REGULATORY MATTERS
12 Months Ended
Dec. 31, 2023
Regulated Operations [Abstract]  
REGULATORY MATTERS REGULATORY MATTERS
STATE REGULATION

Each of the Utilities' retail rates, conditions of service, issuance of securities and other matters are subject to regulation in the states in which it operates - in Maryland by the MDPSC, in New Jersey by the NJBPU, in Ohio by the PUCO, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC. The transmission operations of PE and TrAIL in Virginia, ATSI in Ohio, the Transmission Companies in Pennsylvania, PE and MP in West Virginia, and PE in Maryland are subject to certain regulations of the VSCC, PUCO, PPUC, WVPSC, and MDPSC, respectively. In addition, under Ohio law, municipalities may regulate rates of a public utility, subject to appeal to the PUCO if not acceptable to the utility. Further, if any of the FirstEnergy affiliates were to engage in the construction of significant new transmission facilities, depending on the state, they may be required to obtain state regulatory authorization to site, construct and operate the new transmission facility.

The following table summarizes the key terms of base distribution rate orders in effect for the Utilities as of December 31, 2023:
CompanyRates Effective For CustomersAllowed Debt/EquityAllowed ROE
CEIMay 2009
51% /49%
10.5%
ME(1)
January 2017
48.8% / 51.2%
Settled(2)
MPFebruary 2015
54% / 46%
Settled(2)
JCP&LNovember 2021
48.6% / 51.4%
9.6%
OEJanuary 2009
51% /49%
10.5%
PE (West Virginia)February 2015
51% / 49%
Settled(2)
PE (Maryland)October 2023
47% / 53%
9.5%
PN(1)
January 2017
47.4% /52.6%
Settled(2)
Penn(1)
January 2017
49.9% / 50.1%
Settled(2)
TEJanuary 2009
51% / 49%
10.5%
WP(1)
January 2017
49.7% / 50.3%
Settled(2)
(1) Reflects filed debt/equity as final settlement/orders do not specifically include capital structure. Additionally, on January 1, 2024, FirstEnergy consolidated the Pennsylvania Companies into FE PA, making it a new, single operating entity, and will operate under the rate districts of the former Pennsylvania Companies.
(2) Commission-approved settlement agreements did not disclose ROE rates.

MARYLAND

PE operates under MDPSC approved base rates that were effective as of October 19, 2023. PE also provides SOS pursuant to a combination of settlement agreements, MDPSC orders and regulations, and statutory provisions. SOS supply is competitively procured in the form of rolling contracts of varying lengths through periodic auctions that are overseen by the MDPSC and a third-party monitor. Although settlements with respect to SOS supply for PE customers have expired, service continues in the same manner until changed by order of the MDPSC. PE recovers its costs plus a return for providing SOS.
On March 22, 2023, PE filed a base rate case with the MDPSC, utilizing a test year based on twelve months of actual 2022 data. The base rate case request included an annual increase in base distribution rates of $50.4 million, plus a request to establish a regulatory asset (or liability) to recover (or refund) in a subsequent base rate case the net differences between the amount of pension and OPEB expense requested in the proceeding (based on average expense from 2018 to 2022) and the actual annual amount each year using the delayed recognition method. The rate case additionally requested approval to continue an EDIS to fund three service reliability and resiliency programs, two new proposed programs to assist low-income customers and cost recovery of certain expenses associated with PE’s pilot electric vehicle charger program and its COVID-19 pandemic response. On October 18, 2023, the MDPSC approved an annual increase in base distribution rates of $28 million, effective October 19, 2023. The order denied PE’s request to establish a pension/OPEB regulatory asset (or liability), allowed recovery of most COVID-19 deferred costs; and rejected the continuation of PE’s EDIS, as PE's reliability has improved such that the surcharge recovery mechanism is no longer merited at this time. The MDPSC also ordered an independent audit of certain allocations from FESC to PE and denied recovery of approximately $12 million in rate base associated with certain corporate support costs recorded to capital accounts resulting from the FERC Audit. On January 3, 2024, the MDPSC issued an order granting PE’s request for reconsideration and increased PE’s allowed distribution rates by another $0.7 million.

The EmPOWER Maryland program requires each electric utility to file a plan to reduce electric consumption and demand 0.2% per year, up to the ultimate goal of 2% annual savings. PE recovers program investments with a return through an annually reconciled surcharge, with most costs subject to recovery over a five-year period with a return on the unamortized balance. Maryland law only allows for the utility to recover lost distribution revenue attributable to energy efficiency or demand reduction programs through a base rate case proceeding. On August 1, 2023, PE filed its proposed plan for the 2024-2026 cycle as required by the MDPSC. Consistent with a December 29, 2022, order by the MDPSC phasing out the ability of Maryland utilities to earn a return on EmPOWER investments, PE will be required to expense 33% of its EmPOWER program costs in 2024, 67% in 2025 and 100% in 2026. Notwithstanding the order to phase out PE’s ability to earn a return on its EmPOWER investments, all previously unamortized costs for prior cycles will continue to earn a return and be collected by the end of 2029, consistent with the plan PE submitted on January 11, 2023. In the 2024-2026 order issued on December 29, 2023, the period to pay down the amortized balances was extended through the end of 2031. Additionally at the direction of the MDPSC, PE together with other Maryland utilities are required to address GHG reductions in addition to energy efficiency. In compliance with the MDPSC directive, PE submitted three scenarios with projected costs over a three-year cycle of $310 million, $354 million, and $510 million, respectively. The MDPSC conducted hearings on the proposed plans for all Maryland utilities on November 6-8, 2023. On December 29, 2023, the MDPSC issued an order approving the $310 million scenario for most programs, with some modifications.

