XML 29 R19.htm IDEA: XBRL DOCUMENT v3.10.0.1
Regulatory Matters
9 Months Ended
Sep. 30, 2018
Regulated Operations [Abstract]  
REGULATORY MATTERS
REGULATORY MATTERS

STATE REGULATION

Each of the Utilities' retail rates, conditions of service, issuance of securities and other matters are subject to regulation in the states in which it operates - in Maryland by the MDPSC, in Ohio by the PUCO, in New Jersey by the NJBPU, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC. The transmission operations of PE in Virginia are subject to certain regulations of the VSCC. In addition, under Ohio law, municipalities may regulate rates of a public utility, subject to appeal to the PUCO if not acceptable to the utility. In addition, if any of the FirstEnergy affiliates were to engage in the construction of significant new transmission facilities, depending on the state, they may be required to obtain state regulatory authorization to site, construct and operate the new transmission facility.

Following the adoption of the Tax Act, various state regulatory proceedings have been initiated to investigate the impact of the Tax Act on the Utilities’ rates and charges. State proceedings that have arisen are discussed below. The Utilities continue to monitor and investigate the impact of state regulatory proceedings resulting from the Tax Act.

MARYLAND

PE provides SOS pursuant to a combination of settlement agreements, MDPSC orders and regulations, and statutory provisions. SOS supply is competitively procured in the form of rolling contracts of varying lengths through periodic auctions that are overseen by the MDPSC and a third-party monitor. Although settlements with respect to SOS supply for PE customers have expired, service continues in the same manner until changed by order of the MDPSC. PE recovers its costs plus a return for providing SOS.

The Maryland legislature adopted a statute in 2008 codifying the EmPOWER Maryland goals to reduce electric consumption and demand and requiring each electric utility to file a plan every three years. On July 16, 2015, the MDPSC issued an order setting new incremental energy savings goals for 2017 and beyond, beginning with the goal of 0.97% savings achieved under PE's plan for 2016, and increasing 0.2% per year thereafter to reach 2%. The Maryland legislature in April 2017 adopted a statute requiring the same 0.2% per year increase, up to the ultimate goal of 2% annual savings, for the duration of the 2018-2020 and 2021-2023 EmPOWER Maryland program cycles, to the extent the MDPSC determines that cost-effective programs and services are available. PE's approved 2018-2020 EmPOWER Maryland plan continues and expands upon prior years' programs, and adds new programs, for a projected total cost of $116 million over the three-year period. On December 22, 2017, the MDPSC issued an order approving the 2018-2020 plan with various modifications. PE recovers program costs subject to a five-year amortization. Maryland law only allows for the utility to recover lost distribution revenue attributable to energy efficiency or demand reduction programs through a base rate case proceeding, and to date, such recovery has not been sought or obtained by PE.

On February 27, 2013, the MDPSC issued an order requiring the Maryland electric utilities to submit analyses relating to the costs and benefits of making further system and staffing enhancements in order to attempt to reduce storm outage durations. PE's responsive filings discussed the steps needed to harden the utility's system in order to attempt to achieve various levels of storm response speed described in the February 2013 Order, and projected that it would require approximately $2.7 billion in infrastructure investments over 15 years to attempt to achieve the quickest level of response for the largest storm projected in the February 2013 Order. On July 1, 2014, the Staff of the MDPSC issued a set of reports that recommended the imposition of extensive additional requirements in the areas of storm response, feeder performance, estimates of restoration times, and regulatory reporting, as well as the imposition of penalties, including customer rebates, for a utility's failure or inability to comply with the escalating standards of storm restoration speed proposed by the Staff of the MDPSC. In addition, the Staff of the MDPSC proposed that Maryland utilities be required to develop and implement system hardening plans, up to a rate impact cap on cost. The MDPSC conducted a hearing September 15-18, 2014, to consider certain of these matters, and has not yet issued a ruling on any of those matters.

On September 26, 2016, the MDPSC initiated a new proceeding to consider an array of issues relating to electric distribution system design, including matters relating to electric vehicles, distributed energy resources, advanced metering infrastructure, energy storage, system planning, rate design, and impacts on low-income customers. Comments were filed, and a hearing was held in late 2016. On January 31, 2017, the MDPSC issued a notice establishing five working groups to address these issues over the following eighteen months, and also directed the retention of an outside consultant to prepare a report on costs and benefits of distributed solar generation in Maryland. On January 19, 2018, PE filed a joint petition, along with other utility companies, work group stakeholders, and the MDPSC electric vehicle work group leader, to implement a statewide electric vehicle portfolio. If approved, PE will launch an electric vehicle charging infrastructure program on January 1, 2019, offering up to 2,000 rebates for electric vehicle charging equipment to residential customers, and deploying up to 259 chargers at non-residential customer service locations at a projected total cost of $12 million. PE is proposing to recover program costs subject to a five-year amortization. On February 6, 2018, the MDPSC opened a new proceeding to consider the petition and numerous parties filed comments on the petition on March 27, 2018. The MDPSC held hearings on the petition in May and September, 2018, after which parties filed final comments.

