XML 33 R19.htm IDEA: XBRL DOCUMENT v3.19.1
Regulatory Matters
3 Months Ended
Mar. 31, 2019
Regulated Operations [Abstract]  
REGULATORY MATTERS
REGULATORY MATTERS

STATE REGULATION

Each of the Utilities' retail rates, conditions of service, issuance of securities and other matters are subject to regulation in the states in which it operates - in Maryland by the MDPSC, in Ohio by the PUCO, in New Jersey by the NJBPU, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC. The transmission operations of PE in Virginia are subject to certain regulations of the VSCC. In addition, under Ohio law, municipalities may regulate rates of a public utility, subject to appeal to the PUCO if not acceptable to the utility. Further, if any of the FirstEnergy affiliates were to engage in the construction of significant new transmission facilities, depending on the state, they may be required to obtain state regulatory authorization to site, construct and operate the new transmission facility.

MARYLAND

PE operates under MDPSC approved base rates that were effective as of March 23, 2019. PE also provides SOS pursuant to a combination of settlement agreements, MDPSC orders and regulations, and statutory provisions. SOS supply is competitively procured in the form of rolling contracts of varying lengths through periodic auctions that are overseen by the MDPSC and a third-party monitor. Although settlements with respect to SOS supply for PE customers have expired, service continues in the same manner until changed by order of the MDPSC. PE recovers its costs plus a return for providing SOS.

The EmPOWER Maryland program requires each electric utility to file a plan to reduce electric consumption and demand 0.2% per year, up to the ultimate goal of 2% annual savings, for the duration of the 2018-2020 and 2021-2023 EmPOWER Maryland program cycles, to the extent the MDPSC determines that cost-effective programs and services are available. PE's 2016 starting goal under this requirement was 0.97%. PE's approved 2018-2020 EmPOWER Maryland plan continues and expands upon prior years' programs, and adds new programs, for a projected total cost of $116 million over the three-year period. PE recovers program costs subject to a five-year amortization. Maryland law only allows for the utility to recover lost distribution revenue attributable to energy efficiency or demand reduction programs through a base rate case proceeding, and to date, such recovery has not been sought or obtained by PE.

In 2013, the MDPSC required Maryland electric utilities to submit analyses relating to the costs and benefits of making further system and staffing enhancements in order to attempt to reduce storm outage durations. PE's submitted analysis projected that it would require up to approximately $2.7 billion in infrastructure investments over 15 years to attempt to achieve the quickest level of response for the largest storm projected in MDPSC's scenarios. The MDPSC conducted a hearing in September 2014, but has not taken further action on this matter.

On January 19, 2018, PE filed a joint petition along with other utility companies, work group stakeholders and the MDPSC electric vehicle work group leader to implement a statewide electric vehicle portfolio in connection with a 2016 MDPSC proceeding to consider an array of issues relating to electric distribution system design, including matters relating to electric vehicles, distributed energy resources, advanced metering infrastructure, energy storage, system planning, rate design, and impacts on low-income customers. PE proposed an electric vehicle charging infrastructure program at a projected total cost of $12 million, to be recovered over a five-year amortization. On January 14, 2019, the MDPSC approved the petition subject to certain reductions in the scope of the program.

On January 12, 2018, the MDPSC instituted a proceeding to examine the impacts of the Tax Act on the rates and charges of Maryland utilities. PE must track and apply regulatory accounting treatment for the impacts beginning January 1, 2018, and subsequently submitted a report to the MDPSC, estimating that the Tax Act impacts would be approximately $7 million to $8 million annually for PE’s customers. On October 5, 2018, the MDPSC issued an order requiring PE to provide its customers a one-time credit for tax savings through September 30, 2018, which totaled approximately $5 million, and reserved all other Tax Act impacts to be resolved in the pending rate case. In the rate case order issued on March 22, 2019, the MDPSC directed that a further final one-time credit of $3 million be provided to PE's customers within two billing cycles.

