XML 110 R96.htm IDEA: XBRL DOCUMENT v3.24.0.1
REGULATORY MATTERS - Maryland and New Jersey (Details)
1 Months Ended 12 Months Ended
Feb. 01, 2024
USD ($)
circuit
Jan. 03, 2024
USD ($)
Dec. 29, 2023
USD ($)
Dec. 05, 2023
USD ($)
Dec. 01, 2023
USD ($)
program
Nov. 09, 2023
USD ($)
Oct. 31, 2023
MW
windFarm
Oct. 18, 2023
USD ($)
Aug. 07, 2023
USD ($)
Aug. 01, 2023
USD ($)
Jul. 17, 2023
USD ($)
Apr. 17, 2023
USD ($)
Mar. 22, 2023
USD ($)
program
Mar. 16, 2023
USD ($)
program
Oct. 26, 2022
USD ($)
Nov. 01, 2021
Oct. 28, 2020
USD ($)
Apr. 30, 2021
USD ($)
Dec. 31, 2023
Maryland                                      
Regulatory Matters [Line Items]                                      
Increase base distribution rate               $ 28,000,000                      
Maryland | Subsequent Event                                      
Regulatory Matters [Line Items]                                      
Increase base distribution rate   $ 700,000                                  
PE                                      
Regulatory Matters [Line Items]                                      
Amount of requested rate increase                         $ 50,400,000            
PE | FERC                                      
Regulatory Matters [Line Items]                                      
Support costs               $ 12,000,000                      
PE | Maryland                                      
Regulatory Matters [Line Items]                                      
Number of service reliability and resiliency programs | program                         3            
Number of programs | program                         2            
Incremental energy savings goal per year (percent)                         0.20%            
Incremental energy savings goal thereafter (percent)                         2.00%            
PE | Maryland | Power Purchase Agreements                                      
Regulatory Matters [Line Items]                                      
Annual termination fee                       $ 51,000,000              
Amount of termination fee                       357,000,000              
PE | Maryland | Power Purchase Agreements | Other Current Liabilities                                      
Regulatory Matters [Line Items]                                      
Amount of termination fee                       55,000,000              
PE | Maryland | Power Purchase Agreements | Other Noncurrent Liabilities                                      
Regulatory Matters [Line Items]                                      
Amount of termination fee                       $ 302,000,000              
PE | Maryland | 2021-2023 EmPOWER Program Cycle                                      
Regulatory Matters [Line Items]                                      
Amortization period                         5 years            
PE | Maryland | 2024-2026 EmPOWER Program Cycle                                      
Regulatory Matters [Line Items]                                      
Recovery period for expenditures for cost recovery program                   3 years                  
Public utilities, requested cost percentage, year one                   0.33                  
Public utilities, requested cost percentage, year two                   0.67                  
Public utilities, requested cost percentage, year three                   1                  
Public utilities, requested year one                   $ 310,000,000                  
Public utilities, requested year two                   354,000,000                  
Public utilities, requested year three                   $ 510,000,000                  
Approved amount of rate increase (decrease)     $ 310,000,000                                
JCP And L | New Jersey                                      
Regulatory Matters [Line Items]                                      
Approved amount of rate increase (decrease)                             $ 723,000,000        
Approved ROE                             10.20%        
Public utility, offshore development, percent                             20.00%        
Recovery of transmission incentive rates, percentage                       100.00%              
Recovery of transmission incentive rates, percentage                       50.00%              
Number of cease development | windFarm             2                        
Plant capacity (in MW's) | MW             2,248                        
JCP And L | New Jersey | NJBPU                                      
Regulatory Matters [Line Items]                                      
Amount of requested rate increase                     $ 31,000,000                
Amount of revenue increase                                 $ 94,000,000    
Requested increase to ROE                               9.60%      
JCP And L | New Jersey | NJBPU | Energy Efficiency and Peak Demand Reduction Stipulation Settlement | Utilities and Transmission Companies                                      
Regulatory Matters [Line Items]                                      
Amount of requested rate increase       $ 69,300,000                           $ 203,000,000  
Increase base distribution rate                 $ 192,000,000         $ 185,000,000          
Number of proposed programs | program                           2          
Approved rate plan period                                   3 years  
Approved amount of investment recovery over amortization period                                   $ 160,000,000  
Approved amount of operation costs and maintenance recovery                                   $ 43,000,000  
Number of extension period       6 months                              
Revised requested rate increase         $ 964,000,000                            
Number of energy program | program         10                            
Number of peak demand reduction program | program         1                            
Building decarbonization program | program         1                            
JCP And L | New Jersey | NJBPU | Energy Efficiency and Peak Demand Reduction | Utilities and Transmission Companies                                      
Regulatory Matters [Line Items]                                      
Amortization period                                   10 years  
JCP And L | New Jersey | Subsequent Event | NJBPU | Energy Efficiency and Peak Demand Reduction Stipulation Settlement | Utilities and Transmission Companies                                      
Regulatory Matters [Line Items]                                      
Increase base distribution rate $ 85,000,000                                    
Remaining amount of regulatory liability amortization 18,000,000                                    
Initial investment $ 95                                    
Number of high-priority circuits | circuit 18                                    
JCP&L                                      
Regulatory Matters [Line Items]                                      
Approved ROE                                     9.60%
JCP&L | New Jersey | NJBPU | Energy Efficiency and Peak Demand Reduction | Utilities and Transmission Companies                                      
Regulatory Matters [Line Items]                                      
Amount of requested rate increase           $ 935,000,000                          
Amount of requested rate increase, capital commitments           906,000,000                          
Amount of requested rate increase, operating and maintenance expense           $ 29,000,000