On January 12, 2018, the MDPSC instituted a proceeding to examine the impacts of the Tax Act on the rates and charges of Maryland utilities. PE was required to track and apply regulatory accounting treatment for the impacts beginning January 1, 2018, and submitted a report to the MDPSC on February 15, 2018, estimating that the Tax Act impacts would be approximately $7 million to $8 million annually for PE’s customers. On August 17, 2018, the Staff of the MDPSC filed a reply to PE's February 15, 2018 filing, in which reply the Staff recommended that the MDPSC direct PE to reduce base rates by $6.5 million to reflect reduced federal tax costs pending resolution of PE's upcoming rate case, and that PE further be directed to pay customers a one-time credit for what the Staff estimated were the tax savings to PE through the end of July 2018. On October 5, 2018, the MDPSC issued an order requiring PE to pay a one-time credit for tax savings through September 30, 2018, which PE estimates will be approximately $5 million, and reserved all other Tax Act impacts to be resolved in the pending rate case.

On August 24, 2018, PE filed a base rate case with the MDPSC, which it supplemented on October 22, 2018, to update the partially forecasted test year with a full twelve months of actual data. The rate case requests an annual increase in base distribution rates of $19.7 million, plus creation of an Electric Distribution Investment surcharge to fund four enhanced service reliability programs. The increase is $7.3 million less than it otherwise would have been due to savings resulting from the recent federal tax law changes. The evidentiary hearing will commence on January 22, 2019, and a final order is expected by March 23, 2019.

NEW JERSEY

JCP&L currently provides BGS for retail customers who do not choose a third-party EGS and for customers of third-party EGSs that fail to provide the contracted service. The supply for BGS is comprised of two components, procured through separate, annually held descending clock auctions, the results of which are approved by the NJBPU. One BGS component reflects hourly real time energy prices and is available for larger commercial and industrial customers. The second BGS component provides a fixed price service and is intended for smaller commercial and residential customers. All New Jersey EDCs participate in this competitive BGS procurement process and recover BGS costs directly from customers as a charge separate from base rates.

JCP&L currently operates under rates that were approved by the NJBPU on December 12, 2016, effective as of January 1, 2017. These rates provide an annual increase in operating revenues of approximately $80 million from those previously in place and are intended to improve service and benefit customers by supporting equipment maintenance, tree trimming, and inspections of lines, poles and substations, while also compensating for other business and operating expenses. In addition, on January 25, 2017, the NJBPU approved the acceleration of the amortization of JCP&L’s 2012 major storm expenses that are recovered through the SRC in order for JCP&L to achieve full recovery by December 31, 2019.

Pursuant to the NJBPU's March 26, 2015, final order in JCP&L's 2012 rate case proceeding directing that certain studies be completed, on July 22, 2015, the NJBPU approved the NJBPU staff's recommendation to implement such studies, which included operational and financial components. The independent consultant conducting the review issued a final report on July 27, 2016, recognizing that JCP&L is meeting the NJBPU requirements and making various operational and financial recommendations. The NJBPU issued an Order on August 24, 2016, that accepted the independent consultant’s final report and directed JCP&L, the Division of Rate Counsel and other interested parties to address the recommendations.

In an Order issued October 22, 2014, in a generic proceeding to review its policies with respect to the use of a CTA in base rate cases, the NJBPU stated that it would continue to apply its current CTA policy in base rate cases, subject to incorporating the following modifications: (i) calculating savings using a five-year look back from the beginning of the test year; (ii) allocating savings with 75% retained by the company and 25% allocated to rate payers; and (iii) excluding transmission assets of electric distribution companies in the savings calculation. On November 5, 2014, the Division of Rate Counsel appealed the NJBPU Order regarding the generic CTA proceeding to the Superior Court of New Jersey Appellate Division and JCP&L filed to participate as a respondent in that proceeding supporting the order. On September 18, 2017, the Superior Court of New Jersey Appellate Division reversed the NJBPU's Order on the basis that the NJBPU's modification of its CTA methodology did not comply with the procedures of the NJAPA. JCP&L's existing rates are not expected to be impacted by this order. On December 19, 2017, the NJBPU approved the issuance of proposed rules to modify the CTA methodology consistent with its October 22, 2014, Generic Order, which were published in the NJ Register on January 16, 2018, and republished on February 6, 2018, to correct an error. JCP&L filed comments supporting the proposed rulemaking on April 6, 2018.

At the December 19, 2017, NJBPU public meeting, the NJBPU approved its IIP rulemaking. The IIP creates a financial incentive for utilities to accelerate the level of investment needed to promote the timely rehabilitation and replacement of certain non-revenue producing components that enhance reliability, resiliency, and/or safety. On July 13, 2018, JCP&L filed an infrastructure plan, JCP&L Reliability Plus, which proposed to accelerate $386.8 million of electric distribution infrastructure investment over four years to enhance the reliability and resiliency of its distribution system and reduce the frequency and duration of power outages. JCP&L requested that the NJBPU issue a final order in December 2018. On August 29, 2018, the NJBPU retained the petition for hearing.

On January 31, 2018, the NJBPU instituted a proceeding to examine the impacts of the Tax Act on the rates and charges of New Jersey utilities. The NJBPU ordered New Jersey utilities to: (1) defer on their books the impacts of the Tax Act effective January 1, 2018; (2) to file tariffs effective April 1, 2018, reflecting the rate impacts of changes in current taxes; and (3) to file tariffs effective July 1, 2018, reflecting the rate impacts of changes in deferred taxes. On March 2, 2018, JCP&L filed a petition with the NJBPU, which included proposed tariffs for a base rate reduction of $28.6 million effective April 1, 2018, and a rider to reflect $1.3 million in rate impacts of changes in deferred taxes. On March 26, 2018, the NJBPU approved JCP&L’s rate reduction effective April 1, 2018, on an interim basis subject to refund, pending the outcome of this proceeding. The NJBPU, however, did not address refunds and other proposed rider tariffs at such time, but may be addressed at a later date.