On August 24, 2018, PE filed a base rate case with the MDPSC, which it supplemented on October 22, 2018, to update the partially forecasted test year with a full twelve months of actual data. The rate case requested an annual increase in base distribution rates of $19.7 million, plus creation of an EDIS to fund four enhanced service reliability programs. In responding to discovery, PE revised its request for an annual increase in base rates to $17.6 million. The proposed rate increase reflects $7.3 million in annual savings for customers resulting from the recent federal tax law changes. On March 22, 2019, the MDPSC issued a final order that approved a rate increase of $6.2 million, approved three of the four EDIS programs for four years, directed PE to file a new depreciation study within 18 months, and ordered the filing of a new base rate case in four years to correspond to the ending of the approved EDIS programs.

NEW JERSEY

JCP&L operates under NJBPU approved rates that were effective as of January 1, 2017. JCP&L provides BGS for retail customers who do not choose a third-party EGS and for customers of third-party EGSs that fail to provide the contracted service. All New Jersey EDCs participate in this competitive BGS procurement process and recover BGS costs directly from customers as a charge separate from base rates.

In December 2017, the NJBPU issued proposed rules to modify its current CTA policy in base rate cases to: (i) calculate savings using a five-year look back from the beginning of the test year; (ii) allocate savings with 75% retained by the company and 25% allocated to rate payers; and (iii) exclude transmission assets of electric distribution companies in the savings calculation, which were published in the NJ Register in the first quarter of 2018. JCP&L filed comments supporting the proposed rulemaking. On January 17, 2019, the NJBPU approved the proposed CTA rules with no changes.

Also in December 2017, the NJBPU approved its IIP rulemaking. The IIP creates a financial incentive for utilities to accelerate the level of investment needed to promote the timely rehabilitation and replacement of certain non-revenue producing components that enhance reliability, resiliency, and/or safety. On July 13, 2018, JCP&L filed an infrastructure plan, JCP&L Reliability Plus, which proposed to accelerate $386.8 million of electric distribution infrastructure investment over four years to enhance the reliability and resiliency of its distribution system and reduce the frequency and duration of power outages. On January 23, 2019, the NJBPU granted JCP&L's request to temporarily suspend the procedural schedule in the matter pending settlement discussions. On April 23, 2019, JCP&L filed a Stipulation of Settlement with the NJBPU on behalf of the JCP&L, Rate Counsel, NJBPU Staff and New Jersey Large Energy Users Coalition, which provides that JCP&L will invest up to approximately $97 million in capital in its electric distribution system beginning on June 1, 2019 and continuing through December 31, 2020.  The capital investments will occur in incremental projects that fall under the following three categories: (i) Overhead Circuit Reliability and Resiliency; (ii) Substation Reliability Enhancement; and (iii) Distribution Automation. JCP&L shall seek recovery of the capital investment through an accelerated cost recovery mechanism, provided for in the rules, that includes a revenue adjustment calculation and a process for two rate adjustments. JCP&L expects a NJBPU decision in May 2019.

On January 31, 2018, the NJBPU instituted a proceeding to examine the impacts of the Tax Act on the rates and charges of New Jersey utilities. The NJBPU ordered New Jersey utilities to: (1) defer on their books the impacts of the Tax Act effective January 1, 2018; (2) to file tariffs effective April 1, 2018, reflecting the rate impacts of changes in current taxes; and (3) to file tariffs effective July 1, 2018, reflecting the rate impacts of changes in deferred taxes. On March 2, 2018, JCP&L filed a petition with the NJBPU, which included proposed tariffs for a base rate reduction of $28.6 million effective April 1, 2018, and a rider to reflect $1.3 million in rate impacts of changes in deferred taxes. On March 26, 2018, the NJBPU approved JCP&L’s rate reduction effective April 1, 2018, on an interim basis subject to refund, pending the outcome of this proceeding. The NJBPU, however, did not address refunds and other proposed rider tariffs at such time.