On April 17, 2023, PE submitted a proposal to the MDPSC seeking approval to end its PPA with the Warrior Run generating station. The PPA for Warrior Run was a requirement of the Public Utility Regulatory Policies Act of 1978. PE’s Maryland customers currently pay a surcharge on their electric bill in connection with the Warrior Run PPA, which fluctuates from year to year based on the difference between what PE pays for the output of the plant and what PE is able to recover by reselling that output into PJM. PE negotiated a termination of the PPA, which the MDPSC approved on June 21, 2023, and became effective June 28, 2023, requiring it to pay Warrior Run a fixed amount of $51 million annually through 2029, for a total of $357 million. During the second quarter of 2023, a liability was established for the $357 million termination fee, of which $55 million was included in “Other current liabilities” and $302 million in “Other non-current liabilities”, and as the cost of the termination fee will be recovered through the current surcharge, an offsetting regulatory asset was established on FirstEnergy’s Consolidated Balance Sheets, and results in no impact to FirstEnergy’s or PE’s current or future earnings and is expected to result in savings for PE’s Maryland customers. On July 26, 2023, the MDPSC approved the change in surcharge, effective August 1, 2023, after previously approving the termination of the agreement.

NEW JERSEY

JCP&L operates under NJBPU approved rates that took effect as of January 1, 2021, and were effective for customers as of November 1, 2021. JCP&L provides BGS for retail customers who do not choose a third-party EGS and for customers of third- party EGSs that fail to provide the contracted service. All New Jersey EDCs participate in this competitive BGS procurement process and recover BGS costs directly from customers as a charge separate from base rates.

On March 16, 2023, JCP&L filed a base rate case with the NJBPU, utilizing a test year based on six months of actual data for the second half of calendar year 2022, and six months of forecasted data for the first half of calendar year 2023. The rate case requested an annual net increase in base distribution revenues of approximately $185 million, plus a request to establish a regulatory asset (or liability) to recover (or refund) in a subsequent base rate case the net differences between the amount of pension and OPEB expense requested in the proceeding (based on 2023 expense) and the actual annual amount each year using the delayed recognition method. JCP&L updated its base rate case in filings made on June 2, 2023 and August 7, 2023 to provide actual test-year data for the twelve months ended June 30, 2023, and update its proposed annual net increase in base rate distribution revenues to approximately $192 million. In addition to the above, JCP&L’s request includes, among other things, approval of two new proposed programs to assist low-income customers, cost recovery of certain investments and expenses associated with its electric vehicle and AMI programs, an update of its depreciation rates, modifications to its storm cost recovery, and tariff modifications to update standard construction costs. A procedural schedule was adopted with evidentiary hearings to be held the week of January 8, 2024. On October 17, 2023, JCP&L requested a suspension of the procedural schedule to enter into
formal settlement discussions, which all parties agreed, and the administrative law judge granted the same day. On February 2, 2024, JCP&L, joined by various parties, filed a stipulated settlement with the NJBPU resolving JCP&L’s request for a distribution base rate increase. The settlement provides for an $85 million annual base distribution revenues increase for JCP&L, which, if approved by the NJBPU, is expected to take effect February 15, 2024, and be effective for customers on June 1, 2024. Until those new rates become effective for customers, JCP&L would begin to amortize an existing regulatory liability totaling approximately $18 million to offset the base rate increase that otherwise would have occurred in this period. Under the base rate case settlement agreement, JCP&L also agreed to a two-phase reliability improvement plan to enhance the reliability related to 18 high-priority circuits, the first phase of which will begin no later than March 1, 2024 and represents an approximate investment of $95 million. JCP&L expects to amend its pending EnergizeNJ petition upon receipt of NJBPU approval of the base rate case settlement, to include the second phase of its reliability improvement plan that is expected to address any remaining high-priority circuits not addressed in the first phase. The settlement did not include the request to establish a regulatory asset (or liability) to recover (or refund) net differences between the amount of pension and OPEB expense requested in the proceeding and the actual annual amount each year using the delayed recognition method, however, JCP&L has the ability to pursue in a future separate proceeding.

JCP&L has implemented energy efficiency and peak demand reduction programs in accordance with the New Jersey Clean Energy Act as approved by the NJBPU in April 2021. The NJBPU approved plans include recovery of lost revenues resulting from the programs and a three-year plan (July 2021-June 2024) including total program costs of $203 million, of which $160 million of investment is recovered over a ten-year amortization period with a return as well as $43 million in operations and maintenance expenses and financing costs recovered on an annual basis. On December 5, 2023, JCP&L filed a petition with the NJBPU for a six-month extension of EE&C Plan I, which was originally scheduled to end on June 30, 2024, but would end on December 31, 2024, with the extension. The proposed budget for the extension period would add approximately $69 million to the original program cost. Under the proposal, JCP&L would recover the costs of the extension period and the revenue impact of sales losses resulting therefrom through two separate tariff riders. On December 1, 2023, JCP&L filed a related petition with the NJBPU requesting approval of its EE&C Plan II, which covers the January 1, 2025 through June 30, 2027 period and has a proposed budget of approximately $964 million. EE&C Plan II consists of a portfolio of ten energy efficiency programs, one peak demand reduction program and one building decarbonization program. Under the proposal, JCP&L would recover its EE&C Plan II revenue requirements and lost revenues from reduced electricity sales associated with EE&C Plan II.

On March 6, 2023, the NJBPU issued final rules modifying its regulations to reflect its CTA policy in base rate cases to: (i) calculate savings using a five-year look back from the beginning of the test year; (ii) allocate 100% of CTA savings to customers; and (iii) exclude transmission assets of EDCs in the savings calculation. The final rules of practice were applied by JCP&L in its most recent base rate case filing described above.

On October 28, 2020, the NJBPU approved a stipulated settlement between JCP&L and various parties, resolving JCP&L’s request for distribution base rate increase. The settlement provided for a $94 million annual base distribution revenues increase for JCP&L based on an ROE of 9.6%, which became effective for customers on November 1, 2021. The settlement additionally provided that JCP&L would be subject to a management audit, which began in May 2021. On April 12, 2023, the NJBPU accepted the final management audit report for filing purposes and ordered that interested stakeholders file comments on the report by May 22, 2023, which deadline was extended until July 31, 2023. JCP&L filed its comments on July 31, 2023. The parties have filed responses.