OHIO

The Ohio Companies currently operate under ESP IV which commenced June 1, 2016 and expires May 31, 2024. The material terms of ESP IV, as approved in the PUCO’s Opinion and Order issued on March 31, 2016 and Fifth Entry on Rehearing on October 12, 2016, include Rider DMR, which provides for the Ohio Companies to collect $132.5 million annually for three years, with the possibility of a two-year extension. Rider DMR will be grossed up for federal income taxes, resulting in an approved amount of approximately $168 million annually in 2018 and 2019. Revenues from Rider DMR will be excluded from the significantly excessive earnings test for the initial three-year term but the exclusion will be reconsidered upon application for a potential two-year extension. The PUCO set three conditions for continued recovery under Rider DMR: (1) retention of the corporate headquarters and nexus of operations in Akron, Ohio; (2) no change in control of the Ohio Companies; and (3) a demonstration of sufficient progress in the implementation of grid modernization programs approved by the PUCO. ESP IV also continues a base distribution rate freeze through May 31, 2024. In addition, ESP IV continues the supply of power to non-shopping customers at a market-based price set through an auction process.

ESP IV also continues Rider DCR, which supports continued investment related to the distribution system for the benefit of customers, with increased revenue caps of $30 million per year from June 1, 2016 through May 31, 2019; $20 million per year from June 1, 2019 through May 31, 2022; and $15 million per year from June 1, 2022 through May 31, 2024. Other material terms of ESP IV include: (1) the collection of lost distribution revenues associated with energy efficiency and peak demand reduction programs; (2) an agreement to file a Grid Modernization Business Plan for PUCO consideration and approval (which filing was made on February 29, 2016, and remains pending); (3) a goal across FirstEnergy to reduce CO2 emissions by 90% below 2005 levels by 2045; (4) contributions, totaling $51 million to: (a) fund energy conservation programs, economic development and job retention in the Ohio Companies’ service territories; (b) establish a fuel-fund in each of the Ohio Companies’ service territories to assist low-income customers; and (c) establish a Customer Advisory Agency to ensure preservation and growth of the competitive market in Ohio; and (5) an agreement to file an application to transition to a straight fixed variable cost recovery mechanism for residential customers' base distribution rates, which filing was made on April 3, 2017, and which the PUCO denied on June 13, 2018.

Several parties, including the Ohio Companies, filed applications for rehearing regarding the Ohio Companies’ ESP IV with the PUCO. The Ohio Companies’ application for rehearing challenged, among other things, the PUCO’s failure to adopt the Ohio Companies’ suggested modifications to Rider DMR. The Ohio Companies had previously suggested that a properly designed Rider DMR would be valued at $558 million annually for eight years, and include an additional amount that recognizes the value of the economic impact of FirstEnergy maintaining its headquarters in Ohio. Other parties’ applications for rehearing argued, among other things, that the PUCO’s adoption of Rider DMR is not supported by law or sufficient evidence. On August 16, 2017, the PUCO denied all remaining intervenor applications for rehearing, denied the Ohio Companies’ challenges to the modifications to Rider DMR and added a third-party monitor to ensure that Rider DMR funds are spent appropriately. On September 15, 2017, the Ohio Companies filed an application for rehearing of the PUCO’s August 16, 2017 ruling on the issues of the third-party monitor and the ROE calculation for advanced metering infrastructure. On October 11, 2017, the PUCO denied the Ohio Companies' application for rehearing on both issues. On October 16, 2017, the Sierra Club and the OMAEG filed notices of appeal with the Supreme Court of Ohio appealing various PUCO entries on their applications for rehearing. On November 16, 2017, the Ohio Companies intervened in the appeal. Additional parties subsequently filed notices of appeal with the Supreme Court of Ohio challenging various PUCO entries on their applications for rehearing. On February 26, 2018, appellants filed their briefs. Briefs of the PUCO and the Ohio Companies were filed on May 29, 2018. On July 9, 2018, appellants filed their reply briefs. On September 26, 2018, the Supreme Court of Ohio denied a July 30, 2018 joint motion filed by the OCC, the NOAC, and the OMAEG to stay the portions of the PUCO's orders and entries under appeal that authorized Rider DMR. Oral argument on the appeals is scheduled for January 9, 2019.

Under ORC 4928.66, the Ohio Companies are required to implement energy efficiency programs that achieve certain annual energy savings and total peak demand reductions. Starting in 2017, ORC 4928.66 requires the energy savings benchmark to increase by 1% and the peak demand reduction benchmark to increase by 0.75% annually thereafter through 2020 and the energy savings benchmark to increase by 2% annually from 2021 through 2027, with a cumulative benchmark of 22.2% by 2027. On April 15, 2016, the Ohio Companies filed an application for approval of their three-year energy efficiency portfolio plans for the period from January 1, 2017 through December 31, 2019. The plans as proposed comply with benchmarks contemplated by ORC 4928.66 and provisions of the ESP IV, and include a portfolio of energy efficiency programs targeted to a variety of customer segments, including residential customers, low income customers, small commercial customers, large commercial and industrial customers and governmental entities. On December 9, 2016, the Ohio Companies filed a Stipulation and Recommendation with several parties that contained changes to the plan and a decrease in the plan costs. The Ohio Companies anticipate the cost of the plans will be approximately $268 million over the life of the portfolio plans and such costs are expected to be recovered through the Ohio Companies’ existing rate mechanisms. On November 21, 2017, the PUCO issued an order that approved the filed Stipulation and Recommendation with several modifications, including a cap on the Ohio Companies’ collection of program costs and shared savings set at 4% of the Ohio Companies’ total sales to customers as reported on 2015 FERC Form 1. On December 21, 2017, the Ohio Companies filed an application for rehearing challenging the PUCO’s modification of the Stipulation and Recommendation to include the 4% cost cap, which was denied by the PUCO on January 10, 2018. On March 12, 2018, the Ohio Companies filed a Notice of Appeal with the Supreme Court of Ohio challenging the PUCO’s imposition of a 4% cost cap. Various other parties also filed Notices of Appeal challenging various PUCO entries on their applications for rehearing. The Ohio Companies filed their brief on May 21, 2018. The PUCO filed its brief on July 30, 2018, and the Ohio Companies filed their reply brief on September 10, 2018. Oral argument on the appeals is scheduled for February 20, 2019.