OHIO

The Ohio Companies currently operate under ESP IV through May 31, 2024. ESP IV includes Rider DMR, which provides for the Ohio Companies to collect $132.5 million annually for three years beginning in 2017, with the possibility of a two-year extension and is grossed up for federal income taxes, resulting in an approved amount of approximately $168 million annually in 2018 and 2019. Revenues from Rider DMR will be excluded from the significantly excessive earnings test for the initial three-year term but the exclusion will be reconsidered upon application for a potential two-year extension. The PUCO set three conditions for continued recovery under Rider DMR: (1) retention of the corporate headquarters and nexus of operations in Akron, Ohio; (2) no change in control of the Ohio Companies; and (3) a demonstration of sufficient progress in the implementation of grid modernization programs approved by the PUCO. ESP IV also continues a base distribution rate freeze through May 31, 2024. In addition, ESP IV continues the supply of power to non-shopping customers at a market-based price set through an auction process. On February 1, 2019, the Ohio Companies filed with the PUCO an application requesting a two-year extension of Rider DMR at the same amount and conditions.

ESP IV also continues Rider DCR, which supports continued investment related to the distribution system for the benefit of customers, with increased revenue caps of $30 million per year through May 31, 2019; $20 million per year from June 1, 2019 through May 31, 2022; and $15 million per year from June 1, 2022 through May 31, 2024. ESP IV also includes: (1) the collection of lost distribution revenues associated with energy efficiency and peak demand reduction programs; (2) an agreement to file a Grid Modernization Business Plan for PUCO consideration and approval, which was filed in February 2016, and remains pending as part of the grid modernization settlement described below; (3) a goal across FirstEnergy to reduce CO2 emissions by 90% below 2005 levels by 2045; (4) contributions, totaling $51 million to: (a) fund energy conservation programs, economic development and job retention in the Ohio Companies’ service territories; (b) establish a fuel-fund in each of the Ohio Companies’ service territories to assist low-income customers; and (c) establish a Customer Advisory Council to ensure preservation and growth of the competitive market in Ohio; and (5) an agreement to file an application to transition to a straight fixed variable cost recovery mechanism for residential customers' base distribution rates, which filing the PUCO denied on June 13, 2018.

Several parties, including the Ohio Companies, filed applications for rehearing regarding the Ohio Companies’ ESP IV with the PUCO. On August 16, 2017, the PUCO denied all remaining intervenor applications for rehearing, denied the Ohio Companies’ challenges to the modifications to Rider DMR and added a third-party monitor to ensure that Rider DMR funds are spent appropriately. The Ohio Companies then filed an application for rehearing of the PUCO’s August 16, 2017 ruling on the issues of the third-party monitor and the ROE calculation for advanced metering infrastructure, which the PUCO denied. In October 2017, the Sierra Club and the OMAEG filed notices of appeal with the Supreme Court of Ohio appealing various PUCO entries on their applications for rehearing. The Ohio Companies intervened in the appeal, and additional parties subsequently filed notices of appeal with the Supreme Court of Ohio challenging various PUCO entries on their applications for rehearing. On September 26, 2018, the Supreme Court of Ohio denied a July 30, 2018 joint motion filed by the OCC, the NOAC, and the OMAEG to stay the portions of the PUCO's orders and entries under appeal that authorized Rider DMR. Oral argument on the appeals was held on January 9, 2019.

Under Ohio law, the Ohio Companies are required to implement energy efficiency programs that achieve certain annual energy savings and total peak demand reductions. The Ohio Companies’ 2017-2019 plan, as proposed in April 2016, includes a portfolio of energy efficiency programs targeted to a variety of customer segments, including residential customers, low income customers, small commercial customers, large commercial and industrial customers and governmental entities. In December 2016, the Ohio Companies filed a Stipulation and Recommendation with several parties that contained changes to the plan and a decrease in the plan costs. The Ohio Companies anticipate the cost of the plans will be approximately $268 million over the life of the portfolio plans and such costs are expected to be recovered through the Ohio Companies’ existing rate mechanisms. On November 21, 2017, the PUCO issued an order that approved the proposed plans with several modifications, including a cap on the Ohio Companies’ collection of program costs and shared savings set at 4% of the Ohio Companies’ total sales to customers. On December 21, 2017, the Ohio Companies filed an application for rehearing challenging the PUCO’s modifications, which the PUCO denied on January 10, 2018. On March 12, 2018, the Ohio Companies appealed to the Supreme Court of Ohio challenging the PUCO’s imposition of a 4% cost cap. Various other parties also appealed challenging various PUCO entries on their applications for rehearing. Oral argument on the appeals was held on February 20, 2019.