On July 2, 2020, the NJBPU issued an order allowing New Jersey utilities to track and create a regulatory asset for future recovery of all prudently incurred incremental costs arising from the COVID-19 pandemic beginning March 9, 2020 and continuing until the New Jersey Governor issues an order stating that the COVID-19 pandemic is no longer in effect. New Jersey utilities can request recovery of such regulatory asset in a stand-alone COVID-19 regulatory asset filing or future base rate case. On October 28, 2020, the NJBPU issued an order expanding the scope of the proceeding to examine all pandemic issues, including recovery of the COVID-19 regulatory assets, by way of a generic proceeding. No moratorium on residential disconnections remains in effect for investor-owned electric utilities such as JCP&L. Legislation was enacted on March 25, 2022, prohibiting utilities from disconnecting electric service to customers that have applied for utility bill assistance before June 15, 2022 until such time as the state agency administering the assistance program makes a decision on the application and further requiring that all utilities offer a deferred payment arrangement meeting certain minimum criteria after the state agency’s decision on the application has been made. On July 17, 2023, JCP&L submitted a stand-alone filing to recover approximately $31 million, through October 1, 2023, in incremental costs and interest incurred during the COVID-19 pandemic.

On September 17, 2021, in connection with Mid-Atlantic Offshore Development, LLC, a transmission company jointly owned by Shell New Energies US and EDF Renewables North America, JCP&L submitted a proposal to the NJBPU and PJM to build transmission infrastructure connecting offshore wind-generated electricity to the New Jersey power grid. On October 26, 2022, the JCP&L proposal was accepted, in part, in an order issued by NJBPU. The proposal, as accepted, included approximately $723 million in investments for JCP&L to both build new and upgrade existing transmission infrastructure. JCP&L’s proposal projects an investment ROE of 10.2% and includes the option for JCP&L to acquire up to a 20% equity stake in Mid-Atlantic Offshore Development, LLC. The resulting rates associated with the project are expected to be shared among the ratepayers of all New Jersey electric utilities. On April 17, 2023, JCP&L applied for the FERC “abandonment” transmission rates incentive, which would provide for recovery of 100% of the cancelled prudent project costs that are incurred after the incentive is approved, and 50% of the costs incurred prior to that date, in the event that some or all of the project is cancelled for reasons beyond
JCP&L’s control. FERC staff subsequently requested additional information on JCP&L’s application, which JCP&L provided. On August 21, 2023, FERC approved JCP&L’s application, effective August 22, 2023. On October 31, 2023, offshore wind developer, Orsted, announced plans to cease development of two offshore wind projects in New Jersey—Ocean Wind 1 and 2—having a combined planned capacity of 2,248 MW. At this time, Orsted’s announcement does not affect JCP&L’s awarded projects and JCP&L is moving forward with preconstruction activities for the planned transmission infrastructure. Construction is expected to begin in 2025.

Consistent with the commitments made in its proposal to the NJBPU, JCP&L formally submitted in November 2023 the first part of its application to the United States Department of Energy to finance a portion of the project using low-interest rate loans available under the United States Department of Energy’s Energy Infrastructure Reinvestment Program of the IRA of 2022. JCP&L anticipates submitting the second part of its two-part application in the first quarter of 2024.

On November 9, 2023, JCP&L filed a petition for approval of its second EnergizeNJ with the NJBPU that would, among other things, support grid modernization, system resiliency and substation modernization in technologies designed to provide enhanced customer benefits. JCP&L proposes EnergizeNJ will be implemented over a five-year budget period with estimated costs of approximately $935 million over the deployment period, of which, $906 million is capital investments and $29 million is operating and maintenance expenses. Under the proposal, the costs of EnergizeNJ would be recovered through JCP&L's base rates via annual and semi-annual base rate adjustment filings. Public hearings have been requested but are not yet scheduled. JCP&L has requested that the NJBPU issue a final decision and order no later than May 22, 2024, based on a June 1, 2024, commencement date for EnergizeNJ. JCP&L anticipates filing amendments to the EnergizeNJ program after receipt of approval from the NJBPU of the base rate case stipulation that was filed on February 2, 2024.

OHIO

The Ohio Companies operate under PUCO-approved base distribution rates that became effective in 2009. The Ohio Companies currently operate under ESP IV, effective June 1, 2016 and continuing through May 31, 2024, that continues the supply of power to non-shopping customers at a market-based price set through an auction process. ESP IV also continues the Rider DCR, which supports continued investment related to the distribution system for the benefit of customers, with increased revenue caps of $20 million per year from June 1, 2019 through May 31, 2022; and $15 million per year from June 1, 2022 through May 31, 2024. In addition, ESP IV includes: (1) continuation of a base distribution rate freeze through May 31, 2024; (2) a goal across FirstEnergy to reduce CO2 emissions by 90% below 2005 levels by 2045; and (3) contributions, totaling $51 million to: (a) fund energy conservation programs, economic development and job retention in the Ohio Companies’ service territories; (b) establish a fuel-fund in each of the Ohio Companies’ service territories to assist low-income customers; and (c) establish a Customer Advisory Council to ensure preservation and growth of the competitive market in Ohio.

On April 5, 2023, the Ohio Companies filed an application with the PUCO for approval of ESP V, for an eight-year term beginning June 1, 2024, and continuing through May 31, 2032. ESP V proposes to continue providing power to non-shopping customers at market-based prices set through an auction process, with process enhancements designed to reduce costs to customers. ESP V also proposes to continue riders supporting investment in the Ohio Companies’ distribution system, including Rider DCR with annual revenue cap increases of $15 to $21 million per year, based on reliability performance, and Rider AMI for recovery of approved grid modernization investments. ESP V proposes new riders to support continued maintenance of the distribution system, including vegetation management and storm restoration operating expense. In addition, ESP V proposes four-year energy efficiency and peak demand reduction programs for residential and commercial customers, with cost recovery spread over eight years. ESP V further includes a commitment to spend $52 million in total over the eight-year term, without recovery from customers, on initiatives to assist low-income customers, education and incentives to help ensure customers have good experiences with electric vehicles. Hearings commenced on November 7, 2023 and concluded on December 6, 2023. On December 6, 2023, certain intervenors filed a motion requesting a limited stay of the Ohio Companies’ proposal to continue Rider DCR. The Ohio Companies contested the motion, which is pending.