Ohio law requires electric utilities and electric service companies in Ohio to serve part of their load from renewable energy resources measured by an annually increasing percentage amount through 2026, except that in 2014 SB310 froze 2015 and 2016 requirements at the 2014 level (2.5%), pushing back scheduled increases, which resumed in 2017 (3.5%), and increases 1% each year through 2026 (to 12.5%) and shall remain at 12.5% in 2027 and each year thereafter. The Ohio Companies conducted RFPs in 2009, 2010 and 2011 to secure RECs to help meet these renewable energy requirements. In September 2011, the PUCO opened a docket to review the Ohio Companies' alternative energy recovery rider through which the Ohio Companies recover the costs of acquiring these RECs. The PUCO issued an Opinion and Order on August 7, 2013, approving the Ohio Companies' acquisition process and their purchases of RECs to meet statutory mandates in all instances except for certain purchases arising from one auction and directed the Ohio Companies to credit non-shopping customers in the amount of $43.4 million, plus interest, on the basis that the Ohio Companies did not prove such purchases were prudent. On December 24, 2013, following the denial of their application for rehearing, the Ohio Companies filed a Notice of Appeal and a motion for stay of the PUCO's order with the Supreme Court of Ohio, which was granted. The OCC and the ELPC also filed appeals of the PUCO's order. On January 24, 2018, the Supreme Court of Ohio reversed the PUCO order finding that the order violated the rule against retroactive ratemaking. On February 5, 2018, the OCC and ELPC filed a motion for reconsideration, to which the Ohio Companies responded in opposition on February 15, 2018. On April 25, 2018, the Supreme Court of Ohio denied the motion for reconsideration. As a result, in the second quarter of 2018, the Ohio Companies recognized a pre-tax benefit to earnings (within the Amortization (deferral) of regulatory assets, net line on the Consolidated Statement of Income (Loss)) of approximately $72 million to reverse the liability associated with the PUCO opinion and order.

On December 1, 2017, the Ohio Companies filed an application with the PUCO for approval of a DPM Plan. The DPM Plan is a portfolio of approximately $450 million in distribution platform investment projects, which are designed to modernize the Ohio Companies’ distribution grid, prepare it for further grid modernization projects, and provide customers with immediate reliability benefits. The Ohio Companies have requested that the PUCO issue an order approving the DPM Plan and associated cost recovery so that the Ohio Companies can expeditiously commence the DPM Plan and customers can begin to realize the associated benefits.

On January 10, 2018, the PUCO opened a case to consider the impacts of the Tax Act and determine the appropriate course of action to pass benefits on to customers. The Ohio Companies, effective January 1, 2018, were required to establish a regulatory liability for the estimated reduction in federal income tax resulting from the Tax Act, and filed comments on February 15, 2018, explaining that customers will save nearly $40 million annually as a result of updating tariff riders for the tax rate changes and that the Ohio Companies’ base distribution rates are not impacted by the Tax Act changes because they are frozen through May 2024. The Ohio Companies filed reply comments on March 7, 2018. On October 24, 2018, the PUCO entered an Order in its investigation into the impacts of the Tax Act on Ohio's utilities directing that by January 1, 2019, all Ohio rate-regulated utility companies, unless ordered otherwise, file applications not for an increase in rates to reflect the impact of the Tax Act on each specific utility's current rates.

PENNSYLVANIA

The Pennsylvania Companies operate under DSPs for the June 1, 2017 through May 31, 2019 delivery period, which provide for the competitive procurement of generation supply for customers who do not choose an alternative EGS or for customers of alternative EGSs that fail to provide the contracted service. Under the DSPs, the supply will be provided by wholesale suppliers through a mix of 12 and 24-month energy contracts, as well as one RFP for 2-year SREC contracts for ME, PN and Penn. The DSPs include modifications to the Pennsylvania Companies’ POR programs in order to reduce the level of uncollectible expense the Pennsylvania Companies experience associated with alternative EGS charges.

On December 11, 2017, the Pennsylvania Companies filed DSPs for the June 1, 2019 through May 31, 2023 delivery period. Under the 2019-2023 DSPs, the supply is proposed to be provided by wholesale suppliers through a mix of 3, 12 and 24-month energy contracts, as well as two RFPs for 2-year SREC contracts for ME, PN and Penn. The 2019-2023 DSPs as proposed also include modifications to the Pennsylvania Companies’ POR programs in order to continue their clawback pilot program as a long-term, permanent program. The 2019-2023 DSPs also introduce a retail market enhancement rate mechanism designed to stimulate residential customer shopping, and modifications to the Pennsylvania Companies’ customer class definitions to allow for the introduction of hourly priced default service to customers at or above 100kW. A hearing was held on April 10, 2018, and the ALJ issued a recommended decision dated May 31, 2018. The decision recommended approval of the Pennsylvania Companies' DSPs as originally proposed with two exceptions: it recommended rejecting the proposed retail market enhancement rate mechanism, and establishing limitations on customer assistance program customers' shopping. Exceptions were filed by two parties on June 28, 2018, to which the Pennsylvania Companies filed reply exceptions on July 9, 2018. On September 4, 2018, the PPUC issued an order approving the Pennsylvania Companies' DSPs and directed a working group to further discuss the implementation of customer assistance program shopping limitations and appropriate scripting for the Pennsylvania Companies' customer referral programs. The Pennsylvania Companies and two other parties filed petitions for reconsideration to that order on the limited issue of timing and scope of the working group discussion related to customer assistance program shopping limitations, which are pending PPUC review at this time.