On December 1, 2017, the Ohio Companies filed an application with the PUCO for approval of a DPM Plan. The DPM Plan is a portfolio of approximately $450 million in distribution platform investment projects, which are designed to modernize the Ohio Companies’ distribution grid, prepare it for further grid modernization projects, and provide customers with immediate reliability benefits. On November 9, 2018, the Ohio Companies filed a settlement agreement that provides for the implementation of the first phase of grid modernization plans, including the investment of $516 million over three years to modernize the Ohio Companies’ electric distribution system, and for all tax savings associated with the Tax Act, discussed below, to flow back to customers. On January 25, 2019, the Ohio Companies filed a supplemental settlement agreement that keeps intact the provisions of the settlement described above and adds further customer benefits and protections, which broadened support for the settlement. The settlement has broad support, including PUCO Staff, the OCC, representatives of industrial and commercial customers, a low-income advocate, environmental advocates, hospitals, competitive generation suppliers and other parties. The PUCO conducted a hearing and the settlement agreement remains subject to PUCO approval.

On January 10, 2018, the PUCO opened a case to consider the impacts of the Tax Act and determine the appropriate course of action to pass benefits on to customers. The Ohio Companies, effective January 1, 2018, were required to establish a regulatory liability for the estimated reduction in federal income tax resulting from the Tax Act, and filed comments on February 15, 2018, explaining that customers will save nearly $40 million annually as a result of updating tariff riders for the tax rate changes and that the Ohio Companies’ base distribution rates are not impacted by the Tax Act changes because they are frozen through May 2024. On October 24, 2018, the PUCO entered an Order in its investigation into the impacts of the Tax Act on Ohio's utilities directing that by January 1, 2019, all Ohio rate-regulated utility companies, unless ordered otherwise, file applications not for an increase in rates to reflect the impact of the Tax Act on each specific utility's current rates. On October 30, 2018, the Ohio Companies filed an application to open a new proceeding for the implementation of matters relating to the impact of the Tax Act. As discussed further above, on November 9, 2018, the Ohio Companies filed a settlement agreement that provides for all tax savings associated with the Tax Act to flow back to customers and for the implementation of the first phase of grid modernization plans. As part of the agreement, the Ohio Companies also filed an application for approval of a rider to return the remaining tax savings to customers following PUCO approval of the settlement. On December 19, 2018, the PUCO upheld its January 10, 2018 ruling that utilities should be required to establish a deferred tax liability, effective January 1, 2018, in response to the Tax Act. On January 25, 2019, the Ohio Companies filed a supplemental settlement agreement that keeps intact the provisions of the settlement described above and adds further customer benefits and protections, which broadened support for the settlement. The PUCO conducted a hearing and the settlement agreement remains subject to PUCO approval.

The Ohio Companies’ Rider NMB is designed to recover non-market-based transmission-related costs imposed on or charged to the Ohio Companies by FERC or PJM. On December 14, 2018, the Ohio Companies filed an application for a review of their 2019 Rider NMB, including recovery of future Legacy RTEP costs and previously absorbed Legacy RTEP costs, net of refunds received from PJM. On February 27, 2018, the PUCO issued an Order directing the Ohio Companies to file revised final tariffs recovering Legacy RTEP costs incurred since May 31, 2018, but excluding recovery of approximately $95 million in Legacy RTEP costs incurred prior to May 31, 2018, net of refunds received from PJM. The PUCO solicited comments on whether the Ohio Companies should be permitted to recover the Legacy RTEP charges incurred prior to May 31, 2018. The Ohio Companies, OCC and OMAEG filed comments on March 29, 2019. The Ohio Companies filed reply comments on April 15, 2019.