On May 16, 2022, the Ohio Companies filed their application for determination of the existence of SEET under ESP IV for calendar year 2021, which demonstrated that each of the individual Ohio Companies did not have significantly excessive earnings. This matter remains pending before the PUCO.

On July 15, 2022, the Ohio Companies filed an application with the PUCO for approval of phase two of their distribution grid modernization plan that would, among other things, provide for the installation of an additional 700 thousand smart meters, distribution automation equipment on approximately 240 distribution circuits, voltage regulating equipment on approximately 220 distribution circuits, and other investments and pilot programs in related technologies designed to provide enhanced customer benefits. The Ohio Companies propose that phase two will be implemented over a four-year budget period with estimated capital investments of approximately $626 million and operations and maintenance expenses of approximately $144 million over the deployment period. Under the proposal, costs of phase two of the grid modernization plan would be recovered through the Ohio Companies’ AMI rider, pursuant to the terms and conditions approved in ESP IV. Hearings are scheduled to commence on April 16, 2024. On January 22, 2024, OCC filed a motion requesting a stay of phase two. The Ohio Companies contested the motion, which is pending.
On September 8, 2020, the OCC filed motions in the Ohio Companies’ corporate separation audit and DMR audit dockets, requesting the PUCO to open an investigation and management audit, hire an independent auditor, and require FirstEnergy to show it did not improperly use money collected from consumers or violate any utility regulatory laws, rules or orders in its activities regarding HB 6. On December 30, 2020, in response to the OCC's motion, the PUCO reopened the DMR audit docket, and directed PUCO staff to solicit a third-party auditor and conduct a full review of the DMR to ensure funds collected from customers through the DMR were only used for the purposes established in ESP IV. On June 2, 2021, the PUCO selected an auditor, and the auditor filed the final audit report on January 14, 2022, which made certain findings and recommendations. The report found that spending of DMR revenues was not required to be tracked, and that DMR revenues, like all rider revenues, are placed into the regulated money pool as a matter of routine, where the funds lose their identity. Therefore, the report could not suggest that DMR funds were used definitively for direct or indirect support for grid modernization. The report also concluded that there was no documented evidence that ties revenues from the DMR to lobbying for the passage of HB 6, but also could not rule out with certainty uses of DMR funds to support the passage of HB 6. The report further recommended that the regulated companies' money pool be audited more frequently and the Ohio Companies adopt formal dividend policies. Final comments and responses were filed by parties during the second quarter of 2022.

On September 15, 2020, the PUCO opened a new proceeding to review the political and charitable spending by the Ohio Companies in support of HB 6 and the subsequent referendum effort, and directing the Ohio Companies to show cause, demonstrating that the costs of any political or charitable spending in support of HB 6, or the subsequent referendum effort, were not included, directly or indirectly, in any rates or charges paid by customers. The Ohio Companies initially filed a response stating that the costs of any political or charitable spending in support of HB 6, or the subsequent referendum effort, were not included, directly or indirectly, in any rates or charges paid by customers, but on August 6, 2021, filed a supplemental response explaining that, in light of the facts set forth in the DPA and the findings of the Rider DCR audit report further discussed below, political or charitable spending in support of HB 6, or the subsequent referendum effort, affected pole attachment rates paid by approximately $15 thousand. On October 26, 2021, the OCC filed a motion requesting the PUCO to order an independent external audit to investigate FE’s political and charitable spending related to HB 6, and to appoint an independent review panel to retain and oversee the auditor. In November and December 2021, parties filed comments and reply comments regarding the Ohio Companies’ original and supplemental responses to the PUCO’s September 15, 2020, show cause directive. On May 4, 2022, the PUCO selected a third-party auditor to determine whether the show cause demonstration submitted by the Ohio Companies is sufficient to ensure that the cost of any political or charitable spending in support of HB 6 or the subsequent referendum effort was not included, directly or indirectly, in any rates or charges paid by ratepayers.

In connection with an ongoing audit of the Ohio Companies’ policies and procedures relating to the code of conduct rules between affiliates, on November 4, 2020, the PUCO initiated an additional corporate separation audit as a result of the FirstEnergy leadership transition announcement made on October 29, 2020, as further discussed below. The additional audit is to ensure compliance by the Ohio Companies and their affiliates with corporate separation laws and the Ohio Companies’ corporate separation plan. The additional audit is for the period from November 2016 through October 2020. The final audit report was filed on September 13, 2021. The audit report makes no findings of major non-compliance with Ohio corporate separation requirements, minor non-compliance with eight requirements, and findings of compliance with 23 requirements. Parties filed comments and reply comments on the audit report.

In connection with an ongoing annual audit of the Ohio Companies’ Rider DCR for 2020, and as a result of disclosures in FirstEnergy’s Form 10-K for the year ended December 31, 2020 (filed on February 18, 2021), the PUCO expanded the scope of the audit on March 10, 2021, to include a review of certain transactions that were either improperly classified, misallocated, or lacked supporting documentation, and to determine whether funds collected from customers were used to pay the vendors, and if so, whether or not the funds associated with those payments should be returned to customers through Rider DCR or through an alternative proceeding. On August 3, 2021, the auditor filed its final report on this phase of the audit, and the parties submitted comments and reply comments on this audit report in October 2021. Additionally, on September 29, 2021, the PUCO expanded the scope of the audit in this proceeding to determine if the costs of the naming rights for FirstEnergy Stadium have been recovered from the Ohio Companies’ customers. On November 19, 2021, the auditor filed its final report, in which the auditor concluded that the FirstEnergy Stadium naming rights expenses were not recovered from Ohio customers. On December 15, 2021, the PUCO further expanded the scope of the audit to include an investigation into an apparent nondisclosure of a side agreement in the Ohio Companies’ ESP IV settlement proceedings, but stayed its expansion of the audit until otherwise ordered by the PUCO.

