COMMITMENTS AND CONTINGENCIES - CONTRACTUAL COMMITMENTS (Details) (USD $)
3 Months Ended 6 Months Ended
Jun. 30, 2011
Jun. 30, 2011
Purchased Power Contracts [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
   
Long-term Purchase Commitment [Line Items]    
Long-term Purchase Commitment, Amount   $ 62,000,000
Nuclear Fuel Fabrication [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
   
Long-term Purchase Commitment [Line Items]    
Long-term Purchase Commitment, Amount   23,000,000
Sunrise Powerlink Construction [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
   
Long-term Purchase Commitment [Line Items]    
Long-term Purchase Commitment, Amount   313,000,000
Electric Distribution, Advanced Metering And Generation Infrastructure [Member] | San Diego Gas and Electric Company and Subsidiary [Member]
   
Long-term Purchase Commitment [Line Items]    
Long-term Purchase Commitment, Amount   51,000,000
Natural Gas Infrastructure Construction [Member] | Southern California Gas Company [Member]
   
Long-term Purchase Commitment [Line Items]    
Long-term Purchase Commitment, Amount   345,000,000
Sempra Energy [Member]
   
Payments Under Contractual Commitments [Line Items]    
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due, Current (591,000,000)  
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due In Two Years (395,000,000)  
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due In Three Years (178,000,000)  
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due In Four Years 3,000,000  
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due In Five Years 26,000,000  
Increase (Decrease) In Liquefied Natural Gas Commitments, Payments Due Thereafter 1,300,000,000  
Increase (Decrease) In Natural Gas Contracts Commitments   (94,000,000)
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due, Current (55,000,000)  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due In Two Years (3,000,000)  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due In Three Years (2,000,000)  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due In Four Years (34,000,000)  
Luz Del Sur [Member]
   
Payments Under Contractual Commitments [Line Items]    
Increase (Decrease) In Purchased Power Commitments, Payments Due, Current 192,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Two Years 436,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Three Years 477,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Four Years 524,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Five Years 577,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due Thereafter 4,700,000,000  
Chilquinta Energia [Member]
   
Payments Under Contractual Commitments [Line Items]    
Increase (Decrease) In Purchased Power Commitments, Payments Due, Current 141,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Two Years 283,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Three Years 306,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Four Years 320,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Five Years 355,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due Thereafter 3,100,000,000  
San Diego Gas and Electric Company and Subsidiary [Member]
   
Payments Under Contractual Commitments [Line Items]    
Contractual Commitments, Payments Due, Current 294,000,000  
Contractual Commitments, Payments Due In Two Years 67,000,000  
Contractual Commitments, Payments Due In Three Years 9,000,000  
Contractual Commitments, Payments Due In Four Years 4,000,000  
Contractual Commitments, Payments Due In Five Years 3,000,000  
Contractual Commitments, Payments Due Thereafter 10,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due, Current (2,000,000)  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Two Years 1,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Three Years 2,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Four Years 2,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due In Five Years 2,000,000  
Increase (Decrease) In Purchased Power Commitments, Payments Due Thereafter 57,000,000  
Southern California Gas Company [Member]
   
Payments Under Contractual Commitments [Line Items]    
Contractual Commitments, Payments Due, Current 29,000,000  
Contractual Commitments, Payments Due In Two Years 29,000,000  
Contractual Commitments, Payments Due In Three Years 62,000,000  
Contractual Commitments, Payments Due In Four Years 59,000,000  
Contractual Commitments, Payments Due In Five Years 59,000,000  
Contractual Commitments, Payments Due Thereafter 107,000,000  
Increase (Decrease) In Natural Gas Contracts Commitments   5,000,000
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due, Current (200,000,000)  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due In Two Years 183,000,000  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due In Three Years 23,000,000  
Increase (Decrease) In Natural Gas Contracts Commitments, Payments Due Thereafter $ 1,000,000