The Pennsylvania Companies operate under rates that were approved by the PPUC on January 19, 2017, effective as of January 27, 2017. These rates provide annual increases in operating revenues of approximately $96 million at ME, $100 million at PN, $29 million at Penn, and $66 million at WP, and are intended to benefit customers by modernizing the grid with smart technologies, increasing vegetation management activities, and continuing other customer service enhancements.

Pursuant to Pennsylvania's EE&C legislation in Act 129 of 2008 and PPUC orders, Pennsylvania EDCs implement energy efficiency and peak demand reduction programs. On June 19, 2015, the PPUC issued a Phase III Final Implementation Order setting: demand reduction targets, relative to each Pennsylvania Companies' 2007-2008 peak demand (in MW), at 1.8% for ME, 1.7% for Penn, 1.8% for WP, and 0% for PN; and energy consumption reduction targets, as a percentage of each Pennsylvania Companies’ historic 2010 forecasts (in MWH), at 4.0% for ME, 3.9% for PN, 3.3% for Penn, and 2.6% for WP. The Pennsylvania Companies' Phase III EE&C plans for the June 2016 through May 2021 period, which were approved in March 2016, with expected costs up to $390 million, are designed to achieve the targets established in the PPUC's Phase III Final Implementation Order with full recovery through the reconcilable EE&C riders.

Pursuant to Act 11 of 2012, Pennsylvania EDCs may establish a DSIC to recover costs of infrastructure improvements and costs related to highway relocation projects with PPUC approval. Pennsylvania EDCs must file LTIIPs outlining infrastructure improvement plans for PPUC review and approval prior to approval of a DSIC. On February 11, 2016, the PPUC approved LTIIPs for each of the Pennsylvania Companies. On June 14, 2017, the PPUC approved modified LTIIPs for ME, PN and Penn for the remaining years of 2017 through 2020 to provide additional support for reliability and infrastructure investments. The LTIIPs estimated costs for the remaining period of 2018 to 2020 are: WP $50.1 million; PN $44.8 million; Penn $33.2 million; and ME $51.3 million. On April 10, 2018, the PPUC notified each of the Pennsylvania Companies that the PPUC was initiating a review of the LTIIPs as required by regulation once every five years, and soliciting comments from interested parties. On May 10, 2018, the Pennsylvania Companies each filed comments explaining that their LTIIPs are effective and that changes to the respective LTIIPs are not necessary. No parties other than the Pennsylvania Companies filed comments. On September 20, 2018, the PPUC entered an Order concluding that the Pennsylvania Companies have substantially adhered to the schedules and expenditures outlined in their LTIIPs, but that changes to the LTIIPs as designed are necessary to maintain and improve reliability. The PPUC directed the Pennsylvania Companies to file modified or new LTIIPs within 60 days of the Order; however, on October 17, 2018, the Pennsylvania Companies requested a 60-day extension to file the new or modified LTIIPs.

On February 16, 2016, the Pennsylvania Companies filed riders for PPUC approval for quarterly cost recovery, which were approved by the PPUC on June 9, 2016, and went into effect July 1, 2016, subject to hearings and refund or reallocation among customer classes. On January 19, 2017, in the PPUC’s order approving the Pennsylvania Companies’ general rate cases, the PPUC added an additional issue to the DSIC proceeding to include whether ADIT should be included in DSIC calculations. On February 2, 2017, the parties to the DSIC proceeding submitted a Joint Settlement to the ALJ that resolved the issues that were pending from the order issued on June 9, 2016. On August 31, 2017, the ALJ issued a decision recommending that the complaint of the Pennsylvania OCA be granted by the PPUC such that the Pennsylvania Companies reflect all federal and state income tax deductions related to DSIC-eligible property in the currently effective DSIC rates. On April 19, 2018, the PPUC approved the Joint Settlement without modification and reversed the ALJ's decision that would have required the Pennsylvania Companies to reflect all federal and state income tax deductions related to DSIC-eligible property in currently effective DSIC rates. On May 21, 2018, the Pennsylvania OCA filed an appeal with the Pennsylvania Commonwealth Court of the PPUC's decision of April 19, 2018. On June 11, 2018, the Pennsylvania Companies filed a Notice of Intervention in the Pennsylvania OCA's appeal to Commonwealth Court.