On August 16, 2022, the U.S. Attorney for the Southern District of Ohio requested that the PUCO stay the above pending HB 6- related matters for a period of six months, which request was granted by the PUCO on August 24, 2022. On February 22, 2023, the U.S. Attorney for the Southern District of Ohio again requested that the PUCO stay the above pending HB-6 related matters for a period of six months, which request was granted by the PUCO on March 8, 2023. On August 10, 2023, the U.S. Attorney for the Southern District of Ohio requested that the PUCO stay the above pending HB 6-related matters for a period of six additional months, which was approved by the PUCO on August 23, 2023. On September 22, 2023, OCC filed an application for rehearing challenging the PUCO’s August 23, 2023, order, which the PUCO denied on October 18, 2023. On November 17, 2023, OCC filed an application for rehearing challenging the October 18, 2023 entry to the extent the PUCO decided not to stay ESP V as well as Grid Mod I and Grid Mod II along with the investigations. On November 27, 2023, the Ohio Companies filed a memorandum contra OCC’s application for rehearing. The four cases remain stayed in their entirety, including discovery and motions, and all related procedural schedules are vacated.
In the fourth quarter of 2020, motions were filed with the PUCO requesting that the PUCO amend the Ohio Companies’ riders for collecting the OVEC-related charges required by HB 6 to provide for refunds in the event such provisions of HB 6 are repealed. Neither the Ohio Companies nor FE benefit from the OVEC-related charges the Ohio Companies collect. Instead, the Ohio Companies are further required by HB 6 to remit all the OVEC-related charges they collect to non-FE Ohio electric distribution utilities. The Ohio Companies contested the motions, which are pending before the PUCO.

On May 15, 2023, the Ohio Companies filed their application for determination of the existence of SEET under ESP IV for calendar year 2022, which demonstrated that each of the individual Ohio Companies did not have significantly excessive earnings. This matter remains pending before the PUCO.

See Note 14, "Commitments, Guarantees and Contingencies" below for additional details on the government investigations and subsequent litigation surrounding the investigation of HB 6.

PENNSYLVANIA

The Pennsylvania Companies operated under rates approved by the PPUC, effective as of January 27, 2017. On January 1, 2024, each of the Pennsylvania Companies merged with and into FE PA. As a result of the PA Consolidation, FE PA will have five rate districts in Pennsylvania – four that correspond to the territories previously serviced by ME, PN, Penn, and WP and one rate district that corresponds to WP’s service provided to The Pennsylvania State University. The rate districts created by the PA Consolidation will continue the current rate structure of ME, PN, Penn, and WP until the earlier of 2033 or in the fourth base rate case filed after January 1, 2025.

Pursuant to Pennsylvania Act 129 of 2008 and PPUC orders, the Pennsylvania Companies implemented energy efficiency and peak demand reduction programs with demand reduction targets, relative to 2007 to 2008 peak demands, at 2.9% MW for ME, 3.3% MW for PN, 2.0% MW for Penn, and 2.5% MW for WP; and energy consumption reduction targets, as a percentage of the Pennsylvania Companies’ historic 2009 to 2010 reference load at 3.1% MWh for ME, 3.0% MWh for PN, 2.7% MWh for Penn, and 2.4% MWh for WP. The fourth phase of FE PA’s energy efficiency and peak demand reduction program, which runs for the five -year period beginning June 1, 2021 through May 31, 2026, was approved by the PPUC on June 18, 2020, providing through cost recovery of approximately $390 million to be recovered through Energy Efficiency and Conservation Phase IV Riders for each FE PA rate district.

Pennsylvania EDCs are permitted to seek PPUC approval of an LTIIP for infrastructure improvements and costs related to highway relocation projects, after which a DSIC may be approved to recover LTIIP costs. On January 16, 2020, the PPUC approved the Pennsylvania Companies’ LTIIPs for the five-year period beginning January 1, 2020 and ending December 31, 2024 for a total capital investment of approximately $572 million for certain infrastructure improvement initiatives. On June 25, 2021, the Pennsylvania Office of Consumer Advocate filed a complaint against Penn’s quarterly DSIC rate, disputing the recoverability of the Companies’ automated distribution management system investment under the DSIC mechanism. On January 26, 2022, the parties filed a joint petition for settlement that resolves all issues in this matter, which was approved by the PPUC without modification on April 14, 2022.

Following the Pennsylvania Companies’ 2016 base rate proceedings, the PPUC ruled in a separate proceeding related to the DSIC mechanisms that the Pennsylvania Companies were not required to reflect federal and state income tax deductions related to DSIC-eligible property in DSIC rates. The decision was appealed to the Pennsylvania Supreme Court and in July 2021 the court upheld the Pennsylvania Commonwealth Court’s reversal of the PPUC’s decision and remanded the matter back to the PPUC for determination as to how DSIC calculations shall account for accumulated deferred income taxes and state taxes. The PPUC issued the order as directed.

On March 6, 2023, FirstEnergy filed applications with the PPUC, NYPSC and FERC seeking approval to consolidate the Pennsylvania Companies into a new, single operating entity. The PA Consolidation includes, among other steps: (a) the transfer of certain Pennsylvania-based transmission assets owned by WP to KATCo, (b) the contribution of Class B equity interests of MAIT then held by PN and ME to FE (and ultimately transferred to FET as part of the FET Minority Equity Interest Sale as further described above), (c) the formation of FE PA and (d) the merger of each of the Pennsylvania Companies with and into FE PA, with FE PA surviving such mergers as the successor-in-interest to all assets and liabilities of the Pennsylvania Companies. On August 30, 2023, the parties filed a settlement agreement recommending that the PPUC approve the PA Consolidation subject to the terms of the settlement, which include among other things, $650 thousand over five years in bill assistance for income-eligible customers and the Pennsylvania Companies’ commitment to (i) not seek full distribution rate unification until the earlier of 10 years or in the fourth base rate case filed after January 1, 2025 and (ii) track and share with customers certain operational and administrative efficiency costs associated with the PA Consolidation. The PPUC, NYPSC and FERC approved FirstEnergy’s applications on December 7, 2023, November 16, 2023, and August 14, 2023, respectively. The transaction closed on January 1, 2024 making FE PA FirstEnergy's only regulated utility in Pennsylvania.