PENNSYLVANIA

The Pennsylvania Companies operate under rates approved by the PPUC, effective as of January 27, 2017. These rates were adjusted for the net impact of the Tax Act, effective March 15, 2018. The net impact of the Tax Act for the period January 1, 2018 through March 14, 2018 must also be separately tracked for treatment in a future rate proceeding. The Pennsylvania Companies operate under DSPs for the June 1, 2017 through May 31, 2019 delivery period, which provide for the competitive procurement of generation supply for customers who do not choose an alternative EGS or for customers of alternative EGSs that fail to provide the contracted service. Under the DSPs, the supply will be provided by wholesale suppliers through a mix of 12 and 24-month energy contracts, as well as one RFP for 2-year SREC contracts for ME, PN and Penn. The DSPs include modifications to the Pennsylvania Companies’ POR programs in order to reduce the level of uncollectible expense the Pennsylvania Companies experience associated with alternative EGS charges.

The Pennsylvania Companies' DSPs for the June 1, 2019 through May 31, 2023 delivery period were approved by the PPUC in September 2018. Under the 2019-2023 DSPs, the supply will be provided by wholesale suppliers through a mix of 3, 12 and 24-month energy contracts, as well as two RFPs for 2-year SREC contracts for ME, PN and Penn. The 2019-2023 DSPs also include modifications to the Pennsylvania Companies’ POR programs in order to continue their clawback pilot program as a long-term, permanent program term, and modifications to the Pennsylvania Companies’ customer class definitions to allow for the introduction of hourly priced default service to customers at or above 100kW. The PPUC directed a working group to further discuss the implementation of customer assistance program shopping limitations and appropriate scripting for the Pennsylvania Companies' customer referral programs, and in November 2018, issued a subsequent order to approve additional customer assistance program shopping parameters and further limit the scope of the working group discussion. On December 21, 2018, the PPUC issued a tentative order proposing a model to incorporate the directed shopping restrictions. Comments on the proposal were filed January 22, 2019. On February 28, 2019, the PPUC issued a final order approving the Pennsylvania Companies’ proposal on customer assistance programs shopping limitations and directing script modifications to the Pennsylvania Companies’ customer referral programs. 

Pursuant to Pennsylvania Act 129 of 2008 and PPUC orders, Pennsylvania EDCs implement energy efficiency and peak demand reduction programs. The Pennsylvania Companies' Phase III EE&C plans for the June 2016 through May 2021 period, which were approved in March 2016, with expected costs up to $390 million, are designed to achieve the targets established in the PPUC's Phase III Final Implementation Order with full recovery through the reconcilable EE&C riders.

Pennsylvania EDCs may establish a DSIC to recover costs of infrastructure improvements and costs related to highway relocation projects with PPUC approval. LTIIPs outlining infrastructure improvement plans for PPUC review and approval must be filed prior to approval of a DSIC. On June 14, 2017, the PPUC approved modified LTIIPs for ME, PN and Penn for the remaining years of 2017 through 2020 to provide additional support for reliability and infrastructure investments. On September 20, 2018, following a periodic review of the LTIIPs as required by regulation once every five years, the PPUC entered an Order concluding that the Pennsylvania Companies have substantially adhered to the schedules and expenditures outlined in their LTIIPs, but that changes to the LTIIPs as designed are necessary to maintain and improve reliability and directed the Pennsylvania Companies to file modified or new LTIIPs. On January 18, 2019, the Pennsylvania Companies filed modifications to their current LTIIPs that would terminate those LTIIPs at the end of 2019, and proposed revised LTIIP spending in 2019 of approximately $45 million by ME, $25 million by PN, $26 million by Penn and $51 million by WP. The Pennsylvania Companies also committed to making filings later in 2019, which would propose new LTIIPs for the 2020 through 2024 period.

The Pennsylvania Companies’ approved DSIC riders for quarterly cost recovery went into effect July 1, 2016, subject to hearings and refund or reallocation among customer classes. In the January 19, 2017 order approving the Pennsylvania Companies’ general rate cases, the PPUC added an additional issue to the DSIC proceeding to include whether ADIT should be included in DSIC calculations. On February 2, 2017, the parties to the DSIC proceeding submitted a Joint Settlement to the ALJ that resolved the issues that were pending from the order issued on June 9, 2016. On April 19, 2018, the PPUC approved the Joint Settlement without modification and reversed the ALJ's previous decision that would have required the Pennsylvania Companies to reflect all federal and state income tax deductions related to DSIC-eligible property in currently effective DSIC rates. On May 21, 2018, the Pennsylvania OCA filed an appeal with the Pennsylvania Commonwealth Court of the PPUC's decision of April 19, 2018. On June 11, 2018, the Pennsylvania Companies filed a Notice of Intervention in the Pennsylvania OCA's appeal to the Commonwealth Court. Briefing is complete and oral argument is scheduled for June 3, 2019.

