on estimated future purchases at current contracted rates, as the contracts require no minimum purchases.

Operating Leases

Sempra Renewables entered into a land lease for the Copper Mountain Solar 2 project, which lease expires in 2054. Future payments on the lease are $2 million in 2013, $2 million in 2014, $2 million in 2015, $2 million in 2016 and $59 million thereafter.

Construction and Development Projects

In the first six months of 2012, significant increases to contractual commitments at SDG&E were $67 million primarily for electric transmission and distribution systems. The future payments for these contractual commitments are expected to be $65 million in 2012 and $2 million in 2013.

In connection with the completion of the Sunrise Powerlink project, the CPUC required that SDG&E establish a fire mitigation fund to minimize the risk of fire as well as reduce the potential wildfire impact on residences and structures near the Sunrise Powerlink. The future payments for these contractual commitments are expected to be approximately $3 million per year, subject to escalation of 2% per year, for 58 years.

In the first six months of 2012, significant increases to contractual commitments at SoCalGas were $61 million for construction and infrastructure improvements for natural gas transmission and distribution operations. The payments for these contractual commitments are all expected to be in 2012.