On February 12, 2018, the PPUC initiated a proceeding to determine the effects of the Tax Act on the tax liability of utilities and the feasibility of reflecting such impacts in rates charged to customers. On March 9, 2018, the Pennsylvania Companies submitted their calculation of the net annual effect of the Tax Act on income tax expense and rate base to be $37 million for ME, $40 million for PN, $9 million for Penn, and $30 million for WP. The Pennsylvania Companies also filed comments proposing that rates be adjusted to reflect the tax rate changes prospectively from the date of a final PPUC order via a reconcilable rider, with the amount that would otherwise accrue between January 1, 2018 and the date of a final order being used to invest in the Pennsylvania Companies’ infrastructure. On March 15, 2018, the PPUC issued a Temporary Rates Order making the Pennsylvania Companies’ rates temporary and subject to refund for six months. On May 17, 2018, the PPUC issued orders directing that the Pennsylvania Companies implement a reconcilable negative surcharge mechanism in order to refund to customers the net effect of the Tax Act for the period July 1, 2018, through December 31, 2018, to be prospectively updated for new rates effective January 1, 2019. The Pennsylvania Companies were also directed to establish a regulatory liability for the net impact of the Tax Act for the period of January 1, 2018 through June 30, 2018. On June 14, 2018, the PPUC issued an order revising this directive such that the Pennsylvania Companies must instead establish accounts to track tax savings for the period January 1, 2018, through March 14, 2018, and record regulatory liabilities associated with tax savings for only the period March 15, 2018 through June 30, 2018. The cumulative value of the tracked amounts and the regulatory liability is expected to amount to $12 million for ME, $13 million for PN, $3 million for Penn, and $10 million for WP. These amounts are expected to be addressed in the Pennsylvania Companies' next available rate proceedings, or independent filings to be made within three years, whichever comes sooner. The Pennsylvania Companies filed voluntary surcharges on June1, 2018, to adjust rates for the reduced tax rate, which were effective for bills rendered starting July 1, 2018. For the first six-month period, the surcharge is expected to return to customers $19 million for ME, $20 million for PN, $5 million for Penn, and $15 million for WP.

WEST VIRGINIA

MP and PE provide electric service to all customers through traditional cost-based, regulated utility ratemaking. MP and PE recover net power supply costs, including fuel costs, purchased power costs and related expenses, net of related market sales revenue through the ENEC. MP's and PE's ENEC rate is updated annually.

On August 31, 2018, MP and PE filed a $100.9 million decrease in their ENEC rates proposed to be effective January 1, 2019, which includes a $25.6 million annual decrease impact associated with the settlement regarding the impact of the Tax Act on West Virginia rates, as noted below. Additionally, the August 31, 2018 filing includes an elimination of the Energy Efficiency Cost Rate Surcharge effective January 1, 2019, equating to an additional $2.1 million decrease. The rate decreases represent an approximate 7.2% annual decrease in rates versus those in effect on August 31, 2018. Hearings before the WVPSC are scheduled for November 27 and 28, 2018.

On January 3, 2018, the WVPSC initiated a proceeding to investigate the effects of the Tax Act on the revenue requirements of utilities. MP and PE must track the tax savings resulting from the Tax Act on a monthly basis, effective January 1, 2018. On January 26, 2018, the WVPSC issued an order clarifying that regulatory accounting should be implemented as of January 1, 2018, including the recording of any regulatory liabilities resulting from the Tax Act. MP and PE filed written testimony on May 30, 2018, explaining the impact of the Tax Act on federal income tax and revenue requirements and showing an annual rate impact of $26.2 million. MP and PE, the Staff of the WVPSC, the WV Consumer Advocate, and a coalition of industrial customers entered into a settlement agreement on August 23, 2018, to have $25.6 million in rate reductions flow through to customers beginning September 1, 2018, and to defer to the next base rate case (or a separate proceeding if a base rate case is not filed by August 31, 2020) the amount and classification of the excess ADITs resulting from the Tax Act and the issue of whether MP and PE should be required to credit to customers any of the reduced income tax expense occurring between January 1, 2018 and August 31, 2018. The WVPSC approved the settlement on August 24, 2018.

FERC MATTERS

Reliability Matters

Federally-enforceable mandatory reliability standards apply to the bulk electric system and impose certain operating, record-keeping and reporting requirements on the Utilities, AE Supply, ATSI, MAIT and TrAIL. NERC is the ERO designated by FERC to establish and enforce these reliability standards, although NERC has delegated day-to-day implementation and enforcement of these reliability standards to eight regional entities, including RFC. All of FirstEnergy's facilities are located within the RFC region. FirstEnergy actively participates in the NERC and RFC stakeholder processes, and otherwise monitors and manages its companies in response to the ongoing development, implementation and enforcement of the reliability standards implemented and enforced by RFC.

FirstEnergy believes that it is in compliance with all currently-effective and enforceable reliability standards. Nevertheless, in the course of operating its extensive electric utility systems and facilities, FirstEnergy occasionally learns of isolated facts or circumstances that could be interpreted as excursions from the reliability standards. If and when such occurrences are found, FirstEnergy develops information about the occurrence and develops a remedial response to the specific circumstances, including in appropriate cases “self-reporting” an occurrence to RFC. Moreover, it is clear that NERC, RFC and FERC will continue to refine existing reliability standards as well as to develop and adopt new reliability standards. Any inability on FirstEnergy's part to comply with the reliability standards for its bulk electric system could result in the imposition of financial penalties, or obligations to upgrade or build transmission facilities, that could have a material adverse effect on its financial condition, results of operations and cash flows.