On May 5, 2023, FirstEnergy and Brookfield submitted applications to FERC and to the PPUC to facilitate the FET Minority Equity Interest Sale. On May 12, 2023, the parties also filed an application with the VSCC, which was approved on June 20, 2023. On August 14, 2023, FERC issued an order approving the FET Minority Equity Interest Sale. On November 24, 2023,
CFIUS notified FET, Brookfield and the Abu Dhabi Investment Authority that it has determined that there were no unresolved national security issues and its review of the transaction was concluded. On November 29, 2023, the parties filed a settlement agreement recommending that the PPUC approve the transaction subject to the terms of the settlement, which include among other things, a number of ring-fencing provisions and a commitment to improve transmission reliability over the next five years. The settlement is currently pending PPUC approval.

WEST VIRGINIA

MP and PE provide electric service to all customers through traditional cost-based, regulated utility ratemaking and operate under WVPSC-approved rates that became effective in February 2015. MP and PE recover net power supply costs, including fuel costs, purchased power costs and related expenses, net of related market sales revenue through the ENEC. MP’s and PE’s ENEC rate is updated annually.

On August 25, 2022, MP and PE filed with the WVPSC their annual ENEC case requesting an increase in ENEC rates of $183.8 million beginning January 1, 2023, which represents a 12.2% increase to the rates then in effect. The increase was driven by an under recovery during the review period (July 1, 2021, to June 30, 2022) of approximately $145 million due to higher coal, reagent, and emission allowance expenses. This filing additionally addresses, among other things, the WVPSC’s May 2022 request for a prudence review of current rates. At a hearing on December 8, 2022, the parties in the case presented a unanimous settlement to increase rates by approximately $92 million, effective January 1, 2023, and carry over to MP and PE’s 2023 ENEC case, approximately $92 million at a carrying charge of 4%. In an order dated December 30, 2022, the WVPSC approved the settlement with respect to the proposed rate increase, but MP and PE rates remain subject to a prudence review in their 2023 ENEC case. The order also instructed MP to evaluate the feasibility of purchasing the 1,300 MW Pleasants Power Station and file a summary of the evaluation, which MP and PE filed on March 31, 2023. MP and PE provided the WVPSC with regular status reports throughout the second quarter of 2023 regarding the process of their evaluation. Subsequently, the owner of Pleasants entered into an agreement to sell Pleasants to an indirect wholly owned subsidiary of Omnis Global Technologies, LLC, which transaction closed on August 1, 2023. As a result, MP and PE ceased consideration of the possible purchase of Pleasants and on August 30, 2023, the WVPSC closed the proceeding.

On August 31, 2023, MP and PE filed with the WVPSC their annual ENEC case requesting an increase in ENEC rates of $167.5 million beginning January 1, 2024, which represents a 9.9% increase in overall rates. This increase, which was driven primarily by higher fuel expenses, includes the approximate $92 million carried over from the 2022 ENEC proceeding and a portion of the approximately $267 million under recovery balance at the end of the review period (July 1, 2022 to June 30, 2023). The remaining $75.6 million of the under recovery balance not recovered in 2024 will be deferred for collection during 2025, with an annual carrying charge of 4%. A hearing was held on November 30, 2023, at which time a joint stipulation for settlement that was agreed to by all but one party was presented to the WVPSC. The settlement provides for a net $55.4 million increase in ENEC rates beginning March 27, 2024 with the net deferred ENEC balance of approximately $255 million to be recovered through 2026. There will be no 2024 ENEC case unless MP and PE over or under recover more than $50 million than the 2024 ENEC balance and a party elects to invoke a case filing. An order is expected by March 2024.

On November 22, 2021, MP and PE filed with the WVPSC their plan to construct 50 MWs of solar generation at five sites in West Virginia. The plan includes a tariff to offer solar power to West Virginia customers and cost recovery for MP and PE through a surcharge for any solar investment not fully subscribed by their customers. A hearing was held in mid-March 2022 and on April 21, 2022, the WVPSC issued an order approving, effective May 1, 2022, the requested tariff and requiring MP and PE to subscribe at least 85% of the planned 50 MWs before seeking final tariff approval. MP and PE must seek separate approval from the WVPSC to recover any solar generation costs in excess of the approved tariff. On April 24, 2023, MP and PE sought final tariff approval from the WVPSC for three of the five solar sites, representing 30 MWs of generation, and requested approval of a surcharge to recover any costs above the final approved tariff. The first solar generation site went into service in January 2024 and construction of the remaining four sites are expected to be completed no later than the end of 2025 at a total investment cost of approximately $110 million. On August 23, 2023, the WVPSC approved the customer surcharge and granted approval to construct three of the five solar sites. The surcharge went into effect January 1, 2024.

On January 13, 2023, MP and PE filed a request with the WVPSC seeking approval of new depreciation rates for existing and future capital assets. Specifically, MP and PE are seeking to increase depreciation expense by approximately $76 million per year, primarily for regulated generation-related assets. Any depreciation rates approved by the WVPSC would not become effective until new base rates were established. On August 22, 2023, a unanimous settlement of the case was filed recommending a $33 million per year increase in depreciation expense, effective April 1, 2024. An order from the WVPSC is expected in the first quarter 2024.

On March 2, 2023, the WVPSC ordered an audit of MP and PE focused on: (i) the lobbying and promotional/image building expenses, including those related to HB 6, incurred by MP and PE from 2018 to 2022 (ii) intra-corporate charges, (iii) the accounting for charges included in the ENEC cost recovery accounts of MP and PE during the same time period, and (iv) review and report on the findings, including those specific to MP and PE, set forth in the FERC Audit described below as well as a review and report of the responses by MP and PE thereto. The audit began in September 2023 and concluded with a filing of the report on December 28, 2023. The audit found no evidence that HB 6 related costs were included in the 2022 test year, and no errors or omission were identified that would materially affect lobbying and image building costs or expenses charged to the
ENEC for the period 2018 to 2022. Additionally, there were several recommended adjustments and recommendations, however, none are expected to have a material effect on FirstEnergy, MP or PE. The report was evaluated as part of the ongoing base rate case.