WEST VIRGINIA

MP and PE provide electric service to all customers through traditional cost-based, regulated utility ratemaking and operates under rates approved by the WVPSC effective February 2015. MP and PE recover net power supply costs, including fuel costs, purchased power costs and related expenses, net of related market sales revenue through the ENEC. MP's and PE's ENEC rate is updated annually.

On August 31, 2018, MP and PE filed a $100.9 million decrease in their ENEC rates proposed to be effective January 1, 2019, which included a $25.6 million annual decrease impact associated with the settlement regarding the impact of the Tax Act on West Virginia rates, as noted below. Additionally, the August 31, 2018 filing included an elimination of the Energy Efficiency Cost Rate Surcharge effective January 1, 2019, equating to an additional $2.1 million decrease. The rate decreases represent an approximate 7.2% annual decrease in rates versus those in effect on August 31, 2018. A unanimous settlement was filed with the WVPSC on November 20, 2018, and a hearing was held on November 27, 2018. An order adopting the settlement in full without modification was issued on January 2, 2019.

On January 3, 2018, the WVPSC initiated a proceeding to investigate the effects of the Tax Act on the revenue requirements of utilities. MP and PE must track, and record as a regulatory liability, the tax savings resulting from the Tax Act on a monthly basis, effective January 1, 2018. As a result of a WVPSC-approved settlement on August 24, 2018, MP and PE began to flow through to customers $25.6 million in rate reduction beginning September 1, 2018, and to defer to the next base rate case (or a separate proceeding if a base rate case is not filed by August 31, 2020) the amount and classification of the excess ADITs resulting from the Tax Act and the issue of whether MP and PE should be required to credit to customers any of the reduced income tax expense occurring between January 1, 2018 and August 31, 2018.

FERC REGULATORY MATTERS

Under the FPA, FERC regulates rates for interstate wholesale sales, transmission of electric power, accounting and other matters, including construction and operation of hydroelectric projects. With respect to their wholesale services and rates, the Utilities, AE Supply, AGC, and the Transmission Companies are subject to regulation by FERC. FERC regulations require JCP&L, MP, PE, WP and the Transmission Companies to provide open access transmission service at FERC-approved rates, terms and conditions. Transmission facilities of JCP&L, MP, PE, WP and the Transmission Companies are subject to functional control by PJM and transmission service using their transmission facilities is provided by PJM under the PJM Tariff.

FERC regulates the sale of power for resale in interstate commerce in part by granting authority to public utilities to sell wholesale power at market-based rates upon showing that the seller cannot exert market power in generation or transmission or erect barriers to entry into markets. The Utilities and AE Supply each have been authorized by FERC to sell wholesale power in interstate commerce at market-based rates and have a market-based rate tariff on file with FERC, although major wholesale purchases remain subject to regulation by the relevant state commissions.

Federally-enforceable mandatory reliability standards apply to the bulk electric system and impose certain operating, record-keeping and reporting requirements on the Utilities, AE Supply, and the Transmission Companies. NERC is the ERO designated by FERC to establish and enforce these reliability standards, although NERC has delegated day-to-day implementation and enforcement of these reliability standards to eight regional entities, including RFC. All of the facilities that FirstEnergy operates are located within the RFC region. FirstEnergy actively participates in the NERC and RFC stakeholder processes, and otherwise monitors and manages its companies in response to the ongoing development, implementation and enforcement of the reliability standards implemented and enforced by RFC.

FirstEnergy believes that it is in compliance with all currently effective and enforceable reliability standards. Nevertheless, in the course of operating its extensive electric utility systems and facilities, FirstEnergy occasionally learns of isolated facts or circumstances that could be interpreted as excursions from the reliability standards. If and when such occurrences are found, FirstEnergy develops information about the occurrence and develops a remedial response to the specific circumstances, including in appropriate cases “self-reporting” an occurrence to RFC. Moreover, it is clear that NERC, RFC and FERC will continue to refine existing reliability standards as well as to develop and adopt new reliability standards. Any inability on FirstEnergy's part to comply with the reliability standards for its bulk electric system could result in the imposition of financial penalties, or obligations to upgrade or build transmission facilities that could have a material adverse effect on its financial condition, results of operations and cash flows.