PJM Transmission Rates

PJM and its stakeholders have been debating the proper method to allocate costs for a certain class of new transmission facilities since 2005. While FirstEnergy and other parties advocate for a traditional "beneficiary pays" (or usage based) approach, others advocate for “socializing” the costs on a load-ratio share basis, where each customer in the zone would pay based on its total usage of energy within PJM. This question has been the subject of extensive litigation before FERC and the appellate courts, including before the Seventh Circuit. On June 25, 2014, a divided three-judge panel of the Seventh Circuit ruled that FERC had not quantified the benefits that western PJM utilities would derive from certain new 500 kV or higher lines and thus had not adequately supported its decision to socialize the costs of these lines. The majority found that eastern PJM utilities are the primary beneficiaries of the lines, while western PJM utilities are only incidental beneficiaries, and that, while incidental beneficiaries should pay some share of the costs of the lines, that share should be proportionate to the benefit they derive from the lines, and not on load-ratio share in PJM as a whole. The court remanded the case to FERC, which issued an order setting the issue of cost allocation for hearing and settlement proceedings. On June 15, 2016, various parties, including ATSI and the Utilities, filed a settlement agreement at FERC agreeing to apply a combined usage based/socialization approach to cost allocation for charges to transmission customers in the PJM Region for transmission projects operating at or above 500 kV. For historical transmission costs prior to January 1, 2016, the settlement agreement provides a “black-box” schedule of credits to and payments from customers across PJM’s transmission zones. From January 1, 2016 forward, PJM will collect a charge for the revenue requirement associated with each transmission enhancement through a “50/50” calculation, with 50% based on a load-ratio share and the other 50% solution-based distribution factor (DFAX) hybrid method. On May 31, 2018, FERC approved the settlement agreement as filed, without conditions. As a result of the settlement, FirstEnergy recorded a pre-tax benefit of approximately $73 million and $42 million during the second and third quarters, respectively (within the Other operating expenses line on the Consolidated Statement of Income), relating to the amount of refund the Ohio Companies will receive and retain from PJM for the period prior to January 1, 2016. PJM implemented the settlement for transmission service purchased in July 2018 in customer bills beginning in August 2018. FirstEnergy does not expect a material impact from implementation of the settlement agreement going forward. Requests for rehearing or clarification of FERC's May 31, 2018, orders and related responses remain pending before FERC.

RTO Realignment

On June 1, 2011, ATSI and the ATSI zone transferred from MISO to PJM. While many of the matters involved with the move have been resolved, FERC denied recovery under ATSI's transmission rate for certain charges that collectively can be described as "exit fees" and certain other transmission cost allocation charges totaling approximately $78.8 million until such time as ATSI submits a cost/benefit analysis demonstrating net benefits to customers from the transfer to PJM. Subsequently, FERC rejected a proposed settlement agreement to resolve the exit fee and transmission cost allocation issues, stating that its action is without prejudice to ATSI submitting a cost/benefit analysis demonstrating that the benefits of the RTO realignment decisions outweigh the exit fee and transmission cost allocation charges. On March 17, 2016, FERC denied FirstEnergy's request for rehearing of FERC's earlier order rejecting the settlement agreement and affirmed its prior ruling that ATSI must submit the cost/benefit analysis.

Separately, FirstEnergy joined certain other PJM TOs in a protest of MISO's proposal to allocate MVP costs to energy transactions that cross MISO's borders into the PJM Region. On July 13, 2016, FERC issued its order finding it appropriate for MISO to assess an MVP usage charge for power withdrawals from MISO to PJM. Various parties, including FirstEnergy and the PJM TOs, requested rehearing or clarification of FERC’s order. On September 20, 2018, FERC issued an order denying rehearing and affirming and clarifying its prior decision that MISO may allocate MVP costs to PJM customers for power withdrawals from MISO to PJM as such exports occur.

The outcome of the proceedings that address the remaining open issues related to MVP costs cannot be predicted at this time.

PATH Transmission Project

In 2012, the PJM Board of Managers canceled the PATH project, a proposed transmission line from West Virginia through Virginia and into Maryland. As a result of PJM canceling the project, approximately $62 million and approximately $59 million in costs incurred by PATH-Allegheny and PATH-WV, respectively, were reclassified from net property, plant and equipment to a regulatory asset for future recovery. PATH-Allegheny and PATH-WV requested authorization from FERC to recover the costs with a proposed ROE of 10.9% (10.4% base plus 0.5% for RTO membership) from PJM customers over five years. FERC issued an order denying the 0.5% ROE adder for RTO membership and allowing the tariff changes enabling recovery of these costs to become effective on December 1, 2012, subject to hearing and settlement procedures. On January 19, 2017, FERC issued an order reducing the PATH formula rate ROE from 10.4% to 8.11% effective January 19, 2017 and allowing recovery of certain related costs. On February 21, 2017, PATH filed a request for rehearing with FERC seeking recovery of disallowed costs and requesting that the ROE be reset to 10.4% for the entire amortization period. The Edison Electric Institute submitted an amicus curiae request for reconsideration in support of PATH. On March 20, 2017, PATH also submitted a compliance filing implementing the January 19, 2017 order. Certain affected ratepayers challenged the compliance filing, and FERC Staff requested additional information on, and edits to, the compliance filing, as directed by the January 19, 2017 order. PATH responded to comments and Staff’s request. FERC orders on PATH's requests for rehearing and compliance filing remain pending.

FERC Actions on Tax Act

On March 15, 2018, FERC took action to address the impact of the Tax Act on FERC-jurisdictional rates, including transmission and electric wholesale rates. FERC directed MP, PE and WP to either submit a joint filing to adjust the transmission rate for the Allegheny Power transmission zone in the PJM Region to address the impact of the Tax Act changes in effective tax rate, or to “show cause” as to why such action is not required. FERC established a refund effective date of March 21, 2018 for any refunds as a result of the change in tax rate. On May 14, 2018, MP, PE and WP submitted revisions to their joint stated transmission rate to reflect the reduction in the federal corporate income tax rate. The revisions reduce the rate by 6.70%. There were no comments submitted in response to the proposed revisions, and the matter is now before FERC for further action. FERC is not at this time requiring other FirstEnergy FERC-jurisdictional companies to make changes to their transmission or wholesale rates. However, these rates may be affected by a related FERC "Notice of Inquiry" assessing the impact of the Tax Act on certain rate components.