On May 31, 2023, MP and PE filed a base rate case with the WVPSC requesting a total revenue increase of approximately $207 million utilizing a test year of 2022 with adjustments plus a request to establish a regulatory asset (or liability) to recover (or refund) in a subsequent base rate case the net differences between the amount of pension and OPEB expense requested in the proceeding (based on average expense from 2018 to 2022) and the actual annual amount each year using the delayed recognition method. Among other things, the increase includes the approximate $76 million requested in a depreciation case filed on January 13, 2023 and described more fully above, and amounts to support a new low-income customer advocacy program, storm restoration work and service reliability investments. New rates are expected to be effective by the end of March 2024. On January 23, 2024, MP, PE and various parties filed with a joint settlement agreement with the WVPSC, which recommends a base rate increase of $105 million, inclusive of the $33 million increase in depreciation expense. Additionally, the settlement includes a new low-income customer advocacy program, a pilot program for service reliability investments and recovery of costs related to storm restoration, retired generation assets and COVID-19. The settlement did not include the request to establish a regulatory asset (or liability) for recover (or refund) associated with pension and OPEB expense, however, it did not preclude MP and PE from pursuing that in a future separate proceeding. An order is expected by the end of the first quarter of 2024 with new rates to be effective March 27, 2024.

On August 31, 2023, MP and PE filed its biennial review of their vegetation management program and surcharge. MP and PE have proposed an approximate $17 million increase in the surcharge rates, due to an under recovery in the prior two-year period and increased forecast costs. The case was unanimously settled by the parties on November 29, 2023, approved by the WVPSC on January 8, 2024, and the $17 million increase proposed by MP and PE went into effect on January 1, 2024. See Note 14, “Commitments, Guarantees and Contingencies - Environmental Matters - Clean Water Act" below, for additional details on the EPA's ELG.

FERC REGULATORY MATTERS

Under the Federal Power Act, FERC regulates rates for interstate wholesale sales and transmission of electric power, regulatory accounting and reporting under the Uniform System of Accounts, and other matters, including construction and operation of hydroelectric projects. With respect to their wholesale services and rates, the Utilities, AE Supply and the Transmission Companies are subject to regulation by FERC. FERC regulations require JCP&L, MP, PE, WP and the Transmission Companies to provide open access transmission service at FERC-approved rates, terms and conditions. Transmission facilities of JCP&L, MP, PE, WP and the Transmission Companies are subject to functional control by PJM and transmission service using their transmission facilities is provided by PJM under the PJM Tariff. On January 1, 2024, WP transferred certain of its Pennsylvania-based transmission assets to KATCo.

The following table summarizes the key terms of rate orders in effect for transmission customer billings for FirstEnergy's transmission owner entities as of December 31, 2023:
CompanyRates EffectiveCapital StructureAllowed ROE
ATSIJanuary 2015Actual (13-month average)10.38%
JCP&L
January 2020Actual (13-month average)10.20%
MPJanuary 2021
Lower of Actual (13-month average) or 56%
10.45%
PE January 2021
Lower of Actual (13-month average) or 56%
10.45%
WP(1)
January 2021
Lower of Actual (13-month average) or 56%
10.45%
MAITJuly 2017
Lower of Actual (13-month average) or 60%
10.3%
TrAILJuly 2008Actual (year-end)
12.7%(2) / 11.7%(3)
(1) On January 1, 2024, WP transferred certain of its Pennsylvania-based transmission assets to KATCo
(2) TrAIL the Line and Black Oak Static Var Compensator
(3) All other projects


FERC regulates the sale of power for resale in interstate commerce in part by granting authority to public utilities to sell wholesale power at market-based rates upon showing that the seller cannot exert market power in generation or transmission or erect barriers to entry into markets. The Utilities and AE Supply each have the necessary authorization from FERC to sell their wholesale power, if any, in interstate commerce at market-based rates, although in the case of the Utilities major wholesale purchases remain subject to review and regulation by the relevant state commissions.
Federally enforceable mandatory reliability standards apply to the bulk electric system and impose certain operating, record-keeping and reporting requirements on the Utilities, AE Supply, and the Transmission Companies. NERC is the Electric Reliability Organization designated by FERC to establish and enforce these reliability standards, although NERC has delegated day-to-day implementation and enforcement of these reliability standards to six regional entities, including RFC. All of the facilities that FirstEnergy operates are located within the RFC region. FirstEnergy actively participates in the NERC and RFC stakeholder processes, and otherwise monitors and manages its companies in response to the ongoing development, implementation and enforcement of the reliability standards implemented and enforced by RFC.

FirstEnergy believes that it is in material compliance with all currently effective and enforceable reliability standards. Nevertheless, in the course of operating its extensive electric utility systems and facilities, FirstEnergy occasionally learns of isolated facts or circumstances that could be interpreted as excursions from the reliability standards. If and when such occurrences are found, FirstEnergy develops information about the occurrence and develops a remedial response to the specific circumstances, including in appropriate cases “self-reporting” an occurrence to RFC. Moreover, it is clear that NERC, RFC and FERC will continue to refine existing reliability standards as well as to develop and adopt new reliability standards. Any inability on FirstEnergy’s part to comply with the reliability standards for its bulk electric system could result in the imposition of financial penalties, or obligations to upgrade or build transmission facilities, that could have a material adverse effect on its financial condition, results of operations, and cash flows.

