Regulatory Matters - Maryland and New Jersey (Details)
$ in Millions
12 Months Ended 36 Months Ended
Dec. 17, 2018
USD ($)
Nov. 20, 2018
USD ($)
Oct. 22, 2018
USD ($)
Oct. 05, 2018
USD ($)
Aug. 24, 2018
USD ($)
program
Aug. 17, 2018
USD ($)
Jul. 13, 2018
USD ($)
Mar. 02, 2018
USD ($)
Jan. 19, 2018
USD ($)
Jul. 16, 2015
Feb. 27, 2013
USD ($)
Dec. 31, 2018
Dec. 31, 2020
USD ($)
Feb. 15, 2018
USD ($)
Maryland                            
Regulatory Matters [Line Items]                            
Expected infrastructure investments                     $ 2,700.0      
Expected infrastructure investments, period                     15 years      
PE | MDPSC                            
Regulatory Matters [Line Items]                            
Cost of charging equipment rebates                 $ 12.0          
Charging equipment rebates amortization period                 5 years          
PE | Maryland                            
Regulatory Matters [Line Items]                            
Incremental energy savings goal per year (percent)                   0.20%        
Incremental energy savings goal thereafter (percent)                   2.00%        
Incremental energy savings goal in the next 12 months (percent)                   0.97%        
Amortization period for expenditures for cost recovery program                       5 years    
PE | Maryland | MDPSC                            
Regulatory Matters [Line Items]                            
Requested increase (decrease) in revenues       $ (5.0)   $ (6.5)                
Requested rate increase (decrease)         $ 19.7                  
Number of enhanced service reliability programs | program         4,000,000                  
Revised requested rate increase     $ 17.6                      
Revised rate increase   $ 12.9     $ 7.3                  
Recommended decrease due to jobs act   $ 11.1                        
PE | Maryland | MDPSC | Minimum                            
Regulatory Matters [Line Items]                            
Impact on base rate due to Tax Act                           $ 7.0
PE | Maryland | MDPSC | Maximum                            
Regulatory Matters [Line Items]                            
Impact on base rate due to Tax Act                           $ 8.0
JCP&L                            
Regulatory Matters [Line Items]                            
Approved ROE                       9.60%    
JCP&L | New Jersey | NJBPU                            
Regulatory Matters [Line Items]                            
Requested increase (decrease) in revenues               $ (28.6)            
Approved rate increase due to changes in deferred taxes               $ 1.3            
Forecast | PE | Maryland                            
Regulatory Matters [Line Items]                            
Recovery period for expenditures for cost recovery program                         3 years  
Expenditures for cost recovery program                         $ 116.0  
JCP&L Reliability Plus | JCP&L | NJBPU                            
Regulatory Matters [Line Items]                            
Requested rate increase (decrease)             $ 386.8              
JCP&L Reliability Plus | JCP&L | New Jersey | NJBPU                            
Regulatory Matters [Line Items]                            
Requested increase (decrease) in revenues $ 97.0                          
Infrastructure investment period             4 years              
Approved ROE 8.75%                          
Cost of debt 5.38%