Also, on March 15, 2018, FERC issued a Notice of Inquiry seeking information regarding whether and how FERC should address possible changes to accumulated deferred income taxes and bonus depreciation as a result of the Tax Act. Such possible changes could impact FERC-jurisdictional rates, including wholesale rates. Various entities submitted responses to the Notice of Inquiry. FESC, on behalf of its transmission-owning affiliates, participated in the development of separate comments submitted by Edison Electric Institute and certain PJM TOs. The matter is now before FERC for further action.

PJM Markets: Grid Reliability and Resiliency

On September 28, 2017, the Secretary of Energy released a NOPR requesting FERC to issue rules directing RTOs, including PJM, to incorporate pricing for defined “eligible grid reliability and resiliency resources” into wholesale energy markets. FERC established a docket requesting comments, and issued an order on January 8, 2018 terminating the NOPR proceeding, finding that the NOPR did not satisfy the statutory threshold requirements under the FPA for requiring changes to RTO/ISO tariffs to address resilience concerns. FERC in its order instituted a new administrative proceeding to gather additional information regarding resilience issues. Each RTO/ISO responded to a provided list of questions and various entities submitted comments. The matter is now before FERC for further action. In the event FERC orders resiliency payments in wholesale energy markets, such charges may be levied against LSEs in the PJM Region, including the Utilities. There is no deadline or requirement for FERC to act in this new proceeding and as such the outcome of the proceeding and its impact on the Utilities, if any, cannot be predicted at this time.

PJM Markets: Capacity Pricing Reform

In March 2016, a number of generation owners filed with FERC a complaint against PJM requesting that FERC expand the MOPR in the PJM Tariff to prevent the alleged artificial suppression of prices in PJM capacity markets by state-subsidized generation. However, FERC took no action at that time. In April 2018, PJM filed with FERC two alternative proposals to modify the PJM Tariff to address concerns that state-authorized subsidies to certain generators within PJM may affect market prices.

On June 29, 2018, FERC issued an order granting in part and denying in part the March 2016 complaint and rejecting both of PJM's April 2018 proposals, agreeing with the complaint that PJM's current MOPR is unjust and unreasonable and finding that none of the proposed solutions to MOPR reform were just and reasonable and not unduly discriminatory. FERC established a new FPA Section 206 proceeding to develop a solution to the MOPR construct. FERC's directives in the new proceeding are to revise the MOPR so that it (i) applies to both existing and new resources that receive out-of-market subsidies with very limited exemptions; and (ii) accommodates state policies by allowing a new FRR-like alternative that would remove resources that receive out-of-market subsidies from the capacity market if the unit could be paired with a commensurate amount of load. Resources receiving out-of-market revenues could opt to stay in the capacity market but would be subject to the revised MOPR, or under the FRR-like alternative they could exit the market. FERC established a timeline for comments and expects to issue an order by January 4, 2019, so that the reformed MOPR can be implemented for the 2019 BRA. FERC instituted a refund effective date of July 11, 2018, for the new Section 206 proceeding. On July 30, 2018 FESC, on behalf of the Utilities, submitted a request for clarification or, in the alternative, rehearing of FERC's June 29, 2018 order. Specifically, FESC requested clarification regarding the applicability of FERC's directed MOPR reform to vertically-integrated resources. Various other parties also submitted requests for rehearing or clarification. FERC's order on rehearing remains pending. On October 2, 2018, FESC on behalf of the Utilities submitted comments demonstrating that while MOPR reform may be an interim step, FERC needs to address fundamental flaws in the PJM capacity market.

On August 13, 2018, PJM filed a request for a waiver of certain provisions of the PJM Tariff to delay the 2019 BRA for the 2022/2023 Delivery Year from May 2019 to August 14, 2019 if FERC delays its order in the above Section 206 proceeding as requested by certain parties. PJM also requested waiver of certain deadlines associated with the 2019 BRA, including the posting of planning parameters and submission of a preliminary exception request for deactivating generation resources. FERC issued an order on August 30, 2018 granting the waiver as requested.

Separately, on May 31, 2018, certain merchant generators filed a complaint with FERC against PJM seeking an order finding that PJM's existing MOPR mechanism is unjust and unreasonable, and implementing instead a so-called "Clean" MOPR that would apply to existing and new generation resources of all fuel types and all ownership arrangements, including regulated generation resources such as MP's and JCP&L's existing generation, that receive or have any form of "out-of-market" support, including recovery of generation costs in retail rates. The complainants request a FERC order by May 2019, so that the proposed "Clean" MOPR could be implemented in PJM's 2019 BRA. FESC, on behalf of its affiliates and jointly with EKPC, submitted a protest of the complaint. FESC and EKPC requested FERC reject PJM's proposals, maintain the existing PJM market rules, and direct PJM to develop a holistic solution to the fundamental issues facing its market. Various other entities also submitted protests and comments. FERC did not address the Clean MOPR Complaint in its June 29, 2018 order, which remains pending before FERC. The outcome of FERC's Section 206 proceeding and the Clean MOPR Complaint, and their impact on the Utilities and FirstEnergy's regulated generation sources, if any, cannot be predicted at this time but are not expected to be material.