FERC Audit

FERC’s Division of Audits and Accounting initiated a nonpublic audit of FESC in February 2019. Among other matters, the audit is evaluating FirstEnergy’s compliance with certain accounting and reporting requirements under various FERC regulations. On February 4, 2022, FERC filed the final audit report for the period of January 1, 2015 through September 30, 2021, which included several findings and recommendations that FirstEnergy has accepted. The audit report included a finding and related recommendation on FirstEnergy’s methodology for allocation of certain corporate support costs to regulatory capital accounts under certain FERC regulations and reporting. Effective in the first quarter of 2022 and in response to the finding, FirstEnergy had implemented a new methodology for the allocation of these corporate support costs to regulatory capital accounts for its regulated distribution and transmission companies on a prospective basis. With the assistance of an independent outside firm, FirstEnergy completed an analysis during the third quarter of 2022 of these costs and how it impacted certain FERC-jurisdictional wholesale transmission customer rates for the audit period of 2015 through 2021. As a result of this analysis, FirstEnergy recorded in the third quarter of 2022 approximately $45 million ($34 million after-tax) in expected customer refunds, plus interest, due to its wholesale transmission customers and reclassified approximately $195 million of certain transmission capital assets to operating expenses for the audit period, of which $90 million ($67 million after-tax) are not expected to be recoverable and impacted FirstEnergy’s earnings since they relate to costs capitalized during stated transmission rate time periods. FirstEnergy is currently recovering approximately $105 million of costs reclassified to operating expenses in its transmission formula rate revenue requirements, of which $13 million of costs have been recovered as of December 31, 2023. On December 8, 2023, FERC audit staff issued a letter advising that two unresolved audit matters, primarily related to FirstEnergy’s plan to recover the reclassified operating expenses in formula transmission rates, were being referred to other offices within FERC for further review. These reclassifications also resulted in a reduction to the Regulated Transmission segment’s rate base by approximately $160 million, which is not expected to materially impact FirstEnergy or the segment’s future earnings. The expected wholesale transmission customer refunds were recognized as a reduction to revenue, and the amount of reclassified transmission capital assets that are not expected to be recoverable were recognized within “Other operating expenses” at the Regulated Transmission segment and on FirstEnergy’s Consolidated Statements of Income. Furthermore, FirstEnergy’s distribution utilities are in the process of addressing the outcomes of the FERC Audit with the applicable state commissions and proceedings, which includes seeking continued rate base treatment of approximately $310 million of certain corporate support costs allocated to distribution capital assets. If FirstEnergy is unable to recover these transmission or distribution costs, it could result in future charges and/or adjustments and have an adverse impact on FirstEnergy’s financial condition.

ATSI ROE – Ohio Consumers Counsel v. ATSI, et al.

On February 24, 2022, the OCC filed a complaint with FERC against ATSI, AEP’s Ohio affiliates and American Electric Power Service Corporation, and Duke Energy Ohio, LLC asserting that FERC should reduce the ROE utilized in the utilities’ transmission formula rates by eliminating the 50 basis point adder associated with RTO membership, effective February 24, 2022. The OCC contends that this result is required because Ohio law mandates that transmission owning utilities join an RTO and that the 50 basis point adder is applicable only where RTO membership is voluntary. On December 15, 2022, FERC denied the complaint as to ATSI and Duke, but granted it as to AEP. AEP and OCC appealed FERC’s orders to the Sixth Circuit. FirstEnergy is actively participating in the appeal and the case remains pending. FirstEnergy is unable to predict the outcome of this proceeding, but it is not expected to have a material impact.

Transmission ROE Methodology

On March 20, 2020, FERC initiated a rulemaking proceeding on the transmission rate incentives provisions of Section 219 of the 2005 Energy Policy Act. FirstEnergy submitted comments through the Edison Electric Institute and as part of a consortium of PJM Transmission Owners. In a supplemental rulemaking proceeding that was initiated on April 15, 2021, FERC requested comments on, among other things, whether to require utilities that have been members of an RTO for three years or more and
that have been collecting an “RTO membership” ROE incentive adder to file tariff updates that would terminate collection of the incentive adder. Initial comments on the proposed rule were filed on June 25, 2021, and reply comments were filed on July 26, 2021. The rulemaking remains pending before FERC. FirstEnergy is a member of PJM and its transmission subsidiaries could be affected by the supplemental proposed rule. FirstEnergy participated in comments on the supplemental rulemaking that were submitted by a group of PJM transmission owners and by various industry trade groups. If there were to be any changes to FirstEnergy's transmission incentive ROE, such changes will be applied on a prospective basis.

Allegheny Power Zone Transmission Formula Rate Filings

On October 29, 2020, MP, PE and WP filed tariff amendments with FERC to implement a forward-looking formula transmission rate, to be effective January 1, 2021. In addition, on October 30, 2020, KATCo filed a proposed new tariff to establish a forward-looking formula rate and requested that the new rate become effective January 1, 2021. In its filing, KATCo explained that while it currently owns no transmission assets, it may build new transmission facilities in the Allegheny zone, and that it may seek required state and federal authorizations to acquire transmission assets from PE and WP by January 1, 2022. These transmission rate filings were accepted for filing by FERC on December 31, 2020, effective January 1, 2021, subject to refund, pending further hearing and settlement procedures and were consolidated into a single proceeding. MP, PE and WP, and KATCo filed uncontested settlement agreements with FERC on January 18, 2023. Also on January 18, 2023, MP, PE and WP filed a motion for interim rates to implement certain aspects of the settled rate. The interim rates were approved by the FERC Chief Administrative Law Judge and took effect on January 1, 2023. As a result of the filed settlement, FirstEnergy recognized a $25 million pre-tax charge during the fourth quarter of 2022, which reflects the difference between amounts originally recorded as assets and amounts which will ultimately be recovered from customers as a result. On May 4, 2023, FERC issued an order approving the settlement agreement without condition or modification. Pursuant to the order, a compliance filing was filed on May 19, 2023, that implemented the terms of the settlement. On June 26, 2023, FERC issued a letter order approving the compliance filing.

Transmission Planning Supplemental Projects: Ohio Consumers Counsel v ATSI, et al.

On September 27, 2023, the OCC filed a complaint against ATSI, PJM and other transmission utilities in Ohio alleging that the PJM Tariff and operating agreement are unjust, unreasonable, and unduly discriminatory because they include no provisions to ensure PJM’s review and approval for the planning, need, prudence and cost-effectiveness of the PJM Tariff Attachment M-3 “Supplemental Projects.” Supplemental Projects are projects that are planned and constructed to address local needs on the transmission system. The OCC demands that FERC: (i) require PJM to review supplemental projects for need, prudence and cost-effectiveness; (ii) appoint an independent transmission monitor to assist PJM in such review; and (iii) require that Supplemental Projects go into rate base only through a “stated rate” procedure whereby prior FERC approval would be needed for projects with costs that exceed an established threshold. ATSI and the other transmission utilities in Ohio and PJM filed comments and the complaint is pending before FERC.