RTO Realignment

On June 1, 2011, ATSI and the ATSI zone transferred from MISO to PJM. While many of the matters involved with the move have been resolved, FERC denied recovery under ATSI's transmission rate for certain charges that collectively can be described as "exit fees" and certain other transmission cost allocation charges totaling approximately $78.8 million until such time as ATSI submits a cost/benefit analysis demonstrating net benefits to customers from the transfer to PJM. Subsequently, FERC rejected a proposed settlement agreement to resolve the exit fee and transmission cost allocation issues, stating that its action is without prejudice to ATSI submitting a cost/benefit analysis demonstrating that the benefits of the RTO realignment decisions outweigh the exit fee and transmission cost allocation charges. In a subsequent order, FERC affirmed its prior ruling that ATSI must submit the cost/benefit analysis. ATSI is evaluating the cost/benefit approach.

FERC Actions on Tax Act

On March 15, 2018, FERC issued a NOI seeking information regarding whether and how FERC should address possible changes to ADIT and bonus depreciation as a result of the Tax Act. Such possible changes could impact FERC-jurisdictional rates, including transmission rates. On November 15, 2018, FERC issued a NOPR suggesting mechanisms to revise transmission rates to address the Tax Act’s effect on ADIT. Specifically, FERC proposed utilities with transmission formula rates would include mechanisms to (i) deduct any excess ADIT from or add any deficient ADIT to their rate bases; (ii) raise or lower their income tax allowances by any amortized excess or deficient ADIT; and (iii) incorporate a new permanent worksheet into their rates that will annually track information related to excess or deficient ADIT. Utilities with transmission stated rates would determine the amount of excess and deferred income tax caused by the reduced federal corporate income tax rate and return or recover this amount to or from customers. To assist with implementation of the proposed rule, FERC also issued on November 15, 2018, a policy statement providing accounting and ratemaking guidance for treatment of ADIT for all FERC-jurisdictional public utilities. The policy statement also addresses the accounting and ratemaking treatment of ADIT following the sale or retirement of an asset after December 31, 2017. FESC, on behalf of its affiliated transmission owners, supported comments submitted by Edison Electric Institute requesting additional clarification on the ratemaking and accounting treatment for ADIT in formula and stated transmission rates. FERC's final rule remains pending.

Transmission ROE Methodology

In June 2014, FERC issued Opinion No. 531 revising its approach for calculating the discounted cash flow element of FERC’s ROE methodology and announcing the potential for a qualitative adjustment to the ROE methodology results. Parties appealed to the D.C. Circuit, and on April 14, 2017, that court issued a decision vacating FERC’s order and remanding the matter to FERC for further review. On October 16, 2018, FERC issued its order on remand, in which it proposed a revised ROE methodology. Specifically, in complaint proceedings alleging that an existing ROE is not just and reasonable, FERC proposes to rely on three financial models-discounted cash flow, capital-asset pricing, and expected earnings to establish a composite zone of reasonableness to identify a range of just and reasonable ROEs. FERC then will utilize the transmission utility’s risk relative to other utilities within that zone of reasonableness to assign the transmission utility to one of three quartiles within the zone. FERC would take no further action (i.e., dismiss the complaint) if the existing ROE falls within the identified quartile. However, if the ROE falls outside the quartile, FERC would deem the existing ROE presumptively unjust and unreasonable and would determine the replacement ROE. FERC would add a fourth financial model risk premium to the analysis to calculate a ROE based on the average point of central tendency for each of the four financial models. On March 21, 2019, FERC established NOIs to collect industry and stakeholder comments on the revised ROE methodology that is described in the October 16, 2018 decision, and also whether to make changes to FERC’s existing policies and practices for awarding transmission rates incentives. FirstEnergy plans to comment and participate in this NOI proceeding and in any subsequent rulemaking or